Beruflich Dokumente
Kultur Dokumente
Submitted By:
• The burnt value is way more than the planned value. And
not just this, the value earned is less than what it was
scheduled to be, thus increasing the disparity between
the burned value and the actual value
EVA Template: Technical
Infrastructure
Summary of the case
• MED-X Inc. was a global pharmaceutical company
headquartered in Houston, Texas. MED-X was spending
$3billion annually on indirect goods and services out of
which 1 billion was spent on technology.
• They estimated that a decentralized procurement
model would help save $200 million annually.
• So, they thought of implementing Ariba Buyer solution
that would help organization gain purchasing power and
reduce processing cost and cycle times.
• The project was given to Implementation technologies
with deadline of 1 October, 2001.
• Christopher Martin was the project manager on this
implementation project
• Original project timeline was as follows:
Approx. project start date May1, 2001
Submitted By:
220000 TECHNICAL
INFRASTRUCTURE
165000
PLAN BCWS
110000 ACTUAL BURN ACWP
ACTUAL PERFORM BCWP
55000
0
MAY JULY SEPTEMBER
WHY DID TERRY BAKER THINKS THAT
OVERALL PROJECT WAS GOING ACCORDING
TO THE PLAN TH ENTIRE TIME ?
220000
• TECHNICAL
INFRASTRUCT
URE
165000
PLAN BCWS
110000 ACTUAL PLAN ACWP
BCWP
55000
0
MAY JUN JUL AUG SEP
How much longer will the
project take
Scheduled time: May-Oct i.e. Days=184
= 184/.96
=192(approx.)