MONRIO INDUSTRIAL CORPORATION

Job Hazard Analysis(JHA)

no. Job Step Risk/Hazard Countermeasure


1 Permit to work Illegal Operation Strict compliance of PTW
Clash of Operation PTW shall be available at work area
Permit Approver should conduct work
area inspection prior on the approval

2 Mobilization of tools, Wrong position while Using cart/Trolly for transportation of


Equipment &materials lifting of heavy load materials
tools & materials

3 Selection Craftsman to Lack or poor Conduct toolbox meeting


do the job communication Review hazard analysis
Rush / Shorcut Ensured personnel clearly understand
the specific work activities,emergency
access assembly point areas and safety
requirements

4 Prepare work area Presence of unsuitable Reinforce safe working practice through
materials toolbox meeting prior to start work
5's before working
Barricading the area,display warning
signboard in place

5 Assemble of Scaffold Improper Assembling & Providing of checklist for scaffold ,


Dismantling of Scaffold Pls. see attached checklist

Falling workers Complete wearing of PPE's and full body


harness

6 Plastering Exposure to asbestos Wearing of appropriate PPE's to prevent


from exposure and inhalation of asbestos

Contact with electric Pre task briefing ,under the supervision


current of superior's

Injured resulting fom Proper ergonomics will be apply during


the use of plaster the operation to do the right use of
spraying machince tools and right position of working

Slip,trips and fall Protective fencing against falling from


of workers on level elevated work surface shoul be installed
Full body harnes must be available and
use by a competent workers .
7 Mounting of Ventilation Fingers caught in Pre task briefing
between materials and Supervision of Superior's
tools

Overhead hazard Make sure there is enough lightning in


the area
Checking of 100% tie off of body harness
Hot temperature Drinking station availability

Poor communication Always Ask the superior's before starting


the job

Ergonomics Proper ergonomics shall conduct in TBM

8 Tapping of Wire/Wiring Electricussion During the operation ,proper PPE's


esp. hand gloves for electrical must be use

Availability of fire extinguisher


Standby watchman while operating

TBM with the superiors on how the


right process will flow .

9 Housekeeping Open Debris Proper waste disposal of garbage and


hazardous subtances
Permit signed off