Sie sind auf Seite 1von 3

1. GENERAL CONDITION OF A CONTRACT c.

PAYMENT BOND- a surety bond posted by


a. CHANGE ORDER- post-award modification a contractor to guarantee that its
to the contract. A change order may revise, subcontractors and material suppliers on
add to, or delete previous requirements of the project will be paid.
the work, adjust the contract sum, or d. ALL RISK BOND- insurance coverage that
adjust the contract time can exclude only risks that have been
b. ADVANCE PAYMENT- Ten (10) percent of specifically outlined in the contract.
the Contract Price shall be paid within e. INSURANCES- Insurance is a contract
thirty (30) days of signature of Contract and (policy) in which an individual or entity
receipt of the Performance Guarantee receives financial protection or
c. PROGRESS PAYMENT- payment for Work reimbursement against losses from an
accomplished insurance company.
d. RETENTION MONEY- Progress payments f. GUARANTEE BOND-(15%) approved form
are subject to retention of ten percent of security furnished by the contractor as
(10%), total “retention money” shall be due guarantee to the quality of materials and
for release upon final acceptance of the workmanship performed.
Works. purpose of retention is to ensure 3. ARCHITECTURAL DRAWINGS
that the contractor properly completes the a. SHOP DRAWINGS- set of drawings
activities required of them under the produced by the contractor, supplier,
contract manufacturer, subcontractor, or fabricator.
e. LIQUIDATING DAMAGES- Monetary Examples of these include: elevators,
compensation for a loss, detriment, or structural steel, trusses, pre-cast, windows,
injury to a person or a person's rights or appliances, cabinets, air handling units,
property, Shop drawings are not produced by
f. CONTRACT PRICE ESCALATION- Contract architects and engineers under their
Price is the price stated in the Letter of contract with the owner. The shop drawing
Acceptance and thereafter to be paid by is the manufacturers or the contractor’s
the Procuring Entity to the Contractor for drawn version of information shown in the
the execution of the Works in accordance construction documents.
with this Contract. b. AS BUILT PLAN- the original design
2. CONTRACTORS’ BOND drawings revised to reflect any changes
a. PROPOSAL OR BID BOND- supply bidding made in the field,
process by the contractor to the project 4. SPECIFICATION- that portion of the Contract
owner, to in hopes guarantee that the Documents consisting of the written requirements
winning bidder will undertake the contract for materials, equipment, systems, standards and
under the terms at which they bid. workmanship for the Work, and performance of
b. PERFORMANCE BOND- also known as a related services
contract bond, is a surety bond issued by 5. AGREEMENT- a negotiated and typically legally
an insurance company or a bank to binding arrangement between parties
guarantee satisfactory completion of a 6. ARBITRATION- procedure in which a dispute is
project by a contractor. submitted, by agreement of the parties, to one or
more arbitrators who make a binding decision on
the dispute. In choosing arbitration, the parties opt c. MODE ACCOMPLISHMENT
for a private dispute resolution procedure instead d. SCOPE OF WORK
of going to court. 20. PARTS OF CONTRACT DOCUMENT
7. BID BULLETIN- A brief update or summary of a. AGREEMENT
current news is the contract between the owner and
8. INSTRUCTION TO BIDDERS- provides the the contractor undertaking the project
information necessary for Bidders to prepare described in the Contract Documents
responsive bids, in accordance with the including all supplemental agreements
thereto and all general and special
requirements of the Procuring Entity. It also
provisions pertaining to the work or
provides information on bid submission, opening,
materials therefore
evaluation, and award of contract.
b. GENERAL CONDITION

9. SPECIAL PROVISION as printed documents stipulating the


10. PENALTY CLAUSE- Provision in a contract that procedural and the administrative
aspects of the contract.
imposes a specified sum on the defaulting
c. SPECIFICATION
contracting party for a specified default.
11. PROPOSAL- offer of a bidder are written or printed description of
12. QUOTATION- is a proposal for respective goods & work to e done describing qualities of
material and mode of construction.
services, A formal statement of promise
13. SURETY- organization or person that assumes the
d. WORKING DRAWINGS
responsibility of paying the debt in case the debtor
are graphical presentations of the work
policy defaults or is unable to make the payments. involved in the project. They include all
14. STATUTE OF LIMITATION- a law which forbids supplementary details and shop
prosecutors from charging someone with a crime drawings.
that was committed more than a specified number e. SPECIAL PROVISION
of years ago.
15. NOTICE TO PROCEED (NTP)- Letter from a principal are instructions which may be issued
prior to the bidding to supplement
(client or owner) to a contractor stating the date and/or modify the drawings,
the contractor can begin work subject to the specifications, and/or General
conditions of the contract. Conditions of the contract.
16. BILL OF MATERIALS (QUANTITY OF SURVEY)- a list
of the raw materials, sub-assemblies, intermediate
assemblies, sub-components, parts and the
DEFINE
quantities of each needed to manufacture an end 1. WORK- refer to the Permanent Works and
product. Temporary Works to be executed by the Contractor
17. PROBABLE OF CONSTRUCTION COST- in accordance with this Contract, including (i) the
approximation of the cost of a program, project, or furnishing of all labor, materials, equipment and
operation. others incidental, necessary or convenient to the
18. ACTUAL CONSTRUCTION COST complete execution of the Works
19. PARTS OF PROPOSAL 2. PROVIDE- “provide” shall be understood to
a. MODE AGREEMENT mean “furnish and install”
b. MODE PAYMENT
3. INSTALL- the word “install” shall mean to build 16. 5 INPUTS OF PLANNING CRITICAL PATH METHOD
in, mount positions, connect or apply any (CPM)
object specified ready for the intended use. a. NETWORK
4. FURNISH- The work “furnish” shall be understood b. DURATION ESTIMATE
to mean “Purchase and/or fabricate and c. COST ESTIMATES
deliver to the jobsite or other location when so d. RESOURCE ESTIMATE
designated.”
e. TRADE INDICATORS
5. SCOPE OF WORK
17. SCHEDULE OF ANALYSIS
6. CERTIFICATE OF PAYMENT
a. EARLY START
The Certificate of Payment shall include the
b. EARLY FINISH
value of work accomplished by the Contractor
c. LATE START
during the period covered buy the certificate
and recommendation to the Owner for d. LATE FINISH
payment in an amount the Architect decides
to be properly due.

7. TYPES OF SPECIFICATION
a. PERFORMANCE SPECS
b. DESCRIPTIVE SPECS
c. BRAND NAME SPECS
d. REFERENCE SPECS
e. CLOSE SPECS
f. OPEN SPECS
8. RETRIFICATION- the act of offering an
improvement to replace a mistake; setting right
9. INSURANCE OF CERTIFICATE OF NON FINANCIAL
OBLIGATION- 65% upon project completion
10. SUBSTANTIAL COMPLETION- 98% upon project
completion
11. REQUEST FOR PAYMENT- and owner will pay
contractor within 15days
12. PROGRAMMING- the research and decision-
making process that identifies the scope of work to
be designed.
13. PLANNING- a design and planning for a building,
and can contain architectural drawings,
specifications of the design, calculations, time
planning of the building process, and other
documentation.
14. SCHEDULING
15. METHOD OF PLANNING
a. BAR CHART METHOD
b. CRITICAL PATH METHOD

Das könnte Ihnen auch gefallen