Our Offer Ref.: SE GG
121217-001
RFQ CIVIL WORKS FOR CATHODIC PROTECTION
Date: 08 JUNE 2018
Description: INSTALLATION
HMP MSN
1 Issued for Review
REVISION HISTORY
TABLE OF CONTENTS
1.0 PURPOSE
2.0 SCOPE
3.0 ABBREVIATIONS
4.0 DEFINITIONS
5.0 REFERENCES
8.0 MANPOWER
9.0 HSE
10.0 METHODOLOGY
1.0 PURPOSE
The purpose of this method statement is to portray the safety guidelines and
work method to be followed for the civil works to be undergone for the
installation of Cathodic protection of 4” main natural gas pipeline to SAUDI
GUARDIAN CO. This has been developed to meet safety, quality, project
specifications and contract requirements. It also aims at all works are
inspected, verified by relevant authorities and documented in line with
Project Quality requirements.
2.0 SCOPE
The scope of this method statement includes excavation, trenching, civil works for
foundations and road cutting taking into considerations of all safety and quality
requirements of RC standards and other concerned entities to accomplish the
execution of this work.
3.0 ABBREVIATIONS
4.0 DEFINITIONS
5.0 REFERENCES
8.0 MANPOWER
9.0 HSE
9.1 Contractor shall ensure compliance to approved project specific Safety Plan.
9.2 Safety Officer shall ensure work shall be carried out in a safe manner by
coordinating with site supervisor, sub-contractors etc. Contractor shall
strictly enforce all relevant requirements in compliance to Client PPE
requirement.
9.3 Warning Tape, Work Boot with toe protectors, eye protection with side
shields shall be provided. Dust masks and ear plugs were necessary shall be
worn.
9.4 High visibility vests shall be worn in confined space.
9.5 Daily toolbox talk shall be conducted to educate personal regarding the
hazards involved.
9.6 Vehicular movement shall be as per approved site driving plan.
9.7 Safety induction and required skilled training for craftsman and workers,
third party inspection certificates for equipment and tools, required gate
passes to vehicles and personnel, installing warning and safety signage,
work permits, monitoring of heavy equipment movement shall be
implemented in order to comply with Client requirement.
9.8 Proper housekeeping and stacking of tools shall be ensured.
10.0 METHODOLOGY
The subcontractor shall obtain necessary approval for the proceeding work.
10.1. Site Induction & On arrival to site all personnel are to receive a site
Procedures: specific safety induction to be undertaken by
Project Leader or his representative. During the
course of the induction areas to be covered which
is not exhaustive shall include:
• Welfare facilities
• Emergency Procedures
• Site Rules and Requirements i.e. PPE etc
TRENCHING:-
First the line of the trenching required is defined
by the contractor referring to available drawings.
Then the markings are done and subjected to
inspection for the client. Once the inspection is
done and the line of trenching is approved, then
marking is done.
Manual excavation is carried out for the trenching
TRAFFIC DEVIATION
Prior to the duct bank construction works across
the road crossing, the traffic shall be deviated in
such a way that one track on either side of the road
shall be opened during the first phase. Proper
barricading and crash barriers and warning lights
shall be installed indicating the road deviation.
Sign boards for the road deviation shall be
installed. The road median and one track of each
road shall be cut and excavated and the duct bank
construction shall proceed. Once the curing time is
finished and the road is reinstated and the road is
open for traffic while the other two outer lanes of
the road shall be blocked and deviated in the same
manner.
CONCRETE FOUNDATIONS
For the concrete foundations, the required
locations are provided by the CP installer.
These locations are marked and the area is
excavated, levelled and compacted. Lean Concrete
shall be poured and finished. Then steel fixing is
done and the shuttering works are done with the
sleeves provided inside.
Structural concrete of 4000 psi is poured . Then de
shuttering is done and kept for curing.
EXCAVATION
For visibly contacting the pipe at 3 locations, a
trench 2m wide by 2m deep shall be excavated by
means of excavator upto 30 cm higher than the
pipe depth, then it is manually excavated and the
access to the trench shall be given by sloped depth
so that personals can get down the trench by foot
rather than ladders. The excavated pit shall be
kept dry by the means of dewatering pump and
well point system so that persons can access the
pipeline. Below mentioned points shall be
incorporated during excavation.
Excavation and backfilling shall be carried out in
accordance with SECTION 02315 and as specified
herein.
The Contractor shall perform all excavation of
every description and of whatever substances
encountered, to the depths indicated on the
Contract Drawings or as otherwise specified.
During excavation, material suitable for backfilling
DEWATERING SYSTEM
The ground water which will be present in the
ditch while excavation shall be sucked out by the
installation of dewatering pump with suction well
points installed at around 500mm below the
existing top soil. The well points shall be directly
installed by hydrojetting in case the soil below will
be sand or mud by excavation and installation of
aggregate. In case of hard soil or rock is found
below , drilling shall be done to insert the well
points with aggregate. The well point systems
shall be connected to header pipes which shall be
routed to the water channel by a discharge hose.
During the dewatering process, pump operators
shall be available for the day shift and the night
shifts monitoring the pump.
• Welfare register
• Materials log
• Hire equipment log
• Tool box talks
• Other posters
10.12. First aid box In site office and all vehicles & plant
location
Yes
Safety Boots
Yes
Hard Hats
Yes
Safety Gloves
No
Hearing Protection
Yes
Eye Protection
Yes
High Visibility
No
Respiratory Protection