Beruflich Dokumente
Kultur Dokumente
Part II
Electrical Integrated Startup Commissioning
Scheme
August, 2008
1
India Tengda 2×330MW Coal-fired Power Plant Project—Electrical Commissioning Scheme
Contents
1. Overview
2. Purposes of Commissioning
3. Commissioning Standard
Parameters of Equipment
6. Scope of Commissioning
Procedures
2
India Tengda 2×330MW Coal-fired Power Plant Project—Electrical Commissioning Scheme
1 Overview
India Tengda 2×330MW Coal-fired Power Plant Project (Phase I) is set with two
330MW turbine generator sets. Unit wiring mode is adopted for the generator and
isolated phase bus is employed for the outgoing line from the generator to the main
transformer and house transformer, excitation transformer, PT, and lightning arrester
branch. Among them, there is no any breaker but removable contacts. Each power
supply unit for high-voltage plant is set with two 25MVA transformers. The power
supplies are from the generator outlet, respectively supplied to their 6v working
section.
2.1.1 Examine the correctness of the primary and secondary circuit and voltage
2.1.2 Record the generator’s no load and short circuit curves, and compare them
with the pre-delivery test data, and confirm whether them are qualified.
2.1.3 See “Integrated Test Measures for Excitation System” for details of excitation
3
India Tengda 2×330MW Coal-fired Power Plant Project—Electrical Commissioning Scheme
2.1.5 The synchronization system examination is apposed with the generator. See
2.1.6 Excitation system test after the generator is loaded, unit source switching test,
2.2.1The measures can be carried out after the opinions collection and discussion of
all parties concerned and upon the approval of the startup commission.
2.2.2 The electrical test in the integrated startup process is operated by the electrical
engineering team of the installation company shall coordinate with that; the
operation of the charged parts handed over and associated parts of the system
is conducted by the on-duty operator of the power plant, and the on-duty
operator shall be responsible for dispatching contact during the test operation.
2.2.3 The synchronization mode of the generator and system is operated on the
by on-duty operator of the power plant after synchronization and load. The
4
India Tengda 2×330MW Coal-fired Power Plant Project—Electrical Commissioning Scheme
2.2.4 The setting values of relay protection and automatic equipment for electrical
tests, bus, and 220kV circuit shall be provided by the dispatching unit; the
generator-transformer set and unit parts shall be provided by the power plant.
The dispatching order prevails in case that the setting value changes during
2.2.5 The inverse power supply tests of the main transformer and unit high-voltage
2.2.6 The low-voltage side of the unit high-voltage transformer is no longer set with
short circuit point because the correctness of relevant protection devices has
been examined in the current injecting test and inverse power supply tests of
3 Compilation Basis
3.1 Code of Startup and Completion Acceptance of Thermal Power Plant (1996)
5
India Tengda 2×330MW Coal-fired Power Plant Project—Electrical Commissioning Scheme
3.3 Standard for Quality Inspection & Assessment of Regulation & Commissioning
3.4 Standard for Quality Inspection and Assessment of Thermal Power Engineering
3.9 The Code of Erection and Acceptance for Electric Power Construction
(Electrical Section)
6
India Tengda 2×330MW Coal-fired Power Plant Project—Electrical Commissioning Scheme
Equipment
Device
3.17 Key Points of Anti-accident Measure in Relay and Safety Automation Device
DL 400-91
3.21Regulations on Site Work Safety Insurance of Relay Protection and Grid Safety
Automatic Equipment
3.22 Technical data provided by the manufacturer and relevant design blueprints
Synchronous generator
7
India Tengda 2×330MW Coal-fired Power Plant Project—Electrical Commissioning Scheme
Excitation transformer
Model:
Voltage: 24kV
Capacity: 3X19 kVA
Wiring Group Y/d-11
Impedance Voltage: 7-8%
Main Transformer
Model:
Capacity: 400MVA
Rated Voltage: 235±2×2.5%/24kV
Impedance Voltage 14-15%
Wiring Means: Ynd11
Cooling Means: Forced oil circulation air cooling
Installation Environment: Outdoor
Startup/standby Transformer
Model:
Capacity:
Rated Voltage:
8
India Tengda 2×330MW Coal-fired Power Plant Project—Electrical Commissioning Scheme
Impedance Voltage
Wiring Means:
Voltage Regulation Mode:
6 Scope of Commissioning
6.1 The primary equipment of the major electrical system that the commissioning
relates to mainly include generator, main transformer, unit transformer,
startup/standby transformer, 220kV side SF6 breaker, 6.3kV unit side vacuum
9
India Tengda 2×330MW Coal-fired Power Plant Project—Electrical Commissioning Scheme
breaker, 220kV side isolating switch, 220kV side CT, generator side CT,
generator side PT, lightning arrester, side grounding transformer at the
generator’s neutral point, various cables, enclosed bus, de-excitation switch of
excitation system of the generator, rectifier unit, over-voltage protection, and
de-excitation resistance.
6.2 The secondary equipment within the scope of commissioning mainly include
relay protection of generator-transformer set, relay protection of unit
high-voltage transformer, auto synchronization device, auto excitation regulator,
plant power switching and standby self-input unit, DCS electrical control
system, DCS electrical data acquisition system, and electrical measurement
instruments.
10
India Tengda 2×330MW Coal-fired Power Plant Project—Electrical Commissioning Scheme
civil engineering, lighting and fire facilities shall be qualified through check
and acceptance to ensure safe operation.
7.2.4 The main transformer and unit high-voltage transformer shall be placed at the
setting level according to the dispatching requirements, and the DC resistance
of the setting level shall be measured. The results shall conform to the
requirements described in “Regulations on Handover Test of Electrical
Equipment”. The accident oil discharging system of the main transformer, unit
high-voltage transformer, and startup/standby transformer shall be qualified
for use through check and acceptance; the main transformer, unit high-voltage
transformer, and startup/standby transformer shall be aired out.
7.2.5 The relay protection device and automatic equipment within the scope of
charged parts shall be set according to the requirements of the setting notice
given by the dispatching unit and owner, and checked qualified for operation
by the operator of the power plant.
7.2.6 Air pressure test of the main body of the generator shall be qualified and the
main body shall be applied with qualified stator cooling water assigned by the
manufacturer; the hydrogen cooler and drier have been switched on; hydrogen
making system has prepared qualified hydrogen, and the generator has been
filled with hydrogen according to the rated hydrogen pressure. The fire
facilities of the generator are under good conditions and qualified for use
through check and acceptance.
7.2.7 The results of interlocking test among electrical equipment, steam turbine,
heat control and boiler are satisfied, and transmission test results are correct
and qualified through quality examination.
7.2.8 The transmission test of breakers in electrical equipment circuits is finished
and conforms to the relevant regulations and design requirements, and is
qualified through check and acceptance.
7.2.9 No any work and working ticket in all charged areas of this startup test.
7.3 Preparation before startup
7.3.1 All participants of the startup test shall thoroughly read the measures before
11
India Tengda 2×330MW Coal-fired Power Plant Project—Electrical Commissioning Scheme
startup and understand their own responsibilities, and bring forward questions
for definite results.
7.3.2 The test personnel shall prepare for the relevant blueprints, data and test record
form.
7.3.3 The primary and secondary side switches and isolator of the generator and
transformer are at the off position, and branch switch at the off position.
Operation is not allowed without operation order.
7.3.4 Define the position of short circuit points and prepare for the qualified short
circuit bus.
7.3.5 The measured insulation resistance and absorption factor of the primary
system of the generator and transformer shall conform to the relevant
requirements.
7.3.6 Confirm that the secondary current circuit has no open circuit and the
secondary voltage circuit has no short circuit.
7.3.7 Switch on the primary and secondary insurances of the generator PT, and
examine all protection circuits and control circuit power insurance of the
generator and transformer. Their specifications shall conform to the design
requirements. Enough standby products shall be available.
7.3.8 The setting value of the over-voltage protection operation shall be set as 115V.
The operation starts up the magnetic field breaker at NO contact for tripping.
7.3.10 Switch off 220kV circuit and joint-tripping furnace and press plate of
generator-transformer set and unit high-voltage transformer.
7.3.11 Prepare for introducing the main excitation power supply of the excitation
system before the test (the cable is introduced to high-voltage side of the
excitation transformer from 6.6kV standby section). Please note that the
relevant current instantaneous trip and over-current protections of the
separators for equipment shall be prepared well and proven qualified through
the integrated test of the set with the breaker. The cables shall be tested
qualified before use.
7.3.12 Prepare for the test instruments and meters required for the startup test and
12
India Tengda 2×330MW Coal-fired Power Plant Project—Electrical Commissioning Scheme
13
India Tengda 2×330MW Coal-fired Power Plant Project—Electrical Commissioning Scheme
14
India Tengda 2×330MW Coal-fired Power Plant Project—Electrical Commissioning Scheme
8.5 The duty manager of the power plant shall be responsible for the matters
concerning dispatching contact.
8.6 The thorough examination before the electrical integrated startup test shall be
arranged by the commissioning HQ.
8.7 After the unit is apposed, the operator of the power plant shall be responsible for
the supervision and operation of the electrical unit, and the electrical
commissioning engineer shall coordinate with that.
8.8 Other matters not mentioned in the measures in the startup test are subject to the
relevant regulations.
15
India Tengda 2×330MW Coal-fired Power Plant Project—Electrical Commissioning Scheme
9.2.1.5 Switch on the temporary excitation power supply (the cable is introduced to
high-voltage side of the excitation transformer from 6.6kV standby section).
Examine whether the phase sequence and phase are corresponding to the
high-voltage side of the excitation transformer.
9.2.1.6 Examine and switch on the excitation system, and excite the excitation under
manual control mode. Manually regulate the exciting current and increase
the stator current of the generator to 1500A and secondary current 0.5A.
9.2.1.7 Measure the secondary current amplitude of the generator’s current
transformer, and examine whether the three-phase current is balanced;
examine and confirm the correctness of the generator’s negative sequence
current protection. Record the numerical values of the relevant test
instruments, meters, and data acquisition system on DCS.
9.2.1.8 Measure the phasor relationship of the generator’s other CT secondary
currents based on the CT secondary A-phase current for generator
differential protection at the outlet side of the generator, examine and
confirm the correctness of the generator’s differential protection polarity.
9.2.1.9Regulate the generator excitation and record the current increase and
decrease short circuit curves of the generator. Maximize the primary stator
current of the generator to 10190A and the secondary current 3.4A. Record
the generator’s stator current and excitation current, examine the
corresponding protection operations, and record the numerical values of the
relevant test instruments, meters, and data acquisition system on DCS. See
Table 1 for the record form.
Table 1 Generator’s Short Circuit Test Data
Description 1 2 3 4 5 6 7
Increas
IG
e
IGF
Decrea
IG
se
IGF
9.2.1.10 Upon the completion of the short circuit test, decrease the excitation current
16
India Tengda 2×330MW Coal-fired Power Plant Project—Electrical Commissioning Scheme
to zero to invert and de-excitate for tripping off the magnetic field breaker,
and inform of the installation unit to dismount the short circuit bus.
9.2.2 Short circuit point test (set a short circuit point K2 at the high-voltage side of
the main transformer)
9.2.2.1 Examine and confirm whether the high-voltage side grounding switch of the
main transformer locates at the off position.
9.2.2.2 Switch on the cooler of the main transformer.
9.2.2.3 Switch on the grounding switch at the neutral point of the main transformer.
9.2.2.4 Examine and confirm whether 220kV side isolating switch of the
transformer locates at the off position (the operation of the isolating switch
during the test shall be subject to the instructions of the commissioning
HQ).
9.2.2.5 Switch on the high-voltage side grounding switch of the main transformer.
9.2.2.6 Switch on the high-voltage side outlet breaker of the main transformer, and
dismount the wire core from the protection tripping circuit to the secondary
cable circuit of the breaker.
9.2.2.7 Excite the excitation under manual control mode, manually regulate the
exciting current, and increase the stator current of the generator to 1500A
and secondary current 0.5A.
9.2.2.8 Measure the secondary current amplitude of the current transformers, and
examine whether the three-phase current is balanced; examine and confirm
the correctness of the generator’s negative sequence current protection.
Record the numerical values of the relevant test instruments, meters and
data acquisition system on DCS.
9.2.2.9 Measure the phasor relationship of the generator’s other CT secondary
currents based on the CT secondary A-phase current for the generator
differential protection at the outlet side of the generator and confirm the
correctness of the differential protection polarity of the main transformer.
9.2.2.10 Increase the primary stator current of the generator to 10190A and the
secondary current 3.4A, and measure the differential current in the
17
India Tengda 2×330MW Coal-fired Power Plant Project—Electrical Commissioning Scheme
18
India Tengda 2×330MW Coal-fired Power Plant Project—Electrical Commissioning Scheme
position.
9.2.3.3.3 Switch on the generator’s magnetic field breaker MK.
9.2.3.3.4 Excite the excitation under FCR control mode, manually increase the
voltage to 20% rated voltage, and examine whether the amplitude, phase
and phase sequence of PT secondary circuit are correct.
9.2.3.3.5 Increase the generator’s voltage to 40% rated voltage, and examine
whether the PT secondary current and phase sequence are correct, and
whether the open-delta voltage is about zero.
9.2.3.3.6 Upon confirmation, slowly increase the generator’s voltage to the rated
one, and secondary voltage 110V. The examination is same as above.
9.2.3.3.7 Regulate the excitation and make no-load characteristics of the generator’s
increase and decrease, maximum 1.05 times rated voltage (secondary
115V); conduct the inter-turn dielectric test for the generator (at this time,
the generator’s temporary over-voltage relay shall be reset to 120V, and
the over-voltage protection setting shall be accordingly modified to 120V)
for three minutes. Record the generator’s excitation current and stator
voltage, and examine the corresponding protection operations. See Table 2
for the record form.
Table 2 No-load Test Data of Generator-Transformer Set
Description 1 2 3 4 5 6 7 8 9
IL
Increase
UF
IL
Decrease
UF
9.2.3.3.8 Upon the completion of the test, minimize the excitation, and press the
inverting de-excitation button to decrease the generator’s voltage to zero.
9.2.3.3.9 Trip off the generator’s magnetic field breaker.
9.2.3.3.10 Measure the residual voltage and phase sequence of the generator at the
primary side (note: take care of safety in case that the voltage of the
primary side of the generator is more than 500V).
19
India Tengda 2×330MW Coal-fired Power Plant Project—Electrical Commissioning Scheme
20
India Tengda 2×330MW Coal-fired Power Plant Project—Electrical Commissioning Scheme
indicates that the direction is correct, at this time, switch on the trip.
9.2.3 Service power source switching
See Measures for Service Power Source Switching for details.
9.2.4Load test of excitation system
See Commissioning Measures for Excitation System for details.
9.3 336h full-load commissioning
9.3.1 Record the operation situation of the set and regularly collect and record
operation data.
9.3.2 Solve various technical problems occurred during commissioning.
9.3.3 Handle the defects and abnormalities concerning the commissioning.
21
India Tengda 2×330MW Coal-fired Power Plant Project—Electrical Commissioning Scheme
22