Project Documents
as per Project Management Body of Knowledge (PMBOK® Guide 6th Edition)
Prepared by:
Note: Project document does not required Sponsor approval, and furthermore project manager may or may not share these documents with Sponsor
as per his interests and requirements on the project
Ref: Project Management Body of Knowledge (PMBOK® Guide), page 89 & 559
Course Summary
Overview of Project Documents in project INTIGRATION management
Project
Knowledge Process
Process Document
Area Group
(Output 1st Time)
Project
Develop Project
INTIGRATION Initiating Assumption log
Management
Charter
Project
Direct and Manage
INTIGRATION Executing Issue log
Management
Project Work
Project
Manage Project Lessons learned
INTIGRATION Executing
Management
Knowledge register
Project
Monitoring Perform Integrated
INTIGRATION Change log
Management
and Controlling Change Control
Project
Knowledge Process
Process Document
Area Group
(Output 1st Time)
Project
Develop Project
INTIGRATION Initiating Assumption log
Management
Charter
Project
Direct and Manage
INTIGRATION Executing Issue log
Management
Project Work
Project
Manage Project Lessons learned
INTIGRATION Executing
Management
Knowledge register
Project
Monitoring Perform Integrated
INTIGRATION Change log
Management
and Controlling Change Control
Project
Description Knowledge Process Output from
Document Input to Process
(Contents of Document) Area Group Process
Name
Develop Project
Output 1st Time
Assumption log is used to record all Assumptions Charter
and Constraints throughout the project life cycle Direct & Manage
Project Work
High-level strategic and operational assumptions
and constraints are normally identified in the Monitor & Control
business case Project Work
Close Project or
Lower-level activity and task assumptions are Phase
generated throughout the project such as defining
Project Collect Requirements
Assumption technical specifications, estimates, the schedule,
INTIGRATION Initiating
Log risks, etc.
Management Define Scope Define Scope
It contains information about assumptions and Create WBS
constraints identified as affecting the project
Sequence Activities Sequence Activities
Any New assumptions and constraints may be
identified and it shall be added to the log and the Estimate Act. Estimate Act.
Duration Duration
status of existing assumptions and constraints
may be updated or closed out as the project Develop Schedule Develop Schedule
progress
Control Schedule
Project
Direct and Manage
INTIGRATION Executing Issue log
Management
Project Work
Project
Manage Project Lessons learned
INTIGRATION Executing
Management
Knowledge register
Project
Monitoring Perform Integrated
INTIGRATION Change log
Management
and Controlling Change Control
Project
Description Knowledge Process Input to Output from
Document
(Contents of Document) Area Group Process Process
Name
Project
Description Knowledge Process Input to Output from
Document
(Contents of Document) Area Group Process Process
Name
Perform
Qualitative Risk
The issue log will help the project manager
Analysis
effectively track and manage issues, ensuring
that they are investigated and resolved. Implement Risk
Responses
The issue log is created for the first time as an
Project Monitor Risk Monitor Risk
output of Direct & Manage project work
Issue Log INTIGRATION Executing
process. Identify SH Identify SH
Management
However issues may happen at any time Plan SH
during the project. The issue log is updated as Engagement
a result of the monitoring and control activities Manage SH Manage SH
throughout the project’s life cycle. Engagement Engagement
Monitor SH Monitor SH
Engagement Engagement
Note: Image shows only sample Issue log, however issue logs are created and managed by project
managers and his team depending on the project needs and the organizations standard
Project
Knowledge Process
Process Document
Area Group
(Output 1st Time)
Project
Develop Project
INTIGRATION Initiating Assumption log
Management
Charter
Project
Direct and Manage
INTIGRATION Executing Issue log
Management
Project Work
Project
Manage Project Lessons learned
INTIGRATION Executing
Management
Knowledge register
Project
Monitoring Perform Integrated
INTIGRATION Change log
Management
and Controlling Change Control
Project
Description Knowledge Process Output from
Document Input to Process
(Contents of Document) Area Group Process
Name
Output 1st Time
Manage Project Manage Project
The lessons learned register is created as an Knowledge Knowledge
output of Manage Project Knowledge process
early in the project Direct & Manage Direct & Manage
Project Work Project Work
Thereafter it is used as an input and updated as
an output in many processes throughout the M&C Project Work M&C Project Work
project
Lessons Project
Learned INTIGRATION Executing Close
Close Project/Phase
The lessons learned register can include the Project/Phase
Register Management
category and description of the situation. The
Collect Requirements
lessons learned register may also include the
impact, recommendations, and proposed
Validate Scope Validate Scope
actions associated with the situation. The
lessons learned register may record Control Scope Control Scope
challenges, problems, realized risks and
opportunities, or other content as appropriate Estimate Activity Estimate Activity
Duration Duration
Project
Description Process Output from
Document Knowledge Area Input to Process
(Contents of Document) Group Process
Name
Project
Description Process Output from
Document Knowledge Area Input to Process
(Contents of Document) Group Process
Name
Monitor Monitor
Communications Communications
Identify Risks Identify Risks
Plan Risk Responses Plan Risk Responses
Manage SH Manage SH
Engagement Engagement
Monitor SH Monitor SH
Engagement Engagement
Project
Direct and Manage
INTIGRATION Executing Issue log
Management
Project Work
Project
Manage Project Lessons learned
INTIGRATION Executing
Management
Knowledge register
Project
Monitoring Perform Integrated
INTIGRATION Change log
Management
and Controlling Change Control
Project
Description Knowledge Process Input to Output from
Document
(Contents of Document) Area Group Process Process
Name
1. It is used to document changes that occur Output 1st Time Per Integrated CC
during a project
2. The Disposition of all Change request are Direct & Manage
Project Work
recorded in Change log
3. The change log is used to communicate Close
changes and approved, deferred, and rejected Project/Phase
change requests to the impacted stakeholders Project
Change Log INTIGRATION Executing
4. The change log may introduce a new Management Manage Comm.
stakeholder or change the nature of an
existing stakeholder’s relationship to project Identify SH
5. The change log contains changes to the Plan SH
original scope of the project Engagement
6. The change log may be updated based on any Manage SH Manage SH
change requests Engagement Engagement
Note: Image shows only sample Change log, however change logs are created and managed by
project managers and his team depending on the project needs and the organizations standard
Overview of Project Documents in project SCOPE management
Project
Knowledge Process
Process Document
Area Group
(Output 1st Time)
Project
Collect Requirements
SCOPE Planning
Management
Requirements Documentation
Project
Collect Requirements
SCOPE Planning
Management
Requirements Traceability Matrix
Project
Project Scope
SCOPE Planning Define Scope
Management
Statement
Project
Knowledge Process
Process Document
Area Group
(Output 1st Time)
Project
Collect Requirements
SCOPE Planning
Management
Requirements Documentation
Project
Collect Requirements
SCOPE Planning
Management
Requirements Traceability Matrix
Project
Project Scope
SCOPE Planning Define Scope
Management
Statement
Project
Description Knowledge Process Output from
Document Input to Process
(Contents of Document) Area Group Process
Name
Project
Description Knowledge Process Output from
Document Input to Process
(Contents of Document) Area Group Process
Name
Ref: Project Management Body of Knowledge (PMBOK® Guide), page 147 & 148
Project
Knowledge Process
Process Document
Area Group
(Output 1st Time)
Project
Collect Requirements
SCOPE Planning
Management
Requirements Documentation
Project
Collect Requirements
SCOPE Planning
Management
Requirements Traceability Matrix
Project
Project Scope
SCOPE Planning Define Scope
Management
Statement
Project
Description Knowledge Process Input to Output from
Document
(Contents of Document) Area Group Process Process
Name
Collect
The requirements traceability matrix is a grid that links Output 1st Time
Requirements
product requirements from their origin to the
deliverables that satisfy them Direct & Manage
Its implementation helps ensure that each requirement Project work
adds business value by linking it to the business and Perform
project objectives Integrated CC
It provides a means to track requirements throughout
Define Scope
the project life cycle
It ensure that approved requirements are delivered at Validate Scope Validate Scope
Requirements Project
the end of the project.
Traceability SCOPE Planning Control Scope Control Scope
Finally, it provides a structure for managing changes
Matrix to the product scope Management
Plan Quality Plan Quality
Management Management
Tracing requirements includes but is not limited to:
Business needs, opportunities, goals, and objectives; Plan Procurement Plan Procurement
Project objectives; Management Management
Project scope and WBS deliverables;
Conduct
Product design and Product development; Procurement
Test strategy and test scenarios; and
From High-level to more detailed requirements Control Control
Procurement Procurement
Ref: Project Management Body of Knowledge (PMBOK® Guide), page 148 & 149
Example of Requirements Traceability Matrix
Copy Ref: Project Management Body of Knowledge (PMBOK® Guide), page 149
Project Document
Knowledge Area Process
(Output 1st Time)
Project
Requirements
SCOPE Collect Requirements
Management
Documentation
Project
Requirements Traceability
SCOPE Collect Requirements
Management
Matrix
Project
SCOPE Define Scope Project Scope Statement
Management
Project
Description Knowledge Process Output from
Document Input to Process
(Contents of Document) Area Group Process
Name
The project scope statement is the description
of the project scope, major deliverables,
assumptions, and constraints
It documents the entire scope, including Output 1st Time
project and product scope. Define Scope
Project
Description Knowledge Process Output from
Document Input to Process
(Contents of Document) Area Group Process
Name
Project SCHEDULE
Management
Planning Define Activities Activity Attributes
Project SCHEDULE
Management
Planning Define Activities Milestone List
Project SCHEDULE
Management
Planning Develop Schedule Project Schedule
Project SCHEDULE
Management
Planning Develop Schedule Schedule Data
Project SCHEDULE
Management
Planning Develop Schedule Project Calendars
Project SCHEDULE
Management
Planning Define Activities Activity Attributes
Project SCHEDULE
Management
Planning Define Activities Milestone List
Project SCHEDULE
Management
Planning Develop Schedule Project Schedule
Project SCHEDULE
Management
Planning Develop Schedule Schedule Data
Project SCHEDULE
Management
Planning Develop Schedule Project Calendars
Project SCHEDULE
Management
Planning Define Activities Activity Attributes
Project SCHEDULE
Management
Planning Define Activities Milestone List
Project SCHEDULE
Management
Planning Develop Schedule Project Schedule
Project SCHEDULE
Management
Planning Develop Schedule Schedule Data
Project SCHEDULE
Management
Planning Develop Schedule Project Calendars
Activity attributes extend the description of the Output 1st Time Define Activities
activity by identifying multiple components
associated with each activity
The components for each activity evolve over time, Sequence Sequence
Initial preparation Stage, Activities Activities
Unique activity identifier (ID), WBS ID, and activity
label or activity name
Estimate Activity Estimate Activity
When completed, they may include Project Durations Durations
Activity
Activity descriptions, SCHEDULE Planning
Attributes
Predecessor activities, & successor activities, Management
Logical relationships, leads and lags, Develop Develop
Resource requirements, Schedule Schedule
Imposed dates, constraints, and assumptions
Place of work (location),
Project Calendar activity assigned to Estimate Activity Estimate Activity
Type of effort Involved Resources Resources
Used for Schedule Development
Project SCHEDULE
Management
Planning Define Activities Activity Attributes
Project SCHEDULE
Management
Planning Define Activities Milestone List
Project SCHEDULE
Management
Planning Develop Schedule Project Schedule
Project SCHEDULE
Management
Planning Develop Schedule Schedule Data
Project SCHEDULE
Management
Planning Develop Schedule Project Calendars
Project SCHEDULE
Management
Planning Define Activities Activity Attributes
Project SCHEDULE
Management
Planning Define Activities Milestone List
Project SCHEDULE
Management
Planning Develop Schedule Project Schedule
Project SCHEDULE
Management
Planning Develop Schedule Schedule Data
Project SCHEDULE
Management
Planning Develop Schedule Project Calendars
Ref: Project Management Body of Knowledge (PMBOK® Guide), page 194 & 218
Cont: Project Sch. ND
Project
Description Knowledge Process Output from
Documen Input to Process
(Contents of Document) Area Group Process
t Name
It can include full project details, or have one or
more summary activities.
Ref: Project Management Body of Knowledge (PMBOK® Guide), page 194 & 218
Sample of Schedule Network Diagram
Sample of Network diagram from Primavera copy reference from PMBOK gude 6th edition page no 193
Process Project Document
Knowledge Area Process
Group (Output 1st Time)
Project SCHEDULE
Management
Planning Define Activities Activity List
Project SCHEDULE
Management
Planning Define Activities Activity Attributes
Project SCHEDULE
Management
Planning Define Activities Milestone List
Project SCHEDULE
Management
Planning Develop Schedule Project Schedule
Project SCHEDULE
Management
Planning Develop Schedule Schedule Data
Project SCHEDULE
Management
Planning Develop Schedule Project Calendars
Project SCHEDULE
Management
Planning Define Activities Activity Attributes
Project SCHEDULE
Management
Planning Define Activities Milestone List
Project SCHEDULE
Management
Planning Develop Schedule Project Schedule
Project SCHEDULE
Management
Planning Develop Schedule Schedule Data
Project SCHEDULE
Management
Planning Develop Schedule Project Calendars
Project SCHEDULE
Management
Planning Define Activities Activity Attributes
Project SCHEDULE
Management
Planning Define Activities Milestone List
Project SCHEDULE
Management
Planning Develop Schedule Project Schedule
Project SCHEDULE
Management
Planning Develop Schedule Schedule Data
Project SCHEDULE
Management
Planning Develop Schedule Project Calendars
Ref: Project Management Body of Knowledge (PMBOK® Guide), page 220 & 230
Process Project Document
Knowledge Area Process
Group (Output 1st Time)
Project SCHEDULE
Management
Planning Define Activities Activity List
Project SCHEDULE
Management
Planning Define Activities Activity Attributes
Project SCHEDULE
Management
Planning Define Activities Milestone List
Project SCHEDULE
Management
Planning Develop Schedule Project Schedule
Project SCHEDULE
Management
Planning Develop Schedule Schedule Data
Project SCHEDULE
Management
Planning Develop Schedule Project Calendars
Project SCHEDULE
Management
Planning Define Activities Activity Attributes
Project SCHEDULE
Management
Planning Define Activities Milestone List
Project SCHEDULE
Management
Planning Develop Schedule Project Schedule
Project SCHEDULE
Management
Planning Develop Schedule Schedule Data
Project SCHEDULE
Management
Planning Develop Schedule Project Calendars
Project
Knowledge Process
Process Document
Area Group
(Output 1st Time)
Project
COST Planning Estimate Costs Cost Estimates
Management
Project
Monitoring
COST Control Costs Cost Forecasts
Management
and Controlling
Project
Knowledge Process
Process Document
Area Group
(Output 1st Time)
Project
COST Planning Estimate Costs Cost Estimates
Management
Project
Monitoring
COST Control Costs Cost Forecasts
Management
and Controlling
Project
Description Knowledge Process Input to Output from
Document
(Contents of Document) Area Group Process Process
Name
Project
COST Planning Estimate Costs Cost Estimates
Management
Project
Monitoring
COST Control Costs Cost Forecasts
Management
and Controlling
Project
Description Knowledge Input to Output from
Document Process Group
(Contents of Document) Area Process Process
Name
Project RESOURCE
Management
Executing Acquire Resources Resource Calendars
Process Project Document
Knowledge Area Process
Group (Output 1st Time)
Project RESOURCE
Management
Executing Acquire Resources Resource Calendars
Project Output
Description Knowledge Process Input to
Document from
(Contents of Document) Area Group Process
Name Process
Team charter is a document that establishes the team values,
agreements, & operating guidelines for the team
The team charter may include following: Plan
Output 1st Time
Team values, Resource
Communication guidelines, Management
Decision-making criteria and process,
Conflict resolution process,
Meeting guidelines,
Team agreements, and Ground Rules
It establishes clear expectations regarding acceptable behavior by Project
Team Charter project team members RESOURCE Planning Develop Develop
Early commitment to clear guidelines decreases misunderstandings and Management Team Team
increases productivity
The team charter works best when team develops it, or at least has an
opportunity to contribute to it
All project team members share responsibility for ensuring rules
documented in team charter are followed Manage
Team
The team charter can be reviewed and updated periodically to ensure a
continued understanding of the team ground rules and to orient and
integrate new team members
Ref: Project Management Body of Knowledge (PMBOK® Guide), page 319 & 320
Process Project Document
Knowledge Area Process
Group (Output 1st Time)
Project RESOURCE
Management
Executing Acquire Resources Resource Calendars
Project
Description Knowledge Process Output from
Document Input to Process
(Contents of Document) Area Group Process
Name
Resource requirements identify the types and Estimate Activity
Output 1st Time
quantities of (material, equipment, supplies) resources Resources
required at the following levels
Activity in a work package, Estimate Activity
Each work package, Durations
Aggregated to determine the estimated resources for Develop Schedule Develop Schedule
each work package,
Each WBS branch, or Estimate Cost
Project as a whole
Amount of detail and the level of specificity of the Project Acquire Resources Acquire Resources
Resource
resource requirement descriptions can vary by RESOURCE Planning
Requirements Control Resources
application area Management
The resource requirements’ documentation can include Identify Risks
assumptions that were made in determining types of
resources are applied, their availability, and what Perform Quantitative
quantities are needed Risk Analysis
Resource requirements provide quantitative
assessments of project resource requirements, ideally Plan Procurement
Management
expressed as a range
Resource requirements by time period, often in the
Control Procurement
form of a resource histogram
Project RESOURCE
Management
Executing Acquire Resources Resource Calendars
Project
Description Knowledge Process Input to Output from
Document
(Contents of Document) Area Group Process Process
Name
RBS is a hierarchical representation of resources by
Estimate
category and type that is used for planning,
Output 1st Time Activity
managing, & controlling project work
Resources
Categories example: Labor, Material, Equipment, &
Supplies
Types example: Skill level, Grade level, Required Manage Project
Certifications etc. Knowledge
Ref: Project Management Body of Knowledge (PMBOK® Guide), page 148 & 149
Example of Resource Breakdown Structure
Copy Ref: Project Management Body of Knowledge (PMBOK® Guide), page 327
Process Project Document
Knowledge Area Process
Group (Output 1st Time)
Project RESOURCE
Management
Executing Acquire Resources Resource Calendars
Project
Description Process Output from
Document Knowledge Area Input to Process
(Contents of Document) Group Process
Name
Project RESOURCE
Management
Executing Acquire Resources Resource Calendars
Project
Description Knowledge Process Output from
Document Input to Process
(Contents of Document) Area Group Process
Name
Project RESOURCE
Management
Executing Acquire Resources Resource Calendars
Project
Description Knowledge Process Input to Output from
Document
(Contents of Document) Area Group Process Process
Name
Ref: Project Management Body of Knowledge (PMBOK® Guide), page 148 & 149
Continued Resource Calendars
Project
Description Knowledge Process Input to Output from
Document
(Contents of Document) Area Group Process Process
Name
Ref: Project Management Body of Knowledge (PMBOK® Guide), page 148 & 149
Overview of Project Documents in project SCHEDULE, COST RESOURCE management
Project Document
Knowledge Area Process Group Process
(Output 1st Time)
Ref: Project Management Body of Knowledge (PMBOK® Guide), page 204, 247 & 326
Overview of Project Documents in project QUALITY management
Project QUALITY
Management
Executing Manage Quality Quality Report
Project QUALITY
Management
Executing Manage Quality Quality Report
Project QUALITY
Management
Executing Manage Quality Quality Report
Project QUALITY
Management
Executing Manage Quality Quality Report
Ref: Project Management Body of Knowledge (PMBOK® Guide), page 291 & 305
Process Project Document
Knowledge Area Process
Group (Output 1st Time)
Project QUALITY
Management
Executing Manage Quality Quality Report
Ref: Project Management Body of Knowledge (PMBOK® Guide), page 291 & 305
Overview Project Documents in project COMMUNICATIONS management
Project
Manage Project
COMMUNICATIONS Executing Communications
Management Communications
Process Project Document
Knowledge Area Process
Group (Output 1st Time)
Project
Manage Project
COMMUNICATIONS Executing Communications
Management Communications
Project
Description Process Input to Output from
Document Knowledge Area
(Contents of Document) Group Process Process
Name
3. List of potential risk responses: are identified during Plan Procurement Plan Procurement
the Identify Risks process, it is recorded in the risk Management Management
register. This will be confirmed during the Plan Risk
Identify Stakeholders
Responses process.
Plan SH
Additional data may be recorded for each identified risk, Engagement
depending on the risk register format specified in the Monitor SH Monitor SH
risk management plan Engagement Engagement
Ref: Project Management Body of Knowledge (PMBOK® Guide), page 417
Continued: Risk Register
Project
Description Knowledge Process Output from
Document Input to Process
(Contents of Document) Area Group Process
Name
Results of Perform Qualitative Risk Analysis, Plan Conduct Conduct
Risk Responses, Implement Risk Responses, and Procurements Procurements
Monitor Risks are recorded in the risk register as Control Control
those processes are conducted throughout the Procurements Procurements
project
Direct & Manage Direct & Manage
Project Work Project Work
Risk register may contain limited or extensive risk
information depending on project variables such as Monitor & Control Monitor & Control
size and complexity, this may include Project Work Project Work
Short Risk Title
Close Project or
Risk Assessment of probability & impacts for each risk, Project RISK
Planning Phase
Register Priority level or Risk score Management
Risk Urgency Information
Define Scope
Risk category
Current risk status
Estimate Activity
One or more causes, Durations
One or more effects on objectives,
Risk triggers Develop Schedule Develop Schedule
WBS reference of affected activities
Timing Information (when Identified, Might Occur, Control Schedule
Deadline to take action)
Watch list for low-priority risks or further risk analysis Estimate Costs Estimate Costs
Project
Description Process Output from
Document Knowledge Area Input to Process
(Contents of Document) Group Process
Name
The priority level for each risk can help to Determine Budget Determine Budget
guide the selection of appropriate risk
responses. For example; Control Costs
High-priority threats or opportunities may
require priority action and highly proactive Plan Quality Plan Quality
response strategies. Management Management
Threats and opportunities in the Low-priority
zone may not require proactive management Manage Quality
action beyond being placed in the risk register
as part of the watch list or adding a Control Quality
contingency reserve. Project RISK Plan Resource
Risk Register Planning
Some risks are transferred via a procurement Management Management
agreement
Estimate Activity
Each approved seller comes with its own Resources
unique set of risks, depending on seller’s
organization, the duration of contract, Acquire Resources
external environment, the project delivery
method, the type of contracting vehicle Control Resources Control Resources
chosen, and the final agreed-upon price.
Changes are made to the risk register during Manage
the contracting process, which reflect the Communications
specific risks of each seller
Ref: Project Management Body of Knowledge (PMBOK® Guide), page 417
Process Project Document
Knowledge Area Process
Group (Output 1st Time)
Project
Description Knowledge Process Output from
Document Input to Process
(Contents of Document) Area Group Process
Name
Risk report may also include details of the top
individual project risks, agreed upon responses & Direct & Manage
Project Work
owners, & conclusions and recommendations
It may also include conclusions from risk audits on Monitor & Control
the effectiveness of risk management process Project Work
Project
Identify Stakeholder
STAKEHOLDER Initiating
Management Stakeholders Register
Process Project Document
Knowledge Area Process
Group (Output 1st Time)
Project
Identify Stakeholder
STAKEHOLDER Initiating
Management Stakeholders Register
Project
Description Process Output from
Document Knowledge Area Input to Process
(Contents of Document) Group Process
Name
Output 1st Time
Identify Stakeholders
Plan Stakeholder
Stakeholder register contains information of identified Engagement
stakeholders
Manage Stakeholder Manage Stakeholder
SR includes three important details information Engagement Engagement
Monitor Stakeholder Monitor Stakeholder
1. Identification information: Name, organizational Engagement Engagement
position, location and contact details, and role on
project Plan Risk Management
Project
Stakeholder 2. Assessment information: Major requirements, Identify Risks
STAKEHOLDER Planning
Register expectations, potential for influencing project Management Perform Qualitative Risk
outcomes, and the phase of the project life cycle Analysis
where the stakeholder has the most influence or
impact Plan Risk Responses
Project
Description Process Output from
Document Knowledge Area Input to Process
(Contents of Document) Group Process
Name
Direct and Manage
Information on existing or new stakeholders is Project Work
gathered during the lifecycle of a project and it
Manage Project
is recorded and updated in the stakeholder
Knowledge
register
Collect Requirements
Stakeholder register captures the requirements
and expectations that stakeholders have for Define Scope
the project and who can provide information on Plan Quality Plan Quality
requirements Management Management
Project
Stakeholder
STAKEHOLDER Planning Plan Resource
Register This register may reveal stakeholders’ needs or
expectations for specific resources to be Management Management
used on the project that need to be considered Acquire Resources Acquire Resources
in the Acquire Resources process
Plan Communications Plan Communications
Stakeholder register also used to Plan, Manage Management Management
and Monitor communications activities with Manage Manage
stakeholders (such as any individuals, groups, Communications Communications
or organizations) that will need various types of
Monitor
information
Communications