Project : KHARTOUM-MADANI 12"PIPELINE DETAILED DESIGN

Project N° Contract N° EPPM Document N° Client Document N° Rev

AR 11/11
MoP/SPPC/EPPM/C/2011
R1111-DSH-ME-03-036 0

Date 10/1/2011 Sheet 1 of 9

DATA SHEET

FLAME ARRESTOR DATA SHEET

SUDANESE PETROLEUM PIPELINES


COMPANY SUDAN

0 7/31/2012 Final Issue GMD ELA ZMT


0A 5/30/2012 Issued For Approval MS ELA ZMT
Name Visa Name Visa Name Visa
Rev Date Description

001/ AR11/11 04/10


Rev Date Description
Prepared by Checked by Approved by

001/ AR11/11 04/10


NO. R1111-DSH-ME-03-036
FLAME ARRESTOR DATA SHEET REV. 0
SHEET:2 /9
DATA SHEET

REVISIONS REVISIONS
SHEETS 0A 0 SHEETS 0A 0B 0C
1* X 35
2** X 36
3 X 37
4 X 38
5 X 39
6 X 40
7 X 41
8 X 42
9 X 43
10 44
11 45
12 46
13 47
14 48
15 49
16 50
17 51
18 52
19 53
20 54
21 55
22 56
23 57
24 58
25 59
26 60
27 61
28 62
29 63
30 64
31 65
32 66
33 67
34 68
Note : * front page
** this page
REVISIONS REPORT
REVISION REASON FOR ISSUE
0A Issued For Approval

002/AR11/11 04/10
002/AR11/11 04/10
R1111-DSH-ME-03-036
0
2 /9
A SHEET

REVISIONS

REASON FOR ISSUE


Issued For Approval

002/AR11/11 04/10
002/AR11/11 04/10
NO.
FLAME ARRESTOR DATA SHEET REV.
SHEET:
Project Name12 NPS Multi Product Pipeline from Khartoum to Madani State
Purchase Order Manufacturer
Client SPPC Location SUDAN

A.1 GENERAL
A.1.1 QUANTITY 2
A.1.2 TAG NUMBER 03-FA-1001 / 03-FA-1002
A.1.3 SERVICE MOGAS/KEROSENE
A.1.4 TYPE In-Line
A.1.5 CODE API 2210 / API 2028
A.1.6 CERTIFICATE EN12874 & 94/9/CE ATEX100A
A.1.7 P&ID NUMBER R1111-DWG-PR-03-004
A.2 ENVIRONMENTAL DATA
A.2.1 MIN. TEMPERATURE ON PLACE OF INSTALLATION (WINTER) 5 °C
A.2.2 MAX. TEMPERATURE ON PLACE OF INSTALLATION (SUMMER) 55 °C
A.2.3 RELATIVE HUMIDITY 20 % - 80%
A.2.4 AVERAGE YEARLY RAINFALL 286,3 mm
A.2.5 MAXIMUM DAILY RAINFALL 100 mm
A.2.6 ELEVATION ABOVE SEA LEVELS 410 m
A.2.7 AVERAGE WIND VELOCITY 160 Km/ hr
A.2.8 SEISMIC ZONE ZONE II
A.3 LOCATION
A.3.1 INDOOR OUTDOOR ✘ TANK ROOF
A.3.2 HEATED ✘ UNHEATED
A.3.3 IGNITION SOURCE YES ✘ NO
A.3.4 DISTANCE TO THE SOURCE OF IGNITION N/A
A.3.5 CAN ARISE A HANGFIRE AT THE FLAME ARRESTER ✘ YES NO
A.4 PROCESS DATA
A.4.1 MEDIUM OR MEDIUM MIXTURE MOGAS/KEROSENE
A.4.2 ✘ CHEMICAL STABLE CHEMICAL UNSTABLE UNKNOWN
A.4.3 EXPLOSION GROUP ✘ UNKNOWN
IIB1 IIB2
IEC (MESG*in mm) I (>=1,14) ✘ IIA (>0,9) (>=0,75) IIB3 (>=0,6
(>=0,85)
IIB (>=0,5) IIC (<0,5)
G.M. C (>=0,65) B (>=0,28)
NEC (MESG*in mm) ✘ (>=1,12) D (>=0,9)
A.4.4 DENSITY 2,17-3,96 Kg/m3
A.4.5 OPERATING PRESSURE ATM
AAA
A.4.6 FLOW DIRECTION ffffff As Per P&ID
ai a
a
A.4.7 DESIGN PRESSURE ri 25 mbarg
eirr
A.4.8 OPERATING TEMPERATURE
Nee 37,5 °C
°N
A.4.9 MAXIMUM OPERATING°°
N
TEMPERATURE 55 °C
A.4.10 MAXIMUM FLOW RATE 418 SCFM
A.4.11 MAXIMUM ALLOWABLE PRESSURE DROP 5 mbarg
A.4.12 TANK NOZZLE SIZE 4"
A.4.13 CORROSION ALLOWANCE 1 mm
A.5 MECHANICAL AND DEVICE CHARACTERISTICS
A.5.1 DESIGN
END OF LINE DEFLAGRATION SHORT TIME BURNING ENDURANCE BURNING UN

IN-LINE ✘ DEFLAGRATION STABLE DETONATION UNSTABLE DETONATION UN


✘ UNIDIRECTIONAL BI-DIRECTIONAL
A.5.2 CONNECTION 4" Class 150 RF
A.5.3 MATERIALS
BODY DUCTILE IRON ✘ C-STEEL STAINLESS STEEL OTHER
INTERNALS DUCTILE IRON C-STEEL ✘ STAINLESS STEEL OTHER

NOTES
(1) Internal & External painting/coating shall be as per Project Specification R1111-SPC-PP-00-005
(2) All missing data shall be filled by vendor
R1111-DSH-ME-03-036
0
3/9

2
SENE

028
ATEX100A
03-004

TER) 5 °C
MER) 55 °C
20 % - 80%
286,3 mm
100 mm
410 m
160 Km/ hr
ZONE II

N/A

AS/KEROSENE

IIB3 (>=0,65)

,17-3,96 Kg/m3
TM
s Per P&ID
25 mbarg
7,5 °C
C
18 SCFM
mbarg
4"
1 mm

UNKNOWN

UNKNOWN

0 RF
ect Specification R1111-SPC-PP-00-005
NO.
FLAME ARRESTOR DATA SHEET REV.
SHEET:
Project Name12 NPS Multi Product Pipeline from Khartoum to Madani State
Purchase Order Manufacturer
Client SPPC Location SUDAN

A.1 GENERAL
A.1.1 QUANTITY 1
A.1.2 TAG NUMBER 03-FA-1003
A.1.3 SERVICE GASOIL-KEROSENE
A.1.4 TYPE In-Line
A.1.5 CODE API 2210 / API 2028
A.1.6 CERTIFICATE EN12874 & 94/9/CE ATEX100A
A.1.7 P&ID NUMBER R1111-DWG-PR-03-004
A.2 ENVIRONMENTAL DATA
A.2.1 MIN. TEMPERATURE ON PLACE OF INSTALLATION (WINTER) 5 °C
A.2.2 MAX. TEMPERATURE ON PLACE OF INSTALLATION (SUMMER) 55 °C
A.2.3 RELATIVE HUMIDITY 20 % - 80%
A.2.4 AVERAGE YEARLY RAINFALL 286,3 mm
A.2.5 MAXIMUM DAILY RAINFALL 100 mm
A.2.6 ELEVATION ABOVE SEA LEVELS 410 m
A.2.7 AVERAGE WIND VELOCITY 160 Km/ hr
A.2.8 SEISMIC ZONE ZONE II
A.3 LOCATION
A.3.1 INDOOR OUTDOOR ✘ TANK ROOF
A.3.2 HEATED ✘ UNHEATED
A.3.3 IGNITION SOURCE YES ✘ NO
A.3.4 DISTANCE TO THE SOURCE OF IGNITION N/A
A.3.5 CAN ARISE A HANGFIRE AT THE FLAME ARRESTER ✘ YES NO
A.4 PROCESS DATA
A.4.1 MEDIUM OR MEDIUM MIXTURE GASOIL-KEROSENE
A.4.2 ✘ CHEMICAL STABLE CHEMICAL UNSTABLE UNKNOWN
A.4.3 EXPLOSION GROUP ✘ UNKNOWN
IIB1 IIB2
IEC (MESG*in mm) I (>=1,14) IIA (>0,9) (>=0,75) IIB3 (>=0,6
(>=0,85)
IIB (>=0,5) IIC (<0,5)
G.M. C (>=0,65) B (>=0,28)
NEC (MESG*in mm) D (>=0,9)
(>=1,12)
A.4.4 DENSITY 3,92-3,94 Kg/m3
A.4.5 OPERATING PRESSURE ATM
AAA
A.4.6 FLOW DIRECTION ffffff As Per P&ID
ai a
a
A.4.7 DESIGN PRESSURE ri 25 mbarg
eirr
A.4.8 OPERATING TEMPERATURE
Nee 37,5 °C
°N
A.4.9 MAXIMUM OPERATING°°
N
TEMPERATURE 55 °C
A.4.10 MAXIMUM FLOW RATE 210 SCFM
A.4.11 MAXIMUM ALLOWABLE PRESSURE DROP 5 mbarg
A.4.12 TANK NOZZLE SIZE 3"
A.4.13 CORROSION ALLOWANCE 1 mm
A.5 MECHANICAL AND DEVICE CHARACTERISTICS
A.5.1 DESIGN
END OF LINE DEFLAGRATION SHORT TIME BURNING ENDURANCE BURNING UN

IN-LINE ✘ DEFLAGRATION STABLE DETONATION UNSTABLE DETONATION UN


✘ UNIDIRECTIONAL BI-DIRECTIONAL
A.5.2 CONNECTION 3" Class 150 RF
A.5.3 MATERIALS
BODY DUCTILE IRON ✘ C-STEEL STAINLESS STEEL OTHER
INTERNALS DUCTILE IRON C-STEEL ✘ STAINLESS STEEL OTHER

NOTES
(1) Internal & External painting/coating shall be as per Project Specification R1111-SPC-PP-00-005
(2) All missing data shall be filled by vendor
R1111-DSH-ME-03-036
0
4/9

SENE

028
ATEX100A
03-004

TER) 5 °C
MER) 55 °C
20 % - 80%
286,3 mm
100 mm
410 m
160 Km/ hr
ZONE II

N/A

ROSENE

IIB3 (>=0,65)

3,92-3,94 Kg/m3
ATM
s Per P&ID
25 mbarg
37,5 °C
5 °C
210 SCFM
5 mbarg
3"
1 mm

UNKNOWN

UNKNOWN

0 RF
ect Specification R1111-SPC-PP-00-005
NO.
FLAME ARRESTOR DATA SHEET REV.
SHEET:
Project Name12 NPS Multi Product Pipeline from Khartoum to Madani State
Purchase Order Manufacturer
Client SPPC Location SUDAN

A.1 GENERAL
A.1.1 QUANTITY 3
A.1.2 TAG NUMBER 03-FA-1004 / 03-FA-1005 / 03-FA-1006
A.1.3 SERVICE GASOIL
A.1.4 TYPE In-Line
A.1.5 CODE API 2210 / API 2028
A.1.6 CERTIFICATE EN12874 & 94/9/CE ATEX100A
A.1.7 P&ID NUMBER R1111-DWG-PR-03-004
A.2 ENVIRONMENTAL DATA
A.2.1 MIN. TEMPERATURE ON PLACE OF INSTALLATION (WINTER) 5 °C
A.2.2 MAX. TEMPERATURE ON PLACE OF INSTALLATION (SUMMER) 55 °C
A.2.3 RELATIVE HUMIDITY 20 % - 80%
A.2.4 AVERAGE YEARLY RAINFALL 286,3 mm
A.2.5 MAXIMUM DAILY RAINFALL 100 mm
A.2.6 ELEVATION ABOVE SEA LEVELS 410 m
A.2.7 AVERAGE WIND VELOCITY 160 Km/ hr
A.2.8 SEISMIC ZONE ZONE II
A.3 LOCATION
A.3.1 INDOOR OUTDOOR ✘ TANK ROOF
A.3.2 HEATED ✘ UNHEATED
A.3.3 IGNITION SOURCE YES ✘ NO
A.3.4 DISTANCE TO THE SOURCE OF IGNITION N/A
A.3.5 CAN ARISE A HANGFIRE AT THE FLAME ARRESTER ✘ YES NO
A.4 PROCESS DATA
A.4.1 MEDIUM OR MEDIUM MIXTURE GASOIL
A.4.2 ✘ CHEMICAL STABLE CHEMICAL UNSTABLE UNKNOWN
A.4.3 EXPLOSION GROUP ✘ UNKNOWN
IIB1 IIB2
IEC (MESG*in mm) I (>=1,14) IIA (>0,9) ✘ (>=0,75) IIB3 (>=0,6
(>=0,85)
IIB (>=0,5) IIC (<0,5)
G.M. C (>=0,65) B (>=0,28)
NEC (MESG*in mm) D (>=0,9)
(>=1,12)
A.4.4 DENSITY 3,82-3,92 Kg/m3
A.4.5 OPERATING PRESSURE ATM
AAA
A.4.6 FLOW DIRECTION ffffff As Per P&ID
ai a
a
A.4.7 DESIGN PRESSURE ri 25 mbarg
eirr
A.4.8 OPERATING TEMPERATURE
Nee 37,5 °C
°N
A.4.9 MAXIMUM OPERATING°°
N
TEMPERATURE 55 °C
A.4.10 MAXIMUM FLOW RATE 780 SCFM
A.4.11 MAXIMUM ALLOWABLE PRESSURE DROP 5 mbarg
A.4.12 TANK NOZZLE SIZE 6"
A.4.13 CORROSION ALLOWANCE
A.5 MECHANICAL AND DEVICE CHARACTERISTICS
A.5.1 DESIGN
END OF LINE DEFLAGRATION SHORT TIME BURNING ENDURANCE BURNING UN

IN-LINE ✘ DEFLAGRATION STABLE DETONATION UNSTABLE DETONATION UN


✘ UNIDIRECTIONAL BI-DIRECTIONAL
A.5.2 CONNECTION 6" Class 150 RF
A.5.3 MATERIALS
BODY DUCTILE IRON ✘ C-STEEL STAINLESS STEEL OTHER
INTERNALS DUCTILE IRON C-STEEL ✘ STAINLESS STEEL OTHER

NOTES
(1) Internal & External painting/coating shall be as per Project Specification R1111-SPC-PP-00-005
(2) All missing data shall be filled by vendor
R1111-DSH-ME-03-036
0
5/9

5 / 03-FA-1006

028
ATEX100A
03-004

TER) 5 °C
MER) 55 °C
20 % - 80%
286,3 mm
100 mm
410 m
160 Km/ hr
ZONE II

N/A

IIB3 (>=0,65)

,82-3,92 Kg/m3
ATM
s Per P&ID
25 mbarg
,5 °C

0 SCFM
barg
6"

UNKNOWN

UNKNOWN

0 RF
ect Specification R1111-SPC-PP-00-005
NO.
FLAME ARRESTOR DATA SHEET REV.
SHEET:
Project Name12 NPS Multi Product Pipeline from Khartoum to Madani State
Purchase Order Manufacturer
Client SPPC Location SUDAN

A.1 GENERAL
A.1.1 QUANTITY 2
A.1.2 TAG NUMBER 03-FA-1007 / 03-FA-1008
A.1.3 SERVICE MOGAS
A.1.4 TYPE In-Line
A.1.5 CODE API 2210 / API 2028
A.1.6 CERTIFICATE EN12874 & 94/9/CE ATEX100A
A.1.7 P&ID NUMBER R1111-DWG-PR-03-004
A.2 ENVIRONMENTAL DATA
A.2.1 MIN. TEMPERATURE ON PLACE OF INSTALLATION (WINTER) 5 °C
A.2.2 MAX. TEMPERATURE ON PLACE OF INSTALLATION (SUMMER) 55 °C
A.2.3 RELATIVE HUMIDITY 20 % - 80%
A.2.4 AVERAGE YEARLY RAINFALL 286,3 mm
A.2.5 MAXIMUM DAILY RAINFALL 100 mm
A.2.6 ELEVATION ABOVE SEA LEVELS 410 m
A.2.7 AVERAGE WIND VELOCITY 160 Km/ hr
A.2.8 SEISMIC ZONE ZONE II
A.3 LOCATION
A.3.1 INDOOR OUTDOOR ✘ TANK ROOF
A.3.2 HEATED ✘ UNHEATED
A.3.3 IGNITION SOURCE YES ✘ NO
A.3.4 DISTANCE TO THE SOURCE OF IGNITION N/A
A.3.5 CAN ARISE A HANGFIRE AT THE FLAME ARRESTER ✘ YES NO
A.4 PROCESS DATA
A.4.1 MEDIUM OR MEDIUM MIXTURE MOGAS
A.4.2 ✘ CHEMICAL STABLE CHEMICAL UNSTABLE UNKNOWN
A.4.3 EXPLOSION GROUP ✘ UNKNOWN
IIB1 IIB2
IEC (MESG*in mm) I (>=1,14) IIA (>0,9) (>=0,75) IIB3 (>=0,6
(>=0,85)
IIB (>=0,5) IIC (<0,5)
G.M. C (>=0,65) B (>=0,28)
NEC (MESG*in mm) D (>=0,9)
(>=1,12)
A.4.4 DENSITY 2,17 - 2,22 Kg/m3
A.4.5 OPERATING PRESSURE ATM
AAA
A.4.6 FLOW DIRECTION ffffff As Per P&ID
ai a
a
A.4.7 DESIGN PRESSURE ri 25 mbarg
eirr
A.4.8 OPERATING TEMPERATURE
Nee 37,5 °C
°N
A.4.9 MAXIMUM OPERATING°°
N
TEMPERATURE 55°C
A.4.10 MAXIMUM FLOW RATE 896,17 SCFM
A.4.11 MAXIMUM ALLOWABLE PRESSURE DROP 5 mbarg
A.4.12 TANK NOZZLE SIZE 6"
A.4.13 CORROSION ALLOWANCE
A.5 MECHANICAL AND DEVICE CHARACTERISTICS
A.5.1 DESIGN
END OF LINE DEFLAGRATION SHORT TIME BURNING ENDURANCE BURNING UN

IN-LINE ✘ DEFLAGRATION STABLE DETONATION UNSTABLE DETONATION UN


✘ UNIDIRECTIONAL BI-DIRECTIONAL
A.5.2 CONNECTION 6" Class 150 RF
A.5.3 MATERIALS
BODY DUCTILE IRON ✘ C-STEEL STAINLESS STEEL OTHER
INTERNALS DUCTILE IRON C-STEEL ✘ STAINLESS STEEL OTHER

NOTES
(1) Internal & External painting/coating shall be as per Project Specification R1111-SPC-PP-00-005
(2) All missing data shall be filled by vendor
R1111-DSH-ME-03-036
0
6/9

A-1008

028
ATEX100A
03-004

TER) 5 °C
MER) 55 °C
20 % - 80%
286,3 mm
100 mm
410 m
160 Km/ hr
ZONE II

N/A

AS

IIB3 (>=0,65)

2,17 - 2,22 Kg/m3


ATM
s Per P&ID
25 mbarg
7,5 °C
5°C
6,17 SCFM
mbarg
6"

UNKNOWN

UNKNOWN

0 RF
ect Specification R1111-SPC-PP-00-005
NO.
FLAME ARRESTOR DATA SHEET REV.
SHEET:
Project Name12 NPS Multi Product Pipeline from Khartoum to Madani State
Purchase Order Manufacturer
Client SPPC Location SUDAN

A.1 GENERAL
A.1.1 QUANTITY 1
A.1.2 TAG NUMBER 03-FA-1009
A.1.3 SERVICE KEROSENE
A.1.4 TYPE In-Line
A.1.5 CODE API 2210 / API 2028
A.1.6 CERTIFICATE EN12874 & 94/9/CE ATEX100A
A.1.7 P&ID NUMBER R1111-DWG-PR-03-004
A.2 ENVIRONMENTAL DATA
A.2.1 MIN. TEMPERATURE ON PLACE OF INSTALLATION (WINTER) 5 °C
A.2.2 MAX. TEMPERATURE ON PLACE OF INSTALLATION (SUMMER) 55 °C
A.2.3 RELATIVE HUMIDITY 20 % - 80%
A.2.4 AVERAGE YEARLY RAINFALL 286,3 mm
A.2.5 MAXIMUM DAILY RAINFALL 100 mm
A.2.6 ELEVATION ABOVE SEA LEVELS 410 m
A.2.7 AVERAGE WIND VELOCITY 160 Km/ hr
A.2.8 SEISMIC ZONE ZONE II
A.3 LOCATION
A.3.1 INDOOR OUTDOOR ✘ TANK ROOF
A.3.2 HEATED ✘ UNHEATED
A.3.3 IGNITION SOURCE YES ✘ NO
A.3.4 DISTANCE TO THE SOURCE OF IGNITION N/A
A.3.5 CAN ARISE A HANGFIRE AT THE FLAME ARRESTER ✘ YES NO
A.4 PROCESS DATA
A.4.1 MEDIUM OR MEDIUM MIXTURE KEROSENE
A.4.2 ✘ CHEMICAL STABLE CHEMICAL UNSTABLE UNKNOWN
A.4.3 EXPLOSION GROUP ✘ UNKNOWN
IIB1 IIB2
IEC (MESG*in mm) I (>=1,14) IIA (>0,9) (>=0,75) IIB3 (>=0,6
(>=0,85)
IIB (>=0,5) IIC (<0,5)
G.M. C (>=0,65) B (>=0,28)
NEC (MESG*in mm) D (>=0,9)
(>=1,12)
A.4.4 DENSITY 3,94 Kg/m3
A.4.5 OPERATING PRESSURE ATM
AAA
A.4.6 FLOW DIRECTION ffffff As Per P&ID
ai a
a
A.4.7 DESIGN PRESSURE ri 25 mbarg
eirr
A.4.8 OPERATING TEMPERATURE
Nee 37,5 °C
°N
A.4.9 MAXIMUM OPERATING°°
N
TEMPERATURE 55 °C
A.4.10 MAXIMUM FLOW RATE 280 SCFM
A.4.11 MAXIMUM ALLOWABLE PRESSURE DROP 5 mbarg
A.4.12 TANK NOZZLE SIZE 4"
A.4.13 CORROSION ALLOWANCE
A.5 MECHANICAL AND DEVICE CHARACTERISTICS
A.5.1 DESIGN
END OF LINE DEFLAGRATION SHORT TIME BURNING ENDURANCE BURNING UN

IN-LINE ✘ DEFLAGRATION STABLE DETONATION UNSTABLE DETONATION UN


✘ UNIDIRECTIONAL BI-DIRECTIONAL
A.5.2 CONNECTION 4" Class 150 RF
A.5.3 MATERIALS
BODY DUCTILE IRON ✘ C-STEEL STAINLESS STEEL OTHER
INTERNALS DUCTILE IRON C-STEEL ✘ STAINLESS STEEL OTHER

NOTES
(1) Internal & External painting/coating shall be as per Project Specification R1111-SPC-PP-00-005
(2) All missing data shall be filled by vendor
R1111-DSH-ME-03-036
0
7/9

NE

028
ATEX100A
03-004

TER) 5 °C
MER) 55 °C
20 % - 80%
286,3 mm
100 mm
410 m
160 Km/ hr
ZONE II

N/A

IIB3 (>=0,65)

3,94 Kg/m3
ATM
s Per P&ID
25 mbarg
37,5 °C
°C
280 SCFM
mbarg
4"

UNKNOWN

UNKNOWN

0 RF
ect Specification R1111-SPC-PP-00-005
NO.
FLAME ARRESTOR DATA SHEET REV.
SHEET:
Project Name12 NPS Multi Product Pipeline from Khartoum to Madani State
Purchase Order Manufacturer
Client SPPC Location SUDAN

A.1 GENERAL
A.1.1 QUANTITY 1
A.1.2 TAG NUMBER 03-FA-1010
A.1.3 SERVICE GASOIL
A.1.4 TYPE In-Line
A.1.5 CODE API 2210 / API 2028
A.1.6 CERTIFICATE EN12874 & 94/9/CE ATEX100A
A.1.7 P&ID NUMBER R1111-DWG-PR-03-004
A.2 ENVIRONMENTAL DATA
A.2.1 MIN. TEMPERATURE ON PLACE OF INSTALLATION (WINTER) 5 °C
A.2.2 MAX. TEMPERATURE ON PLACE OF INSTALLATION (SUMMER) 55 °C
A.2.3 RELATIVE HUMIDITY 20 % - 80%
A.2.4 AVERAGE YEARLY RAINFALL 286,3 mm
A.2.5 MAXIMUM DAILY RAINFALL 100 mm
A.2.6 ELEVATION ABOVE SEA LEVELS 410 m
A.2.7 AVERAGE WIND VELOCITY 160 Km/ hr
A.2.8 SEISMIC ZONE ZONE II
A.3 LOCATION
A.3.1 INDOOR OUTDOOR ✘ TANK ROOF
A.3.2 HEATED ✘ UNHEATED
A.3.3 IGNITION SOURCE YES ✘ NO
A.3.4 DISTANCE TO THE SOURCE OF IGNITION N/A
A.3.5 CAN ARISE A HANGFIRE AT THE FLAME ARRESTER ✘ YES NO
A.4 PROCESS DATA
A.4.1 MEDIUM OR MEDIUM MIXTURE GASOIL
A.4.2 ✘ CHEMICAL STABLE CHEMICAL UNSTABLE UNKNOWN
A.4.3 EXPLOSION GROUP ✘ UNKNOWN
IIB1 IIB2
IEC (MESG*in mm) I (>=1,14) IIA (>0,9) ✘ (>=0,75) IIB3 (>=0,6
(>=0,85)
IIB (>=0,5) IIC (<0,5)
G.M. C (>=0,65) B (>=0,28)
NEC (MESG*in mm) D (>=0,9)
(>=1,12)
A.4.4 DENSITY 3,81-3,92 Kg/m3
A.4.5 OPERATING PRESSURE ATM
AAA
A.4.6 FLOW DIRECTION ffffff As Per P&ID
ai a
a
A.4.7 DESIGN PRESSURE ri 25 mbarg
eirr
A.4.8 OPERATING TEMPERATURE
Nee 37,5 °C
°N
A.4.9 MAXIMUM OPERATING°°
N
TEMPERATURE 55 °C
A.4.10 MAXIMUM FLOW RATE 11,33 SCFM
A.4.11 MAXIMUM ALLOWABLE PRESSURE DROP 5 mbarg
A.4.12 TANK NOZZLE SIZE 2"
A.4.13 CORROSION ALLOWANCE
A.5 MECHANICAL AND DEVICE CHARACTERISTICS
A.5.1 DESIGN
END OF LINE DEFLAGRATION SHORT TIME BURNING ENDURANCE BURNING UN

IN-LINE ✘ DEFLAGRATION STABLE DETONATION UNSTABLE DETONATION UN


✘ UNIDIRECTIONAL BI-DIRECTIONAL
A.5.2 CONNECTION 2" Class 150 RF
A.5.3 MATERIALS
BODY DUCTILE IRON ✘ C-STEEL STAINLESS STEEL OTHER
INTERNALS DUCTILE IRON C-STEEL ✘ STAINLESS STEEL OTHER

NOTES
(1) Internal & External painting/coating shall be as per Project Specification R1111-SPC-PP-00-005
(2) All missing data shall be filled by vendor
R1111-DSH-ME-03-036
0
8/9

028
ATEX100A
03-004

TER) 5 °C
MER) 55 °C
20 % - 80%
286,3 mm
100 mm
410 m
160 Km/ hr
ZONE II

N/A

IIB3 (>=0,65)

3,81-3,92 Kg/m3
ATM
s Per P&ID
25 mbarg
37,5 °C
55 °C
,33 SCFM
mbarg
2"

UNKNOWN

UNKNOWN

0 RF
ect Specification R1111-SPC-PP-00-005
NO.
FLAME ARRESTOR DATA SHEET REV.
SHEET:
Project Name12 NPS Multi Product Pipeline from Khartoum to Madani State
Purchase Order Manufacturer
Client SPPC Location SUDAN

A.1 GENERAL
A.1.1 QUANTITY 1
A.1.2 TAG NUMBER 03-FA-1012
A.1.3 SERVICE WATER/MOGAS/KERO/GASOIL
A.1.4 TYPE End Of Line
A.1.5 CODE API 2210 / API 2028
A.1.6 CERTIFICATE EN12874 & 94/9/CE ATEX100A
A.1.7 P&ID NUMBER R1111-DWG-PR-03-004
A.2 ENVIRONMENTAL DATA
A.2.1 MIN. TEMPERATURE ON PLACE OF INSTALLATION (WINTER) 5 °C
A.2.2 MAX. TEMPERATURE ON PLACE OF INSTALLATION (SUMMER) 55 °C
A.2.3 RELATIVE HUMIDITY 20 % - 80%
A.2.4 AVERAGE YEARLY RAINFALL 286,3 mm
A.2.5 MAXIMUM DAILY RAINFALL 100 mm
A.2.6 ELEVATION ABOVE SEA LEVELS 410 m
A.2.7 AVERAGE WIND VELOCITY 160 Km/ hr
A.2.8 SEISMIC ZONE ZONE II
A.3 LOCATION
A.3.1 INDOOR OUTDOOR ✘ TANK ROOF
A.3.2 HEATED ✘ UNHEATED
A.3.3 IGNITION SOURCE YES ✘ NO
A.3.4 DISTANCE TO THE SOURCE OF IGNITION N/A
A.3.5 CAN ARISE A HANGFIRE AT THE FLAME ARRESTER ✘ YES NO
A.4 PROCESS DATA
A.4.1 MEDIUM OR MEDIUM MIXTURE WATER/MOGAS/KERO/GASOIL
A.4.2 ✘ CHEMICAL STABLE CHEMICAL UNSTABLE UNKNOWN
A.4.3 EXPLOSION GROUP ✘ UNKNOWN
IIB1 IIB2
IEC (MESG*in mm) I (>=1,14) IIA (>0,9) (>=0,75) IIB3 (>=0,6
(>=0,85)
IIB (>=0,5) IIC (<0,5)
G.M. C (>=0,65) B (>=0,28)
NEC (MESG*in mm) D (>=0,9)
(>=1,12)
A.4.4 DENSITY 2,17-3,92 Kg/m3 (0,58 kg/m3 water)
A.4.5 OPERATING PRESSURE ATM
AAA
A.4.6 FLOW DIRECTION ffffff As Per P&ID
ai a
a
A.4.7 DESIGN PRESSURE ri 25 mbarg
eirr
A.4.8 OPERATING TEMPERATURE
Nee 37,5 °C
°N
A.4.9 MAXIMUM OPERATING °°
N
TEMPERATURE 55 °C
A.4.10 MAXIMUM FLOW RATE 11,4 SCFM
A.4.11 MAXIMUM ALLOWABLE PRESSURE DROP 5 mbarg
A.4.12 TANK NOZZLE SIZE 2"
A.4.13 CORROSION ALLOWANCE
A.5 MECHANICAL AND DEVICE CHARACTERISTICS
A.5.1 DESIGN
✘ DEFLAGRATION
END OF LINE SHORT TIME BURNING ENDURANCE BURNING UN

IN-LINE DEFLAGRATION STABLE DETONATION UNSTABLE DETONATION UN


UNIDIRECTIONAL BI-DIRECTIONAL
A.5.2 CONNECTION 2" Class 150 RF
A.5.3 MATERIALS
BODY DUCTILE IRON ✘ C-STEEL STAINLESS STEEL OTHER
INTERNALS DUCTILE IRON C-STEEL ✘ STAINLESS STEEL OTHER

NOTES
(1) Internal & External painting/coating shall be as per Project Specification R1111-SPC-PP-00-005
(2) All missing data shall be filled by vendor
R1111-DSH-ME-03-036
0
9/9

/GASOIL
ine
028
ATEX100A
03-004

TER) 5 °C
MER) 55 °C
20 % - 80%
286,3 mm
100 mm
410 m
160 Km/ hr
ZONE II

N/A

GAS/KERO/GASOIL

IIB3 (>=0,65)

7-3,92 Kg/m3 (0,58 kg/m3 water)


TM
s Per P&ID
mbarg
°C

CFM
g
"

UNKNOWN

UNKNOWN

0 RF
ect Specification R1111-SPC-PP-00-005