Beruflich Dokumente
Kultur Dokumente
Results of a heavily burdened charge. The two laser dots are for measuring
scale.
Not that the depth of holes will be the same for both empty holes and blast holes and this parameter
cancels out. In most cases, void space should be in excess of 20% with 27% to 33% void space not an
uncommon target to reach.
Single pass blasting in which the complete loaded design is detonated in a single event has been
developed providing holes are accurately drilled. Some raises 20 m long have been blasted and it is
obvious that drilling accuracy in these instances is paramount.
Shaft Sinking
Shaft sinking requires the use of a beginning sinking cut in order to start the shafting process. In the
past, this was continued until non-weathered competent ground in reached. With the use of bulk
emulsions contained in a carrier similar to a large ANFO pot, packaged products have been mostly
superceded. The drilling and blasting process is similar to drifting but the orientation changes
vertically. Holes are drilled in a V cut with additional holes drilled obliquely toward the shaft
perimeter. Perimeter holes 'look out' to make room for the drill.
Types of Raises
• Conventional (Alimak)
• Raise boring
• VCR Blasting (Drop Raising)
• Longhole Raising (Rapid Raising)
• Uphole Raising (Inverse or Blind Raise)
• Holes drilled with a long hole ITH drill. Accuracy is very important. Vertical Retreat Mining
(VRM) is the mining method; please refer to this section
• Crater charge is used to create void
• Holes are then blasted into this with least burdened holes firing first
• Typically use high density, high energy explosives
• Initiated using millisecond (MS) timing
• Standard hole diameter is 165 mm
Vertical Retreat Mining methodology is used to create void space with adjacent holes being slashed into void
space made but initial blasthole. The sketch on the right shows have VRM charges are plugged and initiated in
an ITH hole.
Longhole Raising
Burden
Shot Reamer Reamer VOID
to
Diameter Diameter Spacing Single
Reamer
(mm) (mm) (m) (m)
Inverse Raising
From a report completed by Helig of Blastronics, there is much variability in the design of inverse
raises and rates of advance that can be obtained. Additional points have been summarized below
(also from Helig);
• drilling accuracy is considered to be perhaps the most critical feature of raise design and that
there is difficulty in establishing incentives based on accuracy rather than footage
• blastholes less than 114 mm produce excessive deviation in raises beyond 20 m in length
• in bad ground, the number of uncharged relief holes and timing between blastholes should be
increased
• powder factor reduction should be considered from the standpoint that adjacent detonating
boreholes may affect one another
• explosives with lower detonation velocities seemed to produce better results in softer ground
conditions, probably due to the fact that brisance isn’t required for soft rock
• the delay interval between adjacent detonating blastholes in the cut region should be
increased to more than a value of 1 second
• the longest possible delays between blastholes in the cut region should be used - the mixing
of short and long delay period detonators should not be considered
• void spacing should be increased to over 30 %
• inverse raises less than 15 m in length can obtain full advance using multiple small diameter
empty holes - longer raises require a large uncharged hole to achieve the same levels of advance on a
routine basis
• studies at INCO indicate that a 200 MS delay per m of raise are required between the
detonation of the first and second blasthole with a raise (a 15 m raise requires around a 3000 MS
delay between the first and second detonating blastholes)
• using multiple decks of explosive columns should not be used - sympathetic propagation deck
to deck has been shown to occur in many instances
Borehole Deviation
Borehole deviation can be attributed to collaring, set - up and bending errors. If collaring error can be
eliminated then deviation can be represented by the following equation;
where:
length of the blasthole calculated in terms of blasthole
D =
diameters
The trajectory of a blasthole drilled in hard rock is represented by the figure shown here;
An extreme case of borehole deviation due to high pull down pressure mixed with bad geology and structure.
where:
L = length of raise in meters
Relief hole diameter is controlled by the length of advance rather than the cross-sectional area of the
raise. Longer raises require a greater void area and typically larger blasthole diameters to maintain
drilling accuracy.
where:
linear charge concentration per meter of blasthole
Q =
(kg/m)
distance between the empty relief hole and the
V =
blasthole in meters
Ø = diameter of the uncharged relief hole in meters
The above equation holds according to Helig for borehole diameters up to 32 mm.