Topic: PID Control Module

Contents
Configure a PID Control Module ............................................................................................................3

12/17/2014 EXP20R300 – CEE C200/C300/ACE 1


Honeywell, Inc.
This page was intentionally left blank.

2 EXP20R300 – CEE C200/C300/ACE 12/17/2014


Honeywell, Inc.
PID Control Module
Configure a PID Control Module

Configure a PID Control Module


Practice

Objective

 Configure a Control Module


 Use las convenciones de nomenclatura para el Módulo de control y los bloques
de funciones dentro del módulo de control
 Configurar un módulo de control con un solo lazo PID

Prerequisites

 Experion PKS Server or Client machine loaded with Experion PKS Engineering
Tools
 Gráfico de Debutanizer_123 cargado en el servidor (esto se requerirá más
adelante para verificar la filosofía de control).
 Control Builder ejecutándose con dos ventanas de árbol abiertas
 Controlador SCE e IOM configurados
 Intercambio de datos de Excel abierto y cargado con la hoja de cálculo de
simulación

12/17/2014 EXP20R300 – CEE C200/C300/ACE 3


Honeywell, Inc.
PID Control Module
Configure a PID Control Module

Introduction

El Heavy Feed Flow FC01 está construido en este laboratorio. Este bucle PID
requiere una transferencia automática y manual sin interrupciones con alarmas,
grupos e historización habilitados.

El bucle PID se construirá, cargará y activará. Los módulos de control restantes, de un


tipo similar, se importan al proyecto.

Para crear una estrategia de control, se debe construir un Módulo de control 11_FC01 y
se deben insertar y conectar bloques de funciones. Una vez que los módulos de control
están construidos o importados, puede probarlos con la simulación.

En esta práctica de laboratorio, creará un módulo de control para un bucle PID simple
11_FC01 para la alimentación pesada a la torre del debutanizador T-100.

4 EXP20R300 – CEE C200/C300/ACE 12/17/2014


Honeywell, Inc.
PID Control Module
Configure a PID Control Module

Crear un Control Module (CM)

 Step Action

1 Abra Control Builder mediante Configuration Studio.


 Abra un Project Tree ventana del árbol del proyecto a la izquierda, una ventana del
árbol del Monitor Tree a la derecha y una ventana del árbol de la Library Tree
debajo de la ventana del árbol del proyecto

Project
Tree
window

Monitoring
Tree
window

Library
Tree
window

12/17/2014 EXP20R300 – CEE C200/C300/ACE 5


Honeywell, Inc.
PID Control Module
Configure a PID Control Module

 Step Action

2 Selecionar File > New > Control Module.

3 Haga doble clic en el fondo del gráfico en blanco.

6 EXP20R300 – CEE C200/C300/ACE 12/17/2014


Honeywell, Inc.
PID Control Module
Configure a PID Control Module

 Step Action

4 En la pestaña Propiedades principales Main, ingrese lo siguiente:


 Name: 11_FC01
 Item Name: 11_FC01_item
 Parent Asset: Analyser_C11
 Description: Heavy Feed To Debutanizer (Maximum 120 characters)
 Click en el boton OK
 Salve y cierre 11_FC01

ATTENTION

Control Builder numera todos los nuevos CM


secuencialmente. Puede usar cualquier nombre
exclusivo de 16 caracteres para el CM en Project.

12/17/2014 EXP20R300 – CEE C200/C300/ACE 7


Honeywell, Inc.
PID Control Module
Configure a PID Control Module

 Step Action

5 Para esta práctica de laboratorio, use los nombres de CM especificados, ya que esto
le permite probar los CM con la hoja de cálculo Excel preconfigurada, utilizada para la
simulación.
 CM 11_FC01 se agrega al nodo No asignado en la ventana Proyecto

ATTENTION

Your Project window may differ. Verify that 11_FC01 is


in the Unassigned node.

8 EXP20R300 – CEE C200/C300/ACE 12/17/2014


Honeywell, Inc.
PID Control Module
Configure a PID Control Module

 Step Action

6 Configure the Parameters for 11_FC01.


 Si la página de propiedades Principal (Main) aún no está abierta, haga clic con el
botón derecho 11_FC01
 Selecione Module Properties

12/17/2014 EXP20R300 – CEE C200/C300/ACE 9


Honeywell, Inc.
PID Control Module
Configure a PID Control Module

 Step Action

7 Ingrese los siguientes detalles de parámetros en la pestaña Principal. (Main)


 Engr Units: m3/hr (Maximo 16 caracteres permitidos)
 Acepte los valores predeterminados para cualquier parámetro restante en la
pestaña Principal

ATTENTION El nombre de cada CM debe ser único en

todo el servidor.

8 Haga clic en la pestaña Pantallas del servidor Server


Displays. Ingrese los siguientes detalles de la pantalla:
Point Detail Display: sysDtlPIDA
Click the OK button.

ATTENTION

La pantalla de detalles del grupo para 11_FC01 en la estación


se seleccionará directamente del tipo de pantalla de detalles
de puntos especificada.

Puede agregar directamente un CM a una Tendencia y Grupo


ingresando números de tendencia / grupo y el lápiz / posición
en las ventanas de Tendencias y Grupos, aquí o después de
construir la estrategia de control en el CM.

10 EXP20R300 – CEE C200/C300/ACE 12/17/2014


Honeywell, Inc.
PID Control Module
Configure a PID Control Module

 Step Action

9 Assign the CM to the controller CEESCEFB61.


 With the CM 11_FC01 selected, click the (Assign) button on the toolbar,
to open the Execution Environment Assignment
 Select 11_FC01 in the CMs/SCMs tab in Available Modules list box
 Select CEESCEFB61 in the Assign To list box
 Click the Assign button
 11_FC01 is added to Assigned Modules list box
 Click the Close button

 11_FC01 is now assigned to CEESCEFB61, as indicated below

12/17/2014 EXP20R300 – CEE C200/C300/ACE 11


Honeywell, Inc.
PID Control Module
Configure a PID Control Module

Add Function Blocks to a CM

After creating a CM, you must design the control strategy by adding relevant Input/Output
blocks and control blocks such as PIDs, device control or logic blocks.
The IOMs configured in the Configure C200 Hardware lab are used here.

 Step Action
1 Double-click 11_FC01 in the Project window to open the chart view, and then maximize
the view.

2 Add Function Blocks to the CM


 From the Library tab, expand the IOCHANNEL group of function blocks
 Select AICHANNEL

12 EXP20R300 – CEE C200/C300/ACE 12/17/2014


Honeywell, Inc.
PID Control Module
Configure a PID Control Module

 Step Action
3 Drag AICHANNEL into the 11_FC01 Project chart view.

4 Drag the following Function Blocks from their respective block Libraries and add to the
CM.
Block Family Block
DATAACQ DATAACQ
REGCTL PID
IOCHANNEL AOCHANNEL

ATTENTION

Add the blocks in the order specified above. For more


information on adding function blocks to a CM, refer to
the Knowledge Builder along the path
Experion R300.0 > Configuration > Control
Building Guide > Control Builder Operations >
Creating a Control Module > Creating an Instance
of a Basic Function Block

12/17/2014 EXP20R300 – CEE C200/C300/ACE 13


Honeywell, Inc.
PID Control Module
Configure a PID Control Module

 Step Action
5 After adding all the blocks, arrange them as shown below.

6 Configure AIChannel parameters:


 Double-click the AICHANNEL block to open the AI parameter configuration form.
 Enter the Channel Name as FI.

14 EXP20R300 – CEE C200/C300/ACE 12/17/2014


Honeywell, Inc.
PID Control Module
Configure a PID Control Module

 Step Action
7 Assign the AI Channel to an AI Module.
Enter following data:
Choose Module Name: AI_3_4_4
Module Type: Automatic when the Module name is selected
Channel Number: 2
 Click the Assign Channel Block button
 11_FC01.FI is assigned as a Channel Name
 Click OK to close the AICHANNEL Parameter Configuration form

12/17/2014 EXP20R300 – CEE C200/C300/ACE 15


Honeywell, Inc.
PID Control Module
Configure a PID Control Module

 Step Action
8 Configure a Data Acquisition Block. Double-click the Data Acquisition Block, to open
the configuration form, and enter the following:
Name: DACA
Description: Heavy Feed to Debutanizer
Engr Units: m3/hr
PVEU Range Hi: 600
PVEU Range Lo: 0
PV Limits Hi: 600.9
PV Limits Lo: -6.9
Clamping Option: ENABLE
Accept the defaults for any remaining parameters.

ATTENTION

You must name this Block DACA so that the


Honeywell supplied Analog Point Details display
functions properly when called from Station

16 EXP20R300 – CEE C200/C300/ACE 12/17/2014


Honeywell, Inc.
PID Control Module
Configure a PID Control Module

 Step Action
9 Select the Show Parameter Names checkbox located at the lower left corner. Note that
the parameter names now appear in place of the parameter descriptions. Uncheck the
box to return to the parameter descriptions.

ATTENTION

This displays the parameter names instead of


parameter descriptions.

Uncheck the Show Parameter Names checkbox.

12/17/2014 EXP20R300 – CEE C200/C300/ACE 17


Honeywell, Inc.
PID Control Module
Configure a PID Control Module

 Step Action
10 To Configure Alarms, select the Alarms tab.
Enter the following:
PV High: 500 Priority: HIGH
PV Low: 0 Priority: Low
Accept the defaults for all remaining parameters.

11 Click OK.

18 EXP20R300 – CEE C200/C300/ACE 12/17/2014


Honeywell, Inc.
PID Control Module
Configure a PID Control Module

 Step Action
12 To Configure a PID Block:
Double click PIDA.
Enter the following:
Name: PIDA
Description: Heavy Feed to Debutanizer
Engineering Units: m3/hr

PVEU Range Hi: 600


PVEU Range Low: 0
Select the Enable Secondary Initialization Option checkbox.

Normal Mode: AUTO


Normal Mode Attribute: OPERATOR
Accept the defaults for all remaining parameters.

ATTENTION

This block must be named PIDA for the Honeywell


supplied standard PID Point Detail Display to function
properly.

12/17/2014 EXP20R300 – CEE C200/C300/ACE 19


Honeywell, Inc.
PID Control Module
Configure a PID Control Module

 Step Action
13 Click the Algorithm tab in the PID configuration form and enter the following
Control Equation type: EQB
Integral Time (T1): 0.2
Linear Gain Options: LIN
Overall Gain: 0.40

ATTENTION

The Algorithm form allows you to configure PID control


equation types, associated PID equation parameters
and gain options for the PID block.

14 Click the SetPoint Tab and enter the following:


High Limit: 600
Low Limit: 0
Enable PV Tracking check

20 EXP20R300 – CEE C200/C300/ACE 12/17/2014


Honeywell, Inc.
PID Control Module
Configure a PID Control Module

 Step Action
15 Click the Alarms tab of PID and enter the following:
OP High Trip Point: 95

12/17/2014 EXP20R300 – CEE C200/C300/ACE 21


Honeywell, Inc.
PID Control Module
Configure a PID Control Module

 Step Action
16 To add or remove Block Pins in a Functional Block :
Click on the Block Pins tab.
Click on the “TOP” value on the PV parameter Location column.
Select LEFT from the drop down combo box.

22 EXP20R300 – CEE C200/C300/ACE 12/17/2014


Honeywell, Inc.
PID Control Module
Configure a PID Control Module

 Step Action
17 As a result of the previous remove/add pins, the PV pin shifted to the left side of the PID
block faceplate, as indicated below.

Click OK.

12/17/2014 EXP20R300 – CEE C200/C300/ACE 23


Honeywell, Inc.
PID Control Module
Configure a PID Control Module

 Step Action
18 Configure the AO Block.
Double-click the AOChannelA Block and enter the following:
Channel Name: FV
Module Name: AO_4_4_4
Channel number: 1
Click the Assign Channel Block Button.
 The AO is assigned to Channel Number 1 of IOM AO_4_4_4

19 Click OK.

24 EXP20R300 – CEE C200/C300/ACE 12/17/2014


Honeywell, Inc.
PID Control Module
Configure a PID Control Module

Connect Function Blocks

After adding the Function Blocks, wire them together to form a Control Strategy. You can wire Blocks
together anytime you choose, before or after configuring block parameters.

 Step Action
1
From the Main Menu, Select Chart > Insert > Wire, OR Click the button in the
toolbar.
 The cursor changes to a PLUS (+) sign inside the Project chart window
 Click the PV pin displayed in the AICHANNEL (FI) block
 Click the P1 pin in the DATAACQ (DACA) block
 These function blocks are now connected

2 Repeat the above steps to connect PV pin of DATAACQ (DACA) to the PV of PIDA.

12/17/2014 EXP20R300 – CEE C200/C300/ACE 25


Honeywell, Inc.
PID Control Module
Configure a PID Control Module

 Step Action
3 Connect the PIDA OP pin to the OP pin of AO.
 Your CM should be similar to the one shown below.

4 Select File > Save.

26 EXP20R300 – CEE C200/C300/ACE 12/17/2014


Honeywell, Inc.
PID Control Module
Configure a PID Control Module

 Step Action
5 Configure History Collection, Trends and Groups.
Double-click on blank space in 11_FC01 project chart to open the configuration form.
Select the Server History tab. Click row 1 under the Parameter column in the History
Configuration table.

Click the (Point Selection) button to open the Point Selection form.

Select the row pertaining to Point 11_FC01 and Block Names PIDA, as indicated above.
Select OP for the Parameter.
Click OK to close the Point selection form.

12/17/2014 EXP20R300 – CEE C200/C300/ACE 27


Honeywell, Inc.
PID Control Module
Configure a PID Control Module

 Step Action
6 11_FC01.PIDA.OP appears in the History Configuration table.
 Select the FAST and STD checkboxes
 11_FC01.PIDA.OP will now be historized

7 Repeat the above steps to configure History Collection for 11_FC01.PIDA.PV in row 2 of
the Parameter column.

28 EXP20R300 – CEE C200/C300/ACE 12/17/2014


Honeywell, Inc.
PID Control Module
Configure a PID Control Module

 Step Action
8 Add Point Parameters to Trends.
Click the Server Displays tab in the configuration form.
In the first row under Trend # enter 1 as the Trend number.
Click the first row under the Pen column and from the drop-down menu select 1-Cyan.
Enter 11_FC01.PIDA.PV as the Trend Parameter.
 You can also select the parameter with the help of Point selection list, as shown in
step 5.
In the Groups section add 11_FC01.PIDA.PV to Group 11, Position 1.
Click OK.

9 Click File > Save.

12/17/2014 EXP20R300 – CEE C200/C300/ACE 29


Honeywell, Inc.
PID Control Module
Configure a PID Control Module

 Step Action
10 Close the 11_FC01 Project chart window.
 This CM is located under CEESCEFB61, which means it is assigned to that
execution environment
 The symbol “ “indicates that the CM has not yet been downloaded to the
controller

 The color gray of the connection icon indicates the CM is in Project mode.
11 Download this CM.
 Select 11_FC01

 Click the on the toolbar


 Click Continue on the Load window showing the warning

 Select the Automatically change… checkbox


 The post load state is selected as ACTIVE by default

30 EXP20R300 – CEE C200/C300/ACE 12/17/2014


Honeywell, Inc.
PID Control Module
Configure a PID Control Module

 Step Action
12 Click OK.
 A Load dialog box appears and closes on a successful download

 In Project, notice that there is no “ “ symbol in front of 11_FC01

13 Click the Monitoring tab to verify that 11_FC01 is active (green).

 If the CM is active (green) skip the next step


 If the CM is inactive (blue) continue to the next step

12/17/2014 EXP20R300 – CEE C200/C300/ACE 31


Honeywell, Inc.
PID Control Module
Configure a PID Control Module

 Step Action
14 Activate the CM (right-click 11_FC01 and select “Activate”) or select 11_FC01 and click

the (Toggle State) button from the toolbar, to open the following.

Click Yes.
 Notice that the 11_FC01 changes to green indicating it is now active
Monitoring tree status information is indicated by different symbols and colors,
as shown below:
CPM/SCE Symbols

1 2 3 4 5 6 7 8

1 Grey - As seen in project tree.


1 Grey – Project tree
2 Grey - Loaded not monitored
3 Red - Communication failure
4 Yellow - Not used
5 Green - Active
6 Red - Failed
7 Yellow - Not Loaded
8 Blue - Loaded

32 EXP20R300 – CEE C200/C300/ACE 12/17/2014


Honeywell, Inc.
PID Control Module
Configure a PID Control Module

 Step Action
CEE/ CEESCE Symbols
1 2 3 4 5 6

1 Grey - As seen in project tree


2 Grey - Loaded not monitored
3 Red - Communication failure
4 Blue - Inactive
5 Green - Active
6 Red - Configuration Error

CM Symbols
1 2 3 4 5

1 Grey - As seen in project tree


2 Grey - Loaded not monitored
3 Red - Communication failure
4 Blue - Inactive
5 Green - Active
15 Open Station, access and refresh the Debutanizer_123 graphic.
 Change the 11_FC01 controller to AUTO mode and enter 400 for the setpoint (SP).

ATTENTION

Open the Tie_Back_New Excel spreadsheet to


observe the values for PV and SP.
If the PV value for the point is not updating then restart
the Tie_Back_New Excel spreadsheet. This
spreadsheet is used for simulation purposes.

12/17/2014 EXP20R300 – CEE C200/C300/ACE 33


Honeywell, Inc.
PID Control Module
Configure a PID Control Module

 Step Action
16 To watch the trend on station:

Click the button on station.


Enter 1 in command line. Change the trend interval, if necessary.
Zoom the line trend to get a closer display.

34 EXP20R300 – CEE C200/C300/ACE 12/17/2014


Honeywell, Inc.
PID Control Module
Configure a PID Control Module

 Step Action
17 To see the CM in the Group display:

 Click button on Station.


 Type 11 and <Enter>.

12/17/2014 EXP20R300 – CEE C200/C300/ACE 35


Honeywell, Inc.
PID Control Module
Configure a PID Control Module

 Step Action
From the Group Display, change the MD to MAN.
Change the OP to 30.
 The PV will start dropping along with the SP since the PV tracking option is
enabled
 This tests your CM 11_FC01

36 EXP20R300 – CEE C200/C300/ACE 12/17/2014


Honeywell, Inc.
PID Control Module
Configure a PID Control Module

 Step Action
18 In Control Builder, import (with CEE assignment) 11_FC02, 11_FC28 and 11_PC15 from
the following location:
C:\Program Files\ Honeywell\ Experion PKS\Engineering Tools\Ixport\Student_DB

ATTENTION

If needed, follow the steps in the Import/Export Lab for


importing the above CMs.

19 From Project, download (with activation) the CMs imported in the previous step.
20 Verify that the three CMs are active (green) in the Monitoring tab.
21 Open Station and access the Debutanizer_123 graphic.

ATTENTION

Verify that the imported CMs have values. (If


necessary, place the imported loops in AUTO mode
and provide suitable SP values to see a PV response.)

12/17/2014 EXP20R300 – CEE C200/C300/ACE 37


Honeywell, Inc.
PID Control Module
Configure a PID Control Module

This page was intentionally left blank.