Beruflich Dokumente
Kultur Dokumente
NEW DELHI
APPELLATE JURISDICTION
I N D E X
VOLUME-I
S. No. Particulars
1 Reply on behalf of Respondent No.1 along with supporting
Affidavit
FILED THROUGH:
NEW DELHI
APPELLATE JURISDICTION
VERSUS
At the outset, the Respondent No. 1 denies each and every averment and/or
the averments made and facts stated in the present reply. It is submitted
that nothing stated in the Appeal may be deemed to have been admitted by
the Respondent No. 1 unless and until the same is expressly admitted in the
Respondent No.1 to, sign, verify, file and defend any case for and on behalf of
PRELIMINARY SUBMISSIONS
that upon having noticed the same this Hon’ble Tribunal observed that
there has been a blatant and gross disregard of the requirements with
mention here that the appropriate manner to cure the technical defect,
affidavits and verifications and to get the same duly notarized and file
the affidavits which had already been notarized and filed the same
affidavits along with the same is not a mere formality. The importance
of the same has been brought to light by the Hon’ble Karnataka High
clear abuse of the process by the Appellant. In view of the act of breach
capital goods from its related entity, namely, Reliance Energy Limited
ground alone.
perusal of the instant appeal makes it amply clear that the alleged
of the Constitution.
IV. It is trite law that if there are to views possible, then merely because
substitute its own view or the other view in the matter. There are no
malafides in passing the Impugned Order. For this reason alone the
VI. The Appellant has not maintained accounts in compliance with various
REPLY ON MERITS:
1.1 It is submitted that the contents of para 1.1 are a matter of record and
merit no reply.
1.2 It is submitted that the contents of para 1.2 are a matter of record and
Electricity Act, 2003 (the Act), the National Electricity Plan, the
National Tariff Policy and the Delhi Electricity Reform Act, 2000 (the
(h) specify State Grid Code consistent with the Grid Code
specified under Clause (h) of sub-section (1) of Section 79;
It is submitted that the Respondent No.1 has to work within the frame
the National Electricity Policy, National Tariff Policy and the National
Electricity Plan.
1.3 The contents of para 1.3 in so far as they relate to matters of record are
reasoned one and the allegation that the reasons are not elaborate does
the Appellant and in accordance with the law and the procedure
consonance with the law and the principles of natural justice namely,
July 1, 2002 and the tariffs in Delhi were governed by the Policy
• The validity of the said notifications ended on March 31, 2007 (i.e
• After due deliberation of the comments received from the public and
Regulations”) vide notification dated May 30, 2007 for the period
Appellant filed its Petition for approval of its ARR under the said
(e) Power purchase cost has been fixed without taking into
consideration the estimated revenues through bilateral
exchanges and UI.
(g) The tariff proposed for each consumer category, slab wise
and voltage wise is not duly supported by a cost of service
model, allocating the cost of business to each category of
the consumer based on voltage wise cost and losses.
10
issued an order dated October 26, 2007 along with the directions
(d) The power purchase cost shall take into account apart
from other parameters, the estimate of revenues received
through bilateral exchanges and UI.
• In view of the above stated discrepancies, vide the said order, the
response to the said order dated October 26, 2007 by way of filing
Appellant had not complied with any of the directions stated supra.
12
Petition.
the Petition filed by the Appellant. Vide the said public notices
the Petition by December 10, 2007 which date was later revised to
The date of public hearing was informed to all the parties who had
1.4 The contents of para 1.4 are wrong and hence denied. It is denied that
1.5 The contents of para 1.5 are misleading and hence denied. It is
figures vis-à-vis the Control Period which is nothing but a result of its
infra.
with in detail in the reply of paragraph no. 8 and are not repeated
2-4. The contents of paras 2 to 4 are matters of record and hence, merit no
reply.
knowledge.
6.1 The contents of para 6.1 are matters of record and hence no reply.
6.2 The contents of para 6.2 are in so far as the same relate to matters of
6.3-6.5 The contents of para 6.3 to 6.5 are matters of record and hence
merit no reply.
6.6 The contents of para 6.6 are in so far as the same relate to matters of
facts of the case alone and the reasoning given therein is in the context
of the Policy Period, period of 5 years. The Respondent No.1 has duly
applied the judgment for the Policy Period. The judgment should not
Hon’ble Supreme Court from the facts and submissions in the instant
appeal.
6.7. The contents of para 6.7 are misleading and hence denied. It is
BSES Yamuna Power Ltd & Ors. reported as (2007) 3 SCC 33, has not
followed the direction laid down by the Hon’ble Supreme Court while
admittedly the Respondent No. 1 passed the order dated 22.09.06 prior
6.8 The contents of para 6.8 are in so far as the same relate to the matter
facts of the case alone and the reasoning given therein is in the context
6.9. It is submitted that the contents of para 6.9 are a matter of record and
merit no reply.
6.10 It is submitted that the contents of para 6.10 are wrong and hence
denied.
6.13 It is submitted that the contents of para 6.13 are wrong and hence
The detail comments with respect to the same have been offered in the
reply to para 8.4.1 infra, and the same are not being repeated here for
6.14 The contents of para under reply in so far as the same relate to the
filing of ARR for wheeling business and ARR for retail supply business
6.15 It is submitted that the contents of paras 6.15 absolutely wrong and
Court dated 15.2.2007 and the order of the Hon’ble Tribunal dated
22.5.2007.
6.18 It is submitted that the contents of para 6.18 are denied. It is denied
that there are any reasonable grounds for relaxation of the provisions
filling the ARR Petition has not waived its right to challenge the MYT
Regulations.
6.19 It is submitted that the contents of para 6.19 in so far as the same
that the contention of the Appellant that vide the impugned order, the
and in facts is not correct and without any merit and hence denied.
7. The contents of para 7 are wrong and hence denied. It is denied that
8.1.1 The contents of para 8.1.1 are false, misleading and hence denied. It is
No.1 has arbitrarily reduced sales estimates for the FY 2007-2008 and
legal force.
8.1.2 The contents of para 8.1.2 are misleading and hence denied. It is
Respondent No.1 has without assigning any reasons reduced the year
contrary to the facts of the matter. A bare perusal of the order makes it
amply clear that the Respondent No.1 has considered the submissions
of the Appellant and came to its finding based on past trends and
the Respondent No.1 recorded the reasons of its coming to its finding
8.1.3 That the contents of para 8.1.3 are wrong and hence denied. It is
submitted that as per the Appellant’s own projections though the year
to year growth is 11.68% for the FY 2008 but the same is only 9.81%
the sales figure submitted by the Appellant for the domestic sub-
and also to submit the assumption it has made with respect to increase
mistake in its sales forecast and later submitted revised sales forecasts
and reasoning which the Appellant has adopted for projection of sales
Respondent No.1 observed that the sales forecast of the Petitioner was
200 slab.
12%, 11% and 10% for FY08, FY09, FY10 and FY11, although
13%,-8.23%, 6%.
(c) Sales projection for DMRC not in-line with the projection made
by DMRC as given below:
sales, the Respondent No.1 has taken the sales projections for DMRC
has been transparent and fair in its projections for the sales. This also
shows that Appellant has not applied its mind while projecting sales
(d) Increase in sales for Public Lighting lower than past years
20
was not able to explain the reasons. Therefore it is submitted that the
explained supra
of the Appellant is not only contrary to the abundantly clear facts but
matter titled S.N. Mukherjee vs. Union of India AIR 1990 SC 1984 the
8.1.4 &8.1.5 The contents of paras 8.1.4 & 8.1.5 are misleading and hence
submitted that the Respondent No.1 has stated in the impugned order
it amply clear that the Respondent No.1 has analyzed the sales
projected by all the distribution licensees for the Control Period. The
Respondent No.1 has observed that the energy sale in the previous
years of all the licensees does not show a uniform trend. The trend of
below:
that the increase in sales on year on year basis for FY 06-07 is 11%, for
Commercial etc) of all the three DISCOMs namely, BRPL, BYPL and
22
NDPL and has forecasted the same for the Control Period by
category and has allocated the consolidated sales forecasted for that
short term and long term trends in sales. The Respondent No.1 has
games, the energy consumption would increase but this increase would
industrial sales.
with the consumer and projection made by them. Respondent No.1 has
CAGR for the last 7 years taken by the Respondent No.1 for
Irrigation &
Agriculture -14.82% -16.64% -14.84% -19.75% -21.87% -13.91% -14.84%
As projected
by Railway
Railway Traction -5.32% -11.16% 3.10% -2.06% -7.43% -11.54%
as projected
DMRC 90.73% 67.95% 31.80% by DMRC
Others 0.87% 46.72% -4.39% 0.87%
2009-10 which would take care of the growth of sales including that on
during FY 10-11.
It is submitted that the table below compares the sales forecast of the
S. Category
FY08 FY08 FY09 FY09 FY11 FY11
No FY10 FY 10
Appella Appella Appella
DERC Appellant DERC DERC DERC
nt nt nt
1
Domestic 3190 3033.25 3553 3201.21 3935 3378.47 4325 3565.55
2 Non-
2270 2239.48 2537 2543.13 2829 2887.96 3100 3279.54
domestic
3
Industrial 624 627.44 636 641.83 649 656.25 661 670.70
4 Public
148 152.8 160 171.42 173 192.31 187 215.75
Lighting
5 Irrigation &
32 24.8 32.03 21.12 32.03 17.98 3203 15.31
Agriculture
6
Railway 25 24.75 24 23.51 24 23.51 24 23.51
7
DMRC 72 92 86 110.00 112 142 146 142.0
8.
Others 197 110.71 173 111.67 156 112.65 143 113.63
It is clear from the above that the commission has considered increased
8.2.1 The contents of para 8.2.1 are a matter of record and hence merit no
reply.
8.2.2 The contents of para 8.2.2 are misleading and hence denied. It is
legal force and lacks factual accuracy. Contrary to the contention of the
99.50% and 99.50% for FY08, FY09, FY10 and FY11 respectively as
Respondent No.1 has derived Distribution losses for each year of the
Control Period for the Appellant from AT&C loss target after assuming
Purchase in MUs)
Efficiency)
26
8.2.3 The contents of para 8.2.3 are misleading and hence denied. It is
misplaced and the argument that the loss reduction of 9.68%. in one
year is difficult to achieve more so when the Tariff Order itself has
been notified just one month before the end of FY2007-08 is not in
8.2.4 - 8.2.7 The contents of paras 8.2.4 to 8.2.7 are misleading hence denied.
FY 08 104.66% 99.00%
FY 09 100.28% 99.25%
FY 10 99.62% 99.50%
FY 11 99.63% 99.50%
27
unachievable in view of the fact that the Impugned Order was notified
only one month prior to the closing of the financial year, it is submitted
losses and thereby distribution losses well in advance as these were set
misplaced.
8.2.8 The contents of para 8.2.8 are misleading and hence denied. It is
submitted that the contention of the Appellant in the para under reply
submits that the AT&C loss targets are binding on the Appellant while
distribution loss levels are not, though power purchase depends upon
Respondent No.1 for reaching the target AT&C loss level, it’s
losses, which would result in higher power purchase quantum and cost.
8.3.1 The contents of para 8.3.1 are wrong and hence denied. It is most
Companies, has been analyzed with utmost care and diligence by the
Appellant is well versed with the fact that power purchase cannot be
8.3.2 The contents of para 8.3.2 are wrong and hence denied. It is submitted
Respondent No.1)
whereof are not repeated here for the sake of brevity. In addition, it is
Respondent No. 1 has approved the AT & C loss target of 17% at the
increase of 433 MUs i.e. 7.37 % over the previous year. The
8.3.3-8.3.5 The contents of paras 8.3.3 to 8.3.5 are misleading and hence
consonance with the reasoning as stated supra and the same may be
read with respect to the contents of the para under reply. For the sake
8515MUs which is 607 MUs i.e. 6.65% less than the power purchased
9.68%. It is further submitted that the Appellant has stated that the
that without taking into consideration the fact that the actual drawl
for the corresponding period of the previous year was 1920MU. As per
1920 MUs are considered for the corresponding period of FY 07-08, the
total power purchase for FY 07-08 comes to 9262 MUS i.e. 747 MU
had submitted the AT&C losses till Nov-07 as 34.24% which was
548 MUs more than approved by the Respondent No.1. The average
billing rate approved for Appellant for FY 07-08 is 481.35 Ps/kWh and
around 6924 MUs for the year 2007-08, which should result in
increased revenue of Rs. 328 crores over the sale figure of the order.
This is evident from the rolling sales figure for Feb. 2007 to Jan. 2008
8.3.6-8.3.9. The contents of paras 8.3.6 to 8.3.9 are misleading and hence
quantum and cost for FY 2007-08, the Respondent No.1 has included
100 MUs from bilateral purchase through intra state sources has been
& UI as per the SLDC for January-March, 2008 has been produced
below :
(in MUs)
It is submitted that from the above table it is very much clear that
sale of 40 MUs which has resulted into a Net Revenue of Rs. 69 crores
Further, the Respondent No.1 has considered that 25% of such short
term peak power shall be available from intra state sources and 75%
addition the Respondent No.1 has taken 100 MUs as additional power
purchase through intra state sources for meeting peak demand during
245 crore against power purchase without giving any calculation for
methodology and regulated losses for deriving the figures for FY 2008-
quota which was made effective after issue of impugned orders. This,
available round the clock, would result into an additional energy of 560
34
further bring down the Appellant’s power purchase cost for FY 2009.
Re: Non inclusion of Reactive Energy Charges and Rebate arising out of
8.3.10-8.3.18 The contents of paras 8.3.10-8.3.18 are wrong and hence denied.
by the Hon’ble Tribunal vide its order dated May 23, 2007. It is
did not allow the reactive energy charges under power purchase to the
Appellant in FY 06, the Hon’ble Tribunal had vide its order dated May
23, 2007 directed the Respondent No.1 to allow the same. Therefore, it
Tribunal the Respondent No.1 has allowed the reactive energy charges
Respondent No.1 has not followed any different methodology for the
FY 2007.
has been raised for the first time. It is submitted that the discrepancy
was observed by the Respondent when it pointed out that in the MYT
Appellant that as per the Delhi Transco Limited’s (DTL) account, the
DTL with respect to which the Appellant had already filed a Petition
mention here that the Respondent No.1 was never informed by the
211 in the MYT petition indicate the reactive energy charges. In view
manner arbitrary.
8.4.1 The contents of para 8.4.1 are wrong and hence denied. It is submitted
that the contention of the Appellant that the AT&C loss levels set up
AT&C loss reduction targets for the Appellant as specified in the MYT
July 27, 2007 referred to by the Appellant did not imply any relaxation
minutes of the meeting and a copy of the letter dated August 07, 2007
ANNEXURE-4.
8.4.2 The contents of para 8.4.2 are misleading and hence denied. It is
No.1 ought to relax the AT&C levels fixed under MYT Regulation is
Respondent No.1 derives its powers from the provisions of DERA and
statutes the Respondent No.1 has to work within the framework of the
8.4.2 & 8.4.3 The contents of paras 8.4.2 & 8.4.3 are misleading and hence
who now has a potential burden of Rs.57 crores (approx. in FY 08) and
Respondent No.1 for reaching the target AT&C loss level, it’s
losses, which would result in higher power purchase quantum and cost.
Accordingly, the Respondent No.1 has set the following AT&C and
8.4.4 & 8.4.5 The contents of paras 8.4.4 & 8.4.5 are wrong and hence
compelling grounds for the exercise of the said power is devoid of any
discretion to use the same lies with the Respondent No.1. The
malafides.
No. 1, it is submitted that the Appellant did not make any specific
Respondent No.1.
C loss level of 17% for Appellant. These regulations were framed under
not accepted by the Respondent No.1 and they were directed to follow
the targets given in the regulations. The relevant extracts of the said
Appellant vide their letter dated 1.04.2008, the rolling figures for loss
level from the period February 2007 to January 2008 stand at 25.04%
framed by the Respondent No.1 has been dealt at length in the matter
was further held that even, under Section 121 of the Electricity Act,
ANNEXURE-5.
till date nor any policy on AT&C losses has been made by Government
for the Appellant as specified in the MYT Regulation, 2007 have been
is submitted that 212 towns in the country have brought down the
41
AT&C losses below 20 percent which also consist of 169 such towns
the urban areas of the country were expected to reduce their losses to
15% by the end of 11th Plan i.e. at the end of FY 2012. The Respondent
No.1 states that Delhi being an urban area with very small number of
8.4.10- 8.4.12 It is submitted that the contents of paras 8.4.10- 8.4.12 are
Appellant that despite their being a difference in the base year AT&C
loss for NDPL and the Appellant, the two DISCOMS have been given
with that of NDPL does not sound reasonable as the opening level of
losses of both, NDPL and the Appellant were fixed at the same level of
48.1% at the beginning of the Policy Period and both were required to
reduce the losses by 17% at the end of the Policy Direction Period. It is
42
submitted that in the light of the aforesaid the claim of the Appellant
outrightly rejected.
the Appellant that the comparison of the Appellant with entities like
form of special courts for power theft related cases, recent amendment
for the Appellant as specified in the MYT Regulation 2007 took into
• 212 towns in the country have brought down the AT&C losses
below 20 percent which also consist 169 such towns that have
FY07 to 17.00% in FY11) for the Control Period. The Respondent No.1
Respondent No.1 has specified the AT&C loss reduction target for the
levels have been worked out on the basis of the following formula as
It is submitted that the Respondent No.1 had issued and notified MYT
fixed AT & C loss level of 17% for Appellant. These regulations were
framed under a valid process of law taking into consideration the views
level targets was not accepted by the Respondent No.1 and they were
The power purchase cost shall take into account apart from
other parameters, the estimate of revenues received through
bilateral exchanges and UI.
The Appellant however did not take action on the directions given by
the Respondent No.1 in the Admission Order and did not modify their
view of the law laid down in the matter of Neyveli Lignite Corporation
Ltd. Vs Tamil Nadu Electricity Board and Others 2007 APTEL 1134
(ELR) has held that the Tribunal has no jurisdiction to examine the
Section 111 of the Electricity Act, 2003. It was further held that even,
under Section 121 of the Electricity Act, which confers on the Hon’ble
the Respondent No.1 as the Hon’ble Tribunal can only issue orders,
of its statutory functions under the Act. The Hon’ble Tribunal in the
Appeal No. 51-53 of 2006 has again confirmed that “this Tribunal
appellate power”.
8.4.20. The contents of the para 8.4.20 are misleading and hence
direction was not complied with. The Respondent No.1 has fixed
8.4.21 The contents of the para 8.4.21 are misleading and hence
same has arisen for the first time before this Hon’ble Tribunal.
8.5.1 That the contents of para 8.5.1 are mere statement of fact and hence
Impugned Order it is submitted that the basis for the stated figure of
the scheme cost even after accounting for all the cost
components.
onwards.
8.5.2-8.5.7 That the contents of paras 8.5.2 to 8.5.7 are wrong and hence
up.
admitted on merits.
submitted subsequently.
years.
The above aspects have been duly outlined at para 3.36 to 3.43
above.
following :
(a) necessity
Delhi
projections
from the Respondent No.1 for individual schemes less than Rs. 2
Extra-High Voltages
by him:
56
Impugned Order.
in the distribution business for the past so many years and the
the high voltage installation. While the Appellant has not placed
which the matter was taken up by them with the Govt. of NCT
hereto as ANNEXURE 8.
High Court in its Orders in such cases have held that the
Rules, 1956 and it has to ensure that all provisions of Rule 77,
ANNEXURE-9.
capitalization.
2006 (KPTCL Vs KERC) and as per the Order dated 29th August 2006,
it was stated that the consumers’ interest do not arise at the stage of
determining the tariff. Till then, the consumers have no say and there
could be no objection from their side. It was mentioned that when the
stated in the said Order of the Hon’ble Tribunal that the Commission
shall undertake a prudent check at the stage when utility claims for
fit the claim be allowed. This Hon’ble Tribunal had further stated that
utility and it is for the utility to bear the brunt of such investment and
ANNEXURE-11.
The Respondent No.1 had analysed the submission with regard to the
Accordingly, for reasons cited above, the Respondent No.1 was bound
64
considered by the Respondent No.1 in the same manner for all the
8.5.8 That the contents of para 8.5.8 are wrong, misleading and contrary to
facts and hence denied. The Respondent No.1 vehemently denies the
question and that the Respondent No.1 had agreed and accepted the
the following:
a) necessity
b) overall suitability
65
projections.
the cost proposed by the utility is on estimate basis and the cost
corrected.
order, and the same is the result of prudence check made at the
the Respondent No.1 and some did not have such approval as
approve the financial changes just for asking and the regulator
as:
has ever been filed showing that the goods were in fact so
the para under reply, that the Respondent No.1 had not before
Tribunal.
parties was not given and it was only stated that the Appellant
Along with this letter, a copy of the evidence available with the
hereto as ANNEXURE-13(colly).
and in law.
71
8.5.9 The contents of para 8.5.9 are misleading and hence denied. It
that the majority view does not follow the legal process as
expenditure schemes in two parts i.e. (i) initial approval (ii) final
a) necessity
b) overall suitability
projections.
No. 1 since its inception and has been judicially endorsed and
2006.
approval.
implied by the same was that for making the disallowance of the
not have relied upon evidence like the purchase rates of REL but
similarly large tender for similar goods at about the same time
the basis adopted by the Respondent No. 1 for holding that that
REL at prices much higher than the market rates, is the only
It is further submitted that in any case, the onus for proving the
exorbitant i.e. 68% higher than the cost of REL and the
of his dissent note, the Member has only mentioned that the
In para-20 of his dissent note, the Member has stated that the
that “It is made clear that this disallowance has been made on
issue is no longer res integra and has been dealt with by this
8.5.10. The contents of para 8.5.10 are wrong and hence denied. It is
8.5.11. The contents of para 8.5.11 are wrong and hence denied. It is
Member’s dissent note does not in any way show that the
high cost purchases made by the Appellant from REL and the
filed.
ANNEXURE-15.
higher]
iv) Whereas the DPR had the estimates in the form of the
the total cost of the scheme; the purchase orders have been
up of the material (quantity wise and rate wise) has not been
tariff fixation.
The Appellant has also stated that it had kept the Respondent
which forms part of its tariff petition was upon the appellant
appellant had been required to show cause about the same and
8.5.12. That the contents of para 8.5.12 are wrong and hence denied. It
made for the reason that the goods were purchased from a
8.5.13. That the contents of para 8.5.13 are wrong and vehemently
question with REL for purchase of the goods were EPC contracts
submitted that the Appellant cannot raise this new issue at the
appellate stage.
reproduced hereunder:
TOTAL 1,155.87
(Rupees in Crores)
purchase.
4) Copy of the Trading Account for the year 2004-05 of REL, which
transaction.
Ltd. for Sales Tax for the year 2004-05. It has been stated in
this order that the total sales of Rs.1233.56 crores shown in the
purchased against the statutory forms SI-35 and C forms and all
sales.” The sales tax returns filed by REL under the Delhi
87
Sales Tax Act, 1975 also make it very clear that REL had made
REL for purchase of the goods. It shows that the order was only
for purchase of capital goods and did not have any element of
deviate the focus of this Hon’ble Tribunal from the fraud played
turn key basis. The fact is that vide this letter it only expressed
the file noting in the same file, that “M/s BSES was asked to
ANNEXURE-19.
The purchase orders placed on REL also show that the format
for purchases for all vendors including REL is same and there is
was only purchase of goods and the EPC part was different for
‘Services’ in 2005-06.
over the goods continues with the Contractor until they are used
Rolling Mills 120 STC 179, by the Hon’ble Apex Court that
to the owner took place only when the contract was executed and
pertinent to mention that in the instant case, REL filed the sales
the goods could not have been offered or subjected to Sales Tax
in 2004-05 and the REL would also not have described the same
REL were not EPC contracts but for “purchase of goods” only. It
just trying to cover up its own wrong doing which was intended
8.5.14. That the contents of para 8.5.14 are wrong and vehemently
with REL was clearly separate from the contract for purchase of
record by the Appellant, its claim that even the payment made
8.5.15 The contents of para 8.5.15 are misleading and hence denied. It
a) necessity
b) overall suitability
projections.
and that too without filing any evidence to show that the goods
onerous task and that the Respondent No.1 has any hesitation
8.5.16. The contents of para 8.5.16 are wrong and hence denied. It is
Respondent No.1 did not make any effort to bring on record any
show that the goods purchased from the Group Company REL
their cost and the Appellant was duly required to show cause
about it.
without any evidence to support the same that the goods were
the appellant, REL had also made the purchases from a number
relevant time than the rates at which the goods were purchased
the same.
8.5.17. The contents of para 8.5.17 are misleading and hence denied. It
time is the rate at which the goods were purchased by REL from
is not the form or the nomenclature but the substance which has
8.5.18. The contents of para 8.5.18 are misleading and hence denied.
Yours sincerely,
Sd/-
97
(RAKESH MEHTA)”
8.5.19. The contents of para 8.5.19 are misleading and hence denied. It
Electricity Act 2003 under which the Respondent No.1 can get
itself investigate the issues and take action and this is what the
licence or the Act/Rules, has been shown and even if there was,
8.5.20. The contents of para 8.5.20 are wrong and hence denied. It is
probably hinting at their oft repeated claim that the market rate
higher than the purchase price of REL and the appellant was
above supra there could have been no better proof of the market
wrong with the evidence relied upon by the Respondent No.1 i.e.
submissions in para 8.5.8 above and the same are not being
the same thing. All through, the appellant is talking of only the
dismissed.
8.5.21. The contents of para 8.5.21 are misleading and hence denied. It
not clear whether the so called approval was initial ‘in principle’
rejected.
in its ARR which forms part of its tariff petition, was on the
the appellant was duly required to show cause about it. As has
relevant time and in the light of the same the contention of the
8.5.22. The contents of para 8.5.22 are misleading and hence denied. It
Appellant.
extent of only 50% of the fresh investment for the MYT period. It is
No.1 has not made any provision to carry forward the un-approved
them are such that they generally do not take more than one year to
No. 1 most respectfully submits that the Appellant has for reasons best
submitted that the Appellant has under para 8.5.25 of Appeal stated
MYT Petition, the Appellant had itself stated the opening CWIP as Rs.
323.36 Crore for FY 08. A copy of the relevant extract of the MYT
that, the details of the capital works in progress (CWIP) for each year
reproduced below :
607.30 532.30
Opening CWIP 1157.30 757.30
475.00 350.00
Net Additions to CWIP 128.24 390.85
550.00 450.00
Capitalisation of Investment 528.24 540.85
Investment capitalised out of 312.50 35.25
464.12 345.43
opening CWIP till FY 07
Investment capitalised out of
0.00 239.75
opening CWIP for investments 0.00
from FY 08 onwards
Investment capitalised out of 237.50 175.00
64.12 195.43
fresh investment
532.30 432.30
Closing CWIP 757.30 607.30
FY 2007-08 onwards.
of its capital schemes generally do not take more than one year to
execute, is not borne out of the facts as can be observed from the trend
¾ The Capital Schemes are not completed within the same year of
8.6.1 The contents of para 8.6.1 are misleading and hence merit no reply. It
Depreciation for MYT Period is line with the lower approval of Capex
to the Appellant the Impugned Order does not even indicate the
8.6.2 The contents of para 8.6.2 are wrong and hence denied. It is denied
dismissed.
8.6.3 In the para under reply the Appellant has reproduced the provisions of
(RoCE). The Respondent No.1 has allowed RoCE based on the MYT
hereunder:
5.7 The RRB shall be determined for each year of the Control
Period at the beginning of the Control Period based on the
approved capital investment plan with corresponding
capitalisation schedule and normative working capital.
5.8 The Regulated Rate Base for the ith year of the Control
Period shall be computed in the following manner:
RRBi = RRB i-1 + ∆ABi /2 + ∆WCi;
Where,
‘i’ is the ith year of the Control Period, i = 1,2,3,4 for the
RRBi: Regulated Rate Base for the ith year of the Control Period;
∆ABi: Change in the Regulated Rate Base in the ith year of the
Where,
of fixed assets;
RRB i-1: Regulated Rate Base for the Financial Year preceding
the ith year of the Control period. For the first year of the
Where;
purpose;
ith year of the Control Period, from the (i-1)th year. For the
consist of
5.9 Return on Capital Employed (RoCE) for the year ‘i’ shall
Where,
RRB - Regulated Rate Base is the asset base for each year of the
capital.
5.10 The WACC for each year of the Control Period shall be computed
D/E 1
Where, WACC = ∗ rd + ∗ re
1 + D / E 1 + D / E
8.6.4-8.6.12 The contents of paras 8.4.6 to 8.6.12 are misconceived and hence
reserves and loans in each year were determined on the basis of capital
during each year of the Policy Direction period was dependent on the
Capital Investment approved during that year. In the light of the same
It is further submitted that for the Control Period the return allowed
Regulation, 2007. As per Regulation, the return for the year shall be
employed to the average of “Net Fixed Asset” for each year. Thus, the
on the capital investment for that year. The addition in equity/ free
reserves and debt during each year of the Control Period is also to the
the capital works that are still in progress, the same cannot be
112
Thus the Respondent No.1 has not considered the closing CWIP of
It is submitted that the Respondent No.1 has also observed that for the
Control Period, the Appellant has reduced the gross assets capitalised
during a year relates to the capital investment in that year and not to
the asset capitalised in the year. Thus the Respondent No.1 has
Appellant has in para 8.6.4 of the instant appeal mentioned that “the
makes it amply clear that the Appellant has contradicted itself and
113
Tribunal.
that the Respondent No.1 in the Impugned Order has allowed return
even on capital invested but not capitalized, for Policy Direction period
should be allowing ROE and Interest Expenses only after the asset is
capitalized and put in use. However, for the Control Period, the
Respondent No.1 was guided by the MYT Regulation and has strictly
It is submitted that Respondent No.1 also accepts that the point of not
including the CWIP was raised by the Appellant in its meeting held in
meeting, it was made very clear to the Appellant that the MYT
Tribunal.
8.6.13 The contents of para 8.6.13 are blatantly wrong and hence denied. It is
submitted that the Appellant in the para under reply has stated that
“the Impugned Order does not even indicate the amount of return
directed to provide the return for each year of the MYT period”. It is
No.1 in the Control Period, are reproduced below from the sake of
ready refrence;
“4.229 For determining the WACC, the Commission has followed the
methodology specified in the MYT Regulations, 2007. Debt to
equity ratio has been considered on the closing values of debt
and equity (including free reserves) approved by the
Commission for each year. The cost of equity has been
considered at 14% and the cost of debt has been determined by
dividing total interest cost (on approved loans) by average debt
approved for that year.”
“4.232 The Commission feels that the Petitioner has misunderstood the
methodology specified for calculating the RoCE and Supply
margin for Wheeling and Retail Supply business respectively. As
per Clause 5.38 of the MYT Regulations, 2007,
“The Commission shall specify a retail supply margin for
the Retail Supply Business in MYT order based on the
Allocation statement provided by the Distribution
Licensee. The Cost allocated to Retail Supply Business as
per allocation statement shall be considered while
determining supply margin.”………
Table 111.
At the outset the Respondent No.1 would like to bring to the notice of
the expenses for FY 2004-05. It states that out of the total A&G
Respondent No.1 has allowed only Rs.29.04 crores and has also not
Respondent No.1 that since they are drafted in accordance with the
provisions of the law and notified, they have a binding effect on all
Hon’ble Tribunal held that the Commission has to approve all the
The Respondent No.1 has, in its tariff order of 2004-05 allowed Rs.
by the Appellant. While doing first true up in the year 2005-06, the
this order.
(Table 3.14, Page 118/177, BRPL Tariff Order 2006-07). This order
order dated 23.05.07 held that the second truing up can be done by
expenses as per the ATE Order as claimed by the Appellant for the
FY 2004-05 stands Rs. 2.06 cores (table 56, page 122, MYT petition,
case-wise details and their expenses where either the Courts have
disallowed any A&G expenses and has approved A&G expenses for
Hon’ble Tribunal.
8.7.1 The contents of para 8.7.1 are wrong and hence denied. In the light of
this Hon’ble Tribunal vide its Order 23.05.2007 is without any basis
the Respondent No.1 has allowed the A&G expenses for the year 2004-
the said order of the Hon’ble Tribunal inter alia states that the
the utility and the true up exercise is mentioned to fill the gap between
the actual expenses at the end of the year and anticipated expenses in
the beginning of the year and the exception with respect to the same
could be where the Respondent No.1 has reason to differ with the
expenses in its MYT petition for the year 2004-05 and hence, the
concocted
8.7.8 The contents of para 8.7.8 are misleading and hence denied. It is
has claimed in the arrears of expenses as per the MYT Petition, the
same has been given effect to by the Respondent No.1 in the impugned
8.7.9-8.7.10. The contents of the paras 8.7.9-8.7.10 are misleading and hence
Respondent No.1 has deducted “one time expenses” to the tune of 4.26
the notice of the Respondent No.1 that such “one time expenses” will
be incurred even during the Control Period and therefore they should
not be deducted while computing the amount for the Base Year 2007,
With respect to the same Respondent No.1 would like to bring to the
• MYT Regulations
120
O&M expenses (a part of which is A&G expenses) for the base year
Licensee, estimates of the actuals for the base year, prudence check
No.1
nature. For determining the base for the control period, the
Tribunal.
No.1 has vide letter dated 16 February 2008 sought explanation from
8.7.11-8.7.12 The contents of the paras 8.7.11-8.7.12 are wrong and hence
submitted that the Respondent No.1 out of the total A&G expenses,
upfront & processing fee for refinancing of DPCL Loan and SVRS
Loan). The Appellant had also submitted that it may incur these
charges in future on account of bank charges for taking loan for its
pertinent to mention that the Appellant has taken loan in each year of
the Policy Direction Period also for capital investment and the
to lower interest rate loans, the Respondent No.1 would, based on the
in the event the Appellant passes on the benefit of lower interest rate
to consumer.
the actual picture of A&G expenses and would have been contrary to
Respondent No.1 has approved A&G expenses for the Petitioner as per
It is submitted that these are not part of the routine expenditure of the
the same does not merit consideration for inclusion in the Base. It is
the base level of A&G expenses for Control Period as all the abnormal
cursory mention is there in the MYT Petition, the same was not
quantified and asked for specifically and hence it had been deemed to
submitted that a new issue, not being a part of the Impugned Order
124
cannot be raised at the appellate stage for the first time and hence the
No.1 has approved the A&G expenses as per the methodology framed
the quality of service and the problems they have to face, while dealing
with the officials of the Appellant. Moreover, that they have neither
complied with the directives of the Respondent No.1 nor the MYT
most respectfully submits that the Appellant is free to take any new
initiative during the MYT period but at the same time Appellant has to
125
8.8.1-.8.8.5 The contents of paras 8.8.1 to .8.8.5 are wrong and hence denied.
the Appellant that the Respondent No.1 has without assigning any
the order of the Hon’ble High Court in the matter titled NDPL vs.
3.109 of the impugned order which reproduced hereunder for the sake
of ready reference :
3.105The Hon’ble High Court in its Order dated 2 July, 2007 has
directed as follows:
(a) The Pension Trust and GoNCTD are not liable to make
of service under the Act and Rules) from the date of their
entitlement date.
DISCOMs.
3.106 The Commission directed BRPL, BYPL and NDPL to file the
3.107 The DISCOMs (BRPL, BYPL and NDPL) have opted for second
settlement.
130
superannuation…”
under:
required to pay monthly pension till the outcome of the award of the
Tribunal. The Tribunal would decide the lump sum amount which the
terminal benefit liability to the Pension Trust. This lump sum amount
would be for the additional pension requirement for the period before
the actual superannuation of the VSS optees and for shifting terminal
date. The monthly pension payments being made to VSS optees shall
the Appellant.
Respondent No.1 has allowed carrying cost of 8% per annum for the
expenses.
a future date. The Appellant has been uncertain about the time of
(k) the Pensioners would not suffer as they are getting the
this may result into getting translated into more and more
133
consumers.
available.
its best understanding of the issues, allowed one time payment and
submitted that the Appellant in its submissions has not challenged the
the Appellant that the Respondent No.1 has disallowed the projection
that since the MYT Regulations are drafted in accordance with the
provisions of law and notified they have a binding effect on all the
134
Para 4.110 at page 137, of BRPL MYT Order 2008-11. A copy of the
is submitted that since the increase in the amount was not certain at
impugned order that the Respondent No.1 shall true up the impact on
actual impact of the same, and hence the concerns of the Appellant
expenses for the Control period, the Respondent No.1 has considered
the following:
expenses for the year 2006-07 in the petition, which have been allowed
by the Respondent No.1 and taken as a base. The Respondent No.1 has
the base. After the adjustment of the Base, the escalation factor
methodology stated in the MYT Regulations and has also given due
8.9.1 The contents of para 8.9.1 are wrong and hence denied. It is submitted
8.9.2-8.9.3 The contents of paras 8.9.2-8.9.3 are wrong and hence denied.
At the very outset is submitted that the petitioner did not claim
Tribunal :
of BRPL 2004-05).
that the Appellant has not submitted any detail for increase
this Hon’ble Tribunal vide order dated 23.05.07 held that the
ANNEXURE-25.
and had directed the Appellant to take prior approval for any
observed as follows:
In the light of the aforesaid and having regard to the fact that the
Appellant in terms of the tariff order did not seek prior approval before
139
exceeding R&M expenses beyond the limit set by the Respondent No.1,
8.9.9-8.9.15 The contents of para 8.9.9 to 8.9.15 are misleading and hence
follows:
“For the FY 2006-07, the Petitioner did not apply for prior
approval from the Commission before exceeding R&M
expenses beyond Rs.70.98 crore limit set for FY 2007.
Therefore, the Commission denied the higher expense of
Rs.89.49 crore claimed by the Petitioner and approves
R&M expenses of Rs.70.98 crore of R&M expenses for FY
2007.”
In the light of the aforesaid and having regard to the fact that the
Appellant in terms of the tariff order did not seek prior approval before
140
exceeding R&M expenses beyond the limit set by the Respondent No.1,
8.9.16-8.9.18 The contents of paras 8.9.16 to 8.9.18 are misleading and hence
below:
clear that the view of the Respondent No.1 with respect to the K factor
8.9.19-8.9.29 The contents of paras 8.9.19 to 8.9.29 are misleading and hence
As has been stated supra the MYT Regulations are binding on the
Regulations, 2007:
“The O&M expenses for the Base Year shall be approved by the
Commission taking into account the latest available audited
accounts, business plan filed by the Licensees, estimates of the
actuals for the Base Year, prudency check and any other factor
considered appropriate by the Commission.”
R&M Expenses and it is very logical that on the same very figure the K
factor is to be calculated.
No.1. In the light of the aforesaid the contention that the R&M
142
factor is misconceived in view of the fact that Clause 4.16 of the MYT
8.10.1 The contents of para 8.10.1 are wrong and hence denied. It is
by the order of the Hon’ble Supreme Court 15.02.2007 read with the
Court directed the matter for the Policy Period and this has been duly
8.10.2 The contents of para 8.10.2 are wrong and hence denied. It is
No.1 has flouted and misapplied the principles underlying the decision
of the Hon’ble Supreme Court to the facts of the present case is based
issued vide the said order. It is pertinent to mention here that the
8.10.3 The contents of para 8.10.3 are misleading and hence denied. It is
8.10.4 -8.10.5 The contents of para 8.10.4 & 8.10.5 are wrong and hence
observed as under:
8.10.6 The contents of para 8.10.6 are wrong and hence denied. It is
8.10.7 The contents of para 8.10.7 are wrong and hence denied. It is
amount of depreciation.
to mention here that the Hon’ble Supreme Court vide its order
A bare perusal of the aforesaid makes it amply clear that the Hon’ble
stating that the Hon’ble Supreme Court has nowhere provided the rate
Supreme Court.
that the rate of 6.69% was upheld by the Hon’ble Supreme Court only
of the fact that the 6.69% rate of depreciation is based on the weighted
upon has not been approved by the Appellant and accordingly could
and the rate of depreciation has been finalized by the Hon’ble Supreme
Court, the Respondent No.1 does not possess the power or the
Supreme Court has in its Order dated 15.02.2007 upheld the rate of
6.69%. for the entire Policy Direction period. The ATE, in its order
dated 23.05.2007 held that the Respondent No.1 has to allow carrying
period @ 9%. It is also held that the Respondent No.1 has to allow
In view of the above Orders of the Supreme Court and the ATE, the
Respondent No.1 has allowed depreciation on the opening GFA for the
year which includes assets created from APDRP grants @ 6.69% for the
Policy Direction period along with the carrying cost @9%. Hence, the
8.11.1 The contents of para 8.11.1 are misleading and hence denied. It is
submitted that the claim of the Appellant that it has been severely
loan and allowed all the refinancing charges and the interest on
charges as per the loans in the opening balance sheet, which are
same as the other side is balance and reflection of the first side
in different terms.
depreciation (to the tune of Rs. 383 crores), but the transfer
151
different heads.
been given effect and considered during the Policy Period, that
previous year.
8.11.6 The contents of the para 8.11.6 are wrong and hence denied. In
be dismissed.
8.12.1-8.12.2 The contents of the paras 8.12.1to 8.12.2 which are matter of
record are not denied. Rest of the paragraph is wrong and hence
denied.
8.12.3-8.12.7 The contents of the paras 8.12.3 to 8.12.7 are misleading and
the Tariff Order of 2005-06, the Appellant had vide letter reference no.
that from the bare perusal of the said letter it is amply clear that the
3.27, Para 3.9.1 of Tariff Order of 2005-06 for BRPL BRPL A copy of
ANNEXURE-30.
However, it is submitted that while doing the second true-up for the
ANNEXURE-31.
Order dated June 26, 2003, for the FY 2004-05, FY 2005-06 and FY
• Consumer Contribution
FY 2004-05
past 2 years, the Respondent No.1 did not considered the same for
the details of sundry creditors and the time period for making
FY 2005-06
the extent of Rs. 88.71 Crore during FY 2004-05 and Rs. 142.56
case, the return on equity during the year be less than the
FY 2006-07
Equity Ratio of 70:30. In case, the return on equity during the year is
Finance for any year, it has allowed funding of this sundry creditor in
157
Tribunal that the Respondent No.1 has not deviated from its
approach but has included Sundry creditors also as one of the Means
Appellant that the Respondent No.1 has deviated from the approach
deserves to be dismissed.
8.13 Lower Approval of Interest Rates for the Loans to be raised by the
Appellant during MYT Period.
8.13.1 The contents of para 8.13.1 are misleading and hence denied. It is
raise loans is baseless and inaccurate in view of the facts of the case.
8.13.4 The contents of para 8.13.4 are wrong and denied. It is submitted
the range of 1.75% to 2.75% below the PLR and has made those rates
as the general norms for the loans to be taken during the MYT
Order, the Respondent No.1 has analysed the terms and conditions of
the loan taken by the Appellant in FY 2007 and noticed that the
4.75% below the PLR. Thus, for the control period, the Respondent
No.1 has stipulated a certain interest rate of 9.5% for all loans that
the appellant may raise, it has also stipulated in Para 4.223 of the
impugned Order that shall true up the means of finance for the
may true up the interest rate considered for new loans to be taken for
at either side.
(risk free returns, risk premium, Prime lending rate etc.) It pertinent
2.75% below the SBI PLR. An extract of the interest rates on the
existing loans and the proposed loans which have been considered by
perusal of the extract annexed that it had been possible for the
Respondent No.1
interest rate for the loans raised by the appellant during the MYT
and is in order.
10-17 The contents of paras 10-17 (wrongly numbered as 13) merit no reply.
18 The Relief clause is wrong and denied. No grounds has been made out
by the Appellant for grant of any relief whatsoever and the appeal is
Respondent No. 1
VERIFICATION:
Verified at New Delhi on this 2nd day of May 2008, that the contents of
objections and para 18 of the reply on merits and the legal averments in
the reply are based on the legal advice received and believed to be true.
Respondent No. 1
THROUGH:
New Delhi
Dated:
161
NEW DELHI
APPELLATE JURISDICTION
VERSUS
I, Mr. Amarendra.K. Tewary, S/o. Mr. Triloki Tewary, age about 53 years,
residing at D II/ 11, Pandara Road, New Delhi, do hereby solemnly affirm
and declare as under:
No.1 to, sign, verify, file and defend any case for and on behalf of
2. That the deponent is fully conversant with the facts of the case and
hence competent to swear this affidavit.
DEPONENT
VERIFICATION:
I, the above deponent, hereby verify that the contents of my above affidavit
are true and correct, no part of it is false and nothing material has been
concealed there from.
Verified at New Delhi on this day the 2nd day of May, 2008.
DEPONENT