Sie sind auf Seite 1von 12

Ø Longitud Parcial Longuitud de Acero Por Tipo

Veces
Nº de
Und
ITEM DESCRIPCIÓN
Pulg. Largo 1/4 3/8 1/2 5/8 3/4 1
ACERO EN VIGAS DE CIMENTACION F'y=4,200 kg/cm² GRADO 60 Kg 10.72
Eje F-F y A-A entre 1-3
Acero Superior L=1+0.2*2-0.03*2 1/2 8 1.34 10.72
Estribos #=((1-2*0.05-2*0.1)/0.2)-1 3/8 14 1.06 14.84
Long. Estribos = (0.25*2+0.4*2-8*0.03) 3/8 0.00
Eje F-F y A-A entre 1-3
Acero Superior L=3.25+0.2*2-0.03*2 1/2 8 3.59 28.72
Estribos #=((3.25-2*0.05-2*0.1)/0.2)-1 3/8 36 1.06 38.16
Long. Estribos = (0.25*2+0.4*2-8*0.03) 3/8 0.00
Eje F-F y A-A entre 1-3
Acero Superior L=2.65+0.2*2-0.03*2 1/2 8 2.99 23.92
Estribos #=((2.65-2*0.05-2*0.1)/0.2)-1 3/8 30 1.06 31.80
Long. Estribos = (0.25*2+0.4*2-8*0.03) 3/8 0.00
Eje F-F y A-A entre 1-3
Acero Superior L=2.15+0.2*2-0.03*2 1/2 8 2.49 19.92
Estribos #=((1-2*0.05-2*0.1)/0.2)-1 3/8 26 1.06 27.56
Long. Estribos = (0.25*2+0.4*2-8*0.03) 3/8 0.00
Eje F-F y A-A entre 1-3
Acero Superior L=4.58+0.2*2-0.03*2 1/2 4 4.92 19.68
Estribos #=((4.58-2*0.05-2*0.1)/0.2)-1 3/8 25 1.06 26.50
Long. Estribos = (0.25*2+0.4*2-8*0.03) 3/8 0.00
Eje F-F y A-A entre 1-3
Acero Superior L=4.35+0.2*2-0.03*2 1/2 4 4.69 18.76
Estribos #=((4.35-2*0.05-2*0.1)/0.2)-1 3/8 7 1.06 7.42
Long. Estribos = (0.25*2+0.4*2-8*0.03) 3/8 0.00
Eje F-F y A-A entre 1-3
Acero Superior L=2.48+0.2*2-0.03*2 1/2 4 2.82 11.28
Estribos #=((2.48-2*0.05-2*0.1)/0.2)-1 3/8 14 1.06 14.84
Long. Estribos = (0.25*2+0.4*2-8*0.03) 3/8 0.00
Eje F-F y A-A entre 1-3
Acero Superior L=2.25+0.2*2-0.03*2 1/2 4 2.59 10.36
Estribos #=((2.25-2*0.05-2*0.1)/0.2)-1 3/8 13 1.06 13.78
Long. Estribos = (0.25*2+0.4*2-8*0.03) 3/8 0.00
Eje F-F y A-A entre 1-3
Acero Superior L=4.65+0.2*2-0.03*2 1/2 4 4.99 19.96
Estribos #=((4.65-2*0.05-2*0.1)/0.2)-1 3/8 25 1.06 26.50
Long. Estribos = (0.25*2+0.4*2-8*0.03) 3/8 0.00
Eje F-F y A-A entre 1-3
Acero Superior L=4.5+0.2*2-0.03*2 1/2 4 4.84 19.36
Estribos #=((4.5-2*0.05-2*0.1)/0.2)-1 3/8 20 1.06 21.20
Long. Estribos = (0.25*2+0.4*2-8*0.03) 3/8 0.00
ACERO EN COLUMNAS F'y=4,200 kg/cm² GRADO 60 Kg
Columna 1
a=1.1+0.2+2.5+0.2+2.5+0.2+2.8+0.27+0.4+0.6+0.5-0.075+0.25 5/8 44 11.45 503.80
11.445 1/2 22 11.45 251.90
Columna 2
a=1.1+0.2+2.5+0.2+2.5+0.2+2.8+0.27+0.4+0.6+0.5-0.075+0.25 1/2 36 11.45 412.20
11.445
Estribos Columna 1 3/8 5 5.20 26.00
Zapata y Cimiento Corrido #=0.5+0.6/0.2-1
4.5
Estribos Columna 1 3/8 19 19.76 375.44
Viga de Cimentacion hasta 1erPiso #=2.8+0.27-2*0.05-6*0.1-6*0.15/0.25-1
4.88
Ø Longitud Parcial Longuitud de Acero Por Tipo

Veces
Nº de
Und
ITEM DESCRIPCIÓN
Pulg. Largo 1/4 3/8 1/2 5/8 3/4 1
#Total de Estribos=5+2+6+6
Estribos Columna 1 3/8 15 15.60 234.00
1erPiso hasta 2doPiso #=2.5-2*0.05-4*0.1-4*0.15/0.25-1
4.6
#Total de Estribos=5+2+4+4
Estribos Columna 1 3/8 15 15.60 234.00
2doPiso hasta 3erPiso #=2.5-2*0.05-4*0.1-4*0.15/0.25-1
4.6
#Total de Estribos=5+2+4+4
Estribos Columna 2 3/8 5 6.70 33.50
Zapata y Cimiento Corrido #=0.5+0.6/0.2-1
4.5
Estribos Columna 2 3/8 19 25.46 483.74
Viga de Cimentacion hasta 1erPiso #=2.8+0.27-2*0.05-6*0.1-6*0.15/0.25-1
4.88
#Total de Estribos=5+2+6+6
Estribos Columna 2 3/8 15 0.00
1erPiso hasta 2doPiso #=2.5-2*0.05-4*0.1-4*0.15/0.25-1
4.6
#Total de Estribos=5+2+4+4
Estribos Columna 2 3/8 15 0.00
2doPiso hasta 3erPiso #=2.5-2*0.05-4*0.1-4*0.15/0.25-1
4.6
#Total de Estribos=5+2+4+4
Columna 1 L=0.25*2+0.25*2-0.04*4+0.1*2
1.04
Columna 2 L=0.25*2+0.40*2-0.04*4+0.1*2
1.34
ACERO EN VIGAS F'y=4,200 kg/cm² GRADO 60 Kg
VIGAS PRINCIPALES
VIGA 1-1 Entre A-E
Acero Superior A-E, L=15.1-2*0.03+2*0.02=15.08 |____| 1/2 1 15.08 15.08
Acero Inferior A-E, L=15.1-2*0.03+2*0.02=15.08 |____| 1/2 1 15.08 15.08
Balancin Superior en A, L=1+0.25-0.03=1.22 --------- 1/2 1 1.22 1.22
Balancin Superior en B, L=1+0.25-=1.25 --------- 1/2 1 1.25 1.25
Balancin Superior en C, L=1+0.25-=1.25 --------- 1/2 1 1.25 1.25
Balancin Superior en D, L=1+0.25-=1.25 --------- 1/2 1 1.25 1.25
VP 1-1 Estribos en A-B, L=0.25*2+0.4*2-0.03*8+0.1*2=1.26 3/8 25 1.26 31.50
4.73-2*0.05-6*0.10-4*0.15=3.43
3.43/0.25-1=12.72
VP 1-1 Estribos en B-C, L=0.25*2+0.4*2-0.03*8+0.1*2=1.26 3/8 16 1.26 20.16
2.4-2*0.05-6*0.10-4*0.15=1.1
1.1/0.25-1=3.4
VP 1-1 Estribos en C-D, L=0.25*2+0.4*2-0.03*8+0.1*2=1.26 3/8 24 1.26 30.24
4.5-2*0.05-6*0.10-4*0.15=3.2
3.2/0.25-1=11.8
VP 1-1 Estribos en D-E, L=0.25*2+0.4*2-0.03*8+0.1*2=1.26 3/8 15 1.26 18.90
2.23-2*0.05-6*0.10-4*0.15=3.2
0.93/0.25-1=2.72
VIGA 2-2 Entre A-E
Acero Superior A-E, L=15.1-2*0.03+2*0.02=15.08 |____| 1/2 1 15.08 15.08
Acero Inferior A-E, L=15.1-2*0.03+2*0.02=15.08 |____| 1/2 1 15.08 15.08
Balancin Superior en A, L=1+0.40-0.03=1.37 --------- 1/2 1 1.37 1.37
Balancin Superior en B, L=1+0.40=1.40 --------- 1/2 1 1.40 1.40
Balancin Superior en C, L=1+0.40=1.40--------- 1/2 1 1.40 1.40
Ø Longitud Parcial Longuitud de Acero Por Tipo

Veces
Nº de
Und
ITEM DESCRIPCIÓN
Pulg. Largo 1/4 3/8 1/2 5/8 3/4 1
Balancin Superior en D, L=1+0.40=1.40 --------- 1/2 1 1.40 1.40
VP 2-2 Estribos en A-B, L=0.25*2+0.4*2-0.03*8+0.1*2=1.26 3/8 24 1.26 30.24
4.5-2*0.05-6*0.10-4*0.15=3.2
3.2/0.25-1=11.8
VP 2-2 Estribos en B-C, L=0.25*2+0.4*2-0.03*8+0.1*2=1.26 3/8 15 1.26 18.90
2.25-2*0.05-6*0.10-4*0.15=0.95
0.95/0.25-1=2.8
VP 2-2 Estribos en C-D, L=0.25*2+0.4*2-0.03*8+0.1*2=1.26 3/8 24 1.26 30.24
4.35-2*0.05-6*0.10-4*0.15=3.05
3.05/0.25-1=11.2
VP 2-2 Estribos en D-E, L=0.25*2+0.4*2-0.03*8+0.1*2=1.26 3/8 15 1.26 18.90
2.15-2*0.05-6*0.10-4*0.15=0.85
0.85/0.25-1=2.4
VIGA 2'-2' Entre E-D
Acero Superior A-E, L=2.65-2*0.03+2*0.02=2.63 |____| 1/2 1 15.08 15.08
Acero Inferior A-E, L=2.65-2*0.03+2*0.02=2.63 |____| 1/2 1 15.08 15.08
VP 2'-2' Estribos en D-E, L=0.25*2+0.4*2-0.03*8+0.1*2=1.26 3/8 15 1.26 18.90
2.15-2*0.05-6*0.10-4*0.15=0.85
0.85/0.25-1=2.4
VIGA 3-3 Entre A-D
Acero Superior A-E, L=15.1-2*0.03+2*0.02=15.08 |____| 1/2 1 15.08 15.08
Acero Inferior A-E, L=15.1-2*0.03+2*0.02=15.08 |____| 1/2 1 15.08 15.08
Balancin Superior en A, L=1+0.40-0.03=1.37 --------- 1/2 1 1.37 1.37
Balancin Superior en B, L=1+0.40=1.40 --------- 1/2 1 1.40 1.40
Balancin Superior en C, L=1+0.40=1.40--------- 1/2 1 1.40 1.40
Balancin Superior en D, L=1+0.40=1.40 --------- 1/2 1 1.40 1.40
VP 3-3 Estribos en A-B, L=0.25*2+0.4*2-0.03*8+0.1*2=1.26 3/8 24 1.26 30.24
4.5-2*0.05-6*0.10-4*0.15=3.2
3.2/0.25-1=11.8
VP 3-3 Estribos en B-C, L=0.25*2+0.4*2-0.03*8+0.1*2=1.26 3/8 15 1.26 18.90
2.25-2*0.05-6*0.10-4*0.15=0.95
0.95/0.25-1=2.8
VP 3-3 Estribos en C-D, L=0.25*2+0.4*2-0.03*8+0.1*2=1.26 3/8 24 1.26 30.24
4.35-2*0.05-6*0.10-4*0.15=3.05
3.05/0.25-1=11.2
VIGAS SECUNDARIAS
VIGA A-A Entre 1-3
Acero Superior 1-3, L=5-2*0.03+2*0.01=4.96 |____| 1/2 1 4.96 4.96
Acero Inferior 1-3, L=5-2*0.03+2*0.01=4.96 |____| 1/2 1 4.96 4.96
VS A-A Estribos en 1-2, L=0.25*2+0.2*2-0.03*8+0.1*2=0.86 3/8 20 0.86 17.20
1-2*0.05-10*0.10-8*0.15=--1.3
0
VS A-A Estribos en 2-3, L=0.25*2+0.2*2-0.03*8+0.1*2=0.86 3/8 23 0.86 19.78
3.25-2*0.05-10*0.10-8*0.15=0.95
0.95/0.25-1=2.8
VIGA B-B Entre 1-3
Acero Superior 1-3, L=5-2*0.03+2*0.01=4.96 |____| 1/2 1 4.96 4.96
Acero Inferior 1-3, L=5-2*0.03+2*0.01=4.96 |____| 1/2 1 4.96 4.96
VS B-B Estribos en 1-2, L=0.25*2+0.2*2-0.03*8+0.1*2=0.86 3/8 20 0.86 17.20
1-2*0.05-10*0.10-8*0.15=--1.3
0
VS B-B Estribos en 2-3, L=0.25*2+0.2*2-0.03*8+0.1*2=0.86 3/8 23 0.86 19.78
3.25-2*0.05-10*0.10-8*0.15=0.95
0.95/0.25-1=2.8
VIGA C-C Entre 1-3
Ø Longitud Parcial Longuitud de Acero Por Tipo

Veces
Nº de
Und
ITEM DESCRIPCIÓN
Pulg. Largo 1/4 3/8 1/2 5/8 3/4 1
Acero Superior 1-3, L=5-2*0.03+2*0.01=4.96 |____| 1/2 1 4.96 4.96
Acero Inferior 1-3, L=5-2*0.03+2*0.01=4.96 |____| 1/2 1 4.96 4.96
VS C-C Estribos en 1-2, L=0.25*2+0.2*2-0.03*8+0.1*2=0.86 3/8 20 0.86 17.20
1-2*0.05-10*0.10-8*0.15=--1.3
0
VS C-C Estribos en 2-3, L=0.25*2+0.2*2-0.03*8+0.1*2=0.86 3/8 23 0.86 19.78
3.25-2*0.05-10*0.10-8*0.15=0.95
0.95/0.25-1=2.8
VIGA D-D Entre 1-3
Acero Superior 1-3, L=5-2*0.03+2*0.01=4.96 |____| 1/2 1 4.96 4.96
Acero Inferior 1-3, L=5-2*0.03+2*0.01=4.96 |____| 1/2 1 4.96 4.96
VS D-D Estribos en 1-2, L=0.25*2+0.2*2-0.03*8+0.1*2=0.86 3/8 20 0.86 17.20
1-2*0.05-10*0.10-8*0.15=-1.3
0
VS D-D Estribos en 2-2', L=0.25*2+0.2*2-0.03*8+0.1*2=0.86 3/8 20 0.86 17.20
1.45-2*0.05-10*0.10-8*0.15=-0.85
0
VS D-D Estribos en 2'-3, L=0.25*2+0.2*2-0.03*8+0.1*2=0.86 3/8 20 0.86 17.20
1.55-2*0.05-10*0.10-8*0.15=-0.75
0
VIGA D-D Entre 1-3
Acero Superior 1-3, L=3.2-2*0.03+2*0.01=3.16 |____| 1/2 1 3.16 3.16
Acero Inferior 1-3, L=3.2-2*0.03+2*0.01=3.16 |____| 1/2 1 3.16 3.16
VS E-E Estribos en 1-2, L=0.25*2+0.2*2-0.03*8+0.1*2=0.86 3/8 20 0.86 17.20
1-2*0.05-10*0.10-8*0.15=-1.3
0
VS E-E Estribos en 2-2', L=0.25*2+0.2*2-0.03*8+0.1*2=0.86 3/8 20 0.86 17.20
1.45-2*0.05-10*0.10-8*0.15=-0.85
0
ACERO EN ZAPATAS F'y=4,200 KG/CM2 GRADO 60 Kg
Zapata 1 (1.5*1.5)
Horizontal 1/2 60 1.35 81.00
Vertical 1/2 60 1.35 81.00
Zapata 2 (2.2*1.5)
Horizontal 1/2 75 2.05 153.75
Vertical 1/2 50 2.05 102.50
Zapata 2 (1.7*1.5)
Horizontal 1/2 22 1.55 34.10
Vertical 1/2 20 1.55 31.00
ACERO EN LOSAS F'y=4,200 KG/CM2 GRADO 60
Acero Positivo(Inferior) A-A Y B-B 1/2 11 5.24 57.64
#Viguetas=(4.65-0.15-0.15)*2.5
10.875
L=0.25+1+0.25+3.25+0.25-0.03-0.03+0.15+0.15
5.24
Acero Positivo(Inferior) C-C Y D-D 1/2 11 5.24 57.64
#Viguetas=(4.65-0.15-0.15)*2.5
10.875
L=0.25+1+0.25+3.25+0.25-0.03-0.03+0.15+0.15
5.24
Acero Positivo(Inferior) D-D Y E-E 1/2 6 3.44 20.64
#Viguetas=(2.40-0.15-0.15)*2.5
5.25
L=0.25+1+0.25+1.45+0.25-0.03-0.03+0.15+0.15
3.44
Ø Longitud Parcial Longuitud de Acero Por Tipo

Veces
Nº de
Und
ITEM DESCRIPCIÓN
Pulg. Largo 1/4 3/8 1/2 5/8 3/4 1
Acero Negativo (Superior) A-A Y B-B 1/2 11 5.24 57.64
#Viguetas=(4.65-0.15-0.15)*2.5
10.875
L=0.25+1+0.25+3.25+0.25-0.03-0.03+0.15+0.15
5.24
Acero Negativo (Superior) C-C Y D-D 1/2 11 5.24 57.64
#Viguetas=(4.65-0.15-0.15)*2.5
10.875
L=0.25+1+0.25+3.25+0.25-0.03-0.03+0.15+0.15
5.24
Acero Negativo (Superior)D-D Y E-E 1/2 6 3.44 20.64
#Viguetas=(2.40-0.15-0.15)*2.5
5.25
L=0.25+1+0.25+1.45+0.25-0.03-0.03+0.15+0.15
3.44
Acero de Temperatura 1/4 19 5.39 102.41
Tramo A-B L=4.5
#Aceros=4.5-0.025/0.25+1=18.9
L=5.15-0.03-0.03+0.15+0.15=5.39
Acero de Temperatura 1/4 5 3.14 15.70
Tramo B-C L=1
#Aceros=1-0.025/0.25+1=4.9
L=2.90-0.03-0.03+0.15+0.15=3.14
Acero de Temperatura 1/4 19 5.39 102.41
Tramo C-D L=4.5
#Aceros=4.5-0.025/0.25+1=18.9
L=5.15-0.03-0.03+0.15+0.15=5.39
Acero de Temperatura 1/4 12 2.89 34.68
Tramo D-E L=2.7
#Aceros=2.7-0.025/0.25+1=11.7
L=2.65-0.03-0.03+0.15+0.15=2.89
ACERO EN ESCALERAS F'y=4,200 KG/CM2 GRADO 60
acero transversal L=1-0.03*2=0.94 1 3/8 0.94 0.00

0.4+2.11+0.42 1 1/2 6 2.93 17.58

#=0.94/0.20+1=5.7 1

0.27+1.16+0.2 1 1/2 6 1.63 9.78

#=0.94/0.20+1=5.7 1

0.89+0.90+0.2 1 1/2 6 1.99 11.94

#=0.94/0.20+1=5.7 1

0.14+1.15+0.30 1 1/2 6 1.59 9.54

#=0.94/0.20+1=5.7 1

0.11+0.96+0.92 1 1/2 6 1.99 11.94

#=0.94/0.20+1=5.7 1
TRAMO 2 1 3/8 0.00
acero transversal L=1-0.03*2=0.94 1 0.94
Ø Longitud Parcial Longuitud de Acero Por Tipo

Veces
Nº de
Und
ITEM DESCRIPCIÓN
Pulg. Largo 1/4 3/8 1/2 5/8 3/4 1

0.10+1.04+0.34 1 1/2 6 1.48 8.88

#=0.94/0.20+1=5.7 1

0.1+0.87+2.19+0.40 1 1/2 6 3.56 21.36

#=0.94/0.20+1=5.7 1

0.27+1.12+0.27 1 1/2 6 1.66 9.96

#=0.94/0.20+1=5.7 1

0.92+1.01+0.11 1 1/2 6 2.04 12.24

#=0.94/0.20+1=5.7 1

0.30+1.20+0.14 1 1/2 6 1.64 9.84

#=0.94/0.20+1=5.7 1
ml 255.20 2103.58 1918.50 503.80 0.00 0.00
PESO ACEROS AREQUIPA S.A. kg/m 0.25 0.56 0.99 1.55 2.24 3.99
Total kg 63.80 1178.00 1899.32 780.89 0.00 0.00
Cantidad de varillas Und. 29.00 234.00 214.00 56.00 0.00 0.00
ITEM

02
02.01
02.01.01
02.01.02
02.01.03
02.02
02.02.01
02.02.02
02.02.03
02.02.04
02.02.05
02.02.06
02.03
02.03.01
02.03.01.01
02.03.02
02.03.02.01
02.03.02.02
02.03.03
02.03.03.01
02.04
02.04.01
02.04.01.01
02.04.01.02
02.04.01.03
02.04.02
02.04.02.01
02.04.02.02
02.04.02.03
02.04.03
02.04.03.01
02.04.03.02
02.04.03.03
02.04.04
02.04.04.01
02.04.04.02
02.04.04.03
02.04.05
02.04.05.01
02.04.05.02
02.04.05.03
02.04.06
02.04.06.01
02.05
02.05.01
02.05.02
02.05.03
DESCRIPCION Und.

MODULO I (02 aulas, 01 dirección, 01 cocina, 02 depositos, 01 alamace, 01 cuarto de limpieza, 01 SS.HH docentes)
TRABAJOS PRELIMINARES
LIMPIEZA DE TERRENO MANUAL m2
TRAZO, NIVELES Y REPLANTEO PRELIMINAR m2
TRAZO, NIVELES Y REPLANTEO DURANTE EL PROCESO m2
MOVIMIENTO DE TIERRAS
EXCAVACIONES DE ZANJAS PARA CIMIENTOS EN TERRENO NORMAL m3
RELLENO Y COMPACTADO DE ZANJAS CON EQUIPO LIVIANO (CON MATERIAL PROPIO) m3
ACARREO MATERIAL EXCEDENTE HASTA 30.00 MT (A MANO USANDO CARRETILLA) m3
ELIMINACION MATERIAL EXCEDENTE DE FORMA MANUAL (USO DE CARRETILLA) m3
NIVELACION INT.Y APISONADO FINAL DEL TERRENO PREVIO AL PISO C/EQUIPO LIVIANO m2
NIVELACION Y APISONADO EN VEREDAS E=4" C/EQUIPO LIVIANO m2
OBRAS DE CONCRETO SIMPLE
CIMIENTOS
CIMIENTOS CORRIDOS MEZCLA 1:10 CEMENTO:HORMIGON + 30% DE PIEDRA GRANDE m3
SOBRECIMIENTOS
CONCRETO EN SOBRECIMIENTO 1:8 CEMENTO:HORMIGON + 25% DE PIEDRA MEDIANA m3
ENCOFRADO Y DESENCOFRADO NORMAL PARA SOBRECIMIENTO m2
FALSO PISO
CONCRETO EN FALSO PISO MEZCAL 1:8 CEMENTO:HORMIGON DE 4" m2
OBRAS DE CONCRETO ARMADO
VIGAS DE CIMENTACION
CONCRETO EN VIGAS DE CIMENTACION F'c = 210 KG/CM2 m3
ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS DE CIMENTACION m2
ACERO EN VIGAS DE CIMENTACION F'y=4,200 kg/cm² GRADO 60 kg
COLUMNAS
CONCRETO EN COLUMNAS F'c = 210 KG/CM2 m3
ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNAS m2
ACERO EN COLUMNAS F'y=4,200 kg/cm² GRADO 60 kg
VIGAS
CONCRETO EN VIGAS F'c=210 kg/cm² m3
ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS m2
ACERO EN VIGAS F'y=4,200 kg/cm² GRADO 60 kg
COLUMNAS DE ARRIOSTRE
CONCRETO EN COLUMNETAS F'c=175 KG/CM2 m3
ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNETAS m2
ACERO EN COLUMNETAS F'y=4,200 KG/CM2 GRADO 60 kg
VIGAS DE ARRIOSTRE
CONCRETO EN VIGUETAS F'C=175 KG/CM2 m3
ENCOFRADO Y DESENCOFRADO NORMAL EN VIGUETAS m2
ACERO EN VIGUETAS F'y=4,200 KG/CM2 GRADO 60 kg
VARIOS
ROTURA DE PROBETAS DE CONCRETO und
ESTRUCTURA DE MADERA
TIJERALES DE MADERA TORNILLO DE 2"x6" SEGUN DISEÑO und
TIJERAL DURMIENTE DE MADERA TORNILLO DE 2"x6" m
CORREAS DE MADERA TORNILLO DE 2"x3" m
Parcial Total

90.00 90.00
90.00 90.00
90.00 90.00

41.84 41.84
34.06 34.06
83.46 83.46
24.16 24.16
176.61 176.61
88.69 88.69

17.89 17.89

3.56 3.56
47.44 47.44

176.61 176.61

6.09 6.09
48.73 48.73
925.20 925.20

8.52 8.52
87.39 87.39
1,002.75 1,002.75

7.28 7.28
66.72 66.72
1,027.42 1,027.42

2.10 2.10
34.82 34.82
291.10 291.10

0.70 0.70
10.82 10.82
93.11 93.11
12.00 12.00

11.00 11.00
20.80 20.80
431.25 431.25