Sie sind auf Seite 1von 2

ACCOMPLISHMENT REPORT

PROJECT: WET PARK PHILIPPINES INC.


LOCATION: GRAND CANAL MALL , MCKINLEY HILL TAGUIG CITY
DATE: APRIL 15, 2019

GENERAL ACTIVITY % COMPLETED TARGET DATE REMARKS


Hauling of Debris/Equipment ONGOING Until end of Project On-going
Assembly of Pool Equipment and Play Sets* 90% April 20, 2019 Awaiting materials
HVAC Installation* 0% May 30, 2019 Awaiting materials
Sprinkler system done
Fire Protection 60% May 30,
awaiting for FDAS
Electrical Roughing-ins 50% June 2019 On-going
Plumbing complete, Awaiting
Sanitary Works 50% May 06, 2019
concrete works
Masonry Works (CHB Laying & Plastering) 80% April 27, 2019 On-going
Drywall Partitions 100% Done Done
Painting Works 60% June 2019 Top coat On-going
Plumbing Works + Testing 50% April 30, 2019 Installation works at pool area
Standby for plumbing
Concreting Works 10% May 06, 2019
completion and testing
Framing complete, Standby
Ceiling Works 60% May 30, 2019
for ducting works
Tile Works 0% May 24, 2019 Tiles for purchasing
Continuous Fabrication Off-
Interior Accents Fabrication/Installation 20% June 2019
site
Temporary Board -up 100% Done Done
Awaiting materials for
Kitchen Cabinetries 0% June 10, 2019
Fabrication
Materials on site awaiting
Glass Works 30% June 2019
installation
Waterproofing (1st Layer) 90% April 30, 2019 Flood test 95% Complete
Awaiting Concrete works
Waterproofing (2nd Layer) 0% May 25, 2019
inside pool area
Boat Café and PVC board wall
Off-Site Preparation/Fabrication 40% June 2019
accents fabrication on-going
Doors and Jambs for
Doors & Jambs Installation 0% May 25, 2019
purchasing
Finishing & Retouching 0% June 2019

*Awaiting additional parts and materials sourced from China, thus causing delays on assembly installation.

BY:

Conrado P. Hiwatig Jr.


Project Manager

Das könnte Ihnen auch gefallen