LV PANEL INSTALLATION
0 02.07.2019
Document1 Page 1 of 6
REVISION RECORD SHEET
NOTES
i) Revisions after Rev. 0 are denoted by a vertical line in the left hand left-hand margin against the revised
0 text, with the revision number displayed next to the revision line as shown example on the left.
ii) Revision 0 is issued for Review and approval. Subsequent revisions are to be 1, 2, 3 etc.
Document1 Page 2 of 6
The purpose of this method statement is to describe the methodology to ensure required safety
& quality for UNLOADING SHIFTING AND POSITIONING OF LV PANEL and control the process
under and above the foundation bases.
Table of Content
1 Objective& Scope
2 References
3 Instrument required
4 Equipment to be deployed
5 Responsibilities
Document1 Page 3 of 6
Working Methodology Statement–Installation of 11 KVA
PANEL Lifting Shifting & Installation Works
The purpose of generating this method statement is to define the procedure to lifting LT PANEL &
position to move the LT PANEL Foundation at final location.
Reference
F15 FORANA crane third party tested D shackle, wire rope sling, and safety belt. Original TPI
certificate will submit.
Responsibilities
Ensure all required submittals area made and required plant/ tools/ material and manpower is
available in timely manner.
Ensure necessary coordination with all involved for timely completion of job.
To obtain work permit.
Prepare JSA
Equipment and machinery required for this activity as per listed below.
Forana F15 Crane Lifting tool such as D shackle, web sling /Belt .Original TPI certificate will be
submit.
Method:
Lifting work permit to be obtain from issuing authority before start the activity.
Barricade all the area before start the Shifting the LT PANEL work .
Only trained team deployed in this erection & shifting activity.
All workers safety induction& physical fitness test done.
Take all team members done the job specific training.
LT PANEL Set will be lift and move kept on channel trench one by one.
Lift the LT PANEL 08 nos LT PANEL in 450 TO 750 PER COLOUMN In Weight each set 2.2
mtrs Length & 600 mtrs Width by F15 FORONA Crane EIGHT no’s 750 KG capacity by
using slings/lifting belts, D-Shackle (6.5 MT capacity) and ladder.
Position the FORONA F15 Crane for lift the LT PANEL Set , Radius of crane will be 12 to 14
Mtr.
Flag man/signal man to be providing during shifting & position work.
2 workmen will be holding the guide ropes for guiding the LT PANEL set while lifting.
Place the LT PANEL set slowly on position.
Ladder to be used for going to top of LT PANEL Set for fixing sling/D shackles.
FORONA F15Crane movement slowly shifting the Resting position of LT PANEL set .
Required Documents:
WORK PERMITò
TBT
APPROVED JSA
LIFTING PLAN
Document1 Page 5 of 6
Working area should be barricaded and hindrance free before shifting & position the LT
PANEL
No person should work in the area while erection work is in Progress.
Cable trench excavation openining should be full ally covered or barricade highlighting
this area before start the activity.
Safety Harness should be worn and shall be fixed in truss or rafter while working in
height
All the people who are assisting for erection work will be worn safety helmets and
Safety shoes.
Other Acoustic material shifting near Foundation area by using F15 Farana.