Project Dynamics
Name: CRM
Implement
ation
Project Ankur
Manager: Gupta
ID Module Requirem Requirem Process Functional
ent ent Sub ID Requirement
Bundle Bundle
3 1.3
• Loan Request is created in D365.
5 1.4 • Approval is required for every product.
• Depending on the price of the product,
loan approval request is sent to the correct
decision maker.
• Price of the Product will be coming from
defined pricelist in the Loan Process.
Project Ankur
Manager: Gupta
ID Module Requirem Requirem Process Functional
ent ent Sub ID Requirement
Bundle Bundle
Project Ankur
Manager: Gupta
ID Module Requirem Requirem Process Functional
ent ent Sub ID Requirement
Bundle Bundle
*Notification for Approval; will be redirected to defined user in Loan 1 2 In Scope Testing
configuration table after matching the criterias.
*Notification for Approval; will be redirected to defined user in Loan 1 2 In Scope Testing
configuration table after matching the criterias.
*Order will be created with required details from Loan Request. 1 2 In Scope Testing
*Out of the Box Order form will be reconfigured.
*Workflow to send the mail to Supply Chain Team for processing Loan
request further in SAP.
*Loan configurations will be set to mainatin the duration user wise. 1 2 In Scope Completed
*Notification for Approval; will be redirected to defined user in Loan 1 2 In Scope Testing
configuration table after matching the criterias.
*Notification for Approval; will be redirected to defined user in Loan 1 2 In Scope Testing
configuration table after matching the criterias.