Beruflich Dokumente
Kultur Dokumente
Front Page
Contents
Project Brief
Project Organization Chart & Communications
Site Plan
Health & Safety Performance Highlights
Health & Safety Key Highlights for December 2018
Planned/Achvd/Balance/Shortfall Amout
site notes
Survey and level clearance
Sequence of activities Structure
Finishing conventional
Aluform
1 Format Daily quality control report
2 Monthly quality control report
3 Non Conformance record
4 Orientation of new joiners in QAPE
5 Quantity training log book
6 Site Audit report
7 Risk Matrix
8 Material Rejection
9 Unit and common area clearance
10 Unit clearance certificate
11 Common area clearance certificate
12 RMC batch ticket
13 Site quality walkthrough plan
14 Site Observation register
15 Inspection schedule
16 Method statement register
17 Concrete Pourcard
18 Qualuty Review meeting MOM
1 ITP Excavation
2 Backfilling
3 Antitermite
4 Reinforcmenet installation
5 Formwork Installation
6 Reinforced cement Concrete
7 Masonry
8 Cement plaster
9 Gypsum Plaster
10 Waterproofing
11 Handrail fixing
12 Internal Painting
13 External Painting
14 Windows
15 Door installation
16 Tiling Dado and flooring
17 False ceiling
18 Road works
Methodology Excavation
PCC
Reinforcement
Aluform
Concrete works
Tile flooring
Tile dado
External painting
Internal Road work
MS hand railing
Sunken waterproofing
Terrace waterproofing
OHT waterproofing
CCGI Window installation
Kitchen Platform fixing
Pre-cast shelf fixing
Tie-rod hole packig
PVC door shutter and frame fixing
Survey
Earthwork
Backfilling
ATT
Foundation,slab and beam
RC column
Reinforcement
RW
Formwork fixing
Construction joint treatment
Honeycomb repairing
Pile extension
Piling
Blockwork
Plastering
Tiling wall
Tiling floor
Shrinkage cracks
Tie rod hole packing
Wall tie grouting
Painting
Waterproofig for sunken slab
Gate - Entry and exit Material inward and outward, visitors, RMC, Steel, Laboour,
MRM DC Material transfer
Cashflow and outflow of material
Material request generated and sent to cluster, rate is negotiated and finalised
Labour physical check contractor wise, site round and physical checking (spot
Gate/Out pass