Sie sind auf Seite 1von 74

ANALYSIS AND ASSESSMENT ON SLAB

CRACKING ISSUE
PHÂN TÍCH ĐÁNH GIÁ VẤN ĐỀ NỨT SÀN

KHU NHÀ Ở CAO TẦNG 381 BẾN CHƯƠNG DƯƠNG


Aug 2011

CTC Department
PhD. NGUYEN HUU THANH
CONTENTS

1. Introduction of Ben Chuong Duong project

2. Slab cracking – Site inspection

3. Analysis for reasons of cracking

4. Conclusions for cracking reason and slab capacity


reduction
5. Assess the thermal and shrinkage crack in internal design
codes

CTC Department 2/11


I. Introduction of Ben Chuong Duong High-rise
Apartment Project
Giới thiệu về dự án Khu Nhà Ở Cao Tầng Bến Chương Dương

CTC Department
PhD. NGUYEN HUU THANH
Architecture

► Two highrise buildings A and B


2 basements and 24 upper floors
Reinforced concrete structure
Diaphragm wall, Bored pile foundation

CTC Department 4/11


Plans

► Ground Floor – Block A BxH = 73 x 35 m

CTC Department 5/11


Plans

► 1st Basement Floor – Block A BxH = 73 x 35 m

CTC Department 6/11


Plans

► Ground Floor – Block B BxH = 52 x 63 m

CTC Department 7/11


Plans

► 1st Basement Floor – Block B BxH = 73 x 35 m

CTC Department 8/11


Sections

►Elevation 1 – Block A

CTC Department 9/11


Sections

►Section B-B – Block A

CTC Department 10/11


Sections

►Elevation 1 – Block B

CTC Department 11/11


Construction Schedule

►Construction started day: 10/08/2009

►2th basement floor concrete casting: 19/01/2010

►1st basement floor concrete casting: 09/01/2010

►Ground floor concrete casting: 27/03/2010

►Basement structure finished: 24/05/2010

CTC Department 12/11


II. SLAB CRACKING - SITE INSPECTION
Nứt sàn – Kiểm tra hiện trường

CTC Department
PhD. NGUYEN HUU THANH
Concrete slab inspection

► Site inspection team


Nguyễn Mạnh Hùng
Nguyễn Văn Thành
► Inspection contents
Measure concrete strength
Record visible crack flaws on slab surfaces
► Inspection area
1st Basement floor
• Bottom surface
• Top surface
Ground floor
• Bottom surface
• Top surface

CTC Department 14/11


Observed Cracking Layouts

► 1st Basement floor Block A – Top surface

CTC Department 15/11


Observed Cracking Layouts

► 1st Basement floor Block A– Bottom surface

CTC Department 16/11


Observed Cracking Layouts

► Ground floor Block A – Top surface

CTC Department 17/11


Observed Cracking Layouts

► Ground floor Block A – Bottom surface

CTC Department 18/11


Observation of Cracking

► Crack flaws – Block A

CTC Department 19/11


Observed Cracking Layouts

► 1st Basement floor Block B – Top surface

CTC Department 20/11


Observed Cracking Layouts

► 1st Basement floor Block B – Bottom surface

CTC Department 21/11


Observed Cracking Layouts

► Ground floor Block B – Top surface

CTC Department 22/11


Observed Cracking Layouts
► Ground floor Block B – Bottom surface

CTC Department 23/11


Observation of Cracking

► Crack flaws – Block B

CTC Department 24/11


Site inspection results

► Inspection Observations

Concrete strenght has average value of 49.2MPa


Several cracks were found on the slab
The cracks distribute at the boundary area of the slab, started form the edge
and propagated to center area
Some cracks developed accross the slab
Many cracks went through the slab thickness
Many cracks have width over the standard limit

CTC Department 25/11


Site inspection results

?
CTC Department 26/11
III. ANALYSIS FOR REASONS OF CRACKING
Phân tích lý do nứt

CTC Department
PhD. NGUYEN HUU THANH
Possible reasons of crack in concrete

►Crack is normaly due to moment, shear force, torsion,


imposed displacement
►Crack may arise from shrinkage or expansive chemical

►Crack may be caused by temperature change

Each of above causes will be covered in next sections

CTC Department 28/11


CRACK DUE TO LOADING

Nứt do tải trọng

CTC Department 29/11


Crack due to moment, shear, torsion

►Crack arise by internal moment, shear force,

Crack arise when applied


load is over the design crack
limit
Crack normally arise at
location of high magnitude of
internal force

CTC Department 30/11


Crack due to moment, shear, torsion

►Crack may arise due to internal moment, shear force,


torsion caused by loading. However, in this case
The design load has not been completely applied in construction stage
The observed cracks do not locate at the maximum internal force
locations
The direction of crack is not perpendicular to bending normal stress

►Conclusion is that the crack is not caused by the design


load

CTC Department 31/11


CRACK DUE TO IMPOSED DISPLACEMENT

Nứt do chuyển vị cưỡng bức

CTC Department 32/11


Causes of imposed displacement

►Movement of diaphragm wall cause Imposed


displacement to basement slab
Settlement of diaphragm wall
Displacement and rotation of DW at basement floor level
Basement construction method, shoring system removal schedule

►Require monitoring system to monitor the settlement of


the building and to control the crack
►Due to lacking of actual measurement data, the
imposed displacement will be determined by numerical
analysis

CTC Department 33/11


Causes of imposed displacement

►Need to find inposed displacement at the 1st basement floor


level

CTC Department 34/11


Analysis to obtain imposed displacement

►Stage construction of basement


Diaphragm wall construction
Excavation
Shoring system instalation
Basement floors casting
Shoring system remove

►Finite Element modeling and analysis

►Analysis results of displacement of diaphragm wall

CTC Department 35/11


Causes of imposed displacement

► Basement construction scheldule

● Step 1: DW construction
● Step 2: first excavation
● Step 3: 1st shoring sys installation
● Step 4: second excavation
● Step 5: 2nd shoring sys installation
● Step 6: third excavation
● Step 7: bottom basement slab casting
● Step 8: uninstall second shoring sys
● Step 9: 1st basement slab casting
● Step 10: uninstall first shoring sys
● Step 11: ground floor slab casting

CTC Department 36/11


Analysis results of imposed displacement

►Maximum imposed displacement results


Ux = 36.25mm
Uz = 10.895mm
Ry = 1/128

Ux

Ry

Uz

CTC Department 37/11


Analysis for crack due to imposed displacement

►Diaphragm wall and slab modeling

►Enforced displacement applied

►Material model

►Analysis for crack

CTC Department 38/11


Analysis for crack due to imposed displacement

►Finite Element model – 1st Basement slab Block A

Slab

Diaphragm wall

Shear wall
Column

Enforced
displacement

CTC Department 39/11


Analysis for crack due to imposed displacement

►Finite Element model – 1st Basement slab Block A

Imposed displacement
applied to the edge of
the slab

CTC Department 40/11


Analysis for crack due to imposed displacement

►Finite Element model – 1st Basement slab Block B

Diaphragm wall

Slab Shear wall

Column

Imposed displacement

CTC Department 41/11


Analysis for crack due to imposed displacement

►Finite Element model – 1st Basement slab Block B

Imposed displacement
applied to the edge of
the slab

CTC Department 42/11


Resulting crack due to imposed displacement

►1st basement slab Block A

Cracking
region

CTC Department 43/11


Resulting crack due to imposed displacement

►1st basement slab Block A Crack flaw

CTC Department 44/11


Resulting crack due to imposed displacement

►1st basement slab Block B

Cracking
region

CTC Department 45/11


Resulting crack due to imposed displacement

►1st basement slab Block B

Cracking
region

CTC Department 46/11


Observation from crack analysis

►Imposed displacement is a reason causing crack

►Basement method and scheldule of shoring system remove


can result in crack in the slab.
►Crack region and direction derived from the analysis of the
slab under imposed displacement do not quite match with the
site inspection results.
►Imposed displacement is secondary cause of crack.

CTC Department 47/11


CRACK DUE TO TEMPERATURE AND
SHRINKAGE
Nứt do nhiệt độ và co ngót

CTC Department 48/11


Early thermal strain

►Internal temperature gradient


Usually arise in massive pour of concrete
Heating form hydration of cement
Low thermal conductivity of concrete
Difference of temperature between in and out side of concrete mass

►Temperature increasing phase


Conrete has not hardened, low elastic modulus, compression stress
dissipation easily.

►Temperature decreasing phase.


Concrete hardened but has low strength, tensile stress exceed tensile
strength, cracking arise.

CTC Department 49/11


Early thermal strain

►Internal temperature gradient

Temperature Temperature
increasing phase decreasing phase
(hydration) (dissipation phase)

CTC Department 50/11


Early thermal strain and shrinkage

►External restrain during cooling


εT = ∆L/L

Non-restrained concrete
No crack arise

Wall poured on
hardened foundation

One way restrained concrete


Crack arise at haft or one
third of span
CTC Department 51/11
Infill restrain

► 1st Basement Floor – Block A Restrain


boundary

Diaphragm
Wall Infill concrete
constructed casting BxH = 73 x 35 m

CTC Department 52/11


Infill restrain

► 1st Basement Floor – Block B BxH = 73 x 35 m

Restrain
boundary

Infill concrete
Diaphragm casting
Wall
constructed

CTC Department 53/11


FE analysis on thermal and shrinkage cracking

►FE models
Temperature
change applied
to the slab part

BLOCK A BLOCK B

►Temperature variation applied to the slab


Initial temperature 50 °C
Final temperature 25°C
Temperature change ∆T = 25°C

CTC Department 54/11


Resulting crack due to thermal and shrinkage

►Basement slab Block A


Cracking
region

CTC Department 55/11


Resulting crack due to imposed displacement

►Basement slab Block A Crack flaw

CTC Department 56/11


Resulting crack due to imposed displacement

►Basement slab Block B

Cracking
region

CTC Department 57/11


Resulting crack due to imposed displacement

►Basement slab Block B

Cracking
region

CTC Department 58/11


Observation from crack analysis

►Early thermal and shrinkage are dominant reasons of crack in


concrete slab.
►Restrained boundary and infill casting are main factors
resulting in crack in the slab.
►Crack region and direction derived from the analysis of the
slab under temperature change have good agreement with the
site inspection results.
►It can be concluded that early thermal and shrinkage in
restrained slab is mayor cause of crack.

CTC Department 59/11


ANALYSIS FOR STRENGTH DEGRADATION OF
CRACKED SLAB
Phân tích sự giảm sức chịu tải của sàn bị nứt

CTC Department 60/11


Analysis for strength degradation

►Non-linear analysis of the slab structure under uniform


loading is carried out in subsequent to thermal crack step to
determine peak load value.
►Uncracked slab is also analyzed for peak load.

►The two peak load values are compared.

►The differences of peak load and slop of Load-defection


curves give the strength and stiffness degradation.

CTC Department 61/11


Analysis for strength degradation

►Non-linear analysis of the slab structure under uniform load


– Block A

7
Po - Pr
Po 6
RP = = 0.114 =11.4%
Po
Pr
5
Eo - Er
Load factor, LF

4
Eo
RE = = 0.571 = 57.1%
Eo
3

2
Origin-Slab
Er Cracked-Slab
1

0
0 50 100 150 200
Deflection, m m

CTC Department 62/11


Analysis for strength degradation

►Non-linear analysis of the slab structure under uniform load


– Block B
5

Po 4.5 Po - Pr
4
RP = = 0.138 =13.8%
Pr Po
3.5 Eo
Load Factor, LF

3 Eo - Er
2.5
RE = = 0.623 = 62.3%
Eo
2

1.5
Er Origin-Slab
1
Cracked-Slab
0.5

0
0 50 100 150 200 250
Deflection, m m

CTC Department 63/11


IV. CONCLUSIONS
KẾT LUẬN

CTC Department
PhD. NGUYEN HUU THANH
Conclusions

►Early thermal and shrinkage strains in the concrete pour


casted into infill restrained area are the main reasons for the
crack in the concrete slab.
►Imposed displacement caused by basement construction
method is potential cause of cracking in the slab. It is
assessed to be secondary reason for the crack being
considered. It participate in development of the advance
early thermal and shrinkage cracks.
►The load capacity and stiffness of the cracked slab reduces
to an order of 15% and 60%, respectively.

CTC Department 65/11


V. ASSESS THERMAL AND SHRINKAGE CRACK IN
INTERNATINAL DESIGN CODE
Đánh giá nứt do nhiệt độ và co ngót trong tiêu chuẩn thiết kế

CTC Department
PhD. NGUYEN HUU THANH
ASSESS EARLY THERMAL AND SHRINKAGE
CRACK USING BS AND EURO CODES

CTC Department 67/11


Early thermal strain and shrinkage

►Thermal strain of concrete

ε T = αT ,c × ∆T
► ∆t : Temperature change
Variation of air temperature, HCM 22~34 °C
Temperature due to cement hydration
Total temperature change normally be ~25 °C

► α : Thermal expansion coefficient


Depend on aggregate of concrete (Table 3.2, BS8110 – 2)
Granite aggregate: α = 10 x 10-6 / °C

► R : restrain factor (0~1) (Table 3.3, BS8110 – 2)

CTC Department 68/11


Early thermal strain and shrinkage

►Thermal strain coefficients

CTC Department 69/11


Early thermal strain and shrinkage

►Shrinkage strain of concrete

► εcd : drying shrinkage strain ► εcd : autogenous shrinkage strain

CTC Department 70/11


Early thermal strain and shrinkage

►Drying shrinkage strain

CTC Department 71/11


Early thermal strain and shrinkage
►Calculations of thermal and shrinkage strains
Thermal strain
εT = 25 x 10 x 10-6 = 25 x 10-5

Shrinkage strain
Drying shrinkage strain
εcd(t) = βds(t, ts) . kh . εcd,0 = 0.0326 x 0.75 x 0.24 x 10-3 = 5.868 x 10-6

Autogenous shrinkage strain


εca(t) = βas(t) εca(∞) = 0.411 x 75 x 10-6 = 30.825 x 10-6

Total shrinkage strain


εcs = εcd + εca = (5.868 + 30.825) 10-6 = 36.693 x 10-6

Total of thermal and shrinkage strains


25 x 10-5 + 3.67 x 10-5 = 28.67 x 10-5

Slab with 40m length can have crack width up to 1cm


CTC Department 72/11
Methods to avoid early thermal and shrinkage crack

►Reduce temperature in concrete pour during casting time

►Use low shrinkage concrete

►Apply appropriate curing methods

►Provide reinforcement with small diameter and distance

►Release the restrain to the concrete after concrete


hardening
►Design construction joint to reduce the length of structure

CTC Department 73/11


CTC Department 74/11

Das könnte Ihnen auch gefallen