VENDOR'S CONFIRMATION
REKIND TERMS AND CONDITIONS PLEASE CHECK
THE BOX
NO DESCRIPTION BIDDER RESPONSE
FOREIGN BIDDER LOCAL BIDDER YES NO
1 Scope Of Works Strictly as stipulated in Requisition (No...........................) and Minutes of Meeting during clarification & negotiation stage
2 Delivery Schedule Best Possible Delivery Time : ..... (weeks) or ..... (months)
3 Delivery Term FOB Port of Loading/ DDP Bojonegoro, East Java (Site) as per Incoterm 2010
7 Agent/Sole Agent Bidder shall inform Agent / Sole Agent information in Indonesia (if N/A -Not Applicable
any)
9 SubBidder information ( if any) Bidder shall inform Sub-Vendor information ( brand, name, Country of Origin, etc)
11 TKDN /Local Content comittment Bidder shall endeavor to maximize manufacturing/fabricating from Indonesian sources, and provide statement letter regarding the
use of such Local Content.
12 Dangerous Good Information ( If Applicable, complete Bidder shall inform the material or goods is catogerized in Dangerous Good or not.
with MSDS certificate)
13 Terms and Conditions Bidder shall follow Contractor's General Term and Condition Doc No : JTB-RJJ000-X0-PRC-900-00013
VENDOR'S CONFIRMATION
REKIND TERMS AND CONDITIONS PLEASE CHECK
THE BOX
NO DESCRIPTION BIDDER RESPONSE
FOREIGN BIDDER LOCAL BIDDER
Payment shall be done by Telegraphic Transfer Remittance with 60 (Sixty) days after the
receipt of correct and complete invoicing documents.
For Engineered Equipment or Fabricated Material
- 5% of Purchase Order Price shall be paid after received approved GA Drawings
-10% of Purchase Order Price shall be paid after Raw Material received at
Bidder’s shop.
- 70% of Purchase Order Price shall be paid after delivery of Material/Equipment
(FOB Port of Origin)
-10 % of Purchase Order Price shall be paid after completion of Final Documents
14 Payment Arrangement (Final Engineering Documents, Manufacturing Data Record, Manuals, etc.)
-5% of Purchase Order Price shall be paid after the end of Warranty Period or
replaced by warranty bond.
A Performance Bond in the form of Standby Letter of Credit in the A Performance Bond in the form of Bank Guarantee in the
amount equivalent to Ten percent (10%) of the Purchase Order price amount equivalent to Ten percent (10%) of the Purchase Order
shall be submitted to REKAYASA as beneficiary within fourteen (14) price shall be submitted to REKAYASA as beneficiary within
16 Performance Bond fourteen (14) days after signing of the Purchase Order. The
days after signing of the Purchase Order. The Performance Bond Performance Bond shall be valid 2 months after delivery
shall be valid 2 months after delivery completion. completion.
Standby Letter of Credit issue by a reputable national Bank Bank Guarantee issue by a reputable national Bank acceptable
acceptable to REKIND
to REKIND
18 Warranty Period Bidder will provide such warranty up to twelve (12) months from the date of Plant Acceptance by COMPANY or within thirty six (36)
months from the date of final delivery of the Materials whichever expires earlier.
A sum equivalent to zero point one percent (0,1 %) of the Purchase Order Price per day of the delayed with the maximum of ten
19 Liquidated Damage of Delay percent(10.0%), without any grace period.
If the vendor delays to submit detail engineering drawing by more than 30 days from the
scheduled date, REKIND shall forthwith deduct 2% of the PURCHASE ORDER PRICE.
VENDOR'S CONFIRMATION
REKIND TERMS AND CONDITIONS PLEASE CHECK
THE BOX
NO DESCRIPTION BIDDER RESPONSE
Bidder shall provide MRBFOREIGN
and VMCBIDDER
according to document listed on Requisition No…. LOCAL BIDDER
Final Documentation consist of : A.Bidder shall submit Index of Table of Content 4 week after PO issued
20 1. MRB- MANUFACTURING RECORD BOOK B. Bidder shall submit MRB and VMC within 5 week after completion delivery
2. VMC -VENDOR MECHANICAL CATALOG
21 Validity Proposal or quotation shall be valid for 180 days from submission date
22 Fix Quantity based on Bill of Quantity Quantity exactly shall be based on Bill of Quantity (BQ), Rekind shall not paid for excessive quantity