Beruflich Dokumente
Kultur Dokumente
CONSTRUCTION CONTRACTS
1. Introduction to construction project stages, overview of
DOCUMENTS the construction contracting methods, and contracts
types.
2. Bidding document
Invitation to bid
Instruction to bidders
Information to bidders & bid data
Biding Forms
General conditions of contract
Specific condition of contract
Specification
BOQ
Drawings
Contract forms
3. Methods of Tendering, Bidding and Awarding
4. Contract Documents and Conditions
1
Project Life Cycle
Full
Ope rations
Percent Complete
Com ple te
Major Contracts
Le t
Pr oje ct "GO"
De cis ion
Appointing Main
Appointing
Contractor
Consultant
Constructing
Designing
The owner defines project goals and objectives, secures the financing, ⌧ Applicable to a wide range of projects.
and specifies the standards and contract terms.
The owner may perform planning, conceptual design and full design,
⌧ Well established and easily understood.
or may engage an outside design professional (designer) for some or ⌧ Clearly defined roles for all parties.
all of these tasks. ⌧ Provides the lowest initial price that competitive
During this planning and preliminary stage, owner and designer work bidders can offer.
as a team to obtain required permits and conduct necessary site
investigations. ⌧ Extensive litigation has resulted in well established
The designer prepares the construction bid documents to reflect the legal precedents.
owner’s project goals and objectives, the project’s site conditions, and ⌧ Insurance and bonding are well defined.
sound engineering practices.
Prospective contractors prepare their bids from these complete and
specific bid documents.
The bidders submit their proposals to the owner, who determines the
most responsive (typically the lowest) bid meeting project
requirements.
In certain circumstances, owner may be justified in selecting a
contractor outright and negotiating contract terms directly.
2
Disadvantages of D-B-B Approach Design-Build Approach
Least-cost approach requires higher level of inspection. Design-build approach is a project delivery system involving a
single contract between the project employer and a
Initial low bid might not result in ultimate lowest cost or design-build contractor covering both the design and
final best value. construction of a project.
The design-builder performs design, construction engineering,
Designers may have limited knowledge of the true cost and construction according to design parameters,
and scheduling implication of design decisions. performance criteria and other requirements
established by the employer or his representative.
The owner contracts with a single entity to provide the design For many owners, delegation of responsibilities leads to
and to construct the project according to that design. satisfactory projects. However, if the parties are
The contract might be negotiated with a single design-builder inexperienced and do not cooperate, the transfer of control
or result from competitive proposals. and risk can be disappointing.
The owner may need to restructure his/her internal
The selection can be based on low price or on a set of value
procedures to accommodate design-build approach.
criteria (experience, staff, bonding capacity, etc.).
Compared to DBB, this involves a significantly different set
Design-build provides the owner with a single point of contact of requirements and expectations for process, timelines and
for project responsibilities, eliminating the need to assist in communications.
resolving designer-contractor disputes.
A clear understanding and documentation of design-build
With the contractor playing a major role in design, costs are processes enhances the quality of design-build projects
typically defined and maintained to a greater degree, and the
coordination of fast-track management to achieve early
completion is greatly simplified.
The design-builder makes many decisions that owner would
make under DBB, due to delegation of greatly increased
authority.
Innovation and quality improvements through: Reduced opportunities for smaller, local construction firms.
- Alternative designs and construction methods Fewer competitors and increased risk may result in higher
initial costs.
suited to the contractor’s capabilities Elimination of traditional checks and balances. Quality may
- Flexibility in the selection of design, materials, and be subordinated by cost or schedule considerations.
construction methods. Less Engineer control over final design.
Higher procurement costs.
• Earlier schedule and cost certainty Traditional funding may not support fast-tracking
construction or may require accelerated cash flow.
Accelerated construction can potentially overextend the
workforce.
3
Others Turnkey
Turnkey Turnkey adds to the design-builder’s
responsibilities the operation and/or maintenance
Turnkey Variations of the completed project.
Direct Labor Approach. Turnkey delivery has the potential for bringing a
new project on line more quickly.
Construction management
Three forms of turnkey project delivery:
Design-build-operate-transfer
Design-build-operate-maintain
Design-build-own-operate-transfer
4
Content of the contract Major Contract Types (traditional)
o Identify the parties
o Promises and responsibilities
o Scope of work
o Price and payment terms
o Commercial terms and conditions
o Project execution plan.
5
Unit Price contract Unit Price / Requirement
Require sufficient design definition to estimate Adequate breakdown and definition of work units
quantities of units Good quantity surveying and reporting system.
Contractors bid based on units of works Adequate drawings.
Time & cost risk (shared) Experience in developing BOQ
Owner : at risk for total quantities
Payment based on the measurement of the finished
Contractor : at risk for fixed unit price.
works.
Large quantities changes (>15-25%) can lead to Quantity sensitive analysis of unit prices to evaluate
increase or decrease of unit price. total bid price for potential quantity variation.
6
Cost + Fixed Fee
Cost Plus Fixed Fee
Fee = percentage of the Advantages Disadvantages Most common form of negotiated contracts
original estimated total figure
Utilized on large multi- Fee amount is Expensive COST = expenses incurred by the contractor
year jobs fixed materials and for the construction of the facility
Ex: WW treatment plant regardless construction Includes: Labor, equipment, materials, and
Facility (Cost = $20 of price techniques may administrative costs
million, Fee = 1%) fluctuation be used to
$20 Million 1% fee = expedite FEE = compensation for expertise
$200,000 Million construction Includes: profit
Provides
incentive to
complete
the project
quickly
7
CONSTRUCTION DOCUMENTS CONSTRUCTION DOCUMENTS
BIDDING REQUIREMENTS
BIDDING REQUIREMENTS
Bidding Requirements are used to attract bidders and explain the procedures to be followed
in preparing and submitting bids .
Bidding requirements help bidders follow established procedures and submit bids that will
not be disqualified because of technicalities. They do not become part of the contract
documents
Bidding documents
All of the construction documents issued to bidders before the signing of an owner-
contractor agreement.
Bid Package
Documents available to the contractor and on which he must make a decision to bid
or not
A set of plans and technical specifications, Proposal form, general conditions,
special conditions,
Description of the project to be constructed
Bid Package is prepared by: