POKHARA UNIVERSITY

Level: Bachelor Semester: Fall Year : 2010


Programme: BE Full Marks: 100
Course: Estimating and Valuation Pass Marks: 45
Time : 3hrs.
Candidates are required to give their answers in their own words as far
as practicable.
The figures in the margin indicate full marks.
Attempt all the questions.
1. a) What is estimate? Write its types and also explain in which 8
conditions they are used?
b) How are following items of work measured and what are the units of 7
measurement and units of payment.
i. Honey comb brick wall in cm (1:4)
ii. Wooden skirting
iii. Centering and shuttering for RCC work
2. Prepare preliminary estimate of a residential building having carpet area 10
1300 Sqm. Take circulation area 20% of built up area. Area covered by
brick walls is 10% of built up area. Assume the plinth area rate civil work
is NRs 17000.00 per Sqm. Cost of water supply and sanitation is 6% of
building cost and cost of electrical work is 8% of building cost. Cost for
contingencies and supervision charges is 5.5% of total cost.
3. a) Work out the valuation of the cinema hall with the following data: 8
i. Cost of land = Rs.5500000.00
ii. Gross income = Rs.12000000.00
iii. Expenses undergone per year:
a) To run cinema including staff salary, electricity charges,
municipal taxes, license fee, stationary and printings etc is
30% of gross income.
b) Repair and maintenance of plants, machinery and tools at 5%
of their capital cost, which is Rs.10000000.00.
c) Sinking fund for machinery whose life is estimated as 30years
at 5% after allowing 10% scrap value.
d) Insurance premium is Rs.155000.00 per year.
Assume years purchase for 60 years at 8% and redemption of
capital at 4%. Annual repair of hall is 2% of gross income.
1
b) Define term value and cost. How do you prepare valuation of
existing building for sale purpose? List the circumstances under 7
which it is carried out.
4. a) Prepare an analysis of rate for 1st class brick work in 1:6 cement 8
mortar per 120 cu.m.
b) Prepare an analysis of rate for providing and laying 40mm thick 7
premix Asphalt carpet including compaction per sq.m.
5. a) Write the difference between book value and market value. 5
b) Calculate the volume of earthwork for the portion of the road having 10
1
formation width of 10m. The road has side slopes of 2:1 and 1 :1
2
(H:V) in banking and cutting respectively. The depth of cut and
height of bank at different chainages at their center lines are given
below.
Chainage (m) Depth of cut (m) Height of fill (m) Transverse
slope (r:1)
0 1.20 - 8:1
120 0.75 - 9:1
240 0.56 - 6:1
360 - 1.75 10:1
480 - 0.93 11:1
6. Estimate the quantities of the following items of work from the 20
accompanying “Building drawing.
a) Earth work (1:3:6) in foundation
b) R.C.C. Work in footing and column up to plinth
i. Concrete work
ii. Form work
iii. Reinforcement Bar
7. Write short notes on (Any Two) 2×5
a) Depreciation and obsolescence
b) Departmental charge
c) Task or out turn work