Sie sind auf Seite 1von 3

STVI INVESTMENT Co.

, Ltd
DESIGN TEAM
Plumbing & Fire Fighting Section

TRAINEE ACTIVITIES AND WORKING SCHEDULE


ACLEDA INSTITUTE OF BUSINESS(AIB)
Date: 20-Feb-17
ITEM DESCRIPTION DURATION START DATE FINISH DATE CHECKING DATE REMARKS
A GETTING START
Understanding and reading some documentation related
1 10 days 20-Feb-17 3-Mar-17
to plumbing and fire fighting technical
Study the Lay-out Plan of AIB Project(Start from Admins,
2 SC1, SC2, DOM, DOF, LIBRARY, FACILITY BUILDING, 2 days 6-Mar-17 8-Mar-17
Outdoor)

ADMS,SC1,SC2, LIBRARY…. BUILDING


B DRAWING DESIGN AND CALCULATION DATA
1 Cold Water System
Schematic Drawing Preparation 1 day 9-Mar-17 10-Mar-17
Pipe sizing for all toilet, Kitchen area & main pipe line 3 days 13-Mar-17 15-Mar-17
Calculation capacity of booster pump 3 days 16-Mar-17 20-Mar-17
Calculation capacity of water storage tank 3 days 21-Mar-17 23-Mar-17
Bill of Quantities 1 day 24-Mar-17 24-Mar-17
Equipment selection and technical spec. 1 day 27-Mar-17 27-Mar-17

2 Sewage Drainage System


Schematic Drawing Preparation 1 day 28-Mar-17 28-Mar-17
Pipe sizing for all toilet, Kitchen area & main pipe line 3 days 29-Mar-17 31-Mar-17
Calculation capacity of waste water treatment plant 2 days 3-Apr-17 4-Apr-17
Bill of Quantities 1 day 5-Apr-17 5-Apr-17
Equipment selection and technical spec. 1 day 6-Apr-17 6-Apr-17

3 Fire Fighting System


Schematic Drawing Preparation 1 day 7-Apr-17 7-Apr-17
Pipe sizing for fire fighting system 3 days 8-Apr-17 10-Apr-17
Calculation capacity of fire pump 3 days 13-Apr-17 17-Apr-17
Calculation capacity of fire storage tanks 2 days 18-Apr-17 19-Apr-17
Bill of Quantities 1 day 20-Apr-17 20-Apr-17
Equipment selection and technical spec. 1 day 21-Apr-17 21-Apr-17

C Design Presentation / Report 31 days 24-Apr-17 25-May-17


STVI INVESTMENT Co., Ltd
DESIGN TEAM
MECHANICAL Section

TRAINEE ACTIVITIES AND WORKING SCHEDULE


ACLEDA INSTITUTE OF BUSINESS(AIB)
Date: 20-Feb-17
ITEM DESCRIPTION DURATION START DATE FINISH DATE CHECKING DATE REMARKS
A GETTING START
Understanding and reading some documentation related
1 10 days 20-Feb-17 3-Mar-17
to AC and Ventillation technical
Study the Lay-out Plan of AIB Project(Start from Admins,
2 SC1, SC2, DOM, DOF, LIBRARY, FACILITY BUILDING, 2 days 6-Mar-17 8-Mar-17
Outdoor)

ADMS,SC1,SC2, LIBRARY…. BUILDING


B DRAWING DESIGN AND CALCULATION DATA
1 Split & VRF System
Schematic Drawing Preparation 1 day 9-Mar-17 10-Mar-17
Pipe sizing for all room 3 days 13-Mar-17 15-Mar-17
Calculation load AC for all room 3 days 16-Mar-17 20-Mar-17
Insulation selection and calculation 3 days 21-Mar-17 23-Mar-17
Bill of Quantities 1 day 24-Mar-17 24-Mar-17
Equipment selection and technical spec. 1 day 27-Mar-17 27-Mar-17

2 Ventillation System
Schematic Drawing Preparation 1 day 28-Mar-17 28-Mar-17
Duct sizing for all toilet, Kitchen area 3 days 29-Mar-17 31-Mar-17
Calculation load for all Fan 2 days 3-Apr-17 4-Apr-17
Bill of Quantities 1 day 5-Apr-17 5-Apr-17
Equipment selection and technical spec. 1 day 6-Apr-17 6-Apr-17

3 Drainage System
Schematic Drawing Preparation 1 day 7-Apr-17 7-Apr-17
Pipe sizing for all pipe line from AC 3 days 8-Apr-17 10-Apr-17
Support pipe spacing 3 days 13-Apr-17 17-Apr-17
Insulation selection and calculation 2 days 18-Apr-17 19-Apr-17
Bill of Quantities 1 day 20-Apr-17 20-Apr-17
Equipment selection and technical spec. 1 day 21-Apr-17 21-Apr-17

C Design Presentation / Report 31 days 24-Apr-17 25-May-17