Beruflich Dokumente
Kultur Dokumente
CRACKING ISSUE
PHÂN TÍCH ĐÁNH GIÁ VẤN ĐỀ NỨT SÀN
CTC Department
PhD. NGUYEN HUU THANH
CONTENTS
CTC Department
PhD. NGUYEN HUU THANH
Architecture
►Elevation 1 – Block A
►Elevation 1 – Block B
CTC Department
PhD. NGUYEN HUU THANH
Concrete slab inspection
► Inspection Observations
?
CTC Department 26/11
III. ANALYSIS FOR REASONS OF CRACKING
Phân tích lý do nứt
CTC Department
PhD. NGUYEN HUU THANH
Possible reasons of crack in concrete
● Step 1: DW construction
● Step 2: first excavation
● Step 3: 1st shoring sys installation
● Step 4: second excavation
● Step 5: 2nd shoring sys installation
● Step 6: third excavation
● Step 7: bottom basement slab casting
● Step 8: uninstall second shoring sys
● Step 9: 1st basement slab casting
● Step 10: uninstall first shoring sys
● Step 11: ground floor slab casting
Ux
Ry
Uz
►Material model
Slab
Diaphragm wall
Shear wall
Column
Enforced
displacement
Imposed displacement
applied to the edge of
the slab
Diaphragm wall
Column
Imposed displacement
Imposed displacement
applied to the edge of
the slab
Cracking
region
Cracking
region
Cracking
region
Temperature Temperature
increasing phase decreasing phase
(hydration) (dissipation phase)
Non-restrained concrete
No crack arise
Wall poured on
hardened foundation
Diaphragm
Wall Infill concrete
constructed casting BxH = 73 x 35 m
Restrain
boundary
Infill concrete
Diaphragm casting
Wall
constructed
►FE models
Temperature
change applied
to the slab part
BLOCK A BLOCK B
Cracking
region
Cracking
region
7
Po - Pr
Po 6
RP = = 0.114 =11.4%
Po
Pr
5
Eo - Er
Load factor, LF
4
Eo
RE = = 0.571 = 57.1%
Eo
3
2
Origin-Slab
Er Cracked-Slab
1
0
0 50 100 150 200
Deflection, m m
Po 4.5 Po - Pr
4
RP = = 0.138 =13.8%
Pr Po
3.5 Eo
Load Factor, LF
3 Eo - Er
2.5
RE = = 0.623 = 62.3%
Eo
2
1.5
Er Origin-Slab
1
Cracked-Slab
0.5
0
0 50 100 150 200 250
Deflection, m m
CTC Department
PhD. NGUYEN HUU THANH
Conclusions
CTC Department
PhD. NGUYEN HUU THANH
ASSESS EARLY THERMAL AND SHRINKAGE
CRACK USING BS AND EURO CODES
ε T = αT ,c × ∆T
► ∆t : Temperature change
Variation of air temperature, HCM 22~34 °C
Temperature due to cement hydration
Total temperature change normally be ~25 °C
Shrinkage strain
Drying shrinkage strain
εcd(t) = βds(t, ts) . kh . εcd,0 = 0.0326 x 0.75 x 0.24 x 10-3 = 5.868 x 10-6