Ref :7.1.

1 Random rubble masonary with hard stone in foundation & plinth in CC-1:6 C:M - 1:6
Vol1
Code Description Unit Quantity Rates Amount
Details for 1 Cu.m
Material
1157 Stone for masonary work cum 1 750 750
1154 Through & bond stone size 24*24*39 cm 100 nos 0.07 5000 350

3.11 cement bag 1.65 250 412.5


sand cum 0.35 1500 525

Total Material 2037.5

Labour
0155' Mason Days 0.75 600 450
0115' M/C Days 1.4 350 490

Total Labour 940

Machinery

Total (Material+Labour+Production) 2977.50


Add 10% for Expenses 148.875
Add 20% Contractor's Profit 1488.75

Cost of 1 Cu.m 4615.13


Say Rs. 4615.00
Ref :7.1.1 Random rubble masonary with hard stone in foundation & plinth in CC-1:6: C:M - 1:6
Vol1
Code Description Unit Quantity Rates Amount
Details for 1 Cu.m
Material
1157 Stone for masonary work cum 1 1100 1100
1154 Through & bond stone size 24*24*39 cm 100 nos 0.07 5000 350

3.11 cement bag 1.65 250 412.5


sand cum 0.35 2000 700
Total Material 2562.5

Labour
0155' Mason Days 0.75 600 450
0115' M/C Days 1.5 350 525

Total Labour 975

Machinery

Total (Material+Labour+Production) 3537.50


Add 17% for Expenses 601.375
Add 20% Contractor's Profit 707.50

Cost of 1 Cu.m 4846.38


Say Rs. 4846.00