1. Check if the correct meter disc according to the incoming water hardness is
mounted on the softener. If not the correct meter disc is mounted replace it as
described under 1.1.
Result:
Sample turns red: Water softener requires regeneration or resin bead replacement.
Exercise Selcoperm
Service Selcoperm
SG test procedure
1. Flush a clean and dry measuring vessel (capacity at least 500 ml) with
electrolyte using electrolyte sample valve.
2. Fill the measuring vessel with a large sample of approximately
500 ml (to ensure an accurate reading) using electrolyte sample
valve.
3. Fill the 100 ml measuring cylinder with the sample.
4. Place the hydrometer in the measuring cylinder and take the
reading.
5. Required SG reading see section 3.2 Typical unit set points.
Adjusting the SG
The SG of the electrolyte is controlled by the amount of brine injected into the
softened water. The brine flow is controlled by a digital dosing pump, and the
manufacturers manual should be referenced for specific operation of the pump.
Increasing the volume of brine injected into the softened water will increase the SG,
and restricting the flow will lower the SG.
Exercise Selcoperm
Service Selcoperm
3. Acid cleaning
Warning
1. Switch off power supply at switch and isolate system from the mains voltage.
2. Connect hose to product sample valve and run to a suitable discharge point.
3. Open product sample valve to drain the degassing column.
Product sample valve must remain open at all times during the
acid cleaning procedure!
4. Connect hose between soft water sample valve and electrolyte sample valve.
5. Open electrolyte sample valve.
6. Open soft water sample valve to flush electrolyser cell for 5 - 10 minutes.
7. Shut off soft water sample valve.
8. Connect the acid wash pump output to electrolyte sample valve.
9. Attach hose to product sample valve and back to acid wash kit.
10. Start pumping acid through system until electrodes are clean.
– Typically 5 - 10 minutes maximum.
11. Once electrodes are clean stop acid wash pump.
12. Remove the acid wash kit.
13. Move hose connected to product sample valve to a suitable discharge point.
14. Reinstall hose from soft water sample valve to electrolyte sample valve.
15. Open soft water sample valve to flush electrolyser cell for 5 – 10 minutes.
16. Close valves and remove hoses.
17. Wipe up any drips.
18. Restart system according to Start-up procedure.
Exercise Selcoperm
Service Selcoperm
4. Service
In order to ensure a long service life and dosing accuracy, wearing parts such as
diaphragms and valves must be regularly checked for signs of wear. Where
necessary, replace worn parts with original spare parts made from suitable materials.
Should you have any questions, please contact your service partner.
Warning
(h) ⃰
The service requirement signals when the replacement of wearing parts is due and
displays the number of the service kit. Press the click wheel to temporarily hide the
service prompt.
When the “Service now” message appears (displayed daily), the pump must be
serviced immediately. To signalise in the “Operation” menu, the symbol
appears in the “Signal/error display” area of the display.
The number of the service kit required is also displayed in the “Info” menu.
For media which result in increased wear, the service interval must be shortened.
Information about carrying out maintenance can be found in the service kit catalog on
our homepage (www.grundfos.com).
Warning
Do not allow any chemicals to leak from the pump. Collect and
dispose of all chemicals correctly!
Before any work to the pump, the pump must be in the “Stop”
operational state or be disconnected from the mains. The system
must be pressure less!
Exercise Selcoperm
Service Selcoperm
1 Safety diaphragm
2 Flange
3 O-ring
4 Diaphragm
5 Valve on discharge side
6 Valve on suction side
7 Dosing head
8 Screws with discs
9 Cover
10 Deaeration valve
4.4 Repairs
Warning
Switch off the pump and disconnect it from the voltage supply
before carrying out maintenance work and repairs!
After consulting Grundfos, please send the pump, together with the safety declaration
completed by a specialist, to Grundfos. The safety declaration can be found at the
end of these instructions. It must be copied, completed and attached to the pump.
Exercise Selcoperm
Service Selcoperm
If the above requirements are not met, Grundfos may refuse to accept delivery of the
pump. The shipping costs will be charged to the sender.