Sie sind auf Seite 1von 4

MONTHLY INSPECTION REPORT

Project:Construction of Legleg Farmers Multi-Purpose Center


Location:San Juan La Union
Contractor:J.A. OLIVAR
Contract Cost:4,983,495.00
Contract Duration:120 days

Work Accomplished to Date: 20-Sep-19


Date of Inspection: 26-Sep-19

ITEM NO. WORK DESCRIPTION CONTRACT AMOUNT AMOUNT TO DATE START FINISH REL. WEIGHT
A EARTHWORKS 12,960.63 12,312.60 21-Mar-19 0.25%
B EMBANKMENT 79,901.13 0.00%
C FORMWORKS SCAFFOLDINGS 155,886.40 155,886.40 27-Mar-19 3.13%
D RENFORCED CONCRETE WORKS 1,366,169.82 1,161,244.35 3-Apr-19 23.30%
E ROOFING & TINSMITHRY 2,891,487.00 2,602,338.30 10-May-19 52.22%
F ELECTRICAL WORKS 193,827.56 0.00%
G PAINTING WORKS 96,353.81 0.00%
H FENCE 134,691.15 0.00%
I MISCELLANEOUS WORKS 52,217.50 47,040.76 21-Mar-19 0.94%
TOTAL 4,983,495.00 3,978,822.41 79.84%

Observation:
Project tarpaulin was place on the construction site having an eyeview visible to every observers.
Construction site was not properly clean for the workers to have a pleasant and workable area that might hinder or slow their progress of works.
Site engineer was cooperative on explaining the details that need to be pointed out during the site inspection.
Progress of work by the contractor is timely, base on the program of work presented by the site engineer.
MONTHLY INSPECTION REPORT

Project:Construction of San Felipe Elementary School Covered


Location:San Juan La Union
Contractor:J.A. OLIVAR
Contract Cost:2,991,000.00
Contract Duration:120 days

Work Accomplished to Date: 20-Sep-19


Date of Inspection: 26-Sep-19

ITEM NO. WORK DESCRIPTION CONTRACT AMOUNT AMOUNT TO DATE START FINISH REL. WEIGHT
A EARTHWORKS 59,277.89 56,314.00 25-Mar-19 1.88%
B FORMWORKS SCAFFOLDINGS 88,220.20 88,220.20 29-Mar-19 11-Apr-19 2.95%
C RENFORCED CONCRETE WORKS 963,769.43 819,204.02 12-Apr-19 27.39%
D ROOFING & TINSMITHRY 1,685,067.55 1,516,560.80 15-May-19 50.70%
E ELECTRICAL WORKS 147,930.30 0.00%
F MISCELLANEOUS WORKS 46,734.63 42,011.28 25-Mar-19 1.40%
TOTAL 2,991,000.00 2,522,310.30 84.33%

Observation:
Upon arriving, surprisingly no workers on the site prompting us that it's been days no work was being executed by the contractor.
Roofing and tinsmithry was satisfactory constructed in conformity with the design and specifications, materials are approved with the preferred
standard based on the design.
Poor workplace, Areas should always be clean with accordance to health and safety program by DOLE.
Project might have slippage because of non continuous work.
MONTHLY INSPECTION REPORT

Project:Construction of Bacsayan Elementary School Covered Court


Location:San Juan La Union
Contractor:J.A. OLIVAR
Contract Cost:1,994,000.00
Contract Duration:100 days

Work Accomplished to Date: 25-Sep-19


Date of Inspection: 26-Sep-19

ITEM NO. WORK DESCRIPTION CONTRACT AMOUNT AMOUNT TO DATE START FINISH REL. WEIGHT
A EARTHWORKS 39,518.59 36,594.18 27-Mar-19 1.84%
B FORMWORKS SCAFFOLDINGS 70,685.35 70,685.35 3-Apr-19 8-Apr-19 3.54%
C RENFORCED CONCRETE WORKS 646,293.98 420,322.58 8-Apr-19 21.08%
D ROOFING & TINSMITHRY 1,085,530.43 595,586.53 9-May-19 29.87%
E ELECTRICAL WORKS 101,805.44 0.00%
F MISCELLANEOUS WORKS 50,166.21 37,119.96 27-Mar-19 1.86%
TOTAL 1,994,000.00 1,160,308.60 58.19%

Observation:
Project tarpaulin is placed properly having an eyeview for the public.
Continous work was observed health safety program was followed with accordance with DOLE.
Progress of work is timely, based on the program of work presented by the site engineer.
Construction is satisfactory, basing on the design and specification of the project same as for the materials that were installed all materials
are properly checked and passed the required standards of each items.