Right of Way from nearest public road
3 Engineering/Constuction Plans
Construction/Building Permits
Delivery of Tower/Cabinets to Site
Tower Works (Type/Height)
Site Development Works
Electrical Works (Power & Grounding)
Concrete Pad for Communication Cabinets
Genset, Daytank & Plith (In case Needed)
Clearing Out
Site 3 (Coordinates)
Site Visit/Survey 10/27 10/29 3
Technical Site Survey Report - TSSR 10/28 10/29 2
1 Lease of Negotiation - MOU 11/4 11/9 6
Verification of Ownership Documents 11/9 11/15 7
Soil Bearing Test 11/15 11/25 11
Contract of Lease
2
Neighbor's Consent & Homeowner's Assn Consent/Certificate
Barangay Resolution / Barangay Clearance
Sanguniang Panglunsod/Sanguniang Bayan Resolution
Department of Health Clearance (DOH) if needed by the Barangay
CAAP - Includes Traverse Computation (in case needed)
Zoning Certification & Location Clearance
DENR / ECC (if needed)
Availability of Electrical Power
Right of Way from nearest public road
3 Engineering/Constuction Plans
Construction/Building Permits
Delivery of Tower/Cabinets to Site
Tower Works (Type/Height)
Site Development Works
Electrical Works (Power & Grounding)
Concrete Pad for Communication Cabinets
Genset, Daytank & Plith (In case Needed)
Clearing Out
Site 4 (Coordinates)
Site Visit/Survey 10/27 10/29 3
Technical Site Survey Report - TSSR 10/28 10/29 2
1 Lease of Negotiation - MOU 11/4 11/9 6
Verification of Ownership Documents 11/9 11/15 7
Soil Bearing Test 11/15 11/25 11
Contract of Lease
2
Neighbor's Consent & Homeowner's Assn Consent/Certificate
Barangay Resolution / Barangay Clearance
Sanguniang Panglunsod/Sanguniang Bayan Resolution
Department of Health Clearance (DOH) if needed by the Barangay
CAAP - Includes Traverse Computation (in case needed)
Zoning Certification & Location Clearance
3
DENR / ECC (if needed)
Availability of Electrical Power
Right of Way from nearest public road
3 Engineering/Constuction Plans
Construction/Building Permits
Delivery of Tower/Cabinets to Site
Tower Works (Type/Height)
Site Development Works
Electrical Works (Power & Grounding)
Concrete Pad for Communication Cabinets
Genset, Daytank & Plith (In case Needed)
Clearing Out
Site 5 (Coordinates)
Site Visit/Survey 10/27 10/29 3
Technical Site Survey Report - TSSR 10/28 10/29 2
1 Lease of Negotiation - MOU 11/4 11/9 6
Verification of Ownership Documents 11/9 11/15 7
Soil Bearing Test 11/15 11/25 11
Contract of Lease
2
Neighbor's Consent & Homeowner's Assn Consent/Certificate
Barangay Resolution / Barangay Clearance
Sanguniang Panglunsod/Sanguniang Bayan Resolution
Department of Health Clearance (DOH) if needed by the Barangay
CAAP - Includes Traverse Computation (in case needed)
Zoning Certification & Location Clearance
DENR / ECC (if needed)
Availability of Electrical Power
Right of Way from nearest public road
3 Engineering/Constuction Plans
Construction/Building Permits
Delivery of Tower/Cabinets to Site
Tower Works (Type/Height)
Site Development Works
Electrical Works (Power & Grounding)
Concrete Pad for Communication Cabinets
Genset, Daytank & Plith (In case Needed)
Clearing Out
Contact Details: XXXXXXXX/XXXXX
3
Right of Way from nearest public road
3 Engineering/Constuction Plans
Construction/Building Permits
Delivery of Tower/Cabinets to Site
Tower Works (Type/Height)
Site Development Works
Electrical Works (Power & Grounding)
Concrete Pad for Communication Cabinets
Genset, Daytank & Plith (In case Needed)
Clearing Out
Site 3 (Coordinates)
Site Visit/Survey 10/27 10/29 3
Technical Site Survey Report - TSSR 10/28 10/29 2
1 Lease of Negotiation - MOU 11/4 11/9 6
Verification of Ownership Documents 11/9 11/15 7
Soil Bearing Test 11/15 11/25 11
Contract of Lease
2
Neighbor's Consent & Homeowner's Assn Consent/Certificate
Barangay Resolution / Barangay Clearance
Sanguniang Panglunsod/Sanguniang Bayan Resolution
Department of Health Clearance (DOH) if needed by the Barangay
CAAP - Includes Traverse Computation (in case needed)
Zoning Certification & Location Clearance
DENR / ECC (if needed)
Availability of Electrical Power
Right of Way from nearest public road
3 Engineering/Constuction Plans
Construction/Building Permits
Delivery of Tower/Cabinets to Site
Tower Works (Type/Height)
Site Development Works
Electrical Works (Power & Grounding)
Concrete Pad for Communication Cabinets
Genset, Daytank & Plith (In case Needed)
Clearing Out
Site 4 (Coordinates)
Site Visit/Survey 10/27 10/29 3
Technical Site Survey Report - TSSR 10/28 10/29 2
1 Lease of Negotiation - MOU 11/4 11/9 6
Verification of Ownership Documents 11/9 11/15 7
Soil Bearing Test 11/15 11/25 11
Contract of Lease
2
Neighbor's Consent & Homeowner's Assn Consent/Certificate
Barangay Resolution / Barangay Clearance
Sanguniang Panglunsod/Sanguniang Bayan Resolution
Department of Health Clearance (DOH) if needed by the Barangay
CAAP - Includes Traverse Computation (in case needed)
Zoning Certification & Location Clearance
3
DENR / ECC (if needed)
Availability of Electrical Power
Right of Way from nearest public road
3 Engineering/Constuction Plans
Construction/Building Permits
Delivery of Tower/Cabinets to Site
Tower Works (Type/Height)
Site Development Works
Electrical Works (Power & Grounding)
Concrete Pad for Communication Cabinets
Genset, Daytank & Plith (In case Needed)
Clearing Out
Site 5 (Coordinates)
Site Visit/Survey 10/27 10/29 3
Technical Site Survey Report - TSSR 10/28 10/29 2
1 Lease of Negotiation - MOU 11/4 11/9 6
Verification of Ownership Documents 11/9 11/15 7
Soil Bearing Test 11/15 11/25 11
Contract of Lease
2
Neighbor's Consent & Homeowner's Assn Consent/Certificate
Barangay Resolution / Barangay Clearance
Sanguniang Panglunsod/Sanguniang Bayan Resolution
Department of Health Clearance (DOH) if needed by the Barangay
CAAP - Includes Traverse Computation (in case needed)
Zoning Certification & Location Clearance
DENR / ECC (if needed)
Availability of Electrical Power
Right of Way from nearest public road
3 Engineering/Constuction Plans
Construction/Building Permits
Delivery of Tower/Cabinets to Site
Tower Works (Type/Height)
Site Development Works
Electrical Works (Power & Grounding)
Concrete Pad for Communication Cabinets
Genset, Daytank & Plith (In case Needed)
Clearing Out