The document outlines an inspection and test plan for excavation of a gas pipeline trench. It details 6 activities to be inspected including reviewing excavation procedures, establishing the trench centerline, locating existing services, equipment inspection, excavating the main trench, and approving the trench dimensions. For each activity, it identifies the responsible persons for inspection and acceptance criteria, and refers to verifying documents like inspection reports. The objectives are to excavate the trench to proper dimensions, depths and clearances according to the approved specifications and diversion requirements.
The document outlines an inspection and test plan for excavation of a gas pipeline trench. It details 6 activities to be inspected including reviewing excavation procedures, establishing the trench centerline, locating existing services, equipment inspection, excavating the main trench, and approving the trench dimensions. For each activity, it identifies the responsible persons for inspection and acceptance criteria, and refers to verifying documents like inspection reports. The objectives are to excavate the trench to proper dimensions, depths and clearances according to the approved specifications and diversion requirements.
The document outlines an inspection and test plan for excavation of a gas pipeline trench. It details 6 activities to be inspected including reviewing excavation procedures, establishing the trench centerline, locating existing services, equipment inspection, excavating the main trench, and approving the trench dimensions. For each activity, it identifies the responsible persons for inspection and acceptance criteria, and refers to verifying documents like inspection reports. The objectives are to excavate the trench to proper dimensions, depths and clearances according to the approved specifications and diversion requirements.
Document No. PTJ-KPC-DA-013-PROC Sl. Activities Responsible Person Character to be Acceptance Verifying Document PTJ KPC No. Checked Criteria 01. Review of Work QA Engineer Approval and Company Approval document Approved procedure Procedure for QC CIVIL Inspector Revision Status H H Trenching 02. Establish Centerline of QA Engineer Co-ordinates Trench Co-ordinates as per TRENCHING Inspection Trench Approved Alignment Sheets Report R S QC CIVIL Inspector 03. Location of Existing QA Engineer Type of service, All services located and TRENCHING Inspection Services exact location and identified Report H W QC CIVIL Inspector depth of service Involved personnel informed 04. Equipment Inspection QA Engineer Safe Operation In safe working order, capability TRENCHING Inspection Capacity to perform the required Report W S HSE Advisor operation 05. Excavation of Main QA Engineer Existing Services Manual Trenching Required. TRENCHING Inspection Trench QC CIVIL Inspector Permit Check soil Permits to be obtained for all Report Holder classification Excavations. Trench Dimensions Minimum depth of cover shall be measured from the top of the pipe to the top of the H W undisturbed surface of the soil Access for traffic or top of graded Working Strip whichever is smallest. Proper controls for diversion of existing facility.
Legend: H = Hold Point, R = Review, W = Witness, S = Surveillance / Monitor
CONTRACT NO.
Dahshour /Abo El-Gharadig 24''/262.5 KM Gas PL veR 0
Document No. PTJ-KPC-DA-013-PROC Sl. Activities Responsible Person Character to be Acceptance Verifying Document PTJ KPC No. Checked Criteria
06. Approval of Trench QA Engineer Cover TRENCHING Inspection
QC CIVIL Inspector Depth to include cover & 150mm Report padding after compaction all around the pipe. Depth The min. depth of cover at crossing of wadies, drainages, ditches, tarmac roads, and live stocks whether or not indicated on the route maps, shall be measured from bottom of wadies, ditches or from the top of roads and tracks (depth shall be extended 5 m outside the H W edge).
Width to provide 150mm for
padding material Top of pipeline will be at min. of 500 mm below the bottom of the underground crossing structures (pipelines, sewers, water lines, Width cables, etc.) 06. Width shall be sum of the Cont. pipeline diameter + 300mm + 500mm clearance between
Legend: H = Hold Point, R = Review, W = Witness, S = Surveillance / Monitor
CONTRACT NO.
Dahshour /Abo El-Gharadig 24''/262.5 KM Gas PL veR 0
Document No. PTJ-KPC-DA-013-PROC Sl. Activities Responsible Person Character to be Acceptance Verifying Document PTJ KPC No. Checked Criteria
outside edges of adjacent
pipelines. Width shall be sum of the pipeline diameter + 300mm for single pipeline.
More width at the bend locations
for better placement
More depth & width to provide
bell holes to be sloped outwards in the sandy areas to prevent sand falling into the trench. Excavated to Specification, Free from Stones and Contamination.
Bends
Tie in locations Overall Profile
Legend: H = Hold Point, R = Review, W = Witness, S = Surveillance / Monitor
CONTRACT NO.
Dahshour /Abo El-Gharadig 24''/262.5 KM Gas PL veR 0