Beruflich Dokumente
Kultur Dokumente
ESTIMATED COST OF
PROPOSED PROJECT
DESCRIPTION OF WORK TO BE DONE Direct Cost
Unit Unit Total
Item no. Description
Cost Cost
B.5 Project Billboard/Signboard each.
B.7 Construction Safety and Health lot
B.8(2) Road Works Safety and Traffic Management lot
B.9 Mobilization/Demobilization l.s
101(6) Removal of Structures and Obstruction cu.m
103(1) Structure Excavation (Common Soil) cu.m
105(1)a Subgrade Preparation (Common Material) sq.m
200(1) Aggregate Subbase Coarse cu.m
311(1)c1 PCC Pavement (Unreinforced) 0.3m thk. (14 days) cu.m
504(3)a Cleaning Culvert Pipe in Place (3.6x3.6m) m
500(1)a3 Box Culverts, 3.6 x 3.6 m m