Job : ERECTION ASH LEACHING STRUCTURE AND DNCG System No. Revision :-
Location : RECOVERY BOILER Area, METHANOL PLAN Area Day / Date : Tuesday, October 30,2018
Day / Week : 67 / 8
:
Man Hours : 480 M/H of 17.898 M/H
DAILY ACTIVITY REPORT
TOOLS AND LIFTING DEVICE
MANPOWER QTY REPORT ERECTION TODAY
QTY
A. INDIRECT MANPOWER GENSET 100 KVA (SILENT MODEL) 1 unit
1. Project Manager 1 Person PICK UP MOBILE L300 1 unit ASH LEACHING VENT GAS STRUCTURE
2.Site Manager 1 Person PICK UP MOBILE L300 1 unit 1. Tightening Bolt elev.+11.900
3.Supervisor electrical 1 Person MOTOR CYCLE 150CC 1 unit 2. Erection main bracing elev.+6.600 to +11.900
4.Foreman STEEL STRUCTURE 1 Person WELDING MACHINE INVERTER 220V 5 unit 3. Preparation erection scrubber,condensor ALVG
5.Administrasi 1 Person CUTTING TORCH 5 unit 4. completion bolt and nut beam tier#2 VG
6.Engineering & Construction 1 Person GRINDING MACHINE 7 INCH 5 unit 5. Touch up finish coat
7.Surveyor 1 Person GRINDING MACHINE 4 INCH 6 unit METHANOL PLAN
8. Quality Control / Welder Inspector 1 Person CUTTING WHEEL MACHINE 14 INCH 1 unit 1. Install grating,handrail elev+8.000
TOTAL 8 Person WELDING MACHINE DONSUN 380V 4 unit 2.Verticallity Methanol tank
B. DIRECT MANPOWER CHAIN BLOCK 3 TON - unit 3. Tightening bolt all structure
1.Fitter 16 Person CHAIN BLOCK 10 TON 2 unit RFC Structure
2.Welder 2 Person LEVER BLOCK 1,5 TON - unit 1. Finishing sruct coloumn
3.Helper 6 Person AUTO LEVELLING 1 unit
4.Mechanical Elektrikal M/E 1 Person WEBBING SLING 4 ton 8 unit ESC Structure
5.Logistik Warehouse Keeper 1 Person WIRE ROPE 25mm 4 unit 1.Prepare erection struct.completed
6 HSE Officer 1 Person WIRE ROPE 20mm 4 unit 2. Padding pedestal evap.scrubber
7 Driver 1 Person Clamp Horizontal 2 unit RFS Structure
8 Operator Crane 1 Person Take Line Rope 100 lot 1. Erection main beam elev.+10.000
9. RIGGER 2 Person Life Line Rope 10mm x 200 MTR 200 lot
10.Schafolder 2 Person CONTAINER 20feet SITE OFFICE 1 unit
11. Pipe fitter 5 Person CONTAINER 20feet SITE W.HOUSE 1 unit ASH LEACH.TANK PLATFORM
12. Painter 2 Person TIG WELDING 5 unit 1. Finishing all structure
13 COMPRESSOR 15 KVA 1 unit
14 SPRAY GUN 1 unit
15 Fire Extinguiser Powder 6Kg 5 bottles
TOTAL MANPOWER 40 Person Exhaust Fan 12inch 1 unit
GRAND TOTAL 48