Beruflich Dokumente
Kultur Dokumente
TABLE OF CONTENTS
1. GENERAL.........................................................................................................................................2
2. SCOPE OF WORK.............................................................................................................................2
3. STRUCTURAL SYSTEM.....................................................................................................................2
3.1 Factory building....................................................................................................................................2
3.2 Ceiling support on the production areas..............................................................................................3
3.3 Drain pipe support...............................................................................................................................3
3.4 External walls support..........................................................................................................................3
4. DESIGN LOAD AND STANDARDS......................................................................................................3
4.1 Gravity Loads........................................................................................................................................4
4.2 Wind Load............................................................................................................................................4
4.3 Earthquake Load..................................................................................................................................5
4.4 Temporary Load...................................................................................................................................5
4.5 Geometric Imperfection.......................................................................................................................5
5. DEFLECTION LIMITS........................................................................................................................5
6. STEELWORK PROTECTIVE COATING/PAINTING................................................................................6
7. GENERAL REQUIRES........................................................................................................................6
8. POST TENDER DOCCUMENTS..........................................................................................................7
9. POST CONSTRUCTION DOCCUMENTS..................................................................................................8
Revision – Date: 30 September 2013 Specification-0351 Structural Pre-Engineering Building – Page 1/8
Sanofi Factory Project
1. GENERAL
“General Conditions of Contract” which shall apply to this section of the works.
2. SCOPE OF WORK
The following is a technical description of the design guidelines for the pre-engineered steel building.
These design criteria must be followed at all times. If Tenderers wish to vary from the following
document then these alternatives must be submitted and noted clearly in their bid document. This
requires Tenderers to submit both a complying and non-complying tender return bid.
This specification is to be read in conjunction with the drawings, other technical tender documents for
Architecture and Mechanical, Electrical and Plumbing (MEP) disciplines.
Refer to the Tender conditions for delivery schedule, shipping, customs clearance, transport, health &
safety, site installation, unit rates, payment terms, retention, warranty conditions, maintenance
requirements and other similar commercial tender requirements.
3. STRUCTURAL SYSTEM
Revision – Date: 30 September 2013 Specification-0351 Structural Pre-Engineering Building – Page 2/8
Sanofi Factory Project
The vertical and horizontal loads will be supported by Main portal steel frames in one direction and
by bracing in the other direction. These frames have pinned connections to column bases in order to
avoid transmitting moments to ground floor and to foundation.
The mezzanine level is composed of concrete slab on metal decking supported by steel beams and
steel columns. These steel columns are only supporting mezzanine floor slab.
The mezzanine floor slab is designed by reinforced concrete slab, not a composite one. This design is
not in the score of work of Tenderers.
However, Tenderers need to provide metal decking for slab formwork with shear studs between steel
beams and metal decking. A minimum shear studs @800mm on steel beams is required.
Steel stairs no 12 & 13 from the mezzanine level and Administration building roof level to the main
warehouse’s roof are provided.
Others small prefabricated stairs between main warehouse’s roof and others lower roofs need to be
designed and supplied by Tenderers.
Movement joints on mezzanine slab at grids 7 & 20 are provided to minimize the temperature and
shrinkage effects on the concrete mezzanine slab.
Refer to the steel plans, sections and elevations for locations of columns, beams, stairs no 12, 13 and
vertical bracing.
In the production areas, next to the mezzanine, a framework of horizontal beams needs to provided
in order to support plaster ceiling and walkable ceiling below. This framework is supported by vertical
steel hangers suspended to the main main steel rafters and columns.
Refer to the steel plans and sections for locations of framework and vertical steel hangers.
This framework and vertical steel hangers are in the scope of work of Tenderers.
In the factory building, interior drain pipes needs to be suspended to roof purlins by steel cables.
The design and supply of this drain pipes and steel cable are by others.
However, the Tenderer must take into consideration the impact of this weight onto the purlins, main
steel rafters and columns.
External walls of factory building are in masonry of 5.5m height. These connect to the main steel
frames in order to transfer wind load into main steel frames.
The design of these walls is not in the score of work of Tenderers.
However, the Tenderer must take into consideration the impact of wind load on external walls onto
the steel frames.
Revision – Date: 30 September 2013 Specification-0351 Structural Pre-Engineering Building – Page 3/8
Sanofi Factory Project
The Client has strict requirements on the minimum loads and standards to be applied to the design
portion of the works and these are noted below.
Acceptable steel design standards are Bristish Standards, American Standards (AISC) or Vietnamese
standards (TCVN). Limits of deflections required are noted below.
In addition to the above international design standards the Client building Insurer has strict additional
design requirements to be followed and these structural items are noted below.
The Tenderer must provide in his return bid document a list of all design codes that they have used
for review by the Client.
If Tenderers wish to use different standards or load values to those documented below then these
alternatives must be submitted and noted clearly in their bid document. This requires Tenderers to
submit both a complying and non-complying tender return bid.
Gravity loads (dead load, superimposed dead load & live load) need to be accordance to with the local
TCVN standard and not less than loads required in the loading drawings S-02-01, S-02-02, S-02-03.
Concerning roof secondary elements such as purlins, claddings…, Client’s Insurance Company requires
roof live load 1kN/m2.
Applicable wind loads and internal/external pressure coefficients are as a minimum to be in accordance
with the local TCVN standard and relate to the building shape, height and location. Load combinations
should follow the specified design standards specified in section 4 above.
Concerning secondary elements such as roof purlins and wall girts, Client’s Insurance Company requires
design of wind load with the following criteria:
- Basic wind speed: 50m/s
- Wind uplift rating:
Field: 5.7 kPa
Perimeter: 7.9 kPa
Corner: 11 kPa
Perimeter strip width: 4.6 m defines the size of the corner zone
- Wall area and Lateral Pressure rating:
Field (zone 4) inward pressure: 2.25 kPa
Field (zone 4) outward pressure: 2.48 kPa
Corners (zone5) inward pressure: 2.25 kPa
Corners (zone 5) outward pressure: 2.85 kPa
Revision – Date: 30 September 2013 Specification-0351 Structural Pre-Engineering Building – Page 4/8
Sanofi Factory Project
Applicable seismic loads and combinations are to be in accordance with the TCVN standard and the
building location.
5. DEFLECTION LIMITS
Due to the different building area functions, façade cladding and brittle ceiling materials there are
strict guidelines on allowable deflections under the serviceability dead, live, wind & seismic load
combinations. The limiting SLS criteria are as follows:
Revision – Date: 30 September 2013 Specification-0351 Structural Pre-Engineering Building – Page 5/8
Sanofi Factory Project
Tenderers can propose alternative solutions of steelwork protective. This must be submitted and
noted clearly in Tenderers bid document. Tenderers are required to submit both a complying and non-
complying tender return bid.
Revision – Date: 30 September 2013 Specification-0351 Structural Pre-Engineering Building – Page 6/8
Sanofi Factory Project
7. GENERAL REQUIRES
a. Sufficient structural drawings of plans, sections, elevations and details to show all relevant
information and full compliance with the specified design requirements.
b. A separate drawing package showing any alternative non-conforming designs that give rise to
an advantageous design for cost, efficiency, erection or otherwise.
c. Columns service load plans to allow for concrete and foundation design checking. The loads
should be noted separately as dead, live, wind (uplift and downward), collateral (ceiling &
services) and seismic. All load locations should be clearly noted with setout dimensions from
the gridline locations.
d. All bracing locations and loads, these should be coordinated and generally follow the locations
shown on the documented plans.
e. All gutter and downpipe locations, sizes and connection details. The locations are to match the
documented locations and sizes indicated on the Architects/MEP pre-engineered tender
drawings.
f. A material specification for all items including, but not limited to the following:
Built up steel plate & welding
Hot rolled sections
Cold formed sections & bolts
Roof panels & fixings
Wall panels & fixings
Vertical & horizontal cross bracing
Holding down bolts
High strength connection bolts
Painting or finishing system to differing steelwork areas.
a. Within 1 week after approval by the Client of the Concept drawings the Contractor shall
provide all completed detailed drawings and connections (in hard copy and soft copy -
AutoCAD format). This package should also include two full sets of all computations (both
hard/soft copy and input, output and section size computation) with the approved detailed
Drawings.
Calculations and computer model input/output will be required to be provided and approved
prior to any fabrication works proceeding. Failure to meet the any of the specified technical
tender requirements may result in rejection of the provided steel sizes.
b. The final detailed drawings shall contain sufficient details to enable the coordination of the
design and construction. Such information is to include, but not limited to:
Set out and size/details of all holding down bolts,
Revision – Date: 30 September 2013 Specification-0351 Structural Pre-Engineering Building – Page 7/8
Sanofi Factory Project
Size and orientation of all columns, rafters, jack beams, purlins, girts and other
miscellaneous steel sections required,
Typical building sections and plans showing all member sizes,
All detailed connections,
Location of all braced bays,
Details of any concrete cast in items or rebates needed,
Typical roofing and walling details showing connections, sizes and all trimming
steel.
c. Early delivery of all holding down bolts to be cast in any concrete elements. Included should
be a setout drawing showing locations and dimensions of all bolts.
b. Supplementary calculation booklet for all revisions to the original tender design documents.
c. “As built” drawings shall be based on a 3D site survey measure of all steelwork installation.
Revision – Date: 30 September 2013 Specification-0351 Structural Pre-Engineering Building – Page 8/8