Sie sind auf Seite 1von 1

ABSTRACT

Name : Maajid Jati Laksamana


NPM : 13315974
Title : Bored pile planning on the Jakarta - Cikampek elevated toll
Road at STA. 17+763 – STA. 17+808
level : Bachelor degree in civil engineering at Gunadarma University
Keywords : Bored pile, carrying capacity of the foundation, foundation
drop, pile cap

(xiv + 104 + attachment)

Study of (bored pile) foundation planning was conducted at the "Jakarta -


Cikampek 2 Elevated Toll Road Construction Project STA. 17+763 – STA.
17+808”. The bored pile in this project is planned to hold the burden of the toll
flyover structure. The purpose of the planning study (bored pile) is to calculate the
carrying capacity of the bored pile group and foundation drop, and to plan the
reinforcement of the bored pile foundation.
The first method used in the bored pile foundation planning process is the
Meyerhof (1976) method with the results of the Standard Penetration Test to
determine the carrying capacity of the foundation permit. The second method is a
semi-empirical method used to calculate the decrease of a single pile foundation
bored pile. The third method is the vesic method, this method is used to calculate
the immediate decrease in the pile group on the bored pile foundation. The fourth
method is the davisson & gill method, this method is used to get the value of the pile
deflection that occurs on a bored pile foundation.
Based on the results of soil investigations at (BH-20) precisely at STA. 17
+ 808 obtained the characteristics of the type of soil is sandy clay with the majority
of clay and the depth of hard soil is at a depth of 19 m with an N-spt value of 66.
Based on the results of the calculation of the bored pile foundation on pier 122 with
a drill pole diameter of 1 m and into a 19 m pole the carrying capacity of a single
pile permit is 567,085 tons. The decrease of single pile foundation on pier 122 is
14,884 mm, while for the decrease in pile foundation group on pier 122 is 34,850
mm.
Based on the results of the calculation of the reinforcement analysis, the
result of longitudinal reinforcement in the bored pile foundation is 16D25 while for
the shear reinforcement of the bored pile foundation is D13-270. The total cost for
the construction of this foundation is detailed in the form of RAB with a value of Rp
4,422,959,675.39