AUXILARY RELAY TESTING

Testing Procedures
 Measure Relay Pick up & Drop off Voltage/current. Download: Auxiliary Te
 Measure Relay Pick up & Drop off Timing.
 Measure Relay Burden.
 Measure Relay Contact Resistance.

Equipment Required
1. Injection Kit (Sverker, Freja, .. etc).
2. Measurement Device (Multi-meter).
3. Connection Cables (Banana Type).

Sverker 760 Multi-meter


Pick Up & Drop Off Test
 Connection will be same as the shown figure.
 Increase voltage until the relay picks up. Note down the pick up value
for voltage & current.
 Decrease voltage until the relay drops off. Note down the drop off
value for voltage & current.

Conne
Pick Up & Drop Off Timing Test
 For timing test we will use one pole of MCB series with Ammeter to cut dc supply off.
 Use the other pole of MCB for starting sverker timer.
 Use any contact from the aux. relay to stop sverker timer.
 Inject 125V directly to the relay coil. Note down the pick up time.
 Energize the relay with 125V then switch the supply off. Note down the drop off time.

Burden Test
 Energize the relay with 125V and measure the dc current.
 Cal

TIMER RELAY TEST


Testing Procedures
 Measure Relay Pick up & Drop off Voltage/current. Download: Auxiliary Te
 Measure Relay Pick up & Drop off Timing.
 Measure Relay Burden (Before & After Operation).
 Measure Relay Contact Resistance.

Equipment Required
1. Injection Kit (Sverker).
2. Measurement Device (Multi-meter).
3. Connection Cables (Banana Type).

Sverker 760 Multi-meter


Pick Up & Drop Off Test
 Connection will be same as the shown figure.
 Increase voltage until the relay picks up. Note down the pick up value
for voltage & current.
 Decrease voltage until the relay drops off. Note down the drop off
value for voltage & current.

Conne
Pick Up & Drop Off Timing Test
 For timing test we will use one pole of MCB series with Ammeter to cut dc supply off.
 Use the other pole of MCB for starting sverker timer.
 Use any contact from the aux. relay to stop sverker timer.
 Inject 125V directly to the relay coil. Note down the pick up time.
 Repeat previous step several times with different time delay.
 Energize the relay with 125V then switch the supply off. Note down the drop off time.

Burden Test
 Adjust the timer with high time delay for example: 2 minutes.
 Energize the relay with 125V and measure the dc current.
 Note down the current before timer operates.
 After 2 minutes relay will pick up. Note down the current after operation.
 Calculate the relay power (W) = 125v x measured current

13.8 & 33kV Switchgear


Aux. Relays Test Meter Test
 Auxiliary relays.  Analog Ammeter & Voltmeter.
 Timers Auxiliary Relays.  Digital Ammeter & Voltmeter.

Equipment Test Stuck Stability Test


 Current Transformers Tests.  Stuck Stability Test.
 Voltage Transformer Tests.

Breaker Test High Voltage Test

 CB Timing Test.  MV Cable Test.


 Bus bar Contact Resistance.  Busbar High Voltage Test.

Gas Insulated Switchgear


GIS Test SF6 GAS Test
 DS, ES Timing Test.  Gauge Calibration Test.
 CB Timing Test.  SF6 Gas tests.
 Bus bar Contact Resistance.

Annunciation Test Energy Meter Test

 RTK Annunciators.  elster Alpha 1800 Meters.


 SACO Annunciators.

Stability Test High Voltage Test


 Busbar Stability Test.  High Voltage Test
 Transformer Stability Test.  HV Cable Test.