Sie sind auf Seite 1von 5

Voltage Profile and Power Loss Improvement in

Distribution System Using MVDS Considering


Economic Enticements
1,2
Firas M. F. Flaih, 1Lin Xiangning, 1Asad Waqar and 1Rasool M. Imran
1
School of Electrical and Electronics Engineering, Huazhong University of Science and Technology, Wuhan 430074, Hubei,
China.
2
General Directorate of North Distribution Electricity, Ministry of Electricity, Iraq.
E-mail: firas_flaih@hust.edu.cn

Abstract— The power demand is exponentially growing power loss in a distributed system is high because of low
across the globe. The standard distribution system fed from a voltage and high current [7]. The distribution networks are
high capacity power transformer and with multiple loads results typically of two types, radial or interconnected. The radial
in lower regulation at the tail ends. Moreover, there is an network leaves the station and passes through the network area
increase in the system power losses and a decrease in voltage with no normal connection to any other supply, and this is
profile. It affects the performance of the existing distribution typical with long rural lines to isolated load areas [2]. With the
system. In this paper, the authors have proposed a medium increased loading and exploitation of the existing power
voltage distribution system (MVDS) to reduce the power losses structure, the probability of occurrence of voltage drop is
and therefore improve the voltage profile for low voltage
significantly increased in the distribution system [8]. In
distribution system (LVDS). New distribution transformers
(DTRs) of small capacity have been introduced in the
distribution system and in rural areas, normally the services try
distribution system along with the replacement of the existing to minimize the cost by reduce wire’s cross section area and
high capacity DTRs. This method has been applied to a 20-node number of poles also they install three phase DTR of large
low voltage radial distribution network, where the voltage profile capacities on the main road close to MV lines which lead to
and losses were unsatisfactory. The simulation has been use of long LV lines, that the main contributing factor of line
performed using the MATLAB environment and the results losses subsequent voltage drop. So far several studies [2]-[6]
demonstrate the effectiveness of the proposed method in terms of introduced the concept of HVDS with low rated distribution
the technical and economic feasibility. It is observed that the transformers to minimize technical and non-technical power
average voltage profile is improved by 15.6%, tail end voltage is losses and improve voltage of radial distribution system. S.A.
enhanced by 23% and losses are reduced by 84% for existing the Sampath Kumar et al. [2] simulated HVDS system of Kovur
LVDS, which achieved economic benefits after 36 months for a SS by using E-TAP Software, K. Amaresh et al. [3] introduced
distribution company (DSCO) and resulted in a prolonged the HVDS with low rated distribution transformers. Md Sarwar
lifetime of the equipment. et al. [4] presented HVDS to reduce the technical power loss in
distribution systems also showed the economic viability of the
Keywords— Low Voltage Distribution System (LVDS); Medium method. P Ravi Babu et al. [5] discussed a method for reducing
Voltage Distribution System (MVDS); Power Losses; Distribution the non-technical losses. K. Spandana and Varsha Reddy [6]
Transformer (DTR); Average Voltage.
presented restructuring of LVDS to HVDS in the agricultural
field. But unfortunately, all the above-mentioned research lacks
I. INTRODUCTION the economic impacts. In this paper, the authors have proposed
The extraordinary growing load demand in Iraq needs more a MVDS with economic enticements to enhance the voltage
generation in parallel. This is due to increased population and profile and minimize power losses by restructuring the existing
especially conversion of agricultural land to residential land. LV lines with MV lines. The implementation of MVDS with
The import of the high power electrical appliances leads low rated distribution transformers improves the quality of
towards blackout. Furthermore, the electricity theft puts more power supply. Under this system of MV line, 11 KV line is
burden on the distribution network that more worsens the extended up to the load as much as possible and a low rated
crises. The best solution to solve this problem is the expansion distribution transformer is installed there. The consumer is
in the generation capacity, but the current government’s policy supplied by a LV line (preferably insulated overhead cable) of
is negating this expansion. Another solution is to reduce the short length.
power losses which will improve the voltage profile and cut
down the overhead costs. Therefore, in the current scenario, the II. LVDS & MVDS DISTRIBUTION SYSTEMS
energy saving scheme is better than the energy generation. An
electric power system consists of three major segments, A. Low Voltage Distribution System
generation, transmission, and distribution [1]. The electricity Distribution systems in Iraq can classify as 416 V for
distribution is the final stage in the delivery of electricity to end LVDS, 11KV for MVDS and 33KV for HVDS. The existing
users [2]. Distribution system provides a link between the high distribution system employs large three-phase 11 KV line
voltage transmission system and low voltage consumers, thus,

978-1-4673-8644-9/16/$31.00 2016
c IEEE 1122
distribution feeders with three-phase lines and three-phase IV. MATHEMATICAL FORMULATION
distribution transformers transforming 11 KV into 416 V. A The power flow is a useful tool in operation, planning, and
distribution system with low voltage employs four core cable optimization of a system. Distribution systems, generally,
and long low voltage lines and multiple loads fed from a large refers to the power system network connected to loads at lower
capacity DTR leads to increasing in system losses that operating voltages [10].
effecting on voltage profile and system performance. The
technical losses should be reasonable and it mainly caused by
the power dissipated in the conductors (LV lines) and A. Power Loss of Radial Distribution Network
equipment that used for transformation (DTRs). The AC power flows are calculated by the following set of
recursive equations derived from the single-line diagram in Fig
B. Medium Voltage Distribution System 2, the voltages at nodes i and i+1 are Vi and Vi+1 respectively.
The current Ij from node i to node i+1 is given by [3] [16]:
MVDS concept is to reconfigure the existing Low voltage
network as Medium Voltage Distribution System, where the Vi −Vi +1
Ij = (1)
11KV line extended up to load as much as possible [9]. The Zj
LV power supply is fed by providing an appropriate capacity
transformer and least length of LV line with a goal to provide Z j = R j + jX j ( 2)
better power quality, reduction of losses and improve consumer
service. In the present system, large capacity DTRs are located Where Zj, Rj and Xj are the impedance, resistance, and
at one point and the connections to each load are extended reactance of branch j respectively. Load current injected at
through LV lines. This long length of LV lines is causing a low node i is given [8] [15]:
voltage condition to the most of the consumers especially at the
tail end and high technical power losses. In the MVDS PLi − jQLi
concept, a length of 0.4 KV lines is converted into 11KV lines Ij = (3)
Vi
and thereby installing the appropriate capacity DTRs, the
supply is provided to end consumer at a standard voltage level.
In this network MT line is extended and LT line is reduced and Where PLi, QLi are the real and reactive power
LT line is very small in length when compared to LVDS respectively at the node i .
system. So the line losses are reduced and there is no chance From (1), (2) and (3), the voltage magnitude of Vi+1 at node i+1
for illegal connections or hooking is possible on MT lines and is given by [3]:
the end user will get the proper, constant voltage, hear the
voltage drop is very less when compared with the existing (1/ 2 ) (1/ 2 )
system. ­ ª§ | V i |2 · º ½
° « ¨ PLi +1 . R j + QLi +1 . X j − ¸ −» °
° «© 2 ¹ » °
III. ALGORITHM °« 2 °
Vi +1 = ® ( R j + X j )( PLi +1 + QLi +1 )
2 2 2 »
¾ (4)
The algorithm flow chart for voltage and power loss ¬ ¼
° °
improvement is shown in Fig.1. ° § | Vi |2 · °
° − ¨ PLi +1 . R j + QLi +1 . X j − 2 ¸ °
¯ © ¹ ¿

Where a node i has voltage Vi and load PLi +jQLi, the


branch that is connected between node i and i+1, is having a
resistance Rj and inductive reactance Xj.

Fig. 2. Simple distribution feeder [16].

Power loss in the branch j from node i to node i+1 is given by


[3] [8] [11-14] [16]:

§ PL 2 + jQL 2 ·
PLloss (i ,i +1) = R j . ¨ i i
¸ (5)
¨ V
2
¸
© i ¹
Fig. 1. Flow chart for voltage and power loss improvement

2016 IEEE 11th Conference on Industrial Electronics and Applications (ICIEA) 1123
By summing up the losses of all branches and adding Nn

transformer load and no-load loss, total real power loss before VAvr =
¦ Vr
i =1 i
(13)
and after the restructuring can be determined as: Nn
ΔVAv = VAvr − VAv0 (14)
Nb NTr
Where Nn the number of nodes, V0Av and VrAv are the average
TPL = ¦PLloss ( i ,i +1) + ¦( PTrNLloss ( z ) + PTrLloss ( z ) )
0
(6)
voltage of Nn nodes.
i =1 z =1
Nb
r
N Tr D. Payback Cost & Payback Period
TPL = ¦ Pr r
Lloss ( i ,i +1) + ¦ ( PTrNLloss ( z ) + PTrLloss ( z ) ) (7) Payback cost is the difference between total power losses in
i =1 z =1 kilowatt hour before and after restructuring multiplied by the
price of one unit as shown:
Where PLloss (i, i+1), PrLloss (i, i+1) are line loss before and after
PbCTperiod = ΔTPLKWh .CU (15)
restructuring. PTrNLloss (z), PTrLloss (z) are load and no-load loss of
DTRs. TPL0, TPLr are total power loss before and after Where CU the cost of one unit (KWh)
restructuring. Nb number of branches. NTr, NrTr are the number
of transformers before and after restructuring respectively. The payback period is the ratio between the differences in
By subtracting total real power loss before and after total cost after and before restructuring in equation (11) to
restructuring, the difference is given by: payback cost in the equation (15), it is important to know after
how many days, months or years the restructuring cover its
ΔTPL = TPL0 − TPLr (8) expenses.
ΔCT
PbPTperiod = (16)
PbCTperiod
B. Cost Analysis for RDN
Cost analysis for radial distribution network tries to find out
the economic viability of the proposed method. The V. CASE STUDY
implementation of method requires the investment on
transformers, low voltage and high voltage poles, the total cost A case study was made by given an existing distribution
calculation before and after the restructuring is given by: system of 416V considering a 20-node practical rural
distribution system in General Directorate of North
Distribution Electricity (GDNDE), Iraq, whose single line
NTr N LVp
diagram is shown in Fig 3. The case includes 8 consumer loads
CT0 = ¦CTr ( z ) + ¦CLVp ( z ) (9) 0.4 KV, the load data of each consumer are shown in Table III.
z =1 z =1 The low voltage distribution system which would run up to the
r N HVp
NTr customer is restructured by medium voltage line 11 KV as
C = ¦CTr ( z ) +
r
T ¦C HVp ( z ) (10) shown in Fig 4. All consumers shall be served through small
z =1 z =1 capacity transformers. For the purposed network, the existing
high rate transformer 250 KVA and LT line 0.4KV feeds the
Where C0T, CrT are the total cost of the system before and after consumers restructured and converted into MV line 11 KV on
restructuring. CLVp (z), CHVp (z) the cost of low voltage and high the MV poles. The consumers served through low rate
voltage pole. NLVp, NHVp are the number of low and high voltage transformers of 30 and 50KVA, all transformers of 8 loads are
poles. CTr (z) is the cost of the transformer. considered as 3-phase balanced load. The transformer load and
By subtracting total cost after and before restructuring, the no load losses detailed are shown in Table IV. The details of
difference is given: the LVDS and MVDS are shown in Table I and Table II.

ΔCT = CTr − CT0 (11)

C. Average Voltage Concept


It is difficult to deal with many node voltages to decide
whether there has been a voltage improvement in the
distribution system or not, because sometimes improvement
happened in some nodes and did not happen to the others, even
in some cases voltage gets worse. In this paper, the authors
have proposed the concept of Average Voltage to deal with all
nodes in the system. The following equations are average
voltage before and after restructuring: Fig. 3. Single line diagram of 20 node LVDS system
Nn
¦ Vi
VAv0 = i =1 (12)
Nn

1124 2016 IEEE 11th Conference on Industrial Electronics and Applications (ICIEA)
TABLE IV. TRANSFORMERS LOAD & NO LOAD LOSSES (11/0.4)
No. KVA Tr. no load losses Tr. load losses
rating KW KW
1 30 0.10 0.60
2 50 0.13 0.87
3 63 0.15 1.04
4 80 0.18 1.25
5 100 0.20 1.50
6 125 0.24 1.80
7 160 0.28 2.20
8 200 0.34 2.60
9 250 0.40 3.05

VI. RESULTS AND DISCUSSION


The power flow analysis is performed to evaluate the
Fig. 4. Single line diagram of 20 node MVDS system
power losses in case of existing network and the proposed
MVDS under specified load conditions. The following results
TABLE I. DETAILS OF THE LVDS
were obtained with the LVDS and MVDS proposed method.
The result of the tail end voltage profile, the average voltage
No. Particulars Remarks of 20 nodes, total power losses in KW, cost in US Dollar,
1 Number of transformers (11/0.416) 1 monthly losses, monthly payback and payback period before
2 Capacity of transformer 250 KVA
3 Nature of load on transformer under loaded
and after restructuring are given in Table V.
4 Length of the LT lines 950 m TABLE V. RESULTS OF LVDS AND MDVS SYSTEMS
5 Number of connected loads 8
6 Total connected loads 237KVA Particulars LVDS MVDS
7 Distance between two poles 50 m Tail end voltage at node 12 319.94 415.89
8 Number of LV poles 20 Tail end voltage at node 19 317.16 415.88
9 Number of LV branches 19 VAv 351.03 415.92
10 Resistance of each branch 0.028Ÿ TPL in KWh 51.39 7.95
11 Initial cost 13108 USD CT in USD 13108 22333
12 Cost of KWh 0.025 USD ǻVAv - 64.89
13 The cost of LV pole. 416 USD ǻTPL in KWh - 43.44
14 Cost 250 KVA Tr. 3333 USD ǻ CT in USD - 9225
Monthly payback losses in KWh - 10162
Monthly payback cost in USD - 254
TABLE II. DETAILS OF MVDS Payback period in months - 36.29

No. Particulars Remarks


1 No. of transformers (11/0.416) 8 The initial and final total cost was calculated (before and
2 Capacity of transformers (5*50+3*30) KVA after restructuring) as shown in Table V. Either in the MVDS
3 Nature of load on transformer under loaded or in the LVDS, the consumer operates his equipment at LT
4 Length of the MT lines 950 m voltage 416V. From Table V, it is observed that an
5 Number of connected loads 8 enhancement of LV average voltage up to a value of 15.6% or
6 Total connected loads 237KVA 64V, tail end voltage was improved by 23% or 98V and power
7 Distance between two poles 50 m losses are reduced by 84%. The initial cost for MVDS network
8 Number of MV poles 20 1.7 times higher than the existing LVDS system, but by
9 Number of MV branches 19 reducing power losses, we can get the difference of
10 The cost of 50KVA Tr. 833 USD expenditure for restructuring LVDS with MVDS within 36
11 The cost of 30KVA Tr. 500 USD months.
12 The cost of MV pole with acc. 833 USD

TABLE III. LOAD DATA


Load No. Node P in KW Q in KVAR Load in
No. KVA
Load 1 20 29.75 18.43 35
Load 2 4 25.50 15.80 30
Load 3 6 22.95 14.22 27
Load 4 7 21.25 13.17 25
Load 5 12 29.75 18.43 35
Load 6 14 17.00 10.53 20
Load 7 17 25.50 15.80 30
Load 8 19 29.75 18.43 35
Fig. 5. Voltage magnitude comparison of 20-node system between LVDS
and MVDS and Average Voltage Difference

2016 IEEE 11th Conference on Industrial Electronics and Applications (ICIEA) 1125
The above diagram shows the graph between voltage Power”, Power, Energy and Control (ICPEC), IEEE Conference, 2013;
magnitude between LVDS and MVDS. In that LVDS voltage pp. 165 - 169.
at the tail end voltage at node 12 and node 19 are 320V and [2] S.A. Sampath Kumar, V. Vasudaven, J. Antony, Madhu Sudhana Raju
and L. Ramesh. “Minimization of Power Losses in Distribution System
317V respectively, but in MVDS tail end voltages is 415V. So
Through HVDS Concepts”. Sustainable Energy and Intelligent
there is much more difference in the system when compared to Systems (SEISCON)., IET Conference, 2011; pp. 86 - 90.
LVDS to MVDS. Tail end voltages will increase up to 23%
[3] K. Amaresh, S. Sivanagaraju, and V. Sankar. “Minimization of Losses
around. in Radial Distribution System by using HVDS”. Power Electronics,
Drives, and Energy Systems (PEDES) IEEE Conference, 2006; pp. 1 -
5.
[4] Md Sarwar, Anwar Shahzad Siddiqui, Zainul A. Jaffery and Imran
Ahmad Quadri. “Techno-Economic Feasibility of HVDS Concept for
Distribution Feeder Power Loss Minimisation”. Power Electronics
(IICPE), IEEE 5th India International Conference on IEEE Conference
2012; pp. 1 - 4.
[5] P Ravi Babu , Sushma B , Ashwin Kumar B. “HVDS approach for
reducing the Technical and Non-technical losses to enhance the
Electrical Distribution System performance”, Power Electronics
(IICPE), IEEE 5th India International Conference on IEEE Conference
Fig. 6. Economic diagram for implementing MVDS 2012; pp.1 - 5.
[6] K. Spandana and Varsha Reddy. A . “Restructuring of a Low Voltage
The economic enticement to reduce power losses in LVDS Distribution System into a High Voltage Distribution System for an
by implementing MVDS is shown in Fig 6. After about 36 Improved Voltage and Power Loss Profile”. Green Energy for
months the distribution company (DSCO) will get the benefit Sustainable Development (ICUE) , IEEE Conference, 2014; pp. 1 - 7.
from the proposed method. [7] Shilpa Kalambe, Ganga Agnihotri, “Loss minimization techniques used
in distribution network: bibliographical survey”, Renewable and
ustainable Energy Reviews; 2014; pp.184–200.
VII. CONCLUSION [8] A. Mohamed Imran and M. Kowsalya. “A new power system
The MVDS concept for minimizing power loss and reconfiguration scheme for power loss minimization and voltage
enhancing system voltage has been discussed in this work. The profile enhancement using Fireworks Algorithm”. , Electrical Power
MVDS system is implemented for 20-node and 8 loads on the and Energy Systems 2014; 62; pp. 312–322.
existing LVDS which reduces the line losses. Technical losses [9] L. Ramesh, M. Madhusudhanaraju, S.P. Chowdhury, S. Chowdhury.
in the distribution network are reduced by replacing 416 V “Voltage Profile Improvement through High Voltage Distribution
lines by 11 KV lines. The initial expenses of MVDS were high, System ”. IET Conference. Sustainable Energy and Intelligent Systems
SEISCON; 2011 ; pp.468 – 473.
but overall expenditure will be refunded within the payback
period, for the existing distribution system the PbP was 36 [10] Dina Khaniya, Anurag K. Srivastava and Noel N. Schulz, “Distribution
Power Flow for Multiphase Meshed or Radial Systems”, Power
months only, after this period the DSCO get the benefit from
Symposium, IEEE Conference, 2008. NAPS '08. 40th North American,
implementing MVDS. Based on the case study results, the pp. 1-5.
proposed method, enhances the voltage profile by 15.6%, tail [11] Thuan Thanh Nguyen and Anh Viet Truong “Distribution network
end voltage by 23%, power losses by 84% and consequently reconfiguration for power loss minimization and voltage profile
enhances the system performance. Since losses are reduced improvement using cuckoo search algorithm”. , Electrical Power and
considerably and there is a huge difference in losses between Energy Systems, 2015 ; 68; pp. 233–242.
LVDS and MVDS. The power can be supplied to additional [12] R. Rajaram, K. Sathish Kumar and N. Rajasekar “Power system
loads without any further expenditure in generation sector. reconfiguration in a radial distribution network for reducing losses and
Moreover, applying this method can reduce fuel cost, which to improve voltage profile using modified plant growth simulation
also contributes to reducing CO2 emissions. This method can algorithm with Distributed Generation (DG)”, Energy Reports 2015 ;
also be applied to other distribution systems to get the same 1; pp. 116–122.
benefits. [13] Djossou Adeyemi Amon “A Modified Bat Algorithm for Power Loss
Reduction in Electrical Distribution System”, TELKOMNIKA
Indonesian Journal of Electrical Engineering, 2015 ; 14; pp. 55–61.
ACKNOWLEDGMENT
[14] YU Yong-zhe and HUANG Jia-dong, “Reconfiguration of Distribution
The authors gratefully acknowledge the staff of the School Network Based on Improved Plant Growth Simulation Algorithm”,
of Electrical & Electronics Engineering / Huazhong University Second International Conference on Intelligent Computation
of Science & Technology and all people who assisted in this Technology and Automation, IEEE Conference, 2009, pp. 387-391.
work. The authors also wish to thank General Directorate of [15] Raksanai Nidhiritdhikrai, Kulyos Audomvongseree and Bundhit Eua-
North Distribution Electricity /Ministry of Electricity / Iraq for arporn “Loss Assessment in a Low-Voltage Distribution System”,
their support. IEEE, 2009.
[16] Firas M. F. Flaih, Lin Xiangning, Samir M. Dawoud and Mohammed
R. Almallah “Cost Analysis of Hybrid Restructuration for Distribution
REFERENCES System to Improve Voltage and Minimize Losses”, TELKOMNIKA
[1] Dr.P.Ravi Babu and Sushma.B. “Operation and Control of Electrical Indonesian Journal of Electrical Engineering, 2015 ; 16; pp. 431–438.
Distribution System with Extra Voltage to minimize the Losses.

1126 2016 IEEE 11th Conference on Industrial Electronics and Applications (ICIEA)

Das könnte Ihnen auch gefallen