Sie sind auf Seite 1von 14

Tolerances for Precast

Concrete Structures
Marvin L. Vander Wal H. Carl Walker
Engineering Coordinator President
Carl Walker & Associates, Inc. Carl Walker & Associates, Inc.
Consulting Engineers Consulting Engineers
Kalamazoo, Michigan Kalamazoo, Michigan

Marvin L.`Vander Wal H. Carl Walker

Tolerances must be selected and specified in


order to properly design and build precast
concrete structures. At the present time,
published lists of tolerances do not completely
cover all the critical areas for individual and
combined concrete members.

The proposed list of tolerances was developed


for concrete structures with a precast concrete
structural system. The included examples
illustrate the application of tolerances to design
and construction. Work should be done by the
building industry to develop more complete
criteria for specifying tolerances and clearances
for building components.

44
ptimal design of precast concrete place concrete and precast concrete are
O structures requires, in addition to
technical competence, a comprehensive
listed in various industry publica-
tions. -5 In project concrete specifica-
knowledge of the capabilities of general tions our design firm includes by refer-
contractors, precast concrete manufac- ence "Specifications for Structural Con-
turers, and precast concrete erectors. A crete for Buildings (ACI 301-72)"2 as
structure must be designed and detailed the standard governing all cast-in-place
in such a manner that the complete concrete. Table 4.3.1 in ACI 301-72
structure will be safe, functional, aes- gives tolerances for formed surfaces in
thetically appealing, and economical. reinforced concrete buildings.
Detailed clearances, between precast In the past, we have rlso specified
concrete members and cast-in-place Manual for Quality.- Control for Plants
concrete or other precast concrete mem- and Production of . Precast Prestressed
bers, must be realistic. Tolerances, de- Concrete Products (PCI MNL-116-70)3
fined as specified permissible variations as the standard for precast concrete
from the dimensions and relationships tolerances.
shown on the drawings, must be eco- By monitoring the construction of
nomically attainable. numerous precast concrete structures,
The design engineer must consider we found that many times a tolerance
tolerances when sizing members, estab- question developed that was not cov-
lishing clearances, designing joints, and ered by our specified tolerances. A care-
designing connections. The contractor, ful search of ACI and PCI literature re-
precaster, and erector must carefully vealed to us that we could not solve
monitor tolerances in order to construct these tolerance questions by including
the structure as designed. additional published standards in our
Tolerances create a common ground project specifications.
for the designer and builder. Designers After consultation with general con-
work to absolute dimensions—some- tractors, precast concrete manufacturers
times to the hundredth of an inch. It is and precast concrete erectors, we de-
impossible to construct buildings to veloped a list of tolerances for buildings
these absolute dimensions. Buildings are designed with a precast concrete struc-
built by people and people are not er- tural system. Many of the following tol-
ror free. erances have not been previously pub-
Tolerances must be compatible with lished, except in the authors' project
the engineer's design to insure that, specifications.
when used to the limits, the elements These tolerances were developed to
are not overstressed. Tolerances must eliminate the indecision created in the
be compatible with abilities of the fab- plant and at the job site when variations
ricator, erector, and builder. Also, they occurred from the project plan and de-
must be compatible with the desired ar- tail dimensions—variations which were
chitectural expression and detail. not specified.
Tolerances must be chosen by the ar- Specifically, this paper will cover
chitect and engineer to meet the spe- tolerances in the following major areas:
cific requirements of the structure. They A. Tolerances for manufacture of
must also be included in the project precast concrete members
specifications, thereby establishing rules B. Tolerances for construction of
for the acceptability of the building cast-in-place concrete site work
components in their individual and that relates to precast concrete
combined states. C. Tolerances for erection of precast
Tabulations of tolerances for cast-in- concrete members

PCI JOURNAL/July-August 1976ҟ 45


A. Tolerances for Manufacture of
Precast Concrete Members

In this section, tolerances are given for '/4 in. up to 40-ft lengths
the following members: 3/8 in. 40 to 60-ft lengths
1. Columns 1/z in. greater than 60-ft lengths
2. Vertical ribbed wall panels d. Deviation from square or desig-
3. Flat wall panels nated skew:
4. Beams and spandrel panels ?/s in. per 12 in. of width, any
5. Double tee deck units cross section
6. Single tee deck units 1 in. maximum, any cross section
1/4 in. any end (with longitudinal
1. Columns (Fig. 1)* centerline)
a. Length: ± 1/2 in. e. Position of haunches and pockets:
b. Cross-sectional dimensions: - 1/4 in. ± i/a in.
c. Vertical alignment (deviation from f. Dimensions of haunches and pock-
straight line parallel to longitudinal ets: ± 1/4 in.
centerline of column): g. Haunch and pocket bearing surface
deviation from specified plane: Ys in.
No tolerances are given in PCI MNL-116-70 h. Difference in relative position of
for manufacture of precast concrete columns.

Fig. 1. Columns

46
Fig. 2. Vertical ribbed wall panels.

adjacent haunch and/or pocket f. Stem to edge of flange: ± 1/s in,


bearing surfaces from specified rela- g. Distance between stems: -!- 1/8 in.
tive position: '/4 in. h. Vertical alignment (deviation from
i. Position of sleeves and inserts: ±¼ straight line parallel to longitudinal
in. centerline of panel):
j. Position of weld plates: ± 1/z in. Abutting panels:
k. Position of anchor bolt holes in base
'Is in. up to 40-ft lengths
plate: -±% in.
3o in. 40 to 60-ft lengths
1. Position of base plates and bearing
% in. greater than 60-ft lengths
plates: ± l/4 in.
m. Position of handling devices: -!-3 in. Non-abutting panels:
1/4 in. up to 40-ft lengths
2. Vertical Ribbed Wall %s in. 40 to 60-ft lengths
Panels (Fig. 2)t /2 in. greater than 60-ft lengths

a. Length: -!- 1%4 in. i. Bowing: same as h. above


b. Width (over-all): ± r/s in. j. Differential bowing between adja-
c. Depth: ± 1/4 in. cent members of the same design:
d. Stem thickness: ±¼ in. 1/4 in.
e. Flange thickness: + 1/a in., — 1/s in. k. Warpage (one corner out of the
plane of the other three): 1/4 in.
i No tolerances a p e given in PCI MNL-116-70 1• Deviation from square or designated
for manufacture of precast concrete ribbed skew:
wall panels.

PCI JOURNAL/July-August 1976ҟ 47


1/4-in. ends, flange and stems 3. Fiat Wall Panels (Fig. 3)T
'/a-in. c penings and block-outs
a. Length and width:
m. Position of tendons: ± 1/s in.
±i/s in. 10 ft or under
n. Position of haunches: ± i/4 in.
o. Dimensions of haunches: ± i/4 in. ±l/s in., —Ilis in. 10 to 20 ft
± 1/s in., - 1/4 in. 20 to 30 ft
p. Haunch bearing surface deviation ±1/4 in. maximum, greater than 30 ft
from specified plane: 1/s in.
q. Difference in relative position of ad- b. Thickness: _tY4 in.. — r/a in,
jacent haunch bearing surfaces from c. Horizontal and vertical alignment
specified relative pzsition: 1/a in. (deviation from straight lines paral-
r. Position of openings and block-outs: lel to center line(s) and/or desig-
±¼ in. nated skew):
s. Dimensions of openings and block- ?/is in. per 10 ft of length
outs: ±± in. 1/a in. maximum
t. Position of sleeves and inserts: ±i/4 d. Bowing: (length of bow)/(480)
in, e. Differential bowing between adja-
cent members: 1/a in.
u. Position of weld plates: ± 11z in.
f. Warpage (one corner out of the
v. Position of flashing reglets: x- 1/4 in.
plane of the other three): 1/a in.
w. Position of anchor bolt holes in base
plate: ±'/s in. g. Difference in length of the two di-
x. Position of base plates and bearing
plates: -F'/4 in. No tolerances are given in PCI MNL-116-70
for manufacture of precast concrete flat wall
y. Position of handling devices: ±3 in. panels.

n
a

Fig. 3. Flat wall panels.

48
a

d /.

Ii'

bҟf

Fig. 4. Beams and spandrel panels.

agonal measurements: 4. Beams and Spandrel


1/8 in. per 6 ft with i/4 in. maximum Panels (Fig. 4)*
(square members)
Y4 in. square openings and block- a. Length: ± 1/z in.
outs *d. Width (over-all) ±^ in.
h. Position of tendons: ±% in. c. Ledge width: -¼ in.
i. Position of reinforcement: ± i/4 in. 'd. Beam width: -± i/4 in.
j. Position of haunches: } 1/4 in. "e. Beam depth: ±/4 in.
k. Dimensions of haunches: -!-'/a in. °f. Ledge depth: ± i/4 in.
1. Haunch bearing surface deviation g. Horizontal alignment (deviation
from specified plane: 1/8 in. from a straight line parallel to lon-
m. Difference in relative position of ad- gitudinal centerline of member):
jacent haunch bearing surfaces from 1/4 in. up to 40-ft lengths
specified relative position: Y4 in. 3/s in. 40 to 60-ft lengths
n. Position of openings and block-outs: 1/z in. greater than 60-ft lengths
1/4 ill. 'h. Camber deviation from specified
o. Dimensions of openings and block- design camber:
outs: x- 1/4 in. 1/s in. per 10 ft but not greater
p. Position of sleeves and inserts: ±'I4 than i in.
in. i. End deviation from square or des-
q. Position of weld plates: ±- in. ignated skew:
r. Position of flashing reglets: - Y4 in.
s. Position of handling devices: ±3 in. ° Tolerances taken from PCI MNL-116-70, 5.5.6.

PCI JOURNAL/July-August 1976ҟ 49


1/4 in. horizontal and vertical °c. Depth: tY4 in.
°j. Position of tendons: -!-'/s in. a d. Stem thickness: -!- 1/s in.
°k. Position of deflection point for de- *e. Flange thickness: +F in., - 1/s in.
flected strands: -6 in. "f. Stem to edge of top flange: ± 1/s in.
1. Position of openings and block- °g. Distance between stems: ± 1/s in.
outs: -±' in. "h. Horizontal alignment (deviation
m. Dimensions of openings and block- from a straight line parallel to lon-
outs: zt:Y4 in. gitudinal centerline of member):
n. Position of sleeves and inserts: ±¼ '/4 in. up to 40-ft lengths
in. % in. 40 to 60-ft lengths
o. Position of weld plates: ±- in. '/z in. greater than 60-ft lengths
p. Position of bearing plates: -L I/a in. °i. Camber deviation from specified
q. Bearing surface deviation from spe- design camber:
cified plane: -±- i/s in. 1/4 in. per 10 ft but not greater
r. Position of handling devices: -±-3 in. than 3/4 in.
j. Differential camber between adja-
cent members of the same design:
5. Double Tee Deck Units 1/a in. per 10 ft but not greater
(Fig. 5)* than s/4 in. for topped decks
*a. Length: -±- 1/z in. ¼ in. per 10 ft but not greater
°b. Width (over-all): ±¼ in. than 3/s in. for untopped decks
k. End deviation from square or des-
a Tolerances taken from PCI MNL-116-70, 5.5.2. ignated skew:

Fig. 5. Double tee deck units.

50
Fig. 6. Single tee deck units.

1/4 in. horizontal and vertical ee. Flange thickness: + 1/4 in., — 1/8 in.
*1. Position of - tendons: 4 in. °f. Horizontal alignment (deviation
e m. Position of deflection points for de- from a straight line parallel to
flected strands: -!-6 in. longitudinal centerline of member):
e n. Position of block-outs: ± 1/z in. '/4 in. up to 40-ft lengths
o. Dimensions of block-outs: —LY4 in. 3/s in. 40 to 60-ft lengths
p. Position of sleeves and inserts: -!-i/4 CJs in. greater than 60-ft lengths
in. °g. Camber deviation from specified
q. Position of weld plates: -±- 1/a in. design camber:
r. Position of bearing plates: -!- x/4 in. 1/a in. per 10 ft but not greater
s. Bearing surface deviation from spe- than s/4 in.
cified plane: 1/s in. h. Differential camber between adja-
t. Difference in relative position of cent members of the same design:
adjacent stem bearing surfaces from I in. per 10 ft but not greater
specified relative position: Y4 in. than 3/4 in. for topped decks
u. Position of handling devices: ±3 in. '/s in. per 10 ft but not greater
than % in. for untopped decks
6. Single Tee Deck Units i. End deviation from square or des-
(Fig. 6)* ignated skew:
r/4 in. horizontal and vertical
a. Length: ± 1/z in.
°b. Width (over-all): -± i/4 in. °j. Position of tendons: ± 1/4 in.
°c. Depth: t% in. °k. Position of deflection point for de-
°d. Width (stem): ±3Ao in. * Tolerances taken from PCI MNL-116-70, 5.5.3.

PCI JOURNAL/July-August 1976ҟ 51


nected strands: ±6 in. o. Position of weld plates: ± viz in.
l. Position of block-outs: - 1/z in. p. Position of bearing plates: i-¼ in.
nn. Dimensions of block-outs: ±} in. q. Bearing ,urface dev'ation from spe-
n. Positic n of sleeves and inserts: zLY4 cified plane: '/s in.
in. r. Position of handling devices: -±3 in.

B. Tolerances for Construction of Cast-in-Place Concrete


Site Work That Relates to Precast Concrete

In this section tolerances are given for location in plan:


the following members! ±2 in. any member, any location
1. Caisson, caisson caps, and pile c. Deviation in plan from straight
caps lines parallel to specified linear
2. Footings building lines:
3. Piers, columns, and walls '/4o in. per ft adjacent members less
4. Anchor bolts and sleeves than 20 ft apart or any wall length
less than 20 ft
1. Caissons, Caisson Caps, I/ in. adjacent members 20 ft or
and Pile Caps more apart or any wall length of
a. Variation of center from specified 20 ft
center in plan: ±2 in. °d. Deviation from plumb:
b. Variation of bearing surface from 1/4 in. any 10 ft of height
specified elevation: ±'/z in. 1 in. maximum for the entire height
e. Variation in elevation from speci-
2. Footings fied elevation:
°a. Variation of dimensions in plan: ± 1/2 in. any member, any location

+2 in., —3's: ; in. f. Deviation_-in elevation from lines


°b. Variation of center from specified parallel to specified grade lines:
center in plan: 1/o in. per ft adjacent members less
2 percent of footing width in di- than 20 ft apart or any wall length
rection of variation less than 20 ft
±2 in. maximum variation '/z in. adjacent members 20 ft or
c. Variation of bearing surface from more apart or any wall length of
specified elevation: -L 11/z in. 20 ft

3. Piers, Columns, and 4. Anchor Bolts and Sleeves


Walls a. Variation from specified location in
plan: ± 1/a in.
a. Variation in cross-sectional dimen-
sions of piers and columns and in b. Variation from specified elevation:
thickness 'of walls: -% in. ±1/z in.
b. Variation, in plan from specified ° Tolerances taken from ACI 301-72, Table 4.3.1.

C. Tolerances for Erection of Precast Concrete Members

In this section tolerances are given for 1. Columns


the following members: 2. Vertical ribbed wall ,panels

52
3. Flat wall panels c. Deviation from plumb:
4. Beams and spandrel panels 1/4 in. any 10 ft of height
5. Tee deck units 1 in. maximum for the entire height
d. Variation in elevation of bearing sur-
faces from specified elevation:
1. Columns ±½ in, any panel, any location
a. Variation in plan from specified lo- e. Deviation in elevation of bearing
cation in plan: surfaces from line parallel to spe-
± i/z in, any column, any location cified grade line:
b. Deviation in plan from straight lines ?%o in. per ft adjacent panels less
parallel to specified linear building than 20 ft apart
lines: 1/z in. maximum between adjacent
1/4o in. per ft adjacent columns less panels
than 20 ft apart f. Jog in alignment of matching edges:
'/z in. adjacent columns 20 ft or 1/4 in.
more apart g. Variation from specified joint width:
o. Difference in relative position of ad- ±V4 in.
jacent columns from specified rela- h. Variation of specified clearance from
tive position: adjacent independent member: ±¼
1/z in. at any deck level in.
d. Deviation from plumb:
'/4 in. any 10 ft of height 3. Flat Wall Panels
1 in. maximum for the entire height a. Variation in plan from specified lo-
e. Variation in elevation of bearing sur- cation in plan:
±1 in. any panel, any location
faces from specified elevations:
±^ in. any column, any location b. Deviation in plan from straight line
f. Deviation in elevation of bearing parallel to specified linear building
surfaces from lines parallel to spe- line:
cified grade lines: 13o in. per ft any length less than
//4o in. per ft adjacent columns less 20 ft
than 20 ft apart ½ in. maximum any 20 ft of length
1/z in. adjacent columns 20 ft or c. Deviation from plumb:
more apart 1/4 in. any 10 ft of height
g. Variation of specified clearance from 1/2 in. maximum for the entire height
adjacent independent member: ±i/4 d. Variation in elevation of bearing sur-
in. faces from specified elevation:
-L% in. any panel, any location
e. Deviation in elevation of bearing
2. Vertical Ribbed Wall surfaces from line parallel to spe-
Panels cified grade line:
a. Variation in plan from specified lo- 1/4o in. per ft any length less than
cation in plan: 20ft
-t in. any panel, any location 1/z in. maximum any 20 ft of length
b. Deviation in plan from straight line f. Jog in alignment of matching edges
parallel to specified linear building 1/4 in.
line: g. Variation from specified joint width:
%o in, per ft any panel or adjacent 1/4in.
panels less than 20 ft apart h. Variation of specified clearance from
1/2 in. maximum between adjacent adjacent independent member: ±'/4
panels in.

PCI JOURNAL/July-August 1976ҟ 53


4. Beams and Spandrel ±a/a in. any tee, any end
Panels f. Deviation in elevation from line par-
allel to specified grade line:
a. Variation in plan from specified lo- 3/4 in. longitudinal
cation in plan: 3/s in. transverse
-!- 1/z in. any beam, any location g. Jog in alignment of adjoining flanges:
b. Deviation in plan from straight line 1/8 in. untopped decks
parallel to specified linear building ?/z in. topped decks
line: h. Variation from specified flange joint
¼o in. per ft any beam less than width: ± i/4 in.
20 ft i. Variation of specified clearance from
1/2 in. maximum any beam adjacent independent member: ±i/4
20 ft or more in length in.
c. Variation from specified bearing
length on support: -} a/4 in.
d. Variation from specified bearing General Discussion
width on support: ± 1/a in.
e. Variation in elevation of bearing sur- It might be helpful to point out the
faces from specified elevation: distinction that is made between varia-
± r/z in. any beam, any location tion and deviation in the above-listed
f. Deviation in elevation of bearing tolerances. A variation is defined as an
surfaces from lines parallel to spe- additive or subtractive (plus or minus)
cified grade lines: difference from a specified dimension
i4o in. per ft any length less than or relati nship. A deviation is defined
20 ft as an absolute difference from a spe-
1/z in. maximum any beam 20 ft or cified relationship.
more in length This distinction can be seen in the
g. Deviation of top of spandrel from column erection tolerances given in
specified elevation: C.l.e. and f. where the variation in
i/2 in. any panel elevation of column bearing surfaces
h. jog in alignment of matching edges: from specified elevation is given as
¼ in. ±1 in. for any location while the devi-
i. Variation of specified clearance from ation of bearing surfaces from a line
adiacent independent member: —LY4 parallel to a specified grade line is
in. given as 1/z in. for adjacent columns
20 ft or more apart.
5. Tee Deck Units We found it necessary to include in
a. Variation in plan from specified lo- the erection tolerances a clearance
cation in plan: variation for "adjacent independent
± 1/z in. any tee, any location members." Adjacent independent mem-
b. Deviation in plan from straight line bers are members that are close to-
parallel to specified linear building gether but are not connected struc-
line: turally.
1/2 in. any tee These members may both be precast
c. Variation from specified bearing concrete or they may be combinations
length on support: ±'3/a in. of precast concrete and cast-in-place,
d. Variation from specified bearing masonry, or steel. Typically, this clear-
width on support: ± i/z in. ance situation develops at an expansion
e. Variation in elevation from specified joint or at the interface between a
elevation: stair tower and a larger structure when

54
P/C COLUMN

COLUMN BASE PLATE

UT-

Fig. 7. Column/footing elevation tolerances.

the two are joined only by an expan-


sion joint. Design Applications
Careful inspection of the listed tol-
erances will reveal that many times Manufacturing, construction, and erec-
one tolerance will override another. tion tolerances must be considered
The column manufacturing tolerances throughout the design phase of a pre-
in A.l.e..and h. allow for a variation in cast concrete structure. This point is
the position of a column haunch of illustrated by two examples based on
-t in. but restrict the relative posi- these tolerances.
tion of adjacent haunch bearing sur-
faces to '/4 in. Thus, while any column
Example 1—Clearance Between
haunch may be '/4 in. low or high, one
Precast Concrete Column and
haunch may not be ¼ in. low and the
Footing
adjacent haunch 1/a in. high.
Similarly, according to erection The column is to be connected to the
tolerances C.I.a. and C.4.a., a col- footing by anchor bolts with non-shrink
umn and beam may both vary from grout filling the void between the
specified location in plan by ± l/z in. column base plate and the footing as
while according to C.4.c. the beam shown in Fig. 7.
bearing length may only vary by x- The minimum thickness of grout
in. In this way, the beam bearing tol- between the base plate and the footing
erance will not permit the column to is to be limited to 1 in. According to
be 1/z in. off the specified location in cast-in-place concrete tolerance B.2.c.
one direction and the beam bearing on and column erection tolerance C.1.e.,
the column to be 1/2 in. off the spe- the bearing surfaces of the footing and
cified location in the opposite direc- column may vary -!- in. from the
tion. specified elevation. The clearance must

PCI JOURNAL/July-August 1976 55


BEAM BEARING FOR
DESIGN = xy

BEAM BEARING ALLOWED


BY TOLERANCES =
(x33/4") (y; I/2")

TOLERANCE ENVELOPE

P/C COUJMN

Fig. 8. Beam/column bearing tolerances.

then be detailed at 2 in. to allow for column pocket. Both the end of the
the possibility that the footing is ' in. beam and the bottom of the pocket
high and the column base plate 1/2 in. must be designed for the worst case
low. of bearing.
The projection of the anchor bolts According to erection tolerances
from the footing must also be checked C.4.c. and d. the beam bearing length
since in cast-in-place concrete tolerance may vary -!- 3/4 in. and the beam bearing
B.4.b. they are allowed to vary ±r in. width may vary ± 1 in. from the spe-
from the specified elevation. cified bearing in the pocket (see Fig. 8).
Thus, the bolt must be detailed to Instead of the specified bearing sur-
project 1 in. more than required for face of 6.0 x 2.0 in. = 132.0 sq. in., the
the 2 in. clearance to allow for the bearing surface, could be 5.25 x 21.50
possibility that the plate is 1/2 in. high in. = 112.88 sq in.
and the bolt is 1/z in. low. The actual bearing stress could be
The bolt must be detailed to have (132.0)/(1.12.88) = 1.17 times greater
1 in. more thread than required for than the bearing stress calculated by
t1'e desi gn connection to allow for the using the detailed dimensions.
possibility that the bolt is % in. high Adding a factor of 0.12 to 1.17 (to
and the plate is % in. low. insure that the connection area has a
10 percent greater design safety factor
Example 2—Bearing of Beam than the connected members) would
in Column Pocket give a reasonable additional load factor
A 24-in, wide beam is to bear 6 in. on for the design of beam and pocket
a 7 x 22-in, raised surface within the bearing of 1.29.

56
structures. Work should also be done
Concluding Remarks to develop criteria for specifying tol-
erances and clearances for the erection
The specification of tolerances for the of precast concrete members on cast-
manufacture and erection of precast in-place concrete and structural steel
concrete and for the construction of frames.
related cast-in-place concrete elimi-
nates indecision and sets the ground
rules for the acceptance of the com- References
plete structure. The specifying of tol-
erances helps engineers to arrive at 1. ACI Committee 347, "Recommend-
logical rather than arbitrary load fac- ed Practice for Concrete Formwork
tors for connection design. (ACI 347-68)," American Concrete
The construction of structures man- Institute, Detroit, Michigan, 1968.
ufactured under these rules will go 2. ACI Committee 301, "Specifications
more smoothly because the specified for Structural Concrete for Build-
tolerances will help to make all parties ings (ACI 301-72)," American Con-
involved aware of their respective re- crete Institute, Detroit, Michigan,
snonsibilities. Careful selection and use 1972.
of tolerances for each specific project 3. PCI MNL 116-70 Manual for Qual-
can only help improve the quality of ity Control for Plants and Produc-
the project and insure a satisfied build- tion of Precast Prestressed Concrete
in e owner. Products, Prestressed Concrete In-
On the precast concrete structural stitute, Chicago, Illinois, 1970.
system projects, for which we have pro- 4. PCI Arch+teetural Precast Concrete,
posed the above listed tolerances, we Prestressed Concrete Institute, Chi-
have experienced a vast improvement cago, Illinois, 1973.
in the design and construction se- 5. PCI Architectural Precast Concrete
quence. The concrete building industry Drafting Handbook, Prestressed
should develop more complete criteria Concrete Institute, Chicago, Illinois,
for specifying tolerances in concrete 1975.

Discussion of this paper is invited.


Please forward your discussion to
PCI Headquarters by December 1, 1976.

PCI JOURNAL/July-August 1976ҟ 57

Das könnte Ihnen auch gefallen