SUB HEAD : 6.

BRICK WORK

Brick work with F.P.S. bricks of class designation 75 in


201 6.1 foundation and plinth in:
6.1.1 Cement mortar 1:4 (1 cement : 4 coarse sand)
Code Description Unit Quantity Rate Amount
Details of cost for 1 cum.
MATERIALS :
2602 Bricks of class designation 75 1000 Nos 494 1 900.00 938.6
Cement mortar 1:4 (Rate as per item No. 3.9) cum .25 2 578.45 644.61
2201 Carriage of bricks 1000 Nos 494 141.88 70.09
9999 Sundries L.S. 2.73 1. 2.73
LABOUR:
123 Mason 1st Class Day .36 151.5 54.54
124 Mason Ilnd Class Day .36 141.6 50.98
115 Coolie Day 1.37 135.25 185.29
101 Bhishti Day .2 138.45 27.69
TOTAL Day 1,974.53
Add 1% for water charges 19.75
TOTAL 1,994.28
Add for contractor’s profit and overheads @15% 299.14
Cost of 1 Cum. 2,293.42
Say 2,293.4

Brick work with F.P.S. bricks of class designation 75 in


6.1 foundation and plinth in:
6.1.2 Cement mortar 1:6 (1 cement : 6 coarse sand)
Code Description Unit Quantity Rate Amount
Details of cost for 1 cum.
MATERIALS :
2602 Bricks of class designation 75 1000 Nos 4.94 1 900.00 938.6
Cement mortar 1:6 (Rate as per item No. 3.11) cum .25 1 987.30 496.82
2201 Carriage of bricks 1000 Nos 4.94 141.88 70.09
9999 Sundries L.S. 2.73 1. 2.73
LABOUR:
123 Mason 1st Class Day .36 151.5 54.54
124 Mason Ilnd Class Day .36 141.6 50.98
115 Coolie Day 1.37 135.25 185.29
101 Bhishti Day .2 138.45 27.69
TOTAL 1,826.74
Add 1% for water charges 18.27
TOTAL 1,845.01
Add for contractor’s profit and overheads @15% 276.75
Cost of 1 Cum. 2,121.76
Say 2,121.75

Brick work with modular bricks of class designation 75


6.2 in foundation and plinth in:
6.2.1 Cement mortar 1:4 (1 cement : 4 coarse sand)
Code Description Unit Quantity Rate Amount
Details of cost for 1 cum.
MATERIALS :
7900 Modular bricks of class designation 75 1000 Nos 487 2 050.00 998.35
2201 Carriage of bricks 1000 Nos 487 141.88 69.1
Cement mortar 1 :4 (1 cement : 4 coarse sand) cum .22 2 578.45 567.26
(Rates as per item no. 3.9)
202 9999 Sundries L.S. 2.73 1. 2.73
LABOUR:
123 Mason 1st Class Day .33 151.5 50.
124 Mason Ilnd Class Day .33 141.6 46.73
115 Coolie Day 1. 135.25 135.25
101 Bhishti Day .18 138.45 24.92
TOTAL 1,894.34
Add 1% for water charges 18.94
TOTAL 1,913.28
Add for contractor’s profit and overheads @15% 286.99
Cost of 1 Cum. 2,200.25
Say

Brick work with modular bricks of class designation 75


6.2 in foundation and plinth in:
6.2.2 Cement Mortar 1:6 (1 cement : 6 coarse sand).
Code Description Unit Quantity Rate Amount
Details of cost for 1 cum.
MATERIALS :
7900 Modular bricks of class designation 75 1000 Nos 487 2 050.00 998.35
2201 Carriage of Bricks 1000 Nos 487 141.88 69.1
Cement mortar 1 :6 (1 cement : 6 coarse sand) cum .22 1,987.3 437.21
(Rates as per item no. 3.11)
9999 Sundries L.S. 2.73 1. 2.73
LABOUR:
123 Mason 1st Class Day .33 151.5 50.
124 Mason Ilnd Class Day .33 141.6 46.73
115 Coolie Day 1. 135.25 135.25
101 Bhishti Day .18 138.45 24.92
TOTAL 1 1,764.29
Add 1% for water charges 17.64
TOTAL 1,781.93
Add for contractor’s profit and overheads @15% 267.29
Cost of 1 Cum. 2,049.22
Say 2,049.2

Brick work with machine moulded perforated bricks of


class designation 125 conforming to IS: 2222 -1991 in
superstructure above plinth level upto floor five level in
cement mortar 1:6 (1 cement : 6 coarse sand) :
6.3
6.3.1 With F.P.S. bricks.
Code Description Unit Quantity Rate Amount
Details of cost for 1 cum.
MATERIALS :
7901 Machine moulded perforated FPS bricks of 1000 Nos 494 3 233.00 1 597.10
class designation 125
2201 Carriage of Bricks 1000 Nos 494 141.88 70.09
Cement mortar 1:6(1 cement: 6 coarse sand). Cum .25 1 987.30 496.82
(Rates as per item no. 3.11)
9999 Sundries L.S 2.73 1. 2.73
LABOUR:
203 123 Mason 1st Class Day .47 151.5 71.2
124 Mason Ilnd Class Day .47 141.6 66.55
115 Coolie Day 1.8 135.25 243.45
101 Bhishti Day .2 138.45 27.69
9999 Scaffolding L.S 22.36 1. 22.36
Extra labour element required for lifting of
materials (above floor two level upto floor
five level)
115 Coolie Day 1.13 135.25 152.83
TOTAL 2,750.82
Add 1 % for water charges 27.51
TOTAL 2,778.33
Add for contractor’s profit and overheads @15% 416.75
Cost of 1 Cum. Say 3,195.08
Say 3,195.1

Brick work with machine moulded perforated bricks of


class designation 125 conforming to IS: 2222 -1991 in
superstructure above plinth level upto floor five level in
cement mortar 1:6 (1 cement : 6 coarse sand) :
6.3
6.3.2 With Modular bricks.
Code Description Unit Quantity Rate Amount
Details of cost for 1 cum.
MATERIALS :
7902 Machine moulded perforated FPS bricks of 1000 Nos 487 3 200.00 1 558.40
class designation 125
2201 Carriage of Bricks 1000 Nos 487 141.88 69.1
Cement mortar 1:6(1 cement: 6 coarse sand). Cum .22 1 987.30 437.21
(Rates as per item no. 3.11)
9999 Sundries L.S 2.73 1. 2.73
LABOUR:
123 Mason 1st Class Day .44 151.5 66.66
124 Mason Ilnd Class Day .44 141.6 62.3
115 Coolie Day 1.43 135.25 193.41
101 Bhishti Day .18 138.45 24.92
9999 Scaffolding L.S 16.38 1. 16.38
Extra labour element required for lifting of
materials (above floor two level upto floor five level)
115 Coolie Day 1.13 135.25 152.83
TOTAL 2,583.94
Add 1 % for water charges 25.84
TOTAL 2,609.78
Add for contractor’s profit and overheads @15% 391.47
Cost of 1 Cum. Say 3,001.25
Say 3,001.25

Brick work with F.P.S. bricks of class designation 75 in


superstructure above plinth level upto floor V level in all
204 6.4 shapes and sizes in :
6.4.1 Cement mortar 1:4 (1 cement : 4 coarse sand)
Code Description Unit Quantity Rate Amount
Details of cost for 1 cum.
MATERIALS :
2602 Bricks of class designation 75 1000 494 1,900. 938.6
Nos
Cement mortar 1:4 (Rate as per item no 3.9) Cum .25 2,578.45 644.61
2201 Carriage of bricks 1000 494 141.88 70.09
Nos
Sundries L.S 2.73 1. 2.73
LABOUR:
123 Mason 1 st Class Day .47 151.5 71.21
124 Mason Ilnd Class Day .47 141.6 66.55
115 Coolie Day 1.8 135.25 243.45
101 Bhishti Day .2 138.45 27.69
9999 Scaffolding L.S 22.36 1. 22.36
Extra labour element required for lifting of
materials (above floor two level upto floor
five level)
115 Coolie Day 1.13 135.25 152.83
TOTAL 2,240.12
Add for water charges @ 1% 22.4
TOTAL 2,262.52
Add for contractor’s profit and over-heads @15% 339.83
Cost of 1 cum. 2,601.9
Say 2,601.9

Brick work with F.P.S. bricks of class designation 75 in


superstructure above plinth level upto floor V level in all
6.4 shapes and sizes in :
6.4.2 Cement mortar 1:6 (1 cement : 6 coarse sand)
Code Discription Unit Quantity Rate Amount
Details of cost for 1 cum.
MATERIALS :
2602 Bricks of class designation 75 Nos 494 1,900. 938.6
Cement mortar 1:6 (Rate as per item no 3.11) Cum .25 1,987.3 496.02
2201 Carriage of bricks 1000 Nos 494 141.88 70.09
Sundries L.S 2.73 1. 2.73
LABOUR:
123 Mason 1 st Class Day .47 151.5 71.21
124 Mason Ilnd Class Day .47 141.6 66.55
115 Coolie Day 1.8 135.25 243.45
101 Bhishti Day .2 138.45 27.69
9999 Scaffolding L.S 22.36 1. 22.36
Extra labour element required for lifting of
materials (above floor two level upto floor
five level)
115 Coolie Day 1.13 135.25 152.83
TOTAL 2,092.63
Add for water charges @ 1% 20.93
TOTAL 2,113.56
Add for contractor’s profit and over-heads @15% 317.03
Cost of 1 cum. 2,463.59
Say 2,463.6

Extra for brick work in superstructure above floor V


level for each four floors or part thereof by mechanical
means by lifting material using mobile crane .
205 6.5
Code Description Unit Quantity Rate Amount
Details of cost for 5.3 cum per four floors .
37 Mobile crane. per day .125 5,000. 625.
Fuel consumption per hour = 8 litre.
1235 Diesel oil litre 8. 30.25 242.
TOTAL 867.
Add 1 % for water charges 8.67
TOTAL 875.67
Add for contractor’s profit and overheads @ 15% 131.35
Cost of 5.3 Cum. 1 007.02
Cost for 1 cum 190.
Say 190.
Extra for forming cavity 5cm to 7.5cm wide in cavity
walls with necessary weep and vent holes including use
of cores and cost of providing and fixing bitumastic
coated M .S. ties 300mm long of 25x3mm section at not
less than 3 ties per sum as per approved design.
6.6
Code Description Unit Quantity Rate Amount
Details of cost for 10sqm.
Materials :
1008 Mild steel 25mmx3mm section 30cm long 30 quintal .054 2 900.00 156.6
No. = 9 metres @ 0.6kg/m = 5.40 kg.
9999 Painting the steel Bitumen L.S 13.52 1. 13.52
2205 Carriage of mild steel tonne .005 47.29 .24
Extra labour for keeping cavity clear and
fixing wall ties and delay caused:
123 Mason 1st class Day .37 151.5 56.06
124 Mason 2nd Class Day .37 141.6 52.39
114 Beldar Day .92 135.25 124.43
9999 Add for use of Core L.S 4.55 1. 4.55
TOTAL 407.79
Add 1 % for water charges 1 4.08
TOTAL 411.87
Add for contractor’s profit and overheads @15% 61.78
Cost for 10 sqm. 473.65
Cost for 1 sqm. 47.37
Say 47.35

Providing half brick masonry with F.P.S. bricks of class


designation 75 in cement mortar 1:3 (1 Cement : 3 coarse
sand) in superstructure for closing cavity 5 to 7.5 cm
wide in cavity wall complete with 10 cm / 11.4 cm wide
bitumen felt type 3 grade 1.
6.7
Code Description Unit Quantity Rate Amount
Details of cost for 10m length
Materials :
Half brick masonry 1:3 (Average)
1x10x0.27 = 2.7
206 Rate as per item No.6.12.1 sqm 2.7 289.6 781.92
Bitumen felt type- 3 grade 1
lxl0mx11.4m =1.14 sqm.
Add for wastage and overlapping @ 5% =
0.06 sqm.
0322 (B) Total= 1.20 sqm. sqm 1.2 45. 54.
Labour:
0123 (B) Mason 1st class Day .12 151.5 18.18
0124 (B) Mason 2nd class Day .12 141.6 16.99
0114 (B) Beldar Day .06 135.25 8.12
TOTAL 879.21
(C) Add for water charges @ 1 % on B .97
TOTAL 880.18
Add for contractor’s profit and overheads at 14.74
15% on (B+C)
Cost of 10 metre 894.92
Cost for 1 metre 89.49
Say 89.5
Brick work 7 cm thick with F.P.S. brick of class
designation 75 in cement mortar 1:3 (1 cement : 3 coarse
6.8 sand) in superstructure.
Code Description Unit Quantity Rate Amount
Details of cost for 10sqm.
Materials:
2602 Bricks of class designation 75 1 000 Nos 377. 1 900.00 716.3
Cement mortar 1:3 (Rate as per item no. 3.8 ) cum .181 3 169.60 573.7
2201 Carriage of bricks 1 000 Nos 377. 141.88 53.49
LABOUR:
123 Mason 1st class Day .72 151.5 109.08
124 Mason 2nd class Day .72 141.6 101.95
115 Coolie Day 1.76 135.25 238.04
101 Bhishti Day .36 138.45 49.84
9999 Sundries and scaffolding L.S. 7.15 1. 7.15
TOTAL 1 849.55
Add 1 % for water charges 18.5
TOTAL 1 868.05
Add for contractor’s profit and overheads @15% 280.21
Cost for 10 sqm. 214.83
Cost for 1 sqm. 214.85
Say

Brick work in plain arches in superstructure including


centring and shuttering complete for span upto 6 metres
with F.P.S. brick of class designation 75 in cement
mortar 1:3 (1 cement : 3 coarse sand).
6.9
Code Description Unit Quantity Rate Amount
Details of cost for 1 cum.
Materials :
2602 Bricks of class designation 75 1 000 Nos 494 1 900.00 938.6
Cement mortar 1:3 (Rate as per item no. 3.8) cum .25 3 169.60 792.4
2201 Carriage of bricks 1 000 Nos 494 141.88 70.09
207 9999 Sundries L.S 2.73 1. 2.73
Centering and Shuttering:
Taking a semi circular arch 3.6m span,
3.6m long and 0.40m thick
Area of centering =
3.142 x 1.8 x 3.6 = 20.37 sqm.
Brick work in Arch.
3.142x2.00x0.4x3.6 = 9.05cum.
Area per cum.
(B) 20.37/9.05 = 2.25 sqm. sqm 2.25 514.7 1,158.08
(Rate same as in item 5.9.9
9999 Scaffolding L.S 18.85 1. 18.85
Labour:
123 Mason 1st class Day .53 151.5 80.3
124 Mason 2nd class Day .53 141.6 75.05
115 Coolie Day 2.29 135.25 309.72
101 Bhishti Day .2 138.45 27.69
TOTAL 3,473.51
Add for water charges @ 1% on all except B 23.15
TOTAL 3,496.66
Add for contractor’s profit and overheads at 350.79
15% on all except B
Cost for 1 cum. 3,847.45
Say 3,847.45
Brick work in gauged arches in superstructure in cement
mortar 1:3 (1 cement : 3 coarse sand) including centring
and shuttering complete, for span upto 6 meters with
F.P.S. brick of class designation 75.
6.1
Code Description Unit Quantity Rate Amount
Details of cost for 1 cum.
Materials :
2602 Bricks of class designation 75 1 000 Nos 538. 1 900.00 1 022.20
Cement mortar 1:3 (Rate as per item no. 3.8) cum .25 3 169.60 792.4
2201 Carriage of bricks 1 000 Nos 538. 141.88 76.33
9999 Sundries L.S 2.73 1. 2.73
Centring and shuttering (Area same as in item
No. 6.9
9999 (B) (Rate same as per item No. 5.9.9 sqm 2.25 514.7 1 158.08
Scaffolding L.S. 18.85 1. 18.85
LABOUR:
123 Mason 1 st class Day 1.13 151.5 171.2
124 Mason 2nd class Day 1.13 141.6 160.01
115 Coolie Day 4.42 135.25 597.8
101 Bhishti Day .2 138.45 27.69
TOTAL 4,027.29
Add for water charges @ 1% on all except B 28.69
TOTAL 4,055.98
Add for contractor’s profit and overheads at 434.68
15%on all except B
Cost for 1 cum. 4,490.66
Say 4,490.65

Extra for additional cost of centring for arches exceeding


6m span including all shuttering, bolting, wedging and
removal (Area of the soffit to be measured).
208 6.11
Code Description Unit Quantity Rate Amount
Details of cost per sqm.
Centering and shuttering for arches and carved
surface exceeding 6m in span (an average of
8m)
Radius R = 5m 2R-2=4+4
tan (4/3)=53.28°
2x53.28°=106°
Surface area
=2x22/7x5x3.6x106/360=33.3 sqm.
Arc=9.25m
Material:
Tie-2x8x0.18x0.05 =0.144cum
Struts-2x2.5x0.1x0.1 =0.050cum.
Struts-2x1.77x0.1x0.1 =0.035cum.
Ribs-6x1.54x0.23x0.1 =0.213cum.
Struts-2x1.72x0.1x0.1 =0.034cum.
Total=0.476cum.
For four such frames =0.476x4= 1.904 cum.
laggings-75x3.6x0.125x0.075=2.531 cum.
Tie-2x3.6x0.225x0.038=0.062cum.
Brace-3x2x2.14x0.225x0.038=0.110
Brace-3x4x3.8x0.225x0.038=0.390
Sleepers-4x3.6x0.20x0.15=0.432
Sleepers-2x4x3.6x0.175x0.075=0.378
Vertical post-4x4x3.6x0.15x0.15=1.296
1197 Total =7.103cum.
Qty taken l/8th of qty for cost using once = 10 cum 887.9 160. 14,206.4
7.103/8 = 0.8885 cum (887.90 cudm)
2204 Carriage of wood cum .8879 60.81 53.99
Fittings:
3 way straps 50mmxl0mm = 32 Nos.
32 no. @0.50cm each = 16m
Straps-50mmx 10mm = 8 Nos. @0.25cm each
= 2m
Total = 18m
18m @ 3.9kg/m = 70.2 kg. = 0.702qtl.
Qty taken l/8th of qty for cost using once =
1225 0.702/8 = 0.0878 qtl. quintal .0878 2,900. 254.62
Bolts 160 Nos. 254 mm long 16mm dia.-
160x 0.254x 1.58=64.21 kg=0.64qtl.
Qty taken 1/8th of qty for cost using once =
1034 0.64/8 = 0.08 qtl. quintal .08 4,300. 344.
Carriage of steel = 0.1342 t
Qty taken 1/8th of qty for cost using once =
2302 0.1342/8 = 0.0168 tonne tonne .0168 47.29 .79
Labour:
112 Carpenter 2nd class Day 28. 141.6 3,964.8
114 Beldar Day 24. 135.25 3,246.
9999 Sundries L.S 134.55 1. 134.55
Less Cost of shuttering etc. for an arch
exceeding 6 m span i.e. for an average of 8 m
span
(A) Rate as per item no- 5.9.9 sqm 33.31 514.7 -17,144.66
TOTAL 5,060.49
Add 1% for water charges on all exept ‘A’ 222.05
TOTAL 5,282.54
209 Add for contractor’s profit and overheads @
15% on all except ‘A’ 3,364.08
Cost of 33.31 sqm. 8,646.62
Cost per sqm. 259.58
Say 259.6

Half brick masonry with F.P.S. brick of class


6.12 designation 75 in foundations and plinth in :
6.12.1 Cement mortar 1 : 3 (1 cement : 3 coarse sand)
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm.
Materials :
2602 Brick of class designation 75 1 000 Nos 565. 1 900.00 1 073.50
Cement mortar 1:3 (Rate as per item No. 3.8) cum .28 3 169.60 887.49
2201 Carriage of bricks 1 000 Nos 565. 141.88 80.16
9999 Sundries & Scaffolding L.S 13.52 1. 13.52
LABOUR:
123 Mason 1 st class Day .45 151.5 68.18
124 Mason 2nd class Day .45 141.6 63.72
115 Coolie Day 1.55 135.25 209.64
101 Bhishti Day .7 138.45 96.92
TOTAL 2 493.13
Add 1% for water charges 24.93
TOTAL 2 518.06
Add for contractor’s profit and overheads @15% 377.71
Cost for 10 sqm. 2 895.77
Cost for 1 sqm. 289.58
Say 289.6

Half brick masonry with F.P.S. brick of class


6.12 designation 75 in foundations and plinth in :
6.12.2 cement mortar 1:4 (1 cement : 4 coarse sand)
Code Discription Unit Quantity Rate Amount
Details of cost for 10 sqm.
Materials :
2602 Brick of class designation 75 1 000 Nos 565. 1 900.00 1 073.50
Cement mortar 1:3 (Rate as per item No. 3.9) cum .28 2,578.45 721.97
2201 Carriage of bricks 1 000 Nos 565. 141.88 80.16
9999 Sundries & Scaffolding L.S 13.52 1. 13.52
LABOUR:
123 Mason 1 st class Day .45 151.5 68.18
124 Mason 2nd class Day .45 141.6 63.72
115 Coolie Day 1.55 135.25 209.64
101 Bhishti Day .7 138.45 96.92
TOTAL 2 327.61
Add 1% for water charges 23.28
TOTAL 2 350.89
Add for contractor’s profit and overheads @15% 352.63
Cost for 10 sqm. 2 703.52
Cost for 1 sqm. 270.35
Say 270.35

Half brick masonry with F.P.S. bricks of class


designation 75 in superstructure above plinth level upto
210 6.13 floor V level.
6.13.1 Cement mortar 1:3 (1 cement :3 coarse sand)
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm.
Materials :
2602 Brick of class designation 75 1 000 Nos 565. 1 900.00 1 073.50
Cement mortar 1:3 (Rate as per item No. 3.8) cum .28 3,169.6 887.49
2201 Carriage of bricks 1 000 Nos 565. 141.88 80.16
9999 Sundries & Scaffolding Day 13.52 1. 13.52
LABOUR:
123 Mason 1st class Day .6 151.5 90.9
124 Mason 2nd class Day .6 141.6 84.96
115 Coolie Day 2. 135.25 270.5
101 Bhishti Day .7 138.45 96.92
Extra labour for lifting materials:
115 Coolie Day 1.29 135.25 174.47
10 x 0.115 x 0.75 x1.5
TOTAL 2 772.42
Add 1% for water charges 27.72
TOTAL 2 800.14
Add for contractor’s profit and overheads @15% 420.02
Cost for 10 sqm. 3 220.16
Cost for 1 sqm. 322.02
Say 322.

Half brick masonry with F.P.S. bricks of class


designation 75 in superstructure above plinth level upto
6.13 floor V level.
6.13.2 Cement mortar 1:4 (1 cement :4 coarse sand)
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm.
Materials :
2602 Brick of class designation 75 1 000 Nos 565. 1,900. 1,073.5
Cement mortar 1:4 (Rate as per item No. 3.9) cum .28 2,578.45 721.97
2201 Carriage of bricks 1 000 Nos 565. 141.88 80.16
9999 Sundries & Scaffolding Day 13.52 1. 13.52
LABOUR:
123 Mason 1st class Day .6 151.5 90.9
124 Mason 2nd class Day .6 141.6 84.96
115 Coolie Day 2. 135.25 270.5
101 Bhishti Day .7 138.45 96.92
Extra labour for lifting materials:
115 Coolie Day 1.29 135.25 174.47
10 x 0.115 x 0.75 x1.5
TOTAL 2,606.9
Add 1% for water charges 26.07
TOTAL 2,632.97
Add for contractor’s profit and overheads @15%
Cost for 10 sqm. 3,027.92
Cost for 1 sqm. 302.79
Say 302.8

Extra for half brick masonry in superstructure, above


floor V level for every four floors or part thereof by
mechanical means by lifting material using mobile crane.
211 6.14
Code Description Unit Quantity Rate Amount
Details of cost for 59.83 sqm per four floors
37 Mobile crane. per day .125 5,000. 625.
Fuel consumption per hour = 8 litre.
1235 Diesel oil litre 8. 30.25 242.
TOTAL 867.
Add 1% for water charges 8.67
TOTAL 875.67
Add for contractor’s profit and overheads @15% 131.35
Cost of 59.83 sqm. 1 007.02
Cost for 1 sqm 16.83
Say 16.85

Extra for providing and placing in position 2 Nos. 6mm


dia. M.S. bars at every third course of half brick
6.15 masonry (with F.P.S. bricks).
Code Description Unit Quantity Rate Amount
Details of cost for 10sqm.
1002 (a) 6mm dia. M.S. bars (round) 2 Nos. @ 30 quintal .132 3,100. 409.2
meter/10sqm. = 60 metre @ 0.22kg/m =13.2
kg-
2205 (B) Carriage of M.S. Bars tonne .0132 47.29 .62
9999 Sundries L.S. 1.82 1. 1.82
TOTAL 411.64
Add 1% for water charges 4.12
TOTAL 415.76
Add for contractor’s profit and overheads @15% 62.36
Cost for 10 sqm. 478.12
Cost for 1 sqm. 47.81
Say 47.8

Tile brick masonry with tile bricks of class designation


6.16 100 in foundation and plinth in:
6.16.1 Cement mortar 1 : 4 (1 cement : 4 coarse sand)
Code Description Unit Quantity Rate Amount
Details of cost for 1 cum.
Materials :
1984 Brick tiles of class designation 100 1000 Nos 777. 1,950. 1 515.15
Cement mortar 1:4(1 Cement: 4 coarse sand) cum .4 2,578.45 1 031.38
(Rate as per item no. 3.9)
2207 Carriage or brick tiles 1000 Nos 777. 85.13 66.15
9999 Sundries L.S. 4.55 1. 4.55
Labour:
123 Mason 1st class Day .7 151.5 106.05
124 Mason 2nd class Day .7 141.6 99.12
115 Coolie Day 1.54 135.25 208.28
101 Bhishti Day .2 138.45 27.69
TOTAL 3 058.37
Add 1 % for water charges 30.58
TOTAL 3 088.95
Add for contractor’s profit and overheads @15% 463.34
Cost for 1 cum. 3 552.29
Say 3,552.3

Tile brick masonry with tile bricks of class designation


212 6.16 100 in foundation and plinth in:
6.16.2 Cement mortar 1 : 6 (1 cement : 6 coarse sand)
Code Description Unit Quantity Rate Amount
Details of cost for 1 cum.
Materials :
1984 Brick tiles of class designation 100 1000 Nos 777. 1,950. 1 515.15
Cement mortar 1:6(Rate as per item no. 3.11) cum .4 2,578.45 794.92
2207 Carriage or brick tiles 1000 Nos 777. 85.13 66.15
9999 Sundries L.S. 4.55 1. 4.55
Labour:
123 Mason 1st class Day .7 151.5 106.05
124 Mason 2nd class Day .7 141.6 99.12
115 Coolie Day 1.54 135.25 208.28
101 Bhishti Day .2 138.45 27.69
TOTAL 2 821.91
Add 1 % for water charges 28.22
TOTAL 2 850.13
Add for contractor’s profit and overheads @15% 427.52
Cost for 1 cum. 3 277.65
Say 3 277.65

Tile brick masonry with machine moulded tile bricks of


class designation 125 conforming to IS : 2690 (Part I) -
1993 in foundation and plinth in cement mortar 1:6 (1
6.17 cement : 6 coarse sand).
Code Description Unit Quantity Rate Amount
Details of cost for 1 cum.
MATERIALS
7904 Machine moulded tile bricks of class 1000 Nos 777. 2 717.00 2,111.11
designation 125
2207 Carriage of Brick tiles 1000 Nos 777. 85.13 66.15
Cement mortar 1:6 (1 cement: 6 coarse sand). cum .4 1 987.30 794.92
(Rates as per item no. 3.11)
9999 Sundries L.S. 4.55 1. 4.55
LABOUR:
123 Mason 1st Class Day .7 151.5 106.05
124 Mason Ilnd Class Day .7 141.6 99.12
115 Coolie Day 1.54 135.25 208.28
101 Bhishti Day .2 138.45 27.69
TOTAL 3,417.87
Add 1% for water charges 34.18
TOTAL 3,452.05
Add for contractor’s profit and overheads @15% 517.81
Cost of 1 Cum. 3,969.86
Say 3,969.85
Tile brick masonry with tile bricks of class designation
100 (Part I) - 1993 in superstructure above plinth level
upto floor V level in Cement mortar 1:6 (1 cement : 6
213 6.18 coarse sand).
Code Discription Unit Quantity Rate Amount
Details of cost for 1 cum.
MATERIALS :
1984 Tile bricks of class designation 100 1000 777. 1,950. 1,515.15
Nos
2207 Carriage of Brick tiles 1000 777. 85.13 66.15
Nos
Cement mortar 1:6 (1 cement: 6 coarse cum .4 1,987.3 794.92
sand).(Rate as item no. 3.11)
9999 Sundries L.S. 4.55 1. 4.55
LABOUR:
123 Mason 1st Class Day .9 151.5 136.35
124 Mason Ilnd Class Day .9 141.6 127.44
115 Coolie Day 1.8 135.25 243.45
101 Bhishti Day .2 138.45 27.69
Extra labour for lifting of materials
115 Coolie Day 1.13 135.25 152.83
9999 Cost of scaffolding L.S. 33.8 1. 33.8
TOTAL 3,074.65
Add for water charges @ 1 % 30.75
TOTAL 3,105.39
Add for contractor’s profit and over-heads@15% 465.81
Cost of 1 cum. 3,571.2
Say 3,571.2

Extra for tile brick masonry with tile bricks of class


designation 100 in superstructure above floor five level
6.19 for every four floors or part thereof.
Code Discription Unit Quantity Rate Amount
Details of cost for 1 cum.
Extra labour element for lifting of materials
(upto floor V level)
0.75x2.00= 1.50
115 Coolie Day 1.5 135.25 202.88
TOTAL 202.88
Add 1% for water charges 2.03
TOTAL 204.91
Add for contractor’s profit and overheads @15% 30.74
Cost for 1 cum. 235.65
Say 235.65

Tile brick masonry with tile bricks of class designation


100 in plain arch work in superstructure in cement
mortar 1:4 (1 cement : 4 coarse sand) including centring
214 6.2 and shuttering complete.
Code Description Unit Quantity Rate Amount
Details of cost for 1 cum.
MATERIALS
1984 Tile bricks 1000 Nos 777. 1,950. 1,515.15
2207 Carriage of Brick tiles 1000 Nos 777. 85.13 66.15
Cement mortar 1:4 (Rate as per item no 3.9 ) cum .35 2,578.45 902.46
9999 Sundries L.S. 5.46 1. 5.46
Centering and shuttering
Area same as in item no 6.9 sqm 2.25 514.7 1,158.08
(A) Rate as per item no. 5.9.9
9999 Scaffolding L.S. 18.85 1. 18.85
Labour:
123 Mason 1st Class Day .79 151.5 119.68
124 Mason Ilnd Class Day .79 141.6 111.86
115 Coolie Day 3.21 135.25 434.15
101 Bhishti Day .2 138.45 27.69
TOTAL 4,359.53
Add 1% for water charges on all except A 32.01
TOTAL 4,391.54
Add for contractor’s profit and overheads @
15% on all except A 485.02
Cost of 1 Cum. 4,876.56
Say 4,876.55

Tile brick masonry with tile bricks of class designation


100 in gauged arch work in superstructure in cement
mortar 1:4 (1 cement : 4 coarse sand) including centring
and shuttering complete.
6.21
Code Description Unit Quantity Rate Amount
Details of cost for 1 cum.
MATERIALS
1984 Tile bricks 1000 Nos 791. 1,950. 1,542.45
2207 Carriage of tiles Brick 1000 Nos 791. 85.13 67.34
Cement mortar 1:4 (Rate as per item no 3.9 ) cum .35 2,578.45 902.46
9999 Sundries and shuttering L.S. 5.46 1. 5.46
Centering and shuttering
Area same as in item no 6.9
(A) Rate as per item no. 5.9.9 sqm 2.25 514.7 1,158.08
9999 Scaffolding L.S. 18.85 1. 18.85
Labour:
123 Mason 1st Class Day 1.5 151.5 227.25
124 Mason Ilnd Class Day 1.5 141.6 212.4
115 Coolie Day 5.33 135.25 720.88
101 Bhishti Day .2 138.45 27.69
TOTAL 4,882.86
Add for water charges @1% on all except ‘A’ 37.25
TOTAL 4,920.11
Add for contractor’s profit and overheads @ 564.3
15% on all except ‘A’
Cost of 1 Cum. 5,484.41
Say 5,484.4

Tile brick masonry work 5 cm thick with tile bricks of


class designation 100 in cement mortar 1:3 (1 cement : 3
215 6.22 coarse sand) in superstructure.
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm.
1984 Tile bricks (22.9cmx 11.2cmx5cm) 1000 Nos 377. 1,950. 735.15
2207 Carriage of tile bricks 1000 Nos 377. 85.13 32.09
Cement mortar 1:3 (Rate as per item no. 3.8) cum .15 3,169.6 475.44
9999 Sundries and scaffolding L.S. 8.06 1. 8.06
LABOUR:
123 Mason 1st class Day .94 151.5 142.41
124 Mason 2nd class Day .94 141.6 133.1
115 Coolie Day 1.88 135.25 254.27
101 Bhishti Day .33 138.45 45.69
TOTAL 1,826.21
Add 1% for water charges 18.26
TOTAL 1,844.47
Add 15% for contractor’s profit and overheads 276.67
Cost of 10 Sqm. 2,121.14
Cost per sqm. 212.11
Say 212.1

Honey-comb brick work 10/11.4 cm thick with bricks of


class designation 75 in cement mortar 1:4 (1 cement : 4
6.23 coarse sand).
Code Description Unit Quantity Rate Amount
Details of cost for 1sqm. of Honey comb
brick works-Materials :
(1) Brick work, with bricks of class
designation 75, in cement mortar 1:4 (1
Cement: 4 Coarse sand) in superstructure
1 m x 1 x 0.143 m x 4.5/7.5 = 0.069 cum cum .069 2,601.9 179.53
Rate as per item no 6.4.1
9999 (A) (2) Extra for delay due to fine work L.S 20.67 1. 20.67
TOTAL 200.2
(B) Add for water charges @ 1 % on ‘A’ .21
TOTAL 200.41
Add for contractor’s profit and overheads @ 3.13
15% on A+B
Cost for 1 sqm. 203.54
Say 203.55

Extra for laying brick work in or under water and/or


liquid mud including cost of pumping or bailing out
6.24 water and removing slush etc. complete.
Code Description Unit Quantity Rate Amount
Details of cost for depth of water 0.30m.
Quantity of concrete = 14 cum.
Pumping hours = 3 hrs. or 0.375 days.
11 Hire charge of pump set of capacity 4000 ltr/hr. Day .375 300. 112.5
114 Beldar for cleaning slush Day 4. 135.25 541.
TOTAL 653.5
Add 1% for water charges 6.54
TOTAL 660.04
216 Add for contractor’s profit and overheads @ 15% 99.01
Cost of 14 cum. per 0.30m depth 759.05
Cost of 1 cum. per m depth 180.73
Say 180.75
NOTE :- The quantity will be calculated by multiplying the depth measured from sub - soil
water level upto the centre of gravity of brick work under sub - water with the quantity
of brick work in cum executed under the sub - soil water. The depth of cento of
gravity shall be reckoned correct to 0.1m, 0.05m or more shall be taken as 0.1 m and
less than 0.05m ignored.

6.25 Extra for laying brick work in or under foul position.


Code Description Unit Quantity Rate Amount
Details of cost for 1 cum.
Extra labour due to slow progress-
Mason 1st class Day .02 151.5 3.03
123 Mason 2nd class Day .02 141.6 2.83
124 Beldar Day .25 135.25 33.81
114 Coolie Day .15 135.25 20.29
115 TOTAL 59.96
Add 1% for water charges .6
TOTAL 60.56
Add for contractor’s profit and overheads @15% 9.08
Cost for 1 cum. 69.64
Say 69.65

Brick work with selected F.P.S. bricks of class


designation 75 in exposed brick work including making
horizontal and vertical grooves 10mm wide 12mm deep
complete from ground level upto plinth level in cement
mortar 1:6 (1 cement : 6 coarse sand)
6.26
Code Description Unit Quantity Rate Amount
Details of cost for 1 cum.
2602 Bricks of class designation 75 1000 Nos 494. 1,900. 938.6
2201 Carriage of bricks 1000 Nos 494. 141.88 70.09
Cement mortar 1:6(1 cement: 6 coarse cum .25 1,987.3 496.82
sand) (Rate as per item no. 3.11)
9999 Sundries including steel/wooden strips for L.S. 16.38 1. 16.38
making grooves.
Labour:
For selection of bricks
114 Beldar Day .5 135.25 67.62
123 Mason 1 st class Day .35 151.5 53.02
124 Mason 2nd class Day .35 141.6 49.56
115 Coolie Day 1.07 135.25 144.72
101 Bhishti Day .2 138.45 27.69
TOTAL 1,864.5
Add 1 % for water charges 18.64
TOTAL 1,883.14
Add for contractor’s profit and overheads @15% 282.47
Cost per cum. 2,165.61
Say 2,165.6

Brick work with modular bricks of class designation 75


in exposed brick work including making horizontal and
vertical grooves 10mm wide 12mm deep complete from
ground level upto plinth level in cement mortar 1:6 (1
217 6.27 cement : 6 coarse sand).
Code Description Unit Quantity Rate Amount
Details of cost for 1 cum.
MATERIALS :
7900 Modular bricks of class designation 75 1000 Nos 487. 2,050. 998.35
2201 Carriage of Bricks 1000 Nos 487. 141.88 69.1
Cement mortar 1:6 (1 cement: 6 coarse cum .22 1,987.3 437.21
sand (Rate as per item no. 3.11)
9999 Sundries l/c steel/ wooden strips for-making L.S. 16.38 1. 16.38
grooves
LABOUR:
123 Mason 1st Class Day .33 151.5 50.
124 Mason Ilnd Class Day .33 141.6 46.73
115 Coolie Day 1. 135.25 135.25
101 Bhishti Day .18 138.45 24.92
TOTAL 1,777.94
Add 1% for water charges 17.78
TOTAL 1,795.72
Add for contractor’s profit and overheads @15% 269.36
Cost of 1 Cum. 2,065.08
Say 2,065.1
Brick work with machine moulded modular bricks of
class designation 125 in exposed brick work including
making horizontal and vertical grooves 10mm wide
12mm deep complete from ground level upto plinth level
in cement mortar 1:6 (1 cement : 6 coarse sand).
6.28
Code Description Unit Quantity Rate Amount
Details of cost for 1 cum.
1986 Modular Bricks of class designation 75 1000 Nos 487. 2,700. 1,314.9
2201 Carriage of bricks 1000 Nos 487. 141.88 69.1
Cement mortar 1:6(1 cement: 6 coarse cum .22 1,987.3 437.21
sand (Rate as per item no 3.11)
9999 Sundries including steel/wooden strips for L.S. 16.38 1. 16.38
making grooves.
Labour:
123 Mason 1 st class Day .33 151. 50.
124 Mason 2nd class Day .33 141.6 46.73
115 Coolie Day 1. 135.25 135.25
101 Bhishti Day .18 138.45 24.92
TOTAL 2,094.49
Add 1 % for water charges 20.94
TOTAL 2,115.43
Add for contractor’s profit and overheads @15% 317.31
Cost per cum. 2,432.74
Say 2,432.75

Brick work with machine moulded F.P.S. bricks of class


designation 125 in exposed brick work including making
horizontal and vertical grooves 10 mm wide 12mm deep
complete from ground level upto plinth level in cement
mortar 1:6 (1 cement : 6 coarse sand)
218 6.29
Code Discription Unit Quantity Rate Amount
Details of cost for 1 cum.
MATERIALS :
7903 Machine moulded modular perforated bricks 1000 Nos 494. 2,767. 1,366.9
of class designation 125
2201 Carriage of Bricks 1000 Nos 494. 14.88 70.09
Cement mortar 1:6,(1 cement: 6 coarse sand). cum .25 1,987.3 496.82
(Rate as per item no 3.11)
9999 Sundries i/c steel /wooden strips for making L.S. 16.38 1. 16.38
grooves
LABOUR:
123 Mason 1st Class Day .36 151.5 54.54
124 Mason Ilnd Class Day .36 141.6 .98
115 Coolie Day 1.37 135.25 185.29
101 Bhishti Day .2 138.25 27.69
TOTAL 2,268.69
Add 1 % for water charges 22.69
TOTAL 2,291.38
Add for contractor’s profit and overheads @15% 343.71
Cost of 1 Cum. 2,635.09
Say 2,635.1
Brick work with machine moulded perforated F.P.S.
bricks of class designation 125 conforming IS : 2222-
1991 in exposed brick work including making horizontal
and vertical grooves 10mm wide 12 mm deep complete
from ground level upto plinth level in cement mortar 1:6
6.3 (1 cement : 6 coarse sand).
Code Discription Unit Quantity Rate Amount
Details of cost for 1 cum.
MATERIALS :
7901 Machine moulded modular perforated bricks 1000 Nos 494. 3,233. 1 597.10
of class designation 125
2201 Carriage of Bricks 1000 Nos 494. 141.88 70.09
2115 Cement mortar 1:6,(1 cement: 6 coarse sand). cum .25 1,987.3 496.82
(Rate as per item no 3.11)
9999 Sundries i/c steel /wooden strips for making L.S. 16.38 1. 16.38
grooves
LABOUR:
123 Mason 1st Class Day .35 151.5 54.54
124 Mason Ilnd Class Day .35 141.6 50.98
115 Coolie Day 1.07 135.25 185.29
101 Bhishti Day .2 138.45 27.69
TOTAL 2,498.89
Add 1 % for water charges 24.99
TOTAL 2,523.88
Add for contractor’s profit and overheads @15% 378.58
Cost of 1 Cum. 2,902.46
Say 2,902.45

Brick work with machine moulded perforated modular


bricks of class designation 125 conforming to IS : 2222 -
1991 in exposed brick work including making horizontal
and vertical grooves 10 mm wide 12mm deep complete
from ground level upto plinth level in cement mortar 1:6
(1 cement : 6 coarse sand).
219 6.31
Code Discription Unit Quantity Rate Amount
Details of cost for 1 cum.
MATERIALS :
7902 Machine moulded modular perforated bricks 1000 Nos 487. 3,200. 1,558.4
of class designation 125
2201 Carriage of Bricks 1000 Nos 487. 141.88 69.1
Cement mortar 1:6 (1 cement: 6 coarse sand). cum .22 1,987.3 437.21
(Rate as per item no 3.11)
9999 Sundries i/c steel /wooden strips for making L.S. 16.38 1. 16.38
grooves
LABOUR:
123 Mason 1st Class Day .33 151.5 50.
124 Mason Ilnd Class Day .33 141.6 46.73
115 Coolie Day 1. 135.25 135.25
101 Bhishti Day .18 138.45 24.92
TOTAL 2,337.99
Add 1 % for water charges 23.38
TOTAL 2,361.37
Add for contractor’s profit and overheads @15% 354.21
Cost of 1 Cum. 2,715.58
Say 2,715.6
Brick work with clay flyash F.P.S. brick of class
designation 75 in superstructure above plinth level upto
6.32 floor five level in :
6.32.1 Cement mortar 1:4(1 cement : 4 coarse sand)
Code Discription Unit Quantity Rate Amount
Details of cost for 1 cum.
Materials :
7008 Clay flyash bricks of class designation 75 1000 Nos 494. 1,412. 697.53
Cement mortar1: 4 (1 cement: 4 coarse sand) cum .25 2,578.45 644.61
(Rate as per item no 3.11)
2201 Carriage of bricks ‘ 1000 Nos. 494. 141.88 70.09
9999 Sundries L.S. 2.75 1. 2.73
Labour:
123 Mason 1st class Day .47 151.5 71.2
124 Mason 2nd class Day .47 141.6 66.55
115 Coolie Day 1.8 135.25 243.45
101 Bhishti Day .2 138.45 27.69
9999 Scaffolding L .S. 8.97 1. 8.97
Extra labour element required for lifting of
materials above floor two level upto floor V
level (0.75 x 1.5 = 1.13)
115 Coolie Day 1.13 135.25 152.83
TOTAL 1,985.65
Add 1 % for water charges 19.86
TOTAL 2,005.51
Add for contractor’s profit and overheads @15% 300.83
Cost per cum. 2,306.34
Say 2,306.35

Brick work with clay flyash F.P.S. brick of class


designation 75 in superstructure above plinth level upto
220 6.32 floor five level in :
6.32.2 Cement mortar 1:6(1 cement: 6 coarse sand)
Code Description Unit Quantity Rate Amount
Details of cost for 1 cum.
Materials :
7008 Clay flyash bricks of class designation 75 1000 Nos 494. 1,412. 697.53
Cement mortar 1 : 6(1 cement: 6 coarse sand) cum .25 1,987.3 496.82
(Rate as per item no 3.11)
2201 Carriage of bricks 1000 Nos 494. 141.88 70.09
9999 Sundries L.S. 2.73 1. 2.73
Labour:
123 Mason 1st class Day .47 151.5 71.2
124 Mason 2nd class Day .47 141.6 66.55
115 Coolie Day 1.8 135.25 243.45
101 Bhishti Day .2 138.45 27.69
9999 Scaffolding L.S 8.97 1. 8.97
Extra labour element required for lifting of
materials above floor two level upto floor V
level (0.75x1.5= 1.13)
115 Coolie Day 1.13 135.25 152.83
TOTAL 1,837.86
Add 1% for water charges 18.38
TOTAL 1,856.24
Add for contractor’s profit and overheads @15% 278.44
Cost per cum. 2,134.68
Say 2,134.7
Extra for exposed brick work/ clay flyash brick work in
superstructure above floor five level, for each four floors
6.33 or part thereof.
Code Description Unit Quantity Rate Amount
Details of cost for per cum. per four floor
Extra labour element required for lifting of
materials
115 0.75x2.00=1.50
Coolie Day 1.5 135.25 202.88
TOTAL 202.88
Add 1 % for water charges 2.03
TOTAL 204.91
Add for contractor’s profit and overheads @15% 30.74
Cost of 1 Cum. 235.65
Say 235.65

Brick work with modular fly ash lime bricks (FALG


Bricks) conforming to IS:12894-2002, class designation
100 average compressive strength in super structure
above plinth level upto floor V level in :
221 6.34
6.34.1 Cement mortar 1:4 (1 cement: 4 coarse sand)
Code Description Unit Quantity Rate Amount
Details of cost for 1 cum.
Materials:
7737 Fly ash bricks of class designation 100 1000 Nos 487. 1,792. 872.7
Cement mortar 1 : 4 (1 cement: 4 coarse sand) cum .22 2,578.45 567.26
(Rate as per Item No. 3.9)
2201 Carriage of bricks’ 1000 Nos 487. 141.88 69.1
9999 Sundries L.S. 2.73 1. 2.73
Labour:
123 Mason 1st class Day .47 151.5 71.2
124 Mason 2nd class Day .47 141.6 66.55
115 Coolie Day 1.8 135.25 243.45
101 Bhishti Day .2 138.45 27.69
9999 Scaffolding L.S. 22.36 1. 22.36
Extra labour element required for lifting of
materials above floor two level upto floor V
level (0.75x1.5 =1.13)
115 Coolie Day 1.13 135.25 152.83
TOTAL 2,095.87
Add 1 % for water charges 20.96
TOTAL 2,116.83
Add for contractor’s profit and overheads @15% 317.52
Cost per cum. 2,434.35
Say 2,434.35

Brick work with modular fly ash lime bricks (FALG


Bricks) conforming to IS:12894-2002, class designation
100 average compressive strength in super structure
above plinth level upto floor V level in :
6.34
6.34.2 Cement mortar 1:6(1 cement: 6 Coarse sand)
Code Description Unit Quantity Rate Amount
Details of cost for 1 cum
Materials :
7737 Fly ash bricks of class designation 100 1000 Nos 487. 1,792. 872.7
Cement.mortar 1:6 (1 cement: 6 coarse sand) cum .22 1,987.3 437.21
Rate as per Item No. 3.11
2201 Carriage of brick’s 1000 Nos 487. 141.88 69.1
9999 Sundries
Labour: L.S. 2.73 1. 2.73
123 Mason 1st class Day .47 151.5 71.2
124 Mason 2nd class Day .47 141.6 66.55
115 Coolie Day 1.8 135.25 243.45
101 Bhishti Day .2 138.45 27.69
9999 Scaffolding L.S. 22.36 1. 22.36
Extra labour element required for lifting of
materials above floor two level upto floor V level
115 Coolie (0.75x1.5= 1.13) Day 1.13 135.25 152.83
TOTAL 1,965.82
Add 1% for water charges 19.66
TOTAL 1,985.48
Add for contractor’s profit and overheads @15% 297.82
Cost per cum. 2,283.3
Say 2,283.3

Brick work with modular calcium silicate bricks machine


moulded conforming to IS:4139-1989, class designation
100 average compressive strength in super structure
above plinth level upto floor V level in :
222 6.35
6.35.1 Cement mortar 1:4 (1 cement: 4 coarse sand)
Code Description Unit Quantity Rate Amount
Details of cost for 1 cum.
Materials :
7738 Calcium silicate bricks of class designation100 1000 Nos 487. 3,083. 501.42
Cement mortar 1 : 4 (1 cement : 4 coarse sand) cum .22 2,578.45 567.26
(Rate as per item No 3.9)
2201 Carriage of bricks 1000 Nos 487 141.88 69.1
9999 Sundries L.S. 2.73 1. 2.73
Labour:
123 Mason 1st class Day .47 151.5 71.2
0 124 Mason 2nd class Day .47 141.6 66.55
115 Coolie Day 1.8 135.25 243.45
101 Bhishti Day .2 138.45 27.69
9999 Scaffolding L.S. 22.36 1. 22.36
Extra labour element required for lifting of
materials above floor two level upto floor V
level
O115 Coolie (0.7 x 1.5 = 1.13) Day 1.13 135.25 152.83
TOTAL 2,724.59
Add 1 % for water charges 27.25
TOTAL 2,751.84
Add for contractor’s profit and overheads @15% 412.78
Cost per cum. 3,164.62
Say 3,164.6

Brick work with modular calcium silicate bricks machine


moulded conforming to IS:4139-1989, class designation
100 average compressive strength in super structure
above plinth level upto floor V level in :
6.35
6.35.2 Cement mortar 1:6 (1 cement: 6 Coarse sand)
Code Description Unit Quantity Rate Amount
Details of cost for 1 cum.
Materials :
7738 Calcium silicate bricks of class designation 100 1000 Nos 487. 3,083. 1,501.42
Cement .mortar 1:6(1 cement: 6 coarse sand) cum .22 1,987.3 437.21
(Rate as per item No. 3.9)
2201 Carriage of bricks 1000 Nos 487. 141.88 69.1
9999 Sundries L.S. 2.73 1. 2.73
Labour:
123 Mason 1st class Day .47 151.5 71.2
124 Mason 2nd class Day .47 141.6 66.55
115 Coolie Day 1.8 135.25 243.45
101 Bhishti Day .2 138.45 27.69
9999 Scaffolding L.S. 22.36 1. 22.36
Extra labour element required for lifting of
materials above floor two level upto floor V level
115 Coolie (0.75 x 1.5 = 1.13) Day 1.13 135.25 152.83
TOTAL 2,594.54
223 Add 1 % for water charges 25.95
TOTAL 2,620.49
Add for contractor’s profit and overheads @15% 393.07
Cost per cum. 3,013.56
Say 3,013.55

Brick work with modular extruded brunt fly ash clay


sewer bricks (Conforming to IS: 4885 - 1988) in
6.36 foundation and plinth :
6.36.1 Cement Mortar 1:4(1 cement: 4 coarse sand)
Code Description Unit Quantity Rate Amount
Details of cost for 1 cum.
Materials :
7736 Extruded burnt flyash clay sewer bricks 1000 Nos 487. 3,550. 1,728.85
Cement mortar 1:4(1 cement: 4 coarse sand) cum .22 2,578.45 567.26
(Rate as per item No. 3.9)
2201 Carriage of bricks 1 000 Nos 487. 141.88 69.1
9999 Sundries L.S. 2.73 1. 2.73
Labour:
123 Mason 1st class Day .33 151.5 50.
124 Mason 2nd class Day .33 141.6 46.73
115 Coolie Day 1. 135.25 135.25
101 Bhishti Day .18 138.45 24.92
TOTAL 2,624.84
Add 1 % for water charges 26.25
TOTAL 2,651.09
Add for contractor’s profit and overheads @15% 397.66
Cost per cum. 3,048.75
Say 3,048.75

Brick work with modular extruded brunt fly ash clay


sewer bricks (conforming to IS : 4885-1988) in arches in
foundation and plinth in cement mortar 1:3 ( 1 cement : 3
6.37 fine sand).
Code Description Unit Quantity Rate Amount
Details of cost for 1 cum.
Materials :
7736 Extruded burnt flyash clay sewer bricks 1000 Nos 487. 3,550. 1,728.85
Cement mortar 1: 3 (1 cement: 3 fine sand). cum .25 2,870. 717.5
(Rate as per item No. 3.3)
2201 Carriage of bricks 1000 Nos 487. 141.88 69.1
9999 Sundries L.S. 2.73 1. 2.73
(A) Centering and shuttering
(Rate as per item no 5.9.9 SH : RCC) sqm 2.25 514.7 1 158.08
Labour:
123 Mason 1st class Day .42 151.5 63.63
124 Mason 2nd class Day .42 141.6 59.47
115 Coolie Day 1.86 135.25 251.57
101 Bhishti Day .2 138.45 27.69
TOTAL 4,078.62
Add 1 % for water charges except on A 29.21
TOTAL 4,107.83
Add for contractor’s profit and overheads @ 442.46
15% except on A
Cost per cum 4,550.29
Say 4,550.3

Providing and laying autoclaved aerated cement blocks


masonry with 100mm thick AAC blocks in super
structure above plinth level upto floor V level in cement
mortar 1:4 (1 cement : 4 coarse sand ) The rate includes
providing and placing in position 2 Nos. 6 mm dia M.S.
bars at every third course of masonry work.
224 6.38
Code Description Unit Quantity Rate Amount
Details of cost for 1 cum.
MATERIALS :
8655 Autoclaved aerated cement (AAC) blocks. cum 1. 1,650. 1,650.
Cement mortar 1:4 cum .15 2,578.45 386.77
(Rate as per Item No. 3.9)
2208 Carriage of AAC blocks cum 1. 53.21 53.21
9999 Sundries L.S 2.73 1. 2.73
LABOUR:
123 Mason 1st Class Day .36 151.5 54.54
124 Mason Ilnd Class Day .36 141.6 50.98
115 Coolie Day 1.37 135.25 185.29
101 Bhishti Day .2 138.45 27.69
(A) Reinforcement bars
Rate as per item no 5.22.1 of SH : RCC kg 13.2 41.5 547.8
TOTAL 2,959.01
Add 1 % for water charges except on (A) 24.11
TOTAL 2,983.12
Add for contractor’s profit and overheads @ 365.3
15% except on (A)
Cost of 1 Cum. 3,348.42
Say 3,348.4

Extra for AAC block masonry in superstructure above


floor V level for every four floors or part there of.
6.39
Code Description Unit Quantity Rate Amount
Details of cost for 1 cum per floor
Extra labour element required for lifting of
materials.
115 Coolie (0.75 x 2 = 1.50) Day 1.5 135.25 202.88
TOTAL 202.88
Add 1% for water charges 2.03
TOTAL 204.91
Add for contractor’s profit and overheads @15% 30.74
Cost per cum. 235.65
Say 235.65
Providing and laying Gypsum panel partitions 100mm
thick with water proof Gypsum panels of size
666x500x100mm, made of calcite phosphor Gypsum
fixed with tongue and groove, jointed with bonding
plaster as per manufacturers specifications in
superstructure above plinth level upto floor V level.
Gypsum blocks will have a minimum compressive
6.4 strength of 9.3 kg/cm2
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm.
MATERIAL
8656 Gypsum panel 666 X 500 X 100 mm size. sqm 10. 544. 5,440.
8657 Bonding plaster for Gypsum panel. kg 25. 50. 1,250.
9999 Sundries & scaffolding L.S. 13.52 1. 13.52
LABOUR
225 123 Mason (brick layer) 1st class Day .5 151.5 75.75
114 Beldar Day 1. 135.25 135.25
TOTAL 6,914.52
Add 1 % for water charges 69.15
TOTAL 6,983.67
Add 15% for contractor’s profit and overheads 1,047.55
Cost for 10 sqm 8,031.22
Cost for 1 sqm 803.12
Say 803.1

Extra for Gypsum panel Partitions in superstructure


above floor V level for every four floors or part thereof.
6.41
Code Description Unit Quantity Rate Amount
Details of cost for 10 sqm. per four floor
Extra labour element for lifting of materials
above floor V level.
115 Coolie Day 1.73 135.25 233.98
Total 233.98
Add for water charges @ 1% 2.34
Total 236.32
Add for contractor’s profit and overheads @ 15% 35.45
Cost for 10 sqm. 271.77
Cost for 1 sqm 27.18
Say 27.2

Brick work with mechanised autoclaved flyash lime


bricks conforming to IS: 12894 :2002 of class
designation 100 in superstructure above plinth level upto
6.42 floor V level in.
6.42.1 Cement mortar 1:4 (1 cement :4 coarse sand).
Code Description Unit Quantity Rate Amount
Details of Cost for 10 cum
MATERIALS
8658 Mechanised Autoclaved flyash lime bricks. 1000 Nos 494. 2,200. 1,086.8
Cement morter 1:4 (1 cement: 4 coarse sand). cum .25 2,578.45 644.61
(Rate as per item no 3.9)
2201 Carriage of Bricks 1000 Nos 494. 141.8 70.09
9999 Sundries L.S. 2.73 1. 2.73
123 Mason 1st class Day .36 151.5 54.54
124 Mason 2nd class Day .36 141.6 50.98
115 Coolie Day 1.37 135.25 185.29
101 Bhisti Day .2 138.45 27.69
TOTAL 2,122.73
Add for water charges @ 1 % 21.23
TOTAL 2,143.96
Add for contractor’s profit and overheads @15% 321.59
Cost for 1 cum 2,465.55
Say 2,465.55

Brick work with mechanised autoclaved flyash lime


bricks conforming to IS: 12894 :2002 of class
designation 100 in superstructure above plinth level upto
226 6.42 floor V level in.
6.42.2 Cement mortar 1:6 (1 cement :6 coarse sand).
Code Description Unit Quantity Rate Amount
Details of Cost for 10 cum
MATERIALS
8658 Mechanised Autoclaved flyash lime bricks. 1000 Nos 494. 2,200. 1,086.8
Cement morter 1:6 (1 cement: 6 coarse sand). cum .25 1,987.3 496.82
(Rate as per item no 3.11)
2201 Carriage of Bricks 1000 Nos 494. 141.88 70.09
9999 Sundries L.S. 2.73 1. 2.73
123 Mason 1st class Day .36 151.5 54.54
124 Mason 2nd class Day .36 141.6 50.98
115 Coolie Day 1.37 135.25 185.29
101 Bhisti Day .21 138.45 27.69
TOTAL 1,974.94
Add for water charges @ 1% 19.75
TOTAL 1,994.69
Add for contractor’s profit and overheads @ 15% 299.2
Cost for 1 cum 2,293.89
Say 2,293.9

Extra for mechanised autoclave flyash lime bricks


conforming to IS: 12894- 1990 of class designation 100
in superstructure above floor V level for each four floors
6.43 or part thereof.
Code Description Unit Quantity Rate Amount
Details of cost for per cum. per four floors
Extra labour element required for lifting of
materials
0.75x2.00= 1.50
115 Coolie Day 1.5 135.25 202.88
TOTAL 202.88
Add 1 % for water charges 2.03
TOTAL 204.91
Add for contractor’s profit and overheads @ 15% 30.74
Cost of 1 Cum. 235.65
Say 235.65

Brick edging 7cm wide 11.4cm deep to plinth protection


with bricks of class designation 75 including grouting
with cement mortar 1:4 (1 cement : 4 fine sand).
6.44
Code Description Unit Quantity Rate Amount
Details of cost for 10m length
9999 Excavation and disposal of surplus earth L.S. 1. 2.73 2.73
2nd class bricks = 42 nos. +
Add wastage @ 10% = 4.2 nos.
= 46.2 nos.
Say 46.00 nos.
2602 Bricks of class designation 75 1000 Nos 46. 1 900.00 87.4
2201 Carriage of bricks 1000 Nos 46. 141.88 6.53
Cement mortat 1:4 (Rate as per item no. 3.4) cum .0036 2 278.85 8.2
Labour
155 Mason Day .1 146.55 14.66
227 114 Beldar Day .1 135.25 13.52
101 Bhisti Day .03 138.45 4.15
9999 Sundries L.S. 1. 2.73 2.73
TOTAL 139.92
Add 1 % for water charges 1.4
TOTAL 141.32
Add 15% for contractor’s profit and overheads 21.2
Cost of 10 metres 162.52
Cost of 1 metre 16.25
Say 16.25

229