Answer :
Project System is a Project management tool from SAP. Which has a very good integration
with the other modules of SAP like FI, CO, MM, SD, PP, HR, DMS. This module basically
co-ordinates and controls all the phases of a project, in direct co-ordination with purchasing
and controlling, from quotation to design and approval, to resource management and cost
settlement. Also beside the integration with the SAP module this Project system also has an
integration with the third party popular Project management tools like Microsoft Projects and
Primavera.
2. Question 2. Define Project Definition?
Answer :
Project definition is a binding framework in SAP for all organizational element created within
a project (e.g. WBS and Networks). Data like company code, plant and person responsible
can be defaulted into WBS if initially entered in the project definition. Such data can also be
defaulted into the project definition via project profile which will then default it to subsequent
WBS.
SAP PM Tutorial
11. Question 11. What Do Activities, Ntw, Wbs Represents?
Answer :
WBS and Networks are two structures that differ in the way in which they enable you to
structure projects and in the functions provided for them in the SAP system. For example, if
you need a hierarchical budget management function for a project, you would want to use a
WBS structure. If, in addition, you also want to do capacity planning, you would have to use
one or several networks as well. Depending on the specific requirements you may be able to
map a project only via a WBS structure, or by using only one or several networks, or a
combination of both.
SAP MM Tutorial
14. Question 14. What Is The Impact Of Coding Mask On The Project And Where Is It
Created (menu Path) ?
Answer :
Coding masks contain the sections for the external identification of projects, and they are
separated by special characters. A section consists either of numbers that are represented by
“0” characters in the coding mask, or alphanumeric characters that are represented by “X”
characters in the mask. You can store a descriptive text for each coding mask and use lock
indicators to control whether the key and the associated mask can be used for operative or
standard WBS structures. Project System >>> Structures >>> Operative Structures >>> Work
Breakdown Structures >>> Project Coding Mask >>> Define Project Coding Mask
Transaction is OPSJ .
15. Question 15. How To Set Field Status Of Wbs As Mandatory, (wbs Element, And Ntw) ?
Answer :
There are five different transactions. Project Definition, WBS Elements, Network Header,
Networks Overview and Network Details. There you will see a table with radio buttons that
indicate whether a field should be set as Input, Required (mandatory), Display, Hide. You can
also define Influence Fields and Field Groups. For Project Definition and WBS Elements:
Project System >>> Structures >>> Operative Structures >>> Work Breakdown Structures
>>> User Interface Settings >>> Define Field Selection for Work Breakdown Structures
Transactions are OPUK (Project Definition), OPUJ (WBS Elements) For Networks: Project
System >>> Structures >>> Operative Structures >>> Network >>> User Interface Settings
>>> Define Field Selection for Networks Transactions are OPUA (Header), OPUB
(Overview), OPUC (Details).
SAP PI Tutorial
23. Question 23. What Is The Organizational Structure Of Ps Module?
Answer :
PS structure consists of Project Definition, WBS Elements and Networks. PS uses structures
from FI/CO, MM, SD, etc. There is no structure of PS but the one provided above.
SAP PS Tutorial
26. Question 26. Can Revenues Be Linked With Activities?
Answer :
No, it can be done at WBS level with 'Billing' operative indicator.
27. Question 27. Can Progress Be Updated In Wbs Elements?
Answer :
Yes, You can use Progress Analysis (EVA) for this.
There are several parameters to define in here at the structures level. First, its the Project
Definition (Proj. Profile), then we have the WBS Level, and then, if used, the
Network/Activity/Subactivity Level. You may include components and services. The
configuration goes into Proj. Definition, WBS and Activity profiles.
2. What is the accounting and Logistical information that gets defined with a Project
Definition?
In the Project Profile, you define the Controlling area, Company Code, Business Area, Plant,
Functional Area, Profit Center and Project Currency for the project. If it is a sales project, you
can also define Sales Organization, Distribution Channel, Division and DIP Profile. In addition,
you also define the Object Class, Planning Profile, Budget Profile, Costing Sheet, Interest
Profile, Investment Profile (CAPEX), Result Analysis Key (CO-PA), Settlement Profile and
Settlement Rule Strategy. You will also define whether costs are actual or statistical. This
information is then copied to lower level WBS elements.
4. What is the menu path & T. Code for defining special characters for Projects?
Project System >>> Structures >>> Operative Structures >>> Work Breakdown Structures >>>
Project Coding Mask >>> Define Special Characters for Projects Transaction is OPSK
Maintenance order.
6. What is the impact of coding mask on the project and where is it created (menu path)?
Coding masks contain the sections for the external identification of projects, and they are
separated by special characters. A section consists either of numbers that are represented by "0"
characters in the coding mask, or alphanumeric characters that are represented by "X" characters
in the mask. You can store a descriptive text for each coding mask and use lock indicators to
control whether the key and the associated mask can be used for operative or standard WBS
structures.
Project System >>> Structures >>> Operative Structures >>> Work Breakdown Structures >>>
Project Coding Mask >>> Define Project Coding Mask
Transaction is OPSJ
There are five different transactions. Project Definition, WBS Elements, Network Header,
Networks Overview and Network Details. There you will see a table with radiobuttons that
indicate whether a field should be set as Input, Required (mandatory), Display, Hide. You can
also define Influence Fields and Field Groups.
Project System >>> Structures >>> Operative Structures >>> Work Breakdown Structures >>>
User Interfase Settings >>> Define Field Selection for Work Breakdown Structures
Project System >>> Structures >>> Operative Structures >>> Network >>> User Interfase
Settings >>> Define Field Selection for Networks
Substitution enables to automatically change master data fields of Project Definitions, WBS
Elements, Network Headers and Activities. For example, you can automatically set the cost
center 9999 for those WBS Elements into which responsible persons with number 0 to 20 have
been entered.
Validation enables you carry out self-defined checks for master data fields of the same elements.
But the result of validations consists of informational messages, warnings or error messages. For
example, you can validate that projects with a specific project profile always begin with the same
key.
This profile is part of the "Planning Board Profile" and it determines the begginning and the end
of the evaluation and planning periods. This means that preevaluation and post evaluation
periods are defined automatically. This is how the Planning Board is displayed graphically.
Evaluation period is the period in which you want to control your project, and it will be
displayed in your planning board. Dont get confused with scheduling, which is how time is
managed in a project.
Project System >>> Structures >>> Project Planning Board >>> Define Time Profiles
Transactions is OPTY
There are two, but you can define your own. SAPPS_Z001 and SAPPS_Z002.
12. What is value categories required for? Where are they maintained?
14. How to create and change planning profile? What is the Menu path?
15. How and where do you control the budget for the project & what is the menu path?
Through the Budget Profile, in transaction OPS9. Path is:
Project System >>> Costs >>> Budget >>> Maintain Budget Profile
Among other things, you will have to define the Time Frame (Annual or Total), Exchange Rate
type, whether or not Availability Control will be used, and the Budgeting Currency. There are
additional settings in that path, such as defining a Budget Profile for a Project Definition among
others.
16. How do you control that the project does not run over allocated budget?
You use Availability Control by defining tolerance limits, which will allow you to define by how
much you can overspend. For example, you can set the system to send you a message wuen 95%
of the budget has been spent, and stop al PR�s when you have reached 100% or 110% of the
budget. Path is Project System >>> Costs >>> Budget >>> Maintain Budget Profile >>> Define
Tolerance Limits
17. What does project version do? How do you define the project version (menu path)?
18. What governs the way scheduling is to be performed? What is the menu path?
19. What setting does NTW scheduling contains? Where are these settings done (menu
path)?
Control Key in transaction OPSU defines whether an activity can be confirmed, scheduled,
capacity requirements determinarion, costs, etc. Other important settings include Network Types,
Parameters for Network Types, Network Profiles and Control Keys.
Project System >>> Structures >>> Operative Structures >>> Network >>> Settings for
Networks
Project System >>> Structures >>> Operative Structures >>> Network >>> Settings for Network
Activities
PS structure consists of Project Definition, WBS Elements and Networks. PS uses structures
from FI/CO, MM, SD, etc. There is no structure of PS but the one provided above.
Project System is one of the key modules of SAP to perform project and portfolio management and
helps you to manage the project life cycle starting from structure, to plan, execution and till the
project completion.
IS PROJECT SYSTEM INTEGRATED WITH OTHER MODULES OF SAP ECC?
Project system is closely integrated with other SAP modules like logistics, material management,
Sales and Distribution, Plant Maintenance, and Production planning module.
FOR RAISING CLIENT BILLING, IS THERE ANY POSSIBILITY OF LINKING LINE ITEMS IN SD
MODULE WITH ACTIVITIES / WBS IN PS MODULE?
It can be linked through DIP Profile and do Resource Related Billing for raising billing.
CAN REVENUES BE LINKED WITH ACTIVITIES?
Instead of this, you can use costing variant for Easy Cost Planning (not for the activities)
IS THERE ANY WAY BY WHICH WE CAN LOCK TWO SPECIFIC WBS ELEMENTS SAY OVERHEADS AND
OTHER EXPENSES, SO THAT THE USER CANNOT RELEASE PR?
The easiest way would be to define the project release process in the bottom-up fashion. That means,
you will only release the activities/WBS elements that you need from time to time during the course
of the project. That way, charges won’t be accrued on a WBS element until it’s released (so, don’t
release it until it’s ready for collecting costs).
IS THERE ANY WAY BY WHICH WE CAN STOP THE NETWORK FROM ATTACHING FURTHER
MATERIALS AFTER IT IS RELEASED?
This is controlled through the change profile, which is assigned to the network profile. In the change
profile, under the Component tab, you can define the release status of the activity at which you can
create/change/delete material components.
HOW CAN WE SET THE OPTIONS FOR CAPACITY REPORTS CM01?
This will possible depend on your config, but the options I use are:
Settings>General>
Tick, Cumulation of reqmts, Dyn. capacity cumul. and then select the hierarchy you have set up.
I then select the financial year (as we are budget driven) using Entry type A and the start/finish of the
financial year.
I select period Month.
Then click tick.
I then select the work centre I require. or arm of the hierarchy.
You can then select standard overview and also select graphs or if you need a detailed list press that
button.
WHAT IS AN EXTERNAL AND AN INTERNAL PROJECT IN TERMS OF PROJECT BUDGET?
You can categorize projects according to the list of activities and project structure or on the basis of
individual activities −
In Project System, Work Breakdown structure WBS and network diagram can be used to structure
the project either in hierarchical order or using network techniques. You can define key milestones
and documents that allow you to monitor the progress of project and helps you to define key interest
of individuals.
WHAT ARE THE DIFFERENT STEPS INVOLVED IN PROJECT PROCESS FLOW?
Create Templates/WBS
Create Project
Project Planning
Budgeting and Release
Project Implementation
Project Completion
WHAT ACTIVITIES OF SAP FICO IS INTEGRATED WITH SAP PROJECT SYSTEM MODULE?
To plan the costs and revenue in the project system, as per the financial planning requirements.
WHAT ACTIVITIES OF SAP MM IS INTEGRATED WITH SAP PROJECT SYSTEM MODULE?
To manage the sales process in project lifecycle- includes quotations for customer projects. This
includes billing, selling and shipping of goods and services required in project lifecycle.
WHAT ACTIVITIES OF SAP PP IS INTEGRATED WITH SAP PROJECT SYSTEM MODULE?
To perform activities like material requirement planning MRP, Bills of material BOM, material
requisition as per MRP, capacity planning and other production planning tasks in project lifecycle.
EXPLAIN ORGANIZATION STRUCTURE AND ELEMENTS IN SAP PROJECT SYSTEM?
When a project is initiated, it starts with the definition and classification of the project structure
which is required to align it with the existing enterprise structure in an organization.
Project System has no organizational structures of its own and we have to incorporate the structure to
enterprise structure by assigning organization elements in different ERP R/3 modules. These
organization elements allow Project system to maintain and get the data correctly.
An Organization structure consists of various elements that have to be created as part of structuring
of project. Following are the organization elements −
Company Code
Business Area
Controlling Area
Plant
WHAT IS COMPANY CODE?
Company code is smallest unit in an organization for which financial statements (profit-loss
statement, etc.) can be generated.
What do you understand by Business Areas? Explain with the example of use?
Business Arears are used to differentiate transactions that come from different line of business in a
company.
Example −
There is a big company XYZ, which runs multiple businesses. Let us say it has 3 different domains
like manufacturing, marketing and sales.
You can use these business areas if other company codes require the same areas.
It is easy to configure if you use Business Area as you just need to attach to the company code and
the other details in business area will get attach itself.
By using Business areas in controlling, you can create Profit and loss statement, Balance sheet, etc.
for business areas so this is used for management accounting in few companies.
Note − Business areas are more used in Controlling as compare to Finance Accounting.
WHAT IS CONTROLLING AREA IN SAP SYSTEM?
Plant is an organizational unit within a company where activities take place. A plant will produce
goods and makes goods available for the company.
WHAT ARE THE DIFFERENT CURRENCY TYPE IN SAP PS SYSTEM?
In SAP PS system, you can manage all the currency dependent data in the Project System using
below different currencies.
Object Currency −
In Project system, it is also possible to assign any object currency to different objects in the system.
WBS element
Project definition
Network header
Network activity
Note that when a company code is assigned to a controlling area and company code contains multiple
currencies in this case you can’t allocate object currency in PS as in this case system automatically
takes the local currency of company code.
Transaction Currency −
In this case, you use the costs and revenues from different business transactions are recorded as per
currency of the business transaction.
HOW DO YOU DEFINE A PROJECT?
Projects has a defined goal which is agreed between company and customer and is defined in Project
Charter.
A Project is complex, unique, and definitive in scope and involves a high certain risk to execute and
complete on time.
Project has defined quality requirements.
Project has definitive cost, duration and resources to work on the project.
WHAT IS THE USE OF DEFINING PS TYPES IN PROJECT DEFINITION?
A Project type is used to group or classify the projects as required- Example: Banking projects
Capital projects or IT development projects.
A Project type is also used for reporting, building authorization and for creating hierarchies and
network in project planning. It can also be used for developing customer requirements e.g. use of
BADI for WBS settlement rule determination based on project type as a parameter.
WHAT IS THE USE OF STATUS PROFILE?
A status profile contains the individual user statuses and the business transaction rules defined for
those statuses. You can define multiple limit number of user status profiles that can be maintained in
SAP system.
WHAT IS THE USE OF SELECTION PROFILE IN SAP PS SYSTEM?
A Selection profile in SAP Project system is used when you have large number of selection objects
repeatedly with same selection condition. Selection condition are used using top down approach.
WHAT ARE THE PARAMETERS OF PROJECT SYSTEM?
There are several parameters to define in here at the structures level. First is the Project Definition
(Proj. Profile), then we have the WBS Level, and then, if used, the Network/Activity/Subactivity
Level. You may include components and services. The configuration goes into Proj. Definition, WBS
and Activity profiles.
WHAT IS THE DIFFERENCE BETWEEN A WBS AND NETWORK STRUCTURE?
WBS and Networks are two structures that differ in the way in which they enable you to structure
projects and in the functions provided for them in the SAP system. For example, if you need a
hierarchical budget management function for a project, you would want to use a WBS structure. If, in
addition, you also want to do capacity planning, you would have to use one or several networks as
well. Depending on the specific requirements you may be able to map a project only via a WBS
structure, or by using only one or several networks, or a combination of both.
WHAT DO YOU UNDERSTAND BY PROJECT PROFILE?
A Project profile is defined to maintain default values and control parameters like planning methods
for costs. The information entered in project profile is copied to project in project definition or also in
the project elements. These information can be changed at later stage.
WHAT INFORMATION IS MAINTAINED UNDER PROJECT PROFILE?
Basic data
Time scheduling
Costs/revenues/finances
Organizational data
WHAT IS THE USE OF SETTLEMENT PROFILE?
In a project, you collect cost and revenues temporarily and they have to settle as part of period end
processing. You need a settlement profile stored in project profile or network type which determines
whether settlement is required, allowed or blocked.
You use the settlement profile to define the following for actual costs −
Full Settlement
Can be settled
Not to be settled
WHAT IS THE USE OF NETWORK PROFILE?
You can create network profile in SAP PS to maintain Network and WBS structure and to define
rules for linking networks.
WHAT IS NETWORK TYPE IN SAP PS SYSTEM?
In SAP PS system, a network type is used to contain the information for controlling and managing
networks. Network is defined as work order that has a structure in common with production,
maintenance and inspection orders.
WHAT DO TIME PROFILES DO?
This profile is part of the “Planning Board Profile” and it determines the beginning and the end of the
evaluation and planning periods. This means that pre evaluation and post evaluation periods are
defined automatically. This is how the Planning Board is displayed graphically.
HOW DO YOU SPECIFY A PERSON RESPONSIBLE FOR WORK CENTER IN PS SYSTEM?
In SAP Project System, you can define the person responsible for Work Center. To define a person
responsible you need to enter person responsible Id and descriptive name of person responsible for
managing work center.
To specify a person responsible for work center, navigate to below path in SAP Easy access.
SPRO → IMG → Project System → Structures → Operative structure → Network → Work Center
→ Specify person responsible for work center.
WHERE DO WE DEFINE TIME PROFILES? WHAT IS EVALUATION PERIOD?
Evaluation period is the period in which you want to control your project, and it will be displayed in
your planning board.
Transactions is OPTY
WHAT IS THE USE OF ACCESS CONTROL LIST?
In SAP Project system, you use access control list to assign authorizations for specific Project system
objects. Access control list function should be activated in project profile or network profile.