Beruflich Dokumente
Kultur Dokumente
INPUT SECTION
REPORT SECTION
WACC 10%
NPV
$127.17
5% $170.40
6% $160.95
7% $151.93
8% $143.30
9% $135.06
WACC
WACC
10% $127.17
11% $119.62
12% $112.40
13% $105.47
14% $98.83
15% $92.47
NPV
$138.64
5% $201.68
6% $187.99
7% $174.86
8% $162.28
9% $150.22
WACC
WACC
10% $138.64
11% $127.52
12% $116.84
13% $106.58
14% $96.71
15% $87.22
Table 5: Project E sensitivity
NPV
$341.51
5% $494.78
6% $461.03
7% $428.92
8% $398.36
9% $369.25
WACC
10% $341.51
11% $315.07
12% $289.84
13% $265.77
14% $242.79
15% $220.84
This model is used to analyze
the sensitivity of each
project's NPV if the WACC
changes from 5% to 15%
NPV
$201.58
5% $312.37
6% $287.85
7% $264.58
8% $242.50
9% $221.52
10% $201.58
11% $182.61
12% $164.57
13% $147.39
14% $131.03
15% $115.43
NPV
$207.97
5% $280.15
6% $264.46
7% $249.43
8% $235.02
9% $221.21
10% $207.97
11% $195.25
12% $183.04
13% $171.31
14% $160.03
15% $149.19
Microsoft Excel 14.0 Answer Report
Worksheet: [ASSIGNMENT 2_GROUP 101_291018.xlsx]OPTIMIZATION MODEL
Report Created: 10/28/2018 5:43:28 PM
Result: Solver found a solution. All Constraints and optimality conditions are satisfied.
Solver Engine
Engine: Simplex LP
Solution Time: 0.016 Seconds.
Iterations: 1 Subproblems: 6
Solver Options
Max Time Unlimited, Iterations Unlimited, Precision 0.000001, Use Automatic Scaling
Max Subproblems Unlimited, Max Integer Sols Unlimited, Integer Tolerance 1%, Assume NonNegative
Variable Cells
Cell Name Original Value Final Value Integer
$C$8 Invest A 1 1 Binary
$D$8 Invest B 0 0 Binary
$E$8 Invest C 0 0 Binary
$F$8 Invest D 1 1 Binary
$G$8 Invest E 1 1 Binary
Constraints
Cell Name Cell Value Formula Status Slack
$H$16 Cost Result $890 $H$16<=$J$16 Not Binding 110
$C$8:$G$8=Binary
DAYSTAR COMPANY
DECISIONS
Project A B C D E
Invest 1 0 0 1 1
OBJECTIVES
Project A B C D E Total
NPV $127.17 $138.64 $201.58 $207.97 $341.51 $676.65
CONSTRAINTS
Project A B C D E Result Condition
Cost $140 $300 $450 $300 $450 $890 <= $1,000
All of 5 projects have positive NPV. Their initial costs are
illustrated below.
This model is used to make the decision that which projects
should the company invest in to maximize the benefit with the
constraint $1,000 capital budget.
Note
Satisfied
Scenario Summary
Current Values: Base case Bad case Good case
Changing Cells:
WACC 10% 10% 15% 5%
Result Cells:
Total NPV $676.65 $676.65 $462.50 $945.33
Notes: Current Values column represents values of changing cells at
time Scenario Summary Report was created. Changing cells for each
scenario are highlighted in gray.