TSK Cabin C Commissioning Plan (Zone wise revised as on date 18'Oct'2019 based on MOM dated on 20'Aug'2019 = Annexure - I )

Sl. Scope of Scope Pending Scope of Scope Pending Scope of Scope Pending
Pending work Start Date End Date Start Date End Date Start Date End Date
No. work Qnty scope work Qnty scope work Qnty Qty

Material status

Workmen Req

Workmen Avl
Total scope (LEU 01 to LEU 14) Zone-1 (LEU 01 to LEU 04) Zone-2 (LEU 05, 06 & 09)

Target Date
Material
a). LEU with LB1 & LB2 each -14 a). LEU with LB1 & LB2 each -04 a). LEU with LB1 & LB2 each -03

UOM
b). CH-11, MSDAC - 38, LVV-14 b). CH-03, MSDAC - 08, LVV-02 b). CH-02, MSDAC - 11, LVV-05
c). Point M/c- 69 c). Point M/c- 18 c). Point M/c- 18
d). Main signal - 42 (with depend SH), Indep SH- 27* d). Main signal - 11, Indep SH- 05 d). Main signal - 11, Indep SH- 07*

Physical completion 30-Nov-19 5-Nov-19 15-Nov-19

1 Main cable and Tail cable Trench Avl 50 26 KM SNT 21.65 14.7 27-Aug-19 10-Nov-19 SNT 5 0 Complete SNT 4.25 3.5 27-Aug-19 20-Oct-19

2 Main cable and Tail cable Laying Avl 50 26 KM SNT 143.5 94.6 27-Aug-19 10-Nov-19 SNT 26.5 0 Complete SNT 28.5 12.4 27-Aug-19 20-Oct-19

3 Power cable and RTU cable End Termination Avl 8 3 Nos. SNT 158 114 11-Sep-19 15-Nov-19 SNT 44 0 Complete SNT 33 33 11-Sep-19 20-Oct-19

4 LEU Relay LB wiring (LB1&LB2) Avl 3 2 Nos. SNT 28 5 11-Oct-19 30-Oct-19 SNT 8 0 Complete SNT 6 0 Complete

5 Earthing arrangements (Earthpit & GI wire) for LEU LB1 & LB2 only 28 Avl 3-Sep-19 15 4 Nos. JSNEPL 28 10 3-Sep-19 14-Nov-19 JSNEPL 8 2 3-Sep-19 25-Oct-19 JSNEPL 6 0 Complete

6 Foundation for JB LB and MSDAC and erection Avl 5 5 Nos. SNT 14 14 2-Oct-19 15-Nov-19 SNT 1 1 2-Oct-19 25-Oct-19 SNT (2) 2 2 5-Oct-19 30-Oct-19
Signal Fdn bal: 1SH* in Z1 (No Track) & 1S/SH in Z4 (Damaged)
7 All cables Armoured Connect with Earth pit for LEU LB1 & LB2 only Local 10 3 Nos. SNT 28 28 5-Sep-19 15-Nov-19 SNT 8 8 5-Sep-19 25-Oct-19 SNT 6 6 16-Sep-19 30-Oct-19
8 SPD wiring at all location N. Avl 3-Sep-19 2 2 Nos. SNT 14 14 1-Oct-19 10-Nov-19 SNT 4 4 1-Oct-19 25-Oct-19 SNT 3 3 6-Oct-19 30-Oct-19
9 CH LB wiring and KLCR Mounting 7 2 Nos. SNT 11 1 26-Oct-19 15-Nov-19 SNT 3 0 Complete SNT 2 0 Complete
10 Bell test - - - Nos. TSTS 14 14 5-Oct-19 20-Nov-19 TSTS 4 4 5-Oct-19 25-Oct-19 TSTS 3 3 16-Oct-19 25-Oct-19
11 Customer Bell test - - - Nos. RITES 14 14 15-Oct-19 25-Nov-19 RITES 4 4 15-Oct-19 25-Oct-19 RITES 3 3 26-Oct-19 30-Oct-19
12 Point JB Installation N. Avl 23-Sep-19 10 0 Nos. SNT 63 63 5-Oct-19 30-Oct-19 SNT 16 16 5-Oct-19 25-Oct-19 SNT 17 17 11-Oct-19 25-Oct-19
13 Field Gear wiring at Point JB end N. Avl 23-Sep-19 5 0 Nos. SNT 63 63 5-Oct-19 4-Nov-19 SNT 16 16 5-Oct-19 25-Oct-19 SNT 17 17 12-Oct-19 25-Oct-19
14 Point Machine, ground rod fitting Installation & Field Gear wiring at Avl 12 5 Nos. SNT 63 55 11-Oct-19 30-Nov-19 SNT 16 12 11-Oct-19 5-Nov-19 SNT 17 16 20-Oct-19 15-Nov-19
Point M/c end

15 Point machine testing and commissioning Avl - - Nos. SNT / 63 63 12-Oct-19 30-Nov-19 SNT / 16 16 12-Oct-19 5-Nov-19 SNT / 17 17 21-Oct-19 15-Nov-19
RITES RITES RITES
16 Simulation Wiring for point operation - - - Nos. TSTS / SNT 14 14 12-Oct-19 30-Nov-19 TSTS / SNT 4 4 12-Oct-19 5-Nov-19 TSTS / SNT 3 3 25-Oct-19 15-Nov-19
17 Power ON - - - Nos. TSTS 14 14 21-Oct-19 30-Nov-19 TSTS 4 4 21-Oct-19 5-Nov-19 TSTS 3 3 25-Oct-19 15-Nov-19
18 MSDAC Wiring (DAC - Termination completed in Z1 (7) & Z2 (4),
Internal wiring pending in all zones) 7 2 Nos. SNT 38 24 6-Oct-19 7-Nov-19 SNT 8 0 Complete SNT 11 5 6-Oct-19 28-Oct-19

LVV Wiring (LVV-Termination completed in Z1 (2) & Z2 (2), Internal


19 wiring pending in all zones) 7 2 Nos. SNT 14 3 6-Oct-19 7-Nov-19 SNT 2 0 Complete SNT 5 0 6-Oct-19 Complete

20 Earthing arrangements (Earthpit & GI wire) for other LB & signal 72 Avl 15 4 Nos. JSNEPL 133 92 3-Sep-19 14-Nov-19 JSNEPL 29 14 3-Sep-19 23-Oct-19 JSNEPL 36 25 6-Oct-19 28-Oct-19

21 All cables Armoured Connect with Earth pit for other LB & signal Local 10 3 Nos. SNT 80 80 5-Sep-19 15-Nov-19 SNT 26 26 5-Sep-19 23-Oct-19 SNT 22 22 6-Oct-19 28-Oct-19

22 Field Gear wiring at Main Signal end (LED unit) Misfit 5 3 Nos. SNT 42 35 10-Sep-19 10-Nov-19 SNT 11 4 10-Sep-19 23-Oct-19 SNT 11 11 6-Oct-19 28-Oct-19
23 Field Gear wiring at Shunt Signal end (LED unit) 5 3 Nos. SNT 27 23 10-Sep-19 10-Nov-19 SNT 5 1 10-Sep-19 23-Oct-19 SNT 7 7 6-Oct-19 28-Oct-19
24 OFC Splicing in LEU location Avl 2 2 Nos. TSTS 14 14 15-Oct-19 25-Nov-19 TSTS 4 4 15-Oct-19 23-Oct-19 TSTS 3 3 17-Oct-19 30-Oct-19
25 Simulation Wiring complete zone - - - Nos. TSTS 14 14 18-Oct-19 30-Nov-19 TSTS 4 4 18-Oct-19 23-Oct-19 TSTS 3 3 1-Nov-19 3-Nov-19
26 Power ON - - - Nos. TSTS 14 14 25-Oct-19 30-Nov-19 TSTS 4 4 25-Oct-19 27-Oct-19 TSTS 3 3 4-Nov-19 7-Nov-19
27 SAT - - - Nos. TSTS 1 1 25-Oct-19 30-Nov-19 TSTS 0.25 0.25 25-Oct-19 30-Oct-19 TSTS 0.25 0.25 8-Nov-19 10-Nov-19
28 Painting and Name tag provision Avl 6 0 Nos. SNT 1 1 25-Oct-19 20-Nov-19 SNT 0.25 0.25 25-Oct-19 30-Oct-19 SNT 0.25 0.25 30-Oct-19 5-Nov-19
29 Indoor works - Auto changeover (ACO) installation Avl 2 2 Nos. SNT 1 0 Complete SNT 1 0 Complete
30 Main Cable laying from PDB to ACO Avl 2 2 Nos. SNT 2 0 Complete SNT 2 0 Complete
31 Main Cable laying from ACO to IPS Avl 2 2 Nos. SNT 2 0 Complete SNT 2 0 Complete
32 Maintenance Free Earthing and connections Avl 5 0 Nos. SNT 4 4 3-Sep-19 5-Nov-19 SNT 4 4 3-Sep-19 5-Nov-19
33 LA class A installation N. Avl 23-Sep-19 5 0 Nos. SNT 1 1 15-Sep-19 5-Nov-19 SNT 1 1 15-Sep-19 5-Nov-19
34 IPS power ON and battery charging Avl 2 2 Nos. SNT 2 2 5-Sep-19 5-Nov-19 SNT 2 2 5-Sep-19 5-Nov-19

35 cable laying on ladder tray from power rack to IPS (Module output
wiring) Avl 2 2 Nos. TSTS 38 38 7-Sep-19 30-Oct-19 TSTS 38 38 7-Sep-19 30-Oct-19

36 Cable terminations at IPS & power rack side Avl 2 2 Nos. TSTS 38 38 13-Sep-19 30-Oct-19 TSTS 38 38 13-Sep-19 30-Oct-19
37 VDU and MTC installation, SPD wiring Avl 2 2 Nos. TSTS 1 1 15-Sep-19 30-Oct-19 TSTS 1 1 15-Sep-19 30-Oct-19
38 Main Cable laying from Power Rack to MSDAC Rack Avl 2 2 Nos. SNT 14 14 5-Sep-19 25-Oct-19 SNT 14 14 5-Sep-19 25-Oct-19
39 Cable terminations at MSDAC Rack and Power Rack Avl 2 2 Nos. SNT 14 14 10-Sep-19 25-Oct-19 SNT 14 14 10-Sep-19 25-Oct-19
40 Main Cable laying from CTR to MSDAC Rack Avl 2 2 Nos. Siemens 28 28 13-Oct-19 25-Oct-19 Siemens 28 28 13-Oct-19 25-Oct-19
41 Cable terminations at MSDAC Rack and CTR Avl 2 2 Nos. Siemens 28 28 13-Oct-19 25-Oct-19 Siemens 28 28 13-Oct-19 25-Oct-19
42 Main Cable laying from CTR to Relay Rack Avl 2 2 Nos. TSTS 14 0 30-Dec-99 30-Dec-99 TSTS 14 0 Complete
43 Cable terminations at Relay Rack and CTR Avl 2 2 Nos. TSTS 14 0 30-Dec-99 30-Dec-99 TSTS 14 0 Complete
44 Tray fixing and Main Cable laying from Ground to Power Rack Avl 2 2 Nos. SNT 24 24 23-Sep-19 11-Nov-19 SNT 6 6 23-Sep-19 25-Oct-19 SNT 8 8 23-Sep-19 25-Oct-19
45 Cable terminations at Power Rack for Outdoor cable Avl 2 2 Nos. SNT 24 24 28-Sep-19 12-Nov-19 SNT 6 6 28-Sep-19 25-Oct-19 SNT 8 8 28-Sep-19 25-Oct-19
46 Tray fixing and Main Cable laying from Ground to CTR Avl 2 2 Nos. SNT 54 54 25-Sep-19 12-Nov-19 SNT 12 12 25-Sep-19 25-Oct-19 SNT 18 18 25-Sep-19 25-Oct-19
47 Cable terminations at CTR Avl 2 2 Nos. SNT 54 54 30-Sep-19 14-Nov-19 SNT 12 12 30-Sep-19 25-Oct-19 SNT 18 18 30-Sep-19 25-Oct-19
NOTE: Commissioning of TSK Cabin C yard scope is in M/s SNT and TSTS only. Other agencies (MMC / JSNEPL) are engaged on risk purchase basis of M/s SNT to support their works. All agencies shall complete their scope as per assigned target dates

TSTS SNT MMC JSNEPL RITES TSL 1 of 2


TSK Cabin C Commissioning Plan (Zone wise revised as on date 18'Oct'2019 based on MOM dated on 20'Aug'2019 = Annexure - I )

Sl. Scope of Scope Pending Scope of Scope Pending


Pending work Start Date End Date Start Date End Date Remarks
No. work Qnty Qty work Qnty Qty

Zone-3 (LEU 07, 08 & 10) Zone-4 (LEU 11 to 14)


a). LEU with LB1 & LB2 each -03 a). LEU with LB1 & LB2 each -04
b). CH-03, MSDAC - 09, LVV-04 b). CH-03, MSDAC - 10, LVV-03
c). Point M/c- 17 c). Point M/c- 16
d). Main signal - 09, Indep SH- 09 d). Main signal - 11, Indep SH- 06

Physical completion 30-Nov-19 30-Nov-19

SNT / SNT / Including 2A


1 Main cable and Tail cable Trench MMC 4 3.6 16-Oct-19 26-Oct-19 MMC 8.4 7.6 30-Sep-19 10-Nov-19 Trench

SNT / SNT / Including 2A


2 Main cable and Tail cable Laying MMC 35.3 30.4 16-Oct-19 26-Oct-19 MMC 53.2 51.8 30-Sep-19 10-Nov-19 Trench
SNT / SNT /
3 Power cable and RTU cable End Termination MMC 33 33 21-Oct-19 30-Oct-19 MMC 48 48 30-Sep-19 15-Nov-19

only LB2
4 LEU Relay LB wiring (LB1&LB2) SNT 6 2 11-Oct-19 30-Oct-19 8 3 21-0ct-19 30-Oct-19 pending due to
3X0.75mm dia.
wire coil

5 Earthing arrangements (Earthpit & GI wire) for LEU LB1 & LB2 only JSNEPL / 6 2 21-Oct-19 30-Oct-19 JSNEPL / 8 6 30-Sep-19 14-Nov-19
MMC MMC

6 Foundation for JB LB and MSDAC and erection SNT 3 3 10-Oct-19 5-Nov-19 SNT (4+4) 8 8 16-Oct-19 15-Nov-19
Signal Fdn bal: 1SH* in Z1 (No Track) & 1S/SH in Z4 (Damaged)
7 All cables Armoured Connect with Earth pit for LEU LB1 & LB2 only SNT 6 6 16-Oct-19 31-Oct-19 SNT 8 8 5-Nov-19 15-Nov-19
8 SPD wiring at all location SNT 3 3 26-Oct-19 30-Oct-19 SNT 4 4 5-Nov-19 10-Nov-19 24 VDC SPD
9 CH LB wiring and KLCR Mounting SNT 3 1 26-Oct-19 5-Nov-19 SNT 3 0 5-Nov-19 15-Nov-19 Wooden
arrangement
10 Bell test TSTS 3 3 6-Nov-19 10-Nov-19 TSTS 4 4 15-Nov-19 20-Nov-19
11 Customer Bell test RITES 3 3 14-Nov-19 17-Nov-19 RITES 4 4 21-Nov-19 25-Nov-19
12 Point JB Installation SNT 18 18 20-Oct-19 25-Oct-19 SNT 12 12 26-Oct-19 30-Oct-19
13 Field Gear wiring at Point JB end SNT 18 18 21-Oct-19 26-Oct-19 SNT 12 12 27-Oct-19 4-Nov-19
14 Point Machine, ground rod fitting Installation & Field Gear wiring at SNT 18 16 26-Oct-19 20-Nov-19 SNT 12 11 1-Nov-19 30-Nov-19
Point M/c end

15 Point machine testing and commissioning SNT 18 18 26-Oct-19 20-Nov-19 SNT / 12 12 1-Nov-19 30-Nov-19
RITES
16 Simulation Wiring for point operation TSTS / SNT 3 3 20-Nov-19 25-Nov-19 TSTS / SNT 4 4 25-Nov-19 30-Nov-19
17 Power ON TSTS 3 3 26-Nov-19 30-Nov-19 TSTS 4 4 25-Nov-19 30-Nov-19
18 MSDAC Wiring (DAC - Termination completed in Z1 (7) & Z2 (4),
Internal wiring pending in all zones) SNT 9 9 26-Oct-19 30-Oct-19 SNT 10 10 2-Nov-19 7-Nov-19

LVV Wiring (LVV-Termination completed in Z1 (2) & Z2 (2), Internal


19 wiring pending in all zones) SNT 4 2 26-Oct-19 30-Oct-19 SNT 3 1 2-Nov-19 7-Nov-19

20 Earthing arrangements (Earthpit & GI wire) for other LB & signal JSNEPL / 35 25 16-Oct-19 30-Oct-19 JSNEPL / 33 28 30-Oct-19 14-Nov-19
MMC MMC

21 All cables Armoured Connect with Earth pit for other LB & signal SNT 16 16 26-Oct-19 5-Nov-19 SNT 16 16 5-Nov-19 15-Nov-19

22 Field Gear wiring at Main Signal end (LED unit) SNT 9 9 26-Oct-19 5-Nov-19 SNT 11 11 5-Nov-19 10-Nov-19
23 Field Gear wiring at Shunt Signal end (LED unit) SNT 9 9 26-Oct-19 5-Nov-19 SNT 6 6 5-Nov-19 10-Nov-19
24 OFC Splicing in LEU location TSTS 3 3 20-Nov-19 23-Nov-19 TSTS 4 4 23-Nov-19 25-Nov-19
25 Simulation Wiring complete zone TSTS 3 3 25-Nov-19 30-Nov-19 TSTS 4 4 25-Nov-19 30-Nov-19
26 Power ON TSTS 3 3 31-Oct-19 2-Nov-19 TSTS 4 4 25-Nov-19 30-Nov-19
27 SAT TSTS 0.25 0.25 25-Nov-19 30-Nov-19 TSTS 0.25 0.25 25-Nov-19 30-Nov-19
28 Painting and Name tag provision SNT 0.25 0.25 10-Nov-19 15-Nov-19 SNT 0.25 0.25 16-Nov-19 20-Nov-19
29 Indoor works - Auto changeover (ACO) installation
30 Main Cable laying from PDB to ACO
31 Main Cable laying from ACO to IPS
32 Maintenance Free Earthing and connections
33 LA class A installation
34 IPS power ON and battery charging

35 cable laying on ladder tray from power rack to IPS (Module output
wiring)
36 Cable terminations at IPS & power rack side
37 VDU and MTC installation, SPD wiring
38 Main Cable laying from Power Rack to MSDAC Rack
39 Cable terminations at MSDAC Rack and Power Rack
40 Main Cable laying from CTR to MSDAC Rack
41 Cable terminations at MSDAC Rack and CTR
42 Main Cable laying from CTR to Relay Rack
43 Cable terminations at Relay Rack and CTR
44 Tray fixing and Main Cable laying from Ground to Power Rack SNT 3 3 10-Oct-19 11-Nov-19 SNT 7 7 20-Oct-19 11-Nov-19 Including 2A
45 Cable terminations at Power Rack for Outdoor cable SNT 3 3 12-Oct-19 12-Nov-19 SNT 7 7 25-Oct-19 12-Nov-19 Including 2A
46 Tray fixing and Main Cable laying from Ground to CTR SNT 11 11 10-Oct-19 12-Nov-19 SNT 13 13 20-Oct-19 12-Nov-19
47 Cable terminations at CTR SNT 11 11 13-Oct-19 14-Nov-19 SNT 13 13 25-Oct-19 14-Nov-19
NOTE: Commissioning of TSK Cabin C yard scope is in M/s SNT and TSTS only. Other agencies (MMC / JSNEPL) are engaged on risk purchase basis of M/s SNT to support their works. All agencies shall complete their scope as per assigned target dates

TSTS SNT MMC JSNEPL RITES TSL 2 of 2