Beruflich Dokumente
Kultur Dokumente
Capability
Discharge
in $/kWh
@ %DOD
Specific
Cycling
Operating
(MWh)
Self
time
uncontrollable and intermittent power generation. Many NaS 200-600 Sec-hrs 0.4-244.8 100-175 2500@100 10-20 75-89 No 325
renewable energy producers are unable to sell their power Ni-Cd 400-2400 Sec-hrs 6.75 30-80 3500@100 10-20 70 0.2-0.3 -40 to 50
due to unavailability of power evacuation infrastructure Li-ion 900-1300 Sec-Min 0.001-50 100-200 1500-3500@80 14-16 75-95 5-Jan -30 to 60
([1]-[2]). Also, failure to meet scheduled dispatches makes VRB 600 Sec-10hrs 2-120 30-50 100-13000@75 10-20 65-85 Very low 0 to 40
them less attractive and more a problem than aid for grid ZBB 500 Sec-10hrs 0.1-4 60-85 2000-2500 8-10 65-85 No 0 to 40
regulators. PSB 300-1000 Sec-10hrs 0.005-120 >400 100-13000@75 15 60-75 No 0 to 40
Energy storage systems have proved to play an
essential role in elimination of these interruptions and Li et al. [4] developed a dispatch schedule where the
making wind power deliverable. The nature of wind power battery storage is operated so as to deliver minimum and
requires a storage which is capable of rapid power maximum wind generation alternatively to extend battery
absorption and delivery. Also, solar energy is available lifetime and costs. Nguyen et al. [5] modified the above
only for a few hours during day and even this, is weather discussed strategy to increase battery lifetime and minimize
dependent. Large scale storages like pumped hydro and errors in wind power. Also the study incorporated a lifetime
compressed air require huge investments and are site cost function based optimization algorithm to reduce the
dependant. Other options like flywheels and battery capacity needed. A short term power dispatch
supercapacitors characteristic of rapid response time have control has also been outlined to depict the behavior of the
limitations in terms of power ratings and are self- system in case of transients in the wind farm output.
discharging. Hence, battery storages are the most suitable Abdullah et al. [6] modelled a stochastic
form of storage to be integrated with renewable systems. programming based dispatch strategy which considered
They are available in many types and ranges as detailed in uncertainties of wind speeds and energy prices. Also a rank
Table I [3]. based dispatch strategy was developed for multiple Battery
222
with a reversal in the direction of current flow. In a flow Hence, the power dispatch is scheduled based on min-
battery, the volume of the electrolyte stored gives the max strategy in such a manner that the discharge intervals
energy capacity of the storage. However, the power are scheduled to be in the peak demand times. And during
capacity depends on the area of contact of electrode with the low demand times the battery is set to charging phase.
the electrolyte solution. VRB batteries find varying This enables the hybrid system to deliver power during
applications such as renewable power penetration in power peak demand times and hence, aid in load leveling. The
grid; load levelling, frequency regulation and energy min-max power dispatch method [5] is as explained
arbitrage. A validated dynamic model o a VRB can be below:
studied in [12]. The SOC of the battery gives an expression Step 1: Selection of time interval Td so as to ensure
of the battery energy levels and is given by that battery is never overcharged or fully discharged.
( Pb (t ))dt Usually, it is set to be an hour on the time scale. Greater
SOC (t ) = SOC (t − 1) + (4) the time interval smoother will be the power dispatch
Ebess
curve.
Where Pb -Battery charge/discharge power (kW); Step 2: The power generated profile is split into N
Ebess -Battery capacity (kWh) sets of data where N will be the number of time intervals
in the simulation period.
III. SIZING OF VRB BASED ON POWER DISPATCH Step 3: In each interval i the minimum and
A. Power Dispatch Based On Min-Max Strategy maximum power generated is identified. Depending on
Q.Li [4] proposed a min-max strategy of power the status of the battery in that particular interval period
dispatch to determine the battery storage capacity for a i
the power dispatch ( Ppd ) is set as follows:
wind farm. Later this was modified by Nguyen et al. [5]
to improve battery lifetime and minimize storage Let Pgen denote the renewable power generated from
capacity. The basic idea is to formulate the power the wind-PV system.
dispatch based on battery operation so that the battery For discharging:
storage undergoes alternating charge and discharge cycle
intervals. During the charging interval the power dispatch
Ppdi = MAX
( i −1) Td ≤t ≤iTd
{Pi
gen (t )}
is set to minimum value of the wind power generated in For charging:
that interval and excess power is used to charge the
battery. On the other hand, in the discharge interval the
Ppdi = MIN
( i −1) Td ≤t ≤iTd
{Pi
gen (t )} (5)
power dispatch is set to maximum value of the wind Using the above procedure the power dispatch curve
power generated and the deficit power is drawn from the i
battery. P is formulated. When the battery is in the discharging
pd
In this paper, we further implement the above state, the power to be delivered is set to maximum value
explained strategy with a modification to incorporate the of the power generated in that interval. Hence, the deficit
peak shaving features. Generally, power grid experiences power is to be discharged from the battery. Similarly,
peak power during mornings and evenings as shown in when the battery is in the charging state a minimum
Fig. 2. But, renewable power generation depends on power level is dispatched to the grid and the remaining
availability of natural sources which are uncontrollable. power is used to charge the battery storage system.
Thus, there occurs power mismatch between the In this study the battery state is set depending on the
generation and demand. peak demand curve of the power grid. It is obvious by
studying the demand curve from Fig. 2, that there are four
major features in the demand curve viz., wee morning
trough, a late morning peak, an mid-afternoon trough, and
an late evening peak. Hence, the time intervals are
segregated into four phases based on the demand phases.
When the battery is in the peak phase then its status is set
to be discharging in order to meet the peak load and vice
versa. Scheduling dispatch as per this strategy helps in
optimum utilization of battery and thus longer lifetime of
battery with fewer charging cycles. Also, the battery size
is effectively reduced compared to battery sizes required
for regulating dispatch based on wind forecasts. As the
investment costs depend on the size, it is imperative that
the battery capacity is reduced as much as possible while
meeting all power requirements.
Fig. 2. General Demand curve of a power grid
Source: TERI analysis
223
B. Sizing Strategy for VRB and solar irradiation in 10 min intervals. Thus the power
VRB battery sizing is based on the power dispatch generated from the hybrid wind system is calculated after
curve as estimated in Section III. To maintain power including efficiencies of the turbine and panel as listed in
balance in the system, it is assumed that the power Table II. The generated power curves thus obtained are
generated is equal to the sum of power dispatch and shown in Fig. 5.
power to/from the battery. Hence, the power absorbed or
discharged from the battery at time t Pb(t) and is given by TABLE II. WIND TURBINE AND SOLAR PANEL DATA
(8)
Irradiation in W/sq.m
{| P (t ) |}
Temperature in ºC
Pchrat [i ] = MAX i
ch
( i −1)Td ≤t ≤iTd 600 30
400 28
the ith interval Td. As the battery capacity must meet the Temperature in
deg.celcius
rated
Pbess = MAX { Pbrat [i ]} (10)
15
1≤ i ≤ N 14
12
rated
is the efficiency then E bess can be evaluated 11
10
rated
using Pbess . 9
224
Evolution of power curve
250
Pw = Wind Power Power curve
Ppv=Solar
Pgen = Total
power
power 250
Pgen = Power form Wind
Ppd = Dispatch
200
200
150
Power in kW
150
Power in kW
100
100
50
50
0
0:00 5:00 9:00 13:00 17:00 21:00 24:00 Charging phase
Time of day
Discharge phase Charging phase Discharge phase
Early morning trough Morning peak Mid−day trough Evening peak Late
0 night 24:00
1:00 5:00 9:00 13:00 17:00 21:00
Time of day trough
Fig. 5. Power curves for wind, solar and combined hybrid system
Fig. 6. Power dispatch curve
Hence, an energy storage system is needed to bridge this 0
Discharge rate of VRB
power gap. VRB storage is very well suited for these −10
applications. −20
−50
−90
120
show that min/max generated power delivery depending Fig. 8. VRB charge power rating
on the battery states.
Sizing of battery storage will now depend on the
power needed for the generation to meet the dispatch Charging power to VRB
225
power is met by discharging the battery. The battery is modified min-max dispatch strategy which considers
assumed to have an initial 60% SOC with 75% DOD and peak demand periods of a power grid. The methodology
care is to be taken to avoid the battery from charging was tested for a 275kW wind-PV HRES with real time
beyond 95% of its capacity. A battery management data and the results have been documented. The battery
system is then included as shown in Fig. 10. The battery thus sized is evaluated for its performance to deliver the
undergoes approximately two complete charge/discharge dispatched load with only 2% LPSP. Also, an energy
cycles which implies that the battery capacity is management framework has been implemented to avoid
effectively utilized to improve its useful lifetime. The over/ under charging of the battery. The performance
power delivered by the hybrid wind-PV-VRB system is shows effective utilization of battery capacity with
plotted in Fig. 11. The delivered power approximately minimum number of charge discharge cycles so as to
follows the dispatch curve with minor exceptions when maximize battery life. Control of battery storage system
battery becomes completely discharged with a LPSP ratio for emission of forecast errors in the wind data can
of 2.7% only. Thus, the VRB battery aids the hybrid further be analyzed as future prospects from this work.
renewable generation to meet the scheduled dispatch
effectively. REFERENCES
1. Weak grid connections stalling China's wind energy growth.
http://www.modernpowersystems.com/news/newsweak-grid-
connections-stalling-china-s-wind-energy-growth.
2. U.S.Department of Energy. 2013 Distributed Wind Market Report.
August 2014.
3. H. Fathima, K. Palanisamy, “Battery energy storage applications in
wind integrated systems – a review”, IEEE sponsored ISEG 2014.
doi: 10.1109/ISEG.2014.7005604.
4. Q. Li, S.S. Choi, Y. Yuan, D.L. Yao, “On the determination of
battery energy storage capacity and short-term power dispatch of a
wind farm”, IEEE Transactions on Sustainable Energy, vol. 2(2),
2011, pp. 148-158.
5. C. Nguyen, H. Lee, T. Chun, “Cost-optimized battery capacity and
short-term power dispatch control for wind farm”, IEEE
Transactions on Industry Applications, vol. 51(1), 2015, pp. 595-
606.
6. M.A. Abdullah, K.M. Muttaqi, D. Sutanto, A.P. Agalgaonkar, “An
effective power dispatch control strategy to improve generation
schedulability and supply reliability of a wind farm using a battery
energy storage system”, IEEE Transactions on Sustainable
Energy, vol.6(3),2015, pp. 1093 - 1102.
doi: 10.1109/TSTE.2014.2350980.
7. D.L. Yao, S.S. Choi, K.J. Tseng, T.T. Lie, “Determination of short-
term power dispatch schedule for a wind farm incorporated with
Fig. 10. Energy management of VRB dual-battery energy storage scheme”, IEEE Transactions on
Sustainable Energy, vol. 3(1), 2012,pp. 74-84.
8. F. Luo, K. Meng, Z.Y. Dong, Y. Zheng, Y. Chen, K.P. Wong,
250
Power delivered curve
“Coordinated operational planning for wind farm with battery
Ppd = disp power
Pgen=Generation
Pdelf = Delivered
energy storage system”, IEEE Transactions on Sustainable
power
Energy, vol. 6(1), 2015, pp. 253-262.
200 9. S. Teleke, M.E. Baran, A.Q. Huang, S. Bhattacharya, L. Anderson,
“Control strategies for battery energy storage for wind farm
dispatching”, IEEE Transactions on Energy Conversion, vol.
150 24(3), 2009, pp. 725-732.
10. S. Teleke, M.E. Baran, S. Bhattacharya, A.Q. Huang, “Optimal
Power in kW
226