433kV 250kVA Transformer Tests


These tests are carried out in accordance with the format of the Works Site Test Report. The tests conducted are:‑
a) Winding Insulation Level
b) Ratio Test www.sayedsaad.com
c) Vector Group

8- HV Pressure Tests (132kV Equipment)


These tests will be carried out in accordance with the Works Site Test Reports.
The magnitude and duration of the test voltage is given in Table below. An opportunity to check VT calibration will be taken during these tests.
Equipment Test Voltage KV Test Duration
132 GIS 115 10 min.
11 KV 24 1 min

9- Supervisory Interface Test


The tests carried out will be:
a) Initiation of the appropriate alarms or indications at source and checking that the correct logic signals are received at the telemetry terminal (TTB) cabinet.
b) Apply a 50V DC voltage to the (TTB) cabinet terminals and check that the correct Circuit Breaker or tap changer command is received and executed.

10 - 11kV VT Tests. www.sayedsaad.com

The tests carried out will be:


a) Insulation Test. www.sayedsaad.com
b) Flick Test. www.sayedsaad.com
The polarity of the VT will be checked by carrying out the flick test.
11 - 11kV CT Tests
The tests carried out will be:
a) Insulation Test. www.sayedsaad.com
b) Flick Test. www.sayedsaad.com
c) Resistance Test
d) Saturation Test
Where more than one CT is in each phase of a circuit, tests where practical will be carried out to prove the CT's are positioned correctly so that arranged overlap of zones of
protection is correct This may be carried out by a) a visual inspection b) a continuity test.

Flick tests will be done on all CT's in a group to prove that they are connected to the protection in the same polarity. These tests will also be done on CT's mounted in
Transformer bushings. The flick test results should be compared with those expected from the schematic diagrams.

All CT's will have the dc secondary loop resistance and individual secondary winding resistances measured. www.sayedsaad.com

The saturation tests will be carried out to prove there are no shorted turns associated with the CT and to establish the knee point voltage of the CT's The magnetization
curve will be plotted for each CT or superimposed on the factory curves in order to determine that the correct CT is installed.

12- 11kV Primary Injection


Tests the tests carried out will be:
a) CT Ratio and Polarity Test
b) Relay Operation Tests
c) Unit Protection Operation and Stability Tests

Primary current shall be passed through each CT to prove its ratio and polarity with reference to other CTs in its group. All relays and instruments will be proved to be wired in
the correct phases.www.sayedsaad.com

All current "test terminals" will be checked for correct phasing, CT shorting Switches will be proved and any withdrawable relays should have their shorting contacts checked.
Inverse time relays shall be made to "creep' on minimum setting.
Transformer biased differential protection. The group of CTs should be proved for ratio and polarity, and the differential relay proved to operate for phase-phase, and phase-
earth fault injection.

Transformer Restricted Earth F a u l t Protections. The groups of CTs shall be proved for ratio and p o l a r i t y and stability by measuring spill currents.

13- 11kV Secondary Injection Tests


The secondary injection tests will be made to prove the relays, transducers and meters are operating a n d measuring correctly.
Secondary injection tests will consist of 'a.c.' injection into the relay coils to prove that the relay calibration is correct
A record of the relay type, serial number, and its setting range shall be recorded. -
The secondary current injection shall take place from the point at which the primary injection checks were made on the CTs.
For inverse time relays, the minimum starting current for which the relay will close its contacts with a maximum time dial setting shall be recorded. The resetting time of the
disc shall b_ recorded, and the time of operation for a current injection of twice, five times and ten times setting current. These results should be carried out on the relays
service setting (or nominal setting if service not known). The results should be compared with the relay curve supplied by the manufacturer. Also the time setting multiplier
characteristics will be checked at 2 points (setting point +1 other point).

For all relays fitted with a mechanical flag, the flag should operate just before the contacts make and the flag mechanism should not interfere with the operation of the relay.

The calibration of all instruments and transducers will be checked at scale and full scale by current and/or voltage injection as appropriate.

14. 11kV Switchgear Contact Resistance Checks


The contact resistance of all primary contacts will be checked by current injection and voltage drop measurement.

15. 11kV Switchgear Operational


Tests The tests carried out will be:
a) Local and Remote Operations of all Circuit Breakers
b) Local and Remote Indications of above
c) Electrical Interlocks of above
d) Gas Monitoring Sequence Tests
e) Alarm Sequence Tests
f) Tripping Tests including Arc Fault Tripping scheme
www.sayedsaad.com
Sequence tests will be carried out to prove all electrical circuits are operating correctly as shown in the schematic diagrams.
The control circuits will be tested by the manual operation of all close-trip Switches from all positions, for all Circuit Breakers and other devices in accordance with the
schematic diagrams.
The operation of all protection circuits will be proved to be in accordance with the protective gear schematic diagrams.
The tests will be conducted by manually making every main relay contact and observing Circuit Breaker tripping, auxiliary relay operation, lock-out relay operation and any
others. Tripping initiated by each relay in a protection scheme will be tested with the appropriate trip link in and out to prove that the link is connected and labeled correctly.
www.sayedsaad.com
The annunciator circuits will be proved to be in accordance with the schematic diagrams including alarm buzzer and/or bell, lights and any other means of alerting staff.
Operation tests of the alarm circuit will be by operating, at source, each alarm initiating relay contact, where possible,-or otherwise by simulation.
Operation of each Circuit Breaker disconnect Switch and earthing Switch will be proved to be free or locked according to the interlock condition shown on the schematic
diagrams.
www.sayedsaad.com
16.HV Pressure Tests (11kV Equipment)
These tests will be carried out in accordance with the Marugame Works Test Sheets. The magnitude and duration of the test voltages are given in Table 1
www.sayedsaad.com
17. Battery and Charger Tests
The batteries and chargers will have already been assembled, checked and put into service during the pre-commissioning stage by members of the commissioning team.
However certain further tests are now done and others repeated during the acceptance testing stage to be witnessed by the client. These tests will be carried out in
accordance with the manufacturers recommended testing procedures and will include the battery discharge tests.
www.sayedsaad.com
18. Multi-Core Cable Tests
All the multi-core cables will have already been checked to be in accordance with the appropriate termination diagrams during the pre-commissioning stage.
The insulation resistance tests will be repeated during the acceptance testing stage when they will be witnessed by the client.
www.sayedsaad.com
19. Earthing Tests
The erection staff will have originally conducted earthing tests but these will be repeated during the acceptance testing stage when they will be witnessed by the client.
www.sayedsaad.com
20. Fire Fighting Equipment Tests
The Subcontractor will have already carried out limited post erection checks, i.e. mechanical checks including a pressure test on the main tank and air leakage tests on the air
receiver.
The commissioning tests for water spray system will be:‑
www.sayedsaad.com
a) Compressor Sequence Tests
b) Alarm Sequence Tests
c) Indication Sequence Tests
d) Deluge Valve Sequence Tests
e) Discharge and Water Spray Tests
f) Inter-tripping Tests
www.sayedsaad.com
The commissioning for the other systems will be:
www.sayedsaad.com
a) Detector Operation Tests
b) Detector Line Supervision Tests
c) Pushbutton Function Tests
d) Tripping Tests
e) Halon Discharge Test
f) Dry Powder Discharge Test