Beruflich Dokumente
Kultur Dokumente
UNIVERSITY OF MORATUWA
BY
N. LOGESWARAN
Q@t&QQ.Sato a^esco. e . ^ a ©
©©3(3^
BY
N. LOGESWARAN
PERMANENT
R KK K M !.
University of Moratuwa
November 1994
t
63058
CONSTRUCTION fi-STfJUCTUR^
ENGINEERING
O E P A R T ^ E M T OF CIVIL E N G I N E E R S
UNlVERSiTI © f MORATUWA.
CONTENTS
Page
ACKNOWLEDGEMENTS Hi
ABSTRACT iv
LIST O F TABLES v
ABBREVIATIONS vi
CHAPTER 1 - INTRODUCTION 1
2.1 Introduction 6
2.2 Building procurement methods in practice in the U.K. 7
2.3 Types of contracts in relation to the traditional 7
method of procurement in the U.K.
2.4 Types of contracts in relation to the alternative 19
method of procurement in the U.K.
2.5 Types of contracts in use in Sri Lanka 33
3.1 Introduction 34
3.2 Standard form of conditions of contract 34
3.3 Conditions of contracts in practice in the U.K. 35
3.4 Historical background of the JCT conditions of contract. 50
3.5 The general conditions of government cotracts for building and 56
civil engineering works
4.1 Introduction 58
4.2 What is FIDIC 58
4.3 FIDIC conditions of contract 60
4.4 FIDIC conditions of contract (First Edition - August 1957) 62
4.5 FIDIC conditions of contract (Second Edition - July 1969) 63
4.6 FIDIC conditions of contract (Third Edition - March 1977) 63
4.7 FIDIC conditions of contract (Fourth Edition - September 1987) 64
4.8 Application of FIDIC conditions of contract for 67
building construction works
5.1 Introduction 73
5.2 Building construction industry in Sri Lanka 73
5.3 ICTAD and its role in the local construction industry 82
5.4 ICTAD conditions of contract 87
5.5 Conditions of contracts in use for local building construction work 89
5.6 Need for a separate conditions of contract for building construction works 91
6.1 Introduction 93
6.2 Analysis of data from the survey 93
7.1 Introduction 99
7.2 Presentation of the comparison of selected conditions of contracts 100
7.3 Modifications proposed to the ICTAD 89 101
REFERENCES
INTERVIEWS A N D DISCUSSIONS
APPENDICES
Appendix A
Appendix B
ii
ACKNOWLEDGEMENTS
I wish to take this opportunity to express my sincere thanks to my Supervisor, Mr. M.W.J.A.De Silva,
Senior Lecturer, Department of Civil Engineering, University of Moratuwa for his valuable guidance
throughout the research work.
I would also like to extend by gratitude to the Department of Civil Engineering, University of Moratuwa
for granting opportunity to follow the post graduate degree course in construction management.
Special thanks should go to Mr. Anura Nanayakkara, Assistant Director (ICTAD) who assisted me in
many ways during the literature survey and the questionnaire survey.
Finally, I would like to thank all those who assisted in numerous ways, in particular, staff of the
Department of Civil Engineering, University of Moratuwa, those who have responded to my
questionnaire survey, those who allocated their valuable time for interviews and discussions and all others
who provided invaluable information and assistance to make this research work a success.
N. LOGESWARAN
November 1994
iii
ABSTRACT
The objective of this research project is to review the ICTAD conditions of contract suitable for local
building construction works. The Government of Sri Lanka had approved the said document in August
1988 to use in the state sector for both building and civil engineering construction works, which was
prepared by the ICTAD, commonly known as the 'ICTAD conditions of contract'.
Since the building and civil engineering construction works have some differences in their character and
contract administration, which are described in chapter 4, the use of one document is not a desirable
approach given the diversity of practices and traditions prevailing in both works.
The ICTAD conditions of contract is a document far from perfect and there are plenty of scope for
improvements, because this was prepared based on the FIDIC conditions of contract (Third edition) which
is 17 years old document. Use of a single document to cover the both construction works is not a
practice in the international construction scene.
By considering all the above action was taken to review the ICTAD conditions of contract mainly through
literature survey, questionnaire survey and the comparison of selected conditions of contracts.
Chapter 7 gives the necessary modifications to the ICTAD conditions of contract. ICTAD should also
take necessary steps to review its conditions of contract for building construction works in association
with the ACCSL, the Institute of Architects, the Institution of Engineers and the Institute of Quantity
Surveyors.
iv
LIST O F TABLES
Page
v
ABBREVIATIONS
vi
22. ICE - Institution of Civil Engineers.
23. ICTAD - Institute of Construction Training And Development.
24. ICTAD 89 - ICTAD Conditions of Contract for Works of Building and Civil Engineering -
Sri Lanka. Revised Edition, January 1989.
25. IDA - International Development Agency.
26. IFAWPCA - International Federation of Asian and Western Pacific Contractors' Associations.
27. IMF - International Monitory Fund.
28. IOB - Institute of Builders.
29. JCLI - Joint Council for Landscape Industries.
30. JCT - Joint Contracts Tribunal.
31. JCT 80 - Joint Contracts Tribunal Standard Form of Building Contract 1980 Edition.
(Local Authorities with Quantities.)
32. JV - Joint Venture.
33. MMRB - Method of Measurement for Roads and Bridge Works.
34. NEC - New Engineering Contract.
35. NFBTE - National Federation of Building Trades Employers.
36. PIP - Public Investment Programme.
37. PWD - Public Works Department.
38. RIBA - Royal Institute of British Architects.
39. RICS - Royal Institution of Chartered Surveyors.
40. SBCC - Scottish Building Contract Committee.
41. SEC - State Engineering Corporation.
42. SLCC - Sri Lanka Construction Consortium.
43. SMM - Standard Method of Measurement.
44. UDA - Urban Development Authority.
45. U.K. - United Kingdom.
46. UNDP - United Nations Development Programme.
47. WB - World Bank.
vii
CHAPTER - 1
CHAPTER 1 - INTRODUCTION
1.1 Background
Conditions o f contract for works of building and civil engineering - Sri Lanka was prepared by
the Institute of Construction Training And Development (ICTAD) and the Government of Sri
Lanka had approved the adoption of the said conditions of contract (Commonly referred as
I C T A D conditions of contract) for state sector construction activities since August 1988. It can
be seen clearly that the ICTAD conditions of contract is very similar to the International
for works of civil engineering construction (Third edition), March 1977 (Commonly referred as
FIDIC conditions of contract third edition) except few modifications to suit local conditions.
In the United Kingdom(U.K.), there are different standard conditions of contracts used for
building and civil engineering works. At the same time there are instances when the FIDIC
conditions of contract (Third edition) which was specifically developed for civil engineering
One could argue whether it is right to use one standard conditions of contract for both building
and civil engineering works as there are some differences in the construction and administration
of these two types. On the other hand, as the ICTAD conditions of contract is based on
conditions of contract specifically applicable for civil engineering works, the argument seems
justifiable.
The private sector consultants in Sri Lanka have been slow to adopt the I C T A D conditions of
contract for building works. Different conditions of contracts are being used by different
consultants in the private sector. Some are modified Joint Contracts Tribunal (JCT) conditions
of contract and some are Royal Institute of British Architects (RIBA) conditions of contract.
1
A s there are large scale investments by the private sector in the building industry it is very
important to have a standard conditions of contract acceptable to private sector consultants in Sri
Lanka.
Therefore, it is considered appropriate to undertake a study to look into the problems of using
I C T A D conditions of contract for both building and civil engineering works. Necessary action
can be initiated by the relevant authorities if a change is required for the development of the
construction industry.
1.2 Objectives
(i) T o investigate the available procurement methods and types of conditions of contracts for
(ii) T o assess the applicability of the ICTAD conditions of contract for building construction
works.
(iii) T o propose revisions or modifications to the ICTAD conditions of contract to suit local
1.3 Methodology
The methodology adopted to achieve the objectives stated in 1.2 are briefly described
below.
(i) L i t e r a t u r e survey
A detailed literature survey was carried out by referring books, journals, publications etc.
2
(ii) S t u d y o f various conditions of contracts a n d comparison
identify the differences of those conditions for building and civil engineering works.
(iii) Q u e s t i o n n a i r e survey
(iv) Interviews
Senior professionals in the industry were interviewed for their views on the acceptability
there is a need for a different conditions of contract for building construction works.
1.4 G u i d e to t h e R e p o r t
Chapter 1 - Deals with the reasons to undertake this study specifying the problem and
Chapter 2 - Deals with various procurement methods and types of contracts for building
Chapter 3 - Deals with various conditions of contracts for building construction works used
in the U.K. for different types of contracts and historical background of the J C T
conditions of contract.
3
Chapter 4 - Deals with historical development of FIDIC conditions of contract and its
Chapter 5 - Deals with the history of building construction industry from ancient times in Sri
Lanka, role of ICTAD and ICTAD conditions of contract together with its
Chapter 7 - Deals with the comparison of conditions of contracts and modifications proposed
Chapter 8 - Covers the conclusions and recommendations made from the research study.
1.5 S u m m a r y o f M a i n Findings
From this research work it is identified that various procurement methods and types of contracts
are available in the international construction scene to cover the various value of works and
scope of works for the building construction works. To achieve a balanced contract management
these are also different standard conditions of contracts available for building construction
works.
In Sri Lanka, the I C T A D 89 is now mostly used for all building construction works, except in
some private organisations, which is based on the FIDIC 3 . From the survey it is found that
most of the professionals involved in the building construction works are preferable to use
FIDIC 3 (now FIDIC 4) rather than ICTAD 89 due to some errors in wordings, headings,
changes made in Part I and Part II. Another important factor is that FIDIC 3 is 17 years old
There are also some notable differences found in the character and contents of building and civil
4
engineering construction works.
Most of the professionals have indicated very few ICTAD 89 clauses for modification which are
general and not specific for building construction works. The notified clauses are 1, 15, 5 1 , 5 2 ,
5 6 , 6 0 , 67 and 7 0 .
There is a considerable outcome from the comparison of selected conditions of contracts rather
than literature survey, questionnaire survey and interviews. As a result of this comparison it is
identified that 25 clauses of the ICTAD 89 can be used without any modification, 12 clauses of
the I C T A D 89 have to be replaced fully by the relevant clause of FIDIC 4 and 35 clauses of the
I C T A D 89 have to be modified/revised.
5
CHAPTER - 2
CHAPTER 2- PROCUREMENT METHODS AND TYPES O F CONTRACTS FOR
2.1 Introduction
The main aim of this chapter is to study the various types of procurement methods and types of
contracts in use in the U.K. and to survey the types of contracts in use in Sri Lanka for building
construction works. In addition, advantages and disadvantages of various types of contracts will
also be studied.
Building construction today often entails complex and intensive site operations, with huge sums
of money locked into development programmes. Contractors may have partial or total design
responsibilities, and in addition may undertake demanding management and co-ordinating roles.
This change of emphasis, together with the increasing range and scale of work, has inevitably
led to a proliferation of alternative forms of building contract. The three most important
considerations for a client are usually cost, time and quality. The business of building
procurement invariably calls for some compromise or conscious balancing of these priorities.
The following factors decide the type of procurement method and type of contract to adopt for
any building project, since the building project may be a new multi-million warehouse or for
reinstating a church damaged by fire or for constructing a luxury hotel with sophisticated
(iv) Whether there is enough time to prepare full information at tender stage.
(vii) Whether the employer is able to state his requirements in detail before work commences.
(viii) Whether the employer needs to know a precise contract sum before work commences.
The choice of form of contract cannot usually be considered until the procurement method and
the type of contract have been established. There are two main methods of procurement
currently practiced in the U . K . , which is likely to prove the most appropriate in a given situation
and will depend upon how and where responsibility for design is to be placed, how the work is
to be co-ordinated, and on what price basis the contract is to be awarded. These procurement
methods are
U.K.
From the early 19th century until about the 1950 s, the ways by which building projects were
promoted and carried out in the U.K. conformed to straightforward and well tried procedures.
If the project was small, the building owner (or 'employer' as he is often called) employed a
7
building contractor to design and construct the building for him. Because buildings generally
conformed to a well-defined pattern, contractors had within their organisation the full range of
In the case of larger projects the employer appointed an architect to design the building,
and he then produced drawings and specification. If the architect considered it necessary (and
the employer approved), he then appointed a quantity surveyor to prepare a bill of quantities.
Then, on the basis of either the specification and drawings or the bill of quantities, contractors
were invited to tender in competition to carry out the work. Usually the lowest tenderer was
Since the mid - 1940 s the architect's nomination and/or appointment of the quantity
surveyor has been gradually superseded by direct appointment by the employer, sometimes
before the selection of the architect and, in some cases, the latter's selection is made on the
The traditional methods of building procurement are still widely used and their respective
Normally there are mainly two types of contracts under the traditional procurement
The main difference between the above is the transfer of financial risk to the employer
or the contractor.
In fixed price contracts, the contractor is paid for work done in accordance with rates,
8
In cost reimbursement contracts, the contractor is paid the actual ascertained cost incurred
by him under pre-defined heads plus a fee to cover his administration and profit.
(i) Based on bills of firm quantities and drawings - (Bill of quantities type lump sum
contract).
(ii) Based on bills of approximate quantities and drawings - (Bill of quantities type measure
The cost reimbursement contracts may also have few types. All these will be described
in detail in 2 . 3 . 1 , 2 . 3 . 2 , 2 . 3 . 3 , 2 . 3 . 4 and 2 . 3 . 5 .
Sum Contract)
The employer appoints an architect to prepare a design and, upon virtual completion of the
design, the quantity surveyor prepares a bill of quantities based upon the architect's drawings
and specification. Contractors are invited to price the bill of quantities and submit competitive
tenders for carrying out the work. The contractor submitting the lowest tender is usually
(i) That both the quantities and the unit rates in the bill form part of the contract.
9
(ii) That completion of the design precedes the signing of the contract.
(iii) The lump sum contract can be employed either with or without a bill of quantities.
Advantages
(i) Both parties have a clear picture of the extent of their respective commitments.
(ii) The unit rates in the bills provide a sound basis for the valuation of any variations to the
design.
Disadvantages
(i) The length of time taken in the design of the project, and in the preparation of the bill
of quantities.
(ii) The problem of dealing with those variations which are so fundamental or extensive as
to change the character of the remainder of the work or the conditions under which it has
This method is largely similar to 2.3.1 (Based on bills of firm quantities and drawings), except
that the quantities given in the bill are approximate only and are subject to later adjustment.
(i) That only the unit rates form part of the contract.
10
(ii) The signing of the contract and the beginning of work on site may proceed before the
design is complete.
The bill of quantities is normally prepared for the particular project and descriptions of work are
as detailed as in a bill of firm quantities, but the time otherwise required for detailed
measurement of the quantities is saved, the quantities given being estimates of likely
requirements. Sometimes the bill re-uses the quantities which were prepared for an earlier
This type of contract is sometimes regarded as a lump sum contract although it is not strictly so,
there being no total price stated in the contract. In effect, it is very similar to a schedule of
Advantages
(i) Construction on site may begin earlier.
Disadvantages
(i) The bill of quantities cannot be relied upon as giving a realistic total cost at tender stage
and in consequence, the parties to the contract are less certain of the extent of their
commitment.
(ii) The construction works have to be measured completely as actually carried out, which
may prove more costly than to have prepared bills of firm quantities initially.
(iii) The architect may feel less pressure to make design decisions which ought to be taken
at an early stage.
(Ramus, 1989).
11
2.3.3. Based o n D r a w i n g s a n d Specifications - ( L u m p S u m C o n t r a c t )
This method closely resembles that described in 2.3.1 (Based on bills of firm quantities and
drawings), the difference being that no bill of quantities is supplied to tenderers, who have to
This procedure is intended to be used for relatively small works of short duration and for sub
contract works, although it is not unknown for quite large contracts to be tendered for on this
(i) That tenderers are supplied only with complete working drawings and a full specification.
(ii) That completion of the design must precede the signing of the contract.
The price is often sub divided in relation to phases of work to facilitate stage payments.
In some contracts there will be some adjustments in price in labour and material as agreed by
Advantages
(i) The time required for the preparation of tender documents is reduced, as the time -
(ii) Both parties can have a clear picture of their respective commitments at the time of
Disadvantages
(i) N o breakdown of the tender sum is immediately available (Although the tenderers may
be asked to provide a contract sum analysis, either as a part of their tender submission
12
or subsequently).
(iii) There is little, if any, control over the percentage rates for additions for overheads and
profit to the prime cost of labour, materials and plant elements in day works. The
tenderers are normally asked to state percentage rates to be used in the event of day
works arising. Where such rates have no effect on the tender sum, there is little
(iv) Any changes of works by the employer during the construction phase is restricted.
(Ramus, 1989).
approximate quantities and drawings), tenders being based upon a schedule of rates such as
standard schedule, 'ad hoc' schedule, and bill of quantities from previous contracts. A particular
advantage arising from its use is that it allows for a contract to be signed and work to start on
site when the design is only in outline form, and in consequence the pre-contract period is
reduced considerably. The tenderer is requested to submit a unit price or rate against a list of
work items typical of those expected for the work. Outline drawings, and sometimes a soil
report, are provided together with approximate quantities. Payment to the contractor for the
actual work done is made on a similar basis to a bill of quantities contract with items measured
(ii) when the details of the design have not yet been worked out or there is considerable
13
(iii) when time is short; and
(iv) where a limited range of repetitive work is required to be carried out, such as external
redecoration of an estate of houses. The contractor tenders on the basis of unit rates,
which are to remain current for the stated period which is usually one year or the
(a) S t a n d a r d Schedule
A standard schedule lists under appropriate trade headings all the items likely to arise in any
construction project, with a unit rate against each item. Tenderers are asked to tender
percentage additions (or deductions) to the listed rates, usually by sections or sub-sections, thus
allowing for variations in construction costs since the date of the preparation of the schedule
used.
Advantages
(i) Tenderers using a particular schedule often soon become familiar both with the item
descriptions and the rates and are able to assess percentage adjustments relatively easily.
Disadvantages
(i) In comparing and assessing a range of tenders, the employer's quantity surveyor has the
task of gauging the effect of a series of variables, making the choice of the most
(ii) The parties are unable to have a precise indication of their respective commitments.
(Ramus, 1989).
This is a schedule specially prepared for a particular project and lists only those items which are
appropriate to that project, including any special or unusual items. An 'ad hoc' schedule may
14
be pre-priced by the employer's quantity surveyor or the rate column may be left blank by the
employer's quantity surveyor for the tenderer to insert individual rates against each item.
Because of the absence of quantities, the latter method makes the comparison and assessment
Advantages
(i) Tenderers are only required to concern themselves with a restricted range of items, thus
(ii) Tenderers are able to obtain a clearer picture of the scope of the work from the items
Disadvantages
(Ramus, 1989).
(C) B i l l o f Q u a n t i t i e s f r o m Previous C o n t r a c t
The bill o f quantities used will normally be for a comparable type of building of similar
constructional form to the proposed project. It is in effect, a pre-priced 'ad hoc' schedule and
will be used in the same way. This is the method of tendering normally used in serial tendering.
Advantages
(i) The time required to prepare tender documents is reduced to the minimum.
15
Disadvantages
(i) The parties are unable to have a precise indication of their respective commitments.
(ii) There may be a considerable discrepancy between the successful tender and the real cost
(Ramus, 1989).
There are three variants of this type of contract, distinguished by the way in which the fee is
calculated. 'Prime Cost' means the total cost to the contractor of purchasing materials, goods
and components, of using or hiring plant and of employing labour, in order to carry out
construction works. Of all the types of contract, this produces the most uncertainty regarding
Tenders contain no total sum and it may be very difficult to form any reliable estimate of the
final cost. It is widely recognized as the most uneconomical type of contract and therefore is
one which normally should be used only in circumstances where none of the other types is
appropriate. Because of the possibility of inefficiency and waste of resources, contracts of this
type need to embody provisions giving the architect/engineer some control over the level of
labour and plant employed. This type of contract is suitable where, to a client, cost is a less
important factor than time. Consequently, a start on site at the earliest possible time may be
financially more advantageous in the long term than a lower final cost of construction which
It should be noted that no site measuring is necessary other than as checks on the quantities of
materials for which the contractor submits invoices, and for purposes of checking nominated
16
The process of calculating and verifying the total prime cost involves a vast amount of
investigation and checking of invoices, time sheets, sub-contractors' accounts, etc., which can
be both tedious and time-consuming. It is therefore in the interests of both the client's quantity
surveyor and the contractor that at the outset a proper system of recording, verifying and valuing
the prime cost is agreed and strictly implemented. In addition, it is vitally important to define
clearly what is intended to be included as prime cost and what is intended to be covered by the
fee.
(ii) when the client wishes to use a contractor who has worked satisfactorily for him before
and who can be trusted to operate efficiently, while being prepared to pay the higher
(v) alteration jobs where there is insufficient time or it is impracticable to produce the
necessary documentation.
Advantages
(i) The time required for preparation of tender documents and for obtaining tenders is
(ii) Work on site may proceed before the detailed design is complete.
Disadvantages
(i) The parties have the least precise indication of their respective commitments.
17
(ii) The cost of construction to the client is likely to be higher than if other types of contract
were to be used.
(iii) The computation and verification of the total prime cost is a long and tedious process.
The contractor is paid a fee equal to an agreed percentage of the prime costs of labour, materials
The outstanding disadvantage (to the client) is that the more inefficient the contractor's
operations are and the greater the waste of resources, the higher the fee paid to the contractor
will be. T o counter this, the percentage is sometimes made to vary inversely as the prime cost.
The contractor is paid a fixed fee, which may be decided on at the initial stage, in addition to
the total prime cost. The only ground on which the fee might be varied is if either the scope
of the work or the conditions of carrying it out were to be materially altered after the contractor
tendered.
A s an incentive to reducing the total prime cost, the agreement provides for a bonus to be paid
to the contractor if the total cost is less than an agreed sum (the 'target') and also a penalty to
The bonus and penalty are commonly 5 0 percent of the difference between the total amounts,
but may be any agreed percentages. The target cost is an estimate of the likely total cost.
18
O d e 3<J»oC&s. § C ' ® ^
The contractor is paid the actual cost of the work plus a fee, with the amount of the fee being
determined by reference to the allowable cost by some form of sliding scale. Thus, the lower
the final cost of the works (Prime cost), the greater will be the value of the fee that the
contractor receives. An incentive then exists for the contractor to carry out the work as quickly
and cheaply as possible, and it does constitute the most efficient of the three types of prime cost
contract.
U.K.
Since the early 1960 s, various alternative ways of promoting and carrying out construction
projects have been devised with varying degrees of success. The reasons why many building
owners and developers considered that the traditional procedures were no longer satisfactory
were
(i) The rapidly spiralling cost of construction meant that large sums of money had to be
(ii) High interest rates meant that the time occupied by the traditional procedures resulted in
(iii) Clients were becoming more knowledgeable on construction matters and were demanding
(Ramus, 1989)
Attention has focused on reducing the time traditionally occupied in producing a design and
19
63058
Another important factor has been bringing the contractor in at an early stage in the design of
a project. The increasing complexity of projects, however led to the realization that it was in
the interests of clients and architects to use the vast amount of knowledge and practical
experience of contractors early in the design process, and that this would make a valuable
There are seven main types of building contracts under the alternative method of procurement.
These are
In this method of procurement, some times referred to as 'turnkey' or 'design and build' or
'design and construct' or 'package deal' or 'all-in' or grass-root contract, the contractor accepts
responsibility for some or all of the design. There should be express reference to this in the
contract, and the extent of design liability should always be set out as clearly as possible.
Unless the contractor states otherwise, it seems that the liability for design is an absolute liability
under which the contractor warrants fitness for the purpose intended.
Sometimes design and build forms limit the design liability of the contractor to the normal
professional duty to exercise reasonable care and skill. Independent consultants engaged by the
20
contractor are therefore under a liability no greater than normal. An indemnity or acceptance
of liability is likely to be worthless unless backed by adequate indemnity insurance, and this is
something that should be checked before a contractor is appointed. Where the contractor does
not have in-house designers and intends to use outside consultants, their identity should be
Design liability can be affected by the extent to which there is reliance on the contractor's skill
and experience. The employer's requirements might be stated briefly and simply, perhaps little
more than a site plan and schedule of accommodation. On the other hand there may be a
document of several hundred pages with precise specifications. The contractor's design input
might be restricted to taking a scheme design supplied by the employer and developing details
Generally it is better to specify in terms of the performance requirement rather than prescribe
in detail, because this leaves the responsibility for design and selection firmly with the
contractor.
It is claimed that design and build contracts offer certainty on the contract sum and bring cost
benefits. The close integration of design and working methods, and the relative freedom of the
contractor to use his purchasing power and the market knowledge most effectively might suggest
this, although it is often virtually impossible to know just how competitive the figures are.
On the matter of speed, it should be possible to ensure a quicker start on site, and the close
integration of design and construction should result in more effective programming. The
desirable benefits of early contractor participation might be brought about when the contractor
is appointed directly by the client and made responsible for the whole process from initial
briefing to the production of the finished building and the contractor effectively takes on the role
of 'Leader of the team'. However time is needed for the employer's consultants to prepare an
adequate set of requirements, and time is also needed to compare and evaluate offers and
schemes from competing tenderers. The success or otherwise of a design and build operation
21
depends to a large extent on the employer properly setting out the requirements in the first place
and then carefully evaluating the contractor's proposals. Once the contract is signed, any
changes are likely to prove costly and the employer has little further opportunity to comment on
The procedure is initiated by the client (or an architect on his behalf) preparing his requirements
in as much or as little detail as he thinks fit. These are then sent to a selection of suitable
contractors, each of whom prepares his proposals on design, time and cost, which he submits
together with an analysis of his tender sum. The client then accepts the proposals he is satisfied
best meet his requirement and enters into a contract with the successful tenderer.
The latter then proceeds to develop his design proposals and to carry out and complete the
works. The client may use the services of an independent architect and quantity surveyor to
advise him on the contractor's proposals as to design and construction methods and as to the
financial aspects respectively. He may also appoint an agent to supervise the works and
generally to act on his behalf to ensure that the contractor's proposals are complied with.
Advantages
(i) Single point responsibility is provided, i.e., the contractor is solely responsible for failure
(ii) The client has only one person to deal with, namely, the contractor, whose design team
(iii) The client is aware of his total financial commitment from the outset.
(iv) Close inter communication between the contractor's design and construction teams
22
resolution of site problems.
Disadvantages
(i) Variations from the original design are discouraged by the contractor and, if allowed, are
expensive.
(ii) The client has no means of knowing whether he is getting value for money unless he
(Ramus, 1989).
This method has been increasing in popularity since the early 1970 s. The client appoints an
independent professional team, and also a management contractor. His involvement at pre-
construction stages will be as an adviser to the team, and during construction he will be
The principal characteristics of management contracting is that the management contractor does
none of the construction work himself but it is divided up into work packages which are sub-let
to sub-contractors, each of whom enters into a contract with the management contractor. The
management contractor is normally either nominated by the client on the basis of the contractor's
(ii) prices for any additional services to be provided before or during the construction period.
23
The management contractor's role therefore is that of providing a construction management
service on a fee basis as part of the client's management team - organizing, co-ordinating,
supervising and managing the construction works in co-operation with the client's other
professional consultants.
As part of his service, he provides and maintains all the necessary site facilities, such as offices,
storage and mess huts, power supplies and other site services, common construction plant,
welfare, essential attendances on the works contractors (e.g.: Unloading and storing materials,
providing temporary roads and hard standings and removing rubbish and debris) and dealing
with labour relations matters. The management contractor undertakes the work on the basis of
a contract cost plan prepared by the quantity surveyor, project drawings, and a project
specification. The employer accepts most of the risk because there is no certainty about costs
and programme.
Advantages
(i) Work can begin on site as soon as the first one or two work packages have been
designed.
(ii) Overlapping of design and construction can significantly reduce the time requirement,
(iii) The contractor's practical knowledge and management expertise are available to assist
(iv) Where the nature and extent of the work may be uncertain, as in refurbishment contracts,
the design of later work packages may be delayed until more information becomes
(v) The contractor, being part of the client's team, is able to identify the client's needs and
24
interests.
(vi) Because works contracts are entered into close to the time of their commencement on
Disadvantages
(i) Uncertainty as to the final cost of the project until the last of the works contracts has
been signed.
(ii) The number of variations and re-measurements required may be greater than on
traditional contracts because of the greater opportunity to make changes in design during
the construction period, due to problems connected with the interface between packages,
and because packages are sometimes let on less than complete design information.
(Ramus, 1989).
This system was introduced at the end of 1983 by the BPF, which represents property,
development, insurance and financial organisations who are the customers of the construction
industry. The system claims to produce good buildings more quickly and at 'lower cost' and
'to remove as much as possible of the overlap of effort between designers, quantity surveyors
(i) Concept.
(v) Construction.
The BPF system broadly follows the traditional procurement pattern but is different in the
25
following respects
(i) The client's representative, who is named in the contract, is in control in the role of
(ii) The client's representative may delegate any or all of his duties to any number of
persons or firms.
(iii) A priced schedule of activities may replace the traditional bill of quantities, with the
(iv) A proportion of the design work is transferred to the contractor, the amount depending
(v) Variations, it is claimed, are reduced to a minimum; by all concerned being encouraged
(vi) There is no provision for nominated sub-contractors or nominated suppliers but certain
work or certain goods may be stipulated to be carried out or supplied by a person or one
(vii) The design leader and other consultants are paid a lump sum fee instead of a percentage
(viii) Disputes are settled by a named adjudicator in order to speed up settlement, with
arbitration in reverse if the parties are not satisfied with his decisions and for those
26
Advantages
(i) S o m e or most of the design work may be transferred to the contractor, thereby obtaining
the benefits of his expertise and also shortening the pre-contract period.
(ii) All those working on a project are aware of their respective duties and responsibilities,
(iii) The matters to be specified or shown in the brief, the master cost plan and in the tender
(iv) The prescribed management structure is calculated to induce a greater sense of urgency
in the minds of the consultants, and the system is designed to reduce as far as possible
Disadvantages
(i) Where a bill of quantities is not provided by the client, the scope of the work covered
consequential loss.
(iii) The pricing of variations will lead to more protracted negotiations between the client's
(v) The use of one contractor in the design process inevitably brings in also those sub-
27
contractors with whom that contractor normally works, which may leave the client in a
(vi) The dominant role of the client's representative could lead to contractors being somewhat
less than satisfied that they will be treated with the same impartiality as they have come
(Ramus, 1989).
Construction management is not a procurement system in itself but is only part of the total
process. It is a professional consultant service to the client, provided on a fee basis , with the
The construction manager is responsible for the organization and planning of the construction
work on site and for arranging for it to be carried out in the most efficient manner. The
construction work itself is normally carried out by a number of contractors, each of whom is
responsible for a defined work package. All the work packages together constitute the total
project. Each works contractor enters into a direct contract with the client.
The construction manger's duties normally include any or all of the following
(i) Co-operation and consultation with the other members of the client's professional team.
(iii) Preparation of materials and components flows and arranging for advance ordering.
(iv) Determining what site facilities and services are required and their location.
(v) Breaking down the project into suitable work packages in consultation with the other
28
members of client's team and recommending suitable contractors to be invited to tender
(vii) Evaluating tenders and making recommendations on them to the client's team.
(viii) Co-ordinating the work of the works contractors to ensure that it is carried out in
(ix) Establishing all necessary management personnel on site with responsibility to manage
(x) Dealing with any necessary variations to the work, providing the design manger with
estimates of their likely cost and subsequently issuing instructions to works contractors.
(xi) Submitting to the quantity surveyor applications from works contractors for periodic
payments and all necessary documentation enabling the final accounts of works
contractors to be settled.
This type of contract is not much used in the U.K. and no standard forms are available.
Advantages
(i) The construction work is more closely integrated into the management of the project.
(ii) Close liaison between the construction manager and design manager leads to prompt
(iii) Detailed design can continue in parallel with construction, work packages being let in
29
succession as the design of each is completed, thus shortening the project time.
(iv) Privity of contract between the client and each of the works contractors provides the
client with a ready means of redress when difficulties such as delays arise.
Disadvantages
(i) The client has one more consultant and a number of contractors with whom to deal
(ii) The client's financial commitment is uncertain until the last of the works contracts has
been signed.
(Ramus, 1989).
Project management is not a procurement system in itself, in that it does not include the site
construction process but only its general supervision. It has been defined as 'the overall
planning, control and co-ordination of a project from inception to completion aimed at meeting
a client's requirements and ensuring completion on time, within cost and to required, quality
standards'.
A number of project management organizations came into existence during the late 1970 s and
1980 s to meet the need for the management of projects which were becoming larger and
increasingly complex. Many clients do not have the in-house skills and experience necessary
for the successful management of construction projects and so need to employ an independent
Quantity surveyors, by their training and experience in financial and contractual matters, coupled
with a detailed knowledge of construction processes, are well qualified to offer a project
nianagement service, and a number of established quantity surveying practices have set up
associated companies offering such a service. Other groups of professionals, such as architects,
engineers and building and valuation surveyors, are also now filling this role.
30
The project manager, in effect, becomes the client's representative, with authority to supervise
and control the entire planning and building operation from acquisition of the site to completion
of the project and settlement of the accounts. The service he provides is essentially one of
planning, organizing and co-ordinating the services provided by surveyors and lawyers in
relation to site acquisition; the architect, engineers and quantity surveyor in relation to project
planning and design; and the contractor and sub-contractors in carrying out the site construction
work; but does not include the carrying out of any of their duties himself.
(Ramus, 1989).
This is an arrangement for building procurement which has developed out of the increasing
proportion of engineering and other specialist services. It has been defined as follows:
A partnership between two or more companies covering building, mechanical and electrical
engineering, or other specialist services for the purpose of tendering for, and executing a
building or civil engineering contract, each of the participating companies having joint and
The basis of such projects is a single contract to which all the partner companies to the joint
venture (JV) are signatories. Any of the standard forms of contract in current use may form the
contract document. Modifications will need to be made to cover joint and several liability of
the participating companies and to provide for any performance warranty which the employer
may require.
JV has the effect of making specialist contractors who under more orthodox arrangements would
be sub-contractors, partners with the building contractor. This does not preclude the use of sub
contractors (Whether nominated, named or listed), a role which is filled by secondary specialist
31
Advantages
(i) The combined resources of participating companies result in greater economy in the use
(ii) There is a greater degree of unified action between the contracting parties.
(iii) Lines of communication between the employer's professional advisers and the building
(iv) Improved integration of work sequences results in a shorter contract time and fewer
management problems.
Disadvantages
(i) If one JV partner withdraws, the remaining partner or partners must accept total liability
(ii) A separate, unified JV bank account must be arranged and maintained by all the partners.
(iii) Separate insurance policies must be taken out on behalf of all the JV partners,
(iv) A board of management with a single managing director needs to be appointed jointly
(Ramus, 1989).
32
2.4.7 B u i l d i n g Contracts u n d e r 'Design, M a n a g e , C o n s t r u c t '
total integrated service from a single source. It can be led by the contractor, or by some other
professional. The latter is more likely when the design aspects of the project are a high priority.
There are no standard forms available as yet, although some contracting organizations
may have their own forms. Architects adopting this approach will need a specialist lawyer to
Contracts where the architect administers a series of separate trades contracts where there
is no main or general contractor, may also fall into this category. As well as being the designer,
the architect assumes the managing and co-ordinating roles for the project. The trades contracts
will ordinarily be direct between the employer and the firms concerned. (Hugh at el 1990).
2.5 T y p e s of C o n t r a c t s i n use i n S r i L a n k a
(i) Under the traditional procurement method such as measure and pay, lump sum,
cost plus fixed fee basis, cost plus percentage fee basis and target cost; and
(ii) Under the alternative procurement method such as design and build contracts.
There are also occasions, procurement using management methods for high quality finish works
In general, the admeasurement type contracts (measure and pay) are used in almost all
government contracts. But there are instances, the public and private sector organisations used
33
CHAPTER - 3
CHAPTER 3 - CONDITIONS OF CONTRACTS FOR BUILDING
CONSTRUCTION WORKS
3.1 Introduction
After studying the various procurement methods and types of contracts for the building
construction works in chapter 2, the next step will be to study the conditions of contracts for
This chapter covers various types of conditions of contracts in practice in the U . K . for building
construction works.
Since the JCT family conditions of contracts are widely used in the U . K . and most of the
english speaking countries (i.e. with or without modifications), the historical development of JCT
contracts for building and civil engineering works are also included in this chapter.
3.2 S t a n d a r d F o r m of Conditions of C o n t r a c t
The advantages of using detailed contract provisions based upon a standard form of contract
which holds a reasonable balance between the requirements and interests of the parties concerned
and in particular allocates fairly the risks and responsibilities between the contracting parties.
The use of standard conditions of contract will not only facilitate the successful completion of
a contract but will, in all probability, result in lower tender prices, as tenderers will be familiar
with the conditions that will apply under the contract. This implies that they will not need to
make financial provision for contract conditions with which they are not familiar and whose
consequences they may have difficulty in assessing. The wide spread use of standard conditions
of contract also provides a stable basis for training and educating personnel responsible for
34
contract management and avoids their having to work with ever changing contract conditions.
(i) Their contents will be well known and understood by the parties involved.
(ii) Their wording embodies much experience in resolving difficulties of interpretation and
enforcement.
(Hugh at el 1990).
Generally in the selection of the standard form of conditions of contract the following factors
are considered.
(i) Availability.
(ii) Sector.
(iii) Familiarity.
(Hugh at el 1990).
For the majority of building contracts which concern architects, standard printed forms are
readily available in the U . K . , and these should be used without alternations. There is also the
practical point that if a contractor is asked to tender knowing that it is proposed to use a special
or amended form of contract, his first action will be to pass it to his legal advisers for checking.
The cost of this will then be reflected in his tender. It is sound advice to resist alterations and
35
amendments whereever possible.
However, there may be instances where no standard form of building contract fits the client's
requirements and a specially drafted agreement is needed. There is an increasing trend towards
non-standard agreements in the U.K. Any such drafting should be entrusted to a lawyer with
the appropriate specialist knowledge, and he or she should always be engaged direct by the
client.
The standard forms of conditions of contracts currently in use for the building construction
( T r a d i t i o n a l M e t h o d of P r o c u r e m e n t )
3.3.1.1 J C T S t a n d a r d F o r m of B u i l d i n g C o n t r a c t
1 9 8 0 E d i t i o n ( J C T 80)
This form is suitable for major building works. There are 4 recitals, 5 articles and 41
clauses in all. There is also an appendix which requires very careful attention to complete
properly. The conditions are set out in 4 parts. Part 1 will normally apply in all cases. Part
2 covers nomination which may or may not be applicable. Part 3 refers to the fluctuations
alternatives, although the actual detailed clauses are published separately and incorporated by
There are six different versions, however, very similar in content. These are
36
(v) Local authorities without quantities.
These forms are suitable for contract types 2.3.1 (Based on bills of firm quantities and
(Hugh at el 1990).
of sub-contractor.
TNS/1 Standard form of tender by nominated supplier tender and schedules 1 and 2 .
37
3.3.1.2 T h e G e n e r a l Conditions of G o v e r n m e n t C o n t r a c t s f o r B u i l d i n g a n d C i v i l
E n g i n e e r i n g W o r k s - F o r m G C / W o r k s / 1 : E d i t i o n 3 , D e c e m b e r 1 9 8 9 (Revised
1990)
This form is suitable for major works of central government contracts. The form GC/Works/1
was produced in 1973, and the second edition first appeared in September 1977. It was drafted
unilaterally on the part of government for use specifically by crown departments. The current
It is usually, but not necessarily, used with firm quantities, and it can be applicable to re-
measurement contracts for work of civil engineering rather than building contracts. There are
no recitals and articles, but the contract incorporates the tender and the written acceptance.
There is no appendix, but detail is carried in the abstract of particulars. There are 61
conditions. The form is complex in parts, but the drafting is relatively clear. The contract
expressly includes the specification as well as bill of quantities and drawings as forming part of
one contract.
It has been used for private jobs in the private sector, but substantial amendments are
needed, and its use under such circumstances is definitely not advised.
(Hugh at el 1990).
(i) Government works sub-contract condition (GW/SC) for use with (GC/WKS/1)
(iii) GW price adjustment formula provisions (GW/S/FR) for use with (GW/Sc)
Also there is a general conditions of government contract for building and civil
engineering works for lump sum without quantities dated August 1991.
38
3.3.2 T h e S h o r t e r L u m p S u m F o r m s ( T r a d i t i o n a l M e t h o d of P r o c u r e m e n t )
( 1 9 8 0 E d i t i o n ) - ( J C T M W 80)
The minor building works form of contract (MW 80) has proved very popular ever since it was
first published in 1968. Following the publication of the 1963 edition of the JCT standard form
of building contract, it became clear that a form was needed for a lump sum form more
appropriate in minor building and repair work, and for which quantities were not necessary.
There are 3 recitals which will always apply. The fourth recital allows for the naming of a
quantity surveyor, although the conditions ascribe no particular role for this person. The fifth
recital applies where a guarantee/warranty scheme is to be part of the contract. There are 4
articles and 37 clauses in all, listed and numbered under nine section headings. There is no
appendix, but entries may be required in upto ten places in the actual conditions.
There is only one version of MW 80 for use in either the private or local authority sector. JCT
M W 80 is designed for use where minor building works are to be carried out for an agreed lump
sum and where an architect/supervising officer has been appointed on behalf of the employer.
or may not be 'contract drawings', a 'contract specification' and schedules which are also
contract documents.
39
The contractor will price a detailed contract document, or may provide a lump sum price
supported by a schedule of rates. There is no published sub-contract. Also this is not suited
(Hugh at el 1990).
3.3.2.2. J C T I n t e r m e d i a t e F o r m of B u i l d i n g C o n t r a c t f o r W o r k s of S i m p l e C o n t e n t
(1984 Edition ) - ( J C T I F C 84 )
In October 1981 the JCT established a working party to prepare an intermediate form and the
intermediate form was published in 1984. This is not suitable for contracts subject to Scottish
Law. There are 2 recitals, 5 articles and 74 clauses in all. There is an appendix. The
(i) Building works of simple content and without complex services installations.
(ii) Lump sum contract to be priced entirely by the contractor and that therefore the job must
(iii) Contract period not exceeding 12 months, but experience has shown that the form can
There is only one version of the form to cover for both local authority and private sectors, and
architect/contract administrator, and to name the quantity surveyor appointed. The contract
documents are the contract drawings, and either the bill of quantities or the
specification/schedules of work.
(Hugh at el 1990).
40
(iii) NAM/FR Formula rules for named sub-contractors.
( A C A ) F o r m of B u i l d i n g A g r e e m e n t 1982
(Second E d i t i o n 1984)
This is suitable for use on a very wide range of jobs of various sizes and types. ACA
contract working party claimed that their intention was to produce a form which was a flexible
and fairly balanced contract for an efficient architect working with an efficient contractor for an
efficient client'. Early criticism was that the form was drafted unilaterally without any
contribution from contractors. However, it has been used successfully on a wide variety of jobs,
including fast-track. Major client bodies appear to have used the form without problems, and
the BPF co-operated over a version of the form suitable for use under the BPF system. There
is little evidence of problems with the form. The second edition (1984) included a number of
A feature of the contract is its flexibility, made possible by the use of alternatives. There is no
restriction as to the size or type of job for which form is suitable. It can be used with or
without bill of quantities and where no quantity surveyor is appointed. It can be used where the
The contract can be fixed price, or fluctuations based on a simple A C A index can be
incorporated. The form is suitable for use under English or Scots Law.
(Hugh at el 1990).
41
(ii) AC A Architect's instructions.
3.3.2.4 T h e G e n e r a l Conditions of G o v e r n m e n t C o n t r a c t s f o r B u i l d i n g a n d C i v i l
Engineering M i n o r W o r k s - F o r m G C / W o r k s / 2
for use specifically by crown departments for small works. It is not intended for use with
quantities. There are no recitals or articles, but the contract incorporates the tender and written
acceptance. There is no appendix, but detail is carried in the abstract of particulars. There are
37 conditions, and the wording of many of the conditions is similar to GC/Works/1 ( Second
edition). T h e contract refers to documents as being the specification and the drawings. The
contract is based on a fixed price which does not even allow for increases in levies and taxes.
(i) A general conditions of contract for demolition works dated September 1990.
(ii) A general conditions of government contracts for building, civil engineering, mechanical
(Hugh at el 1990).
A g r e e m e n t a n d Conditions of C o n t r a c t f o r L a n d s c a p e W o r k s
T h e JCLI originally had two standard forms for landscape works based on JCT 1963 with and
without quantities. In 1978 these were replaced by a single form modelled on the then current
JCT minor works agreement 1968. In 1985 the JCLI published a supplement to the JCT
(Hugh at el 1990).
42
Related documents are
The ASI came into being in 1989 as a result of the amalgamation of the Faculty of Architects
and Surveyors (FAS) and the Construction Surveyors Institute. The several contracts
recommended to its members are those issued by the F A S . The forms issued are
- For larger, more complex work, and the same form can be used with or without
quantities.
There is also an F A S sub-contract (1981 edition), and various contract administration form, all
F A S copyright.
All these forms of contract are set out in a similar manner with recitals, articles of agreement,
(Hugh at el 1990)
43
3.3.2.7 T h e Scottish B u i l d i n g C o n t r a c t C o m m i t t e e ( S B C C ) F o r m s of C o n t r a c t
There are important differences between the Law of England and Wales, and Scots Law. A
Scottish supplement is published which adapts the various editions of JCT 80 for use under Scots
Law, and adapted forms for nominated sub-contractors are available. There is also a Scottish
The SBCC also publishes its own building contract for minor building works. It is intended for
building works of a simple, straight forward content, and when the contract is not likely to
exceed 12 months duration. The SBCC forms are not suitable for use other than under Scots
Law.
(Hugh at el 1990).
3.3.3 M e a s u r e m e n t F o r m s ( T r a d i t i o n a l M e t h o d of P r o c u r e m e n t )
3.3.3.1 J C T S t a n d a r d F o r m of B u i l d i n g C o n t r a c t 1980 E d i t i o n w i t h A p p r o x i m a t e
Quantities
This version of the standard JCT form was first produced in 1979 in response to pressure from
property developers. They wanted a traditional method of building procurement, with as early
a start on site as possible. This form still allows for some design development in parallel with
construction work. There are two versions for local authorities and private use. This form is
44
suitable for contract type 2 . 3 . 2 (Based on bills of approximate quantities and drawings)
described in chapter 2 .
(Hugh at el 1990).
The full title of the document is "Conditions of contract and forms of tender agreement and bond
This is a form which is clearly suited to the scale and relatively imprecise nature of civil
engineering operations, which make re-measurement inevitable. The conditions show that the
form is not really intended for building work and that it is not appropriate for lump sum
contracts.
The first edition was produced in 1945 jointly by the ICE, the Association of Consulting
Engineers and the Federation of Civil Engineering Contractors. The conditions are contained
in 72 clauses. The form of agreement identifies which documents will be part of the contract -
drawings, specification, or priced bill of quantities. The appendix to the tender carries the
important details about time, and any requirements about completion by sections.
The key person in terms of contract administration is 'the engineer', who must be named.
The sixth edition of the conditions of contract was published in January 1991. There are no
separate edition for public and private use. ICE conditions of contract creates a re-measurement
(Hugh at d 1990)
In 1991, the ICE published the N E C to provide maximum flexibility with a core contract and
45
(ii) Conventional contract with bill of quantities.
With a variety of secondary options for use where necessary, the employer is free to choose the
3.3.3.3. T h e I C E C o n d i t i o n s of C o n t r a c t f o r M i n o r W o r k s - ( F i r s t E d i t i o n 1988)
The full title is "Conditions of contract, agreement and contract schedule for use in connection
with minor works of civil engineering construction". It is produced under the name of the ICE,
but the sponsoring authorities include the Association of Consulting Engineers and the Federation
It is intended for use where the risks are small, the contract period six months or less, there are
no nominations, and for smaller value of jobs. Reports indicate that it is being used where both
The conditions are conveniently grouped under 12 headings, and are commendably straight
forward and easy to read. The form is suitable for lump sum or re-measurement. Further
flexibility is possible because it can also be used with or without a priced bill of quantities. This
(Hugh at el 1990).
46
3.3.4 Cost Plus F o r m s ( T r a d i t i o n a l M e t h o d of P r o c u r e m e n t )
For making good damage arising during and after the 1939 - 45 war, contracts based on the cost
of labour and materials plus an addition to cover the contractor's overheads and profit were an
obvious solution. In 1967 the JCT published a prime cost form which incorporated a 'fixed fee',
although revised in 1976, it is still basically this 1967 form which is current.
The agreement includes 5 recitals, although these are not headed as such. There are no articles
identified, but clause 1 requires entries to indicate those persons who will act as 'architect' and
'quantity surveyor'. The contract conditions are set out in 32 clauses. It is followed by 6
schedules and the appendix. There are also private and local authority editions. This form is
There is a general conditions of government contracts for prime cost contract for building and
(Hugh at el 1990).
3.3.5 Design a n d B u i l d F o r m s ( A l t e r n a t i v e M e t h o d of P r o c u r e m e n t )
E d i t i o n ( J C T W C D 81)
In the mid - 1970 s , when idustrialised building was at a peak, contractor-led design and build
became an important method of building procurement. For this purpose, drafting the new form
However, when it was finally published as the JCT standard form of building contract with
contractor's design 1981 edition (JCT W C D 81), it was an immediate success and has been
47
generally accepted by the building industry.
There are 4 recitals, 5 articles, and 39 clauses in all. There are three appendices. Also many
of the clauses are similar to JCT 80, but special clauses are included to meet and deal with this
type of arrangement. This form is suitable for contract type 2 . 4 . 1 (Building contracts under
(Hugh at el 1990).
3.3.5.2 J C T S t a n d a r d F o r m of B u i l d i n g C o n t r a c t W i t h Q u a n t i t i e s , 1 9 8 0 E d i t i o n -
Many projects for which a lump sum contract is otherwise appropriate still require design input
from the contractor for some part of the work. It should be emphasised that this does not turn
it into a design build form, but merely modifies a 'work and materials' contract by importing
a restricted design obligation. The JCT Contractor's Designed Portion Supplement (CDPS) is
for use in conjunction with the standard form of building contract with quantities (Local
authorities and private 1980 editions). The CDPS is a 9 page document. It includes a
(Hugh at el 1990).
a n d Construction
The manual of the BPF system was published in 1983 and immediately attracted a great deal of
attention. It formalised a new way of working, and was a response to what many saw as a
tangle of responsibilities created by the traditional system. It called for a change of attitudes and
working methods on the part of designers and contractors in the interests of efficiency and
profitability.
(Hugh at el 1990).
48
T h e A C A F o r m (1984) B P F E d i t i o n
This is a specially produced version of the ACA form which is intended for use only
(Hugh at el 1990).
3.3.5.3.2 J C T S t a n d a r d F o r m of B u i l d i n g C o n t r a c t 1 9 8 1 E d i t i o n W i t h C o n t r a c t o r ' s
Design a n d I n c o r p o r a t i n g O p t i o n a l S u p p l e m e n t a r y Provisions. S I t o S 7
The JCT, unlike the A C A , has not produced a special edition of a form for use with the BPF
system. Instead it has made various general improvements to the C D 81 form, and published
(Hugh at el 1990).
3.3.6 M a n a g e m e n t F o r m s ( A l t e r n a t i v e M e t h o d of P r o c u r e m e n t )
3.3.6.1 J C T S t a n d a r d F o r m of M a n a g e m e n t C o n t r a c t ( 1 9 8 7 E d i t i o n ) J C T M C 8 7
For 'fast-track' projects, where the employer nevertheless wants design by the professional team
In December 1979 the RIBA Council, on the advice of its contracts committee, asked the JCT
to prepare a standard form of management contract. At that time numerous forms existed
prepared by contractors for their own projects, and many firms would only enter into a
In December 1987 the JCT issued the standard form of management contract together with a
There is one contract between the employer and the management contractor and this can cover
49
the pre-construction and the construction period.
The standard form of management contract consists of 5 recitals and 8 articles of agreement, the
conditions of contract and an appendix. This form is suitable for contract type 2.4.2.(Building
(Hugh at el 1990).
F o r m of M a n a g e m e n t C o n t r a c t
When the JCT published its management contract in 1987, it also published the related standard
forms of works contract at the same time. There are three parts, these are
Consists of the invitation to tender, the tender by the works contractor, and the
(Hugh at el 1990).
Several bodies in the U.K. produce their own building contracts and sub-contracts forms, but
by far the greatest number is published by the JCT. A whole family of documents is now
available to cover a wide variety of work which ranges from construction or maintenance and
repair work on the one hand to management contracting on the other. These various forms are
50
described in 3 . 3 . (Hugh at el 1990).
The following are the events of the building contract formation in the U.K. (Spiers, 1983).
(i) In 1866, the meeting in Edinburgh of 'the General Builders Association' (Representing
buildings in the North of England and Parts of Scotland), by considering the industrial
expansion increasing trend and a widening social circle, recommended that the contracts
should be specific, defined in their terms, the provisions and stipulation of contract
agreements be perfectly mutual ( The consideration on one side being money and the
(ii) In 1870, the establishment of 'the Builders Society' and the RIBA (Formed in 1834)
combined to produce a form of contract for use in London, whereby now both bodies had
(iii) Following the demise of the General Builders Association (1865 - 1871), a representative
group of contractors chose to meet in the railway junction town of Crewe in 1878 and
formed 'the National Association of Master Builders of Great Britain' (Today it is the
NFBTE).
(iv) In 1901, the Building Employers' Organisation adopted a more representative structure,
and changed its title to "the National Federation of Building Trades Employers (NFBTE)
(v) T w o years later, following a long struggle in which it had issued its own version of the
1870 'London form of contract', a settlement was reached with the RIBA after mediation
(vi) The 1903 form of contract was a considerable step forward, and although it became
51
known as the 'National' form. There was no intention on the part of either party to
produce a standard form of contract for all building works nor is there any evidence to
suggest that any of the parties was trying to secure unfair advantage.
(vii) All records point to the contrary within their own disciplines, the RIBA, the IOB and the
N F B T E were in a minority, but their 'National' contract was a prize others did not have,
and would not be given. That is, until 1908 when the builders changed their minds and
(viii) The RIBA disagreed and amended clause 30 (Final certificate) without reference to
others. This brought resentment, but once resolved, it established the principle of the
(ix) D u e to the impact of following technical changes the N F B T E union membership was
(a) The introduction of reinforced concrete reduced the work of the mason.
(b) Plumbers grew depressed as asphalt roofing and iron piping replaced lead work.
(c) Machinery took joinery into a factory away from the site.
(d) Electrical work came into its own, as did hot water systems.
The Building unions were unable to cope with it all and became rather isolated from the
militancy of unions in other industries and were somewhat subdued. These changes left their
mark on the quantity surveyor. Previously he had been known as the 'measurer', working
(x) The new technology created specialists where those were employed as nominated sub
(xi) In 1918, the National Federation of Building Trade Operatives opened joint negotiations
52
with employers. Dissatisfaction with the agreed conditions of contract grew under the
(xii) In 1919, there was no form and contract generally acceptable to the industry as a whole
and there was no established machinery through which the position could be remedied.
The N F B T E gave notice to the RIBA to rescind the agreement of 1903 regarding the
issue of an agreed form of contract. This was the period of the Building Code issued by
(xiii) In 1922, the first edition of the Standard Method of Measurement (SMM) was published
and also the contract conference was established in the same year.
(xv) In 1928, the chairman of the contract conference in his conclusion stated that it is
difficult to measure the advantages that will follow from the general adoption of this
(xvi) Although approved by the council of the RIBA, the 1928 form was rejected by its wider
membership. The builders were persuaded to postpone their campaign in support. The
1928 form had been too great a break with tradition and it was now for the architects to
prepare a new draft which followed more closely the form of the clauses in the 1909
form. Whatever the architects motives the position reached in 1903 and confirmed in
(xvii) The next three years (1928-1931) covered the search for a solution in which each of the
parties could be honestly convinced that their interpretation was precisely the same as the
others. The essence of agreement lay with the presumed unwritten qualities of individual
colleagues. The JCT founded in 1931 that enabled the N F B T E and IOB to accept the
1931 form. The JCT, which initially consisted of the representatives from the RIBA and
53
the predecessors of the NFBTE, was setup to be responsible not only for the publication
(xix) Ironically, the IOB sanctioned the 1931 form along with the RIBA and N F B T E , but
unlike those two bodies it did not became a member of the JCT.
(xx) In 1931, the Architects Act was passed to establish the criteria to protect the public
(xxi) At the beginning of thirties, contracting firms varied generally in size, area of operations
and type of work undertaken. The depression affected the building industry most
severely in 1933 when tens of thousands of workers were unemployed, but a year later
In the years which have followed, representatives from other bodies such as the Royal
associations, the SBCC, the two main organisations representing specialist sub
contractors and the Association of Consulting Engineers have joined the JCT and two
(xxii) In 1937, when the first standard form specially adapted for use by local authorities was
issued, the JCT had received sufficient feed back from the use of 1931 form to be able
(xxiii) Although the 1939 standard forms were issued in both private and local authority
(xxiv) Since 1931, new editions of the contract have been published in 1937, 1939, 1950, 1957
and 1963 and amendments and revised clauses to the contract have followed at
increasingly frequent intervals. The latest edition 1963 was made between RIBA, RICS,
54
County Councils Associations, Association of Municipal Corporations, Urban District
Councils Association, Rural District Councils Association, Greater London Council and
the N F B T E . Also since 1963, membership of the JCT has been increased by
The 1963 edition was published in 4 versions - with and without quantities, and for
private and local authorities use. In 1964 the arbitrary contract procedures situation
(xxv) Revised form of building contract published in July 1977 with the amendments to
retention fund provisions. This revision was based on the original 1963 edition.
(xxvi) The forms of prime cost contract for use in the repair of war damaged property were
issued in 1946 and revised in 1956 to provide for a cost plus percentage contract and a
(xxvii)Re-measurement contracts were published in October 1975, by the JCT designed for use
with approximate quantities and applicable in both the private and local authorities
sectors.
(xxvii)JCT 80 is the latest in a series of standard forms prepared by the JCT and replaces the
July 1977 revision of the 1963 edition. JCT 80 is nearly twice as long as the 1963
edition and contains many new procedural requirements. The volume of the new
contract, its language and the unfamiliar style and presentation all combine to make its
The principal reason for the publication of the new edition of the standard form was to
55
In 1966, the Federation of Associations of Specialists and Sub-Contractors (FASS) and
JCT which thereupon assumed responsibility for the production of the standard form or
associated documents, with the consequent amendments to the main contract, have
In the 1970s and 1980s, other interested professional bodies (Other than JCT) published their
own contract forms in response to the increasing variety of contractual and building
(iii) Architects and Surveyors Institute (Formerly the Faculty of Architects and Surveyors).
3.5 The General Conditions of Government Contracts for Building and Civil
Engineering W o r k s
This form which generally used by government departments and for government corporations
differs from the JCT contract forms for private or local authorities use. The very origin of the
form is quite different as the government form originates from an Inter-Departmental Committee
representing the Ministries involved with construction who consult with the Employers
Federations in the construction industry. The responsibility of the form primarily rests with the
The position of the architect, surveyor, or other supervising officer under the JCT contract form
is replaced by the term "The Project Manager". These forms are used even when an
56
independent consultant is employed to design and supervise the building works.
The contract form is suitable for use with or without quantities or with approximate quantities
or for use in conjunction with a schedule of rates either for measurement of work as it is carried
out, or to assist with costing variations in the case of lump sum contract without quantities.
Under the government contract the contractor has to give notices and pay all fees and indemnify
the authority (Employer) but there is no provision for the sums due to be added to the contract
sum. The contractor must accordingly make provision for them when he submits his tender.
Another provision relates to the status of the superintending officer. Under the terms of this
57
!
CHAPTER - 4
CHAPTER 4 - HISTORICAL BACKGROUND OF THE FIDIC CONDITIONS OF
CONSTRUCTION WORKS
4.1 Introduction
(i) Study the history of FIDIC and FIDIC conditions of contract; and
(ii) Find out the applicability of FIDIC conditions of contract for building
construction works. Also this chapter covers some of the notable characteristics
4.2 W h a t is F I D I C
FIDIC is the acronym of the French title of the International Federation of Independent
It was not until the end of the world war in 1945 that the FIDIC began to expand and include
among its membership those countries which contained the largest Associations of Consulting
Engineers. Today FIDIC membership numbers 5 3 , countries from all parts of the world.
FIDIC is a non-profit association, representing consulting engineers throughout the world and
facilitating the achievement of projects by the three principal parties namely client, contractor
and consultant.
FIDIC arranges seminars, conferences and other events in furtherance of its goals which are
58
representatives of the international financing organisations.
(v) T o act as a central source of information for the member associations.(Campbell, 1986).
During its development it has become apparent that the FIDIC must jealously guard the standard
of the service which the members of its constituent member associations can offer, and a
substantial contributing factor to this has been its insistence on the maintenance of strict
independence so that the counsel and advice given to clients are unaffected by any possibility
With the ever-growing interest to aid developing and less developed countries and with the
tendency of lands which were formerly not industrialised to see their future supported by
industrialisation.
FIDIC has an obviously expanding part to play in the international picture which can be a major
contribution to world development and, through that, to peace and prosperity. FIDIC is actively
working to encourage the development of the profession in countries which are in the process
of development and much of the practical help is being provided by member associations in the
industrialised countries.
FIDIC has prepared standard forms for contracts for the construction of civil works and for
electrical and mechanical works and these are the best recognised standard conditions available
for international contracts. They have done much to establish the working pattern between the
client, consulting engineer and contractor which in itself has been of great advantage to each of
Those who are already familiar with both the fourth and the fifth editions of the conditions of
contract issued by the ICE will be well aware of points of similarity contained in clauses in both
of these ICE conditions and FIDIC conditions. They should not, however because of their
knowledge of the ICE conditions, assume that the FIDIC is equally applicable in usage- It is
59
not. FIDIC is a form of contract not necessarily subject to the laws of England, nor in the
wording precisely the same as the ICE conditions either in syntax or definition, and because of
this the FIDIC contract must be regarded separately in its own right and should be read and fully
understood with these points in mind. FIDIC is established through the laws of the land which
govern the contract and it is therefore of primary importance that the identification of the law
applicable to the contract is made clear, as well as the ruling language where the contract
documents are written in more than one language. In FIDIC condition of contract
(ii) Supported by; The engineer, his representative and assistants, nominated and other sub
(iii) Others involved; Insurers, providers of geological details etc. designers and specialist
engineers.
FIDIC has also developed standard forms of agreement between client and consulting engineer
for pre-investment studies, design and supervision and project management services.
For a project to be achieved successfully the first essential is to have available competent
designs, drawings and specifications together with either a bill of quantities or a schedule of
rates, to facilitate the computation of the cost of the works. Taken together with these
documents, the conditions of contract establish a working relationship within which an employer
can expect to receive from an efficient contractor a soundly executed project within a reasonable
To achieve optimum results it is essential that when tenders are invited, the tenderers are not
asked to cover in their quoted rates for risks which an experienced contractor could not
60
It is in the employers interest for him to assume responsibility under the contract for costs
arising from events which may never occur, which lie outside contractors control and which
cannot be covered by insurance, or where the cost of insurance is prohibitive. These events may
Competent and experienced contractors are then able to submit competitive tenders without
having to include contingency sums to cover unpredictable hazards and the employer will only
have to meet the cost of dealing with events which actually occur, arising from special risks.
Close co-operation and team work between employer, contractor and engineer with a mutual
desire to produce a satisfactory product by well organised, safe and efficient methods, will
reduce to a minimum the risk of delays or misunderstandings. Whatever may be the extent of
the engineers delegated duties, he will inevitably consult the employer before taking action which
will have a significant effect on the nature of the works, their cost or the time for their
completion. It is when mistrust or lack of confidence creeps in that troubles arise and a contract
runs into difficulties. N o wording in the conditions of contract will prevent this from happening
if the team work is faulty and one or more of the parties fails to perform.
The degree to which the employer will allow the engineer to act without first consulting him will
depend on the degree of mutual confidence, the technical and managerial capacity of both parties
The FIDIC conditions of contract (Wallace, 1974) is intended for works of civil engineering
construction which are to be measured and evaluated by bill of quantities. It consists of a single
printed document commencing with a short explanatory memorandum, and six separate minutes,
all of which are signed on behalf of various sponsoring bodies. It is then followed by 72 general
conditions in part I (one of which, the fluctuations clause, is merely an uncompleted heading),
and then by a number of similar uncompleted heads for separate agreement by the parties in
parts II and III (Part II - Special conditions, Part III - Relating to dredging and reclamation
work.). These two latter parts are refered to somewhat misleadingly as "Conditions of Particular
61
Application", but are in reality only suggested subject on which the parties are required to make
their own express agreements. Like the English ICE condition, the document also contains a
(Virtually identical) form of tender and appendix, and also a form of agreement. Like the
English ICE conditions, the contract contemplates the existence of drawings, and a specification
FIDIC is not suitable, without alteration, for works using a lump sum, fixed price or target cost
contract where the basis for payment is not admeasurement nor in their present form for design
Based on the considerations described in 4.3 and applying their knowledge of civil engineering
contracts being carried out throughout the world, the FIDIC and the International Federation of
Building and Public Works (FIBTP - "Federation Internationale du Batiment et des Travaux
Publics") now known as the International European Construction Federation drafted and issued
construction.
Upto that time there were no conditions (Refer 12) which had been specifically prepared to
govern international contracts. The first edition of the FIDIC conditions (The red book as it
quickly became known because the title was long and the cover was red) was published at a time
when international contracting was in its boom period and the need for a standard set of
conditions became apparent. The first edition was based on a form of contract in use in the
U.K. which was published by the ICE (Conditions of contract - Fourth edition) and thus very
much reflected traditions and a legal system that were specifically British. Subsequently the
document, which is the only standard conditions of contract for works of civil engineering
construction in use on a worldwide basis, was approved and ratified by the International
Federation of Asian and Western Pacific Contractors' Associations (IFAWPCA) in 1969, and
by the Associated General Contractors of America (AGCA) and the Inter-American Federation
62
of the Construction Industry (FIIC - La Federation Inter-Americana de La Industria de La
Construction) in 1971.
There is no difference in the wording of the conditions in the second edition, published in 1969.
(Wallace, 1974). The purpose of this edition was merely to record the slight change in the
present name of the FIBTP organisation, and the addition of the IFAWPCA as a further
sponsoring body, and to include a list of suggested headings for special clauses for dredging and
reclamation work. (i.e. The Part III of the contract conditions - This Part III was drafted to
provide particular changes to the general conditions when the document was to be used for
A print of this latter edition in 1973 added minutes of approval and ratification by two new
sponsoring bodies - the AGCA and the FIIC. FIDIC conditions of contract (second edition) is
firmly based with only minimal alterations on the fourth edition of the ICE conditions of
The terms of the third edition of the conditions of contract (International) for works of civil
engineering construction which did involve a complete revision, was published in March 1977,
prepared by the Federation Internationale Europeenne de la construction (FIEC) and the FIDIC
are approved by those organisations, and also by the AGCA, the FIIC and the I F A W P C A , and
are recommended by them for general use for the purposes of contracts for the construction of
such works where tenders are invited on an international basis. It is further agreed that;
63
(i) Without the derogating from the provisions of clause 5(1) of the said conditions as to the
designation in any contract of any specified language as the "Ruling language" for the
purposes of such contract the version in English of the said conditions shall be considered
as the official and authentic text thereof for the purposes of translation there of into any
other language.
(ii) Official translations from English of the said conditions shall be prepared into French,
German and Spanish and into such other languages as FIDIC and FIEC may from time
Employers should not be encouraged to meddle with the words of the standard Part I portion of
the FIDIC form. Evidence collected in 1973 from 113 projects, carried out under the FIDIC
form (Second edition) in 5 0 different countries indicated that difficulties had arisen where
FIDIC conditions of contract (Third edition) incorporates some of the changes made in the fifth
edition of the ICE conditions of contract published in 1973 but has still retained much of its
4.7 F I D I C C o n d i t i o n s of C o n t r a c t ( F o u r t h E d i t i o n - S e p t e m b e r 1987)
members of the Civil Engineering Contracts Committee (CECC) which upto that time had been
charged with monitoring the use of the third edition. (Refer 12).
The results of the work of the drafting committee, which comprised the members from the
1987 and the fourth edition of the conditions of contract for works of civil engineering
construction was published at the annual conference of FIDIC held in Lausanne, Switzerland in
64
September 1987. There are many important differences between the third and the fourth edition
(Refer 12).
The executive committee decided to drop the word "International" from the title of the document
as with slight modification in Part II it is also suitable for domestic contracts. FIDIC also
strongly recommends all users of the conditions to insist the Part I of the document should be
Also FIDIC conditions of contract (Third edition) was being criticised by employers (owners)
for being too anglo-saxon in its concept and language, presumably the result of a far wider use
than it had previously enjoyed. Certain amendments were identified which were being applied
almost consistently by employers and it was considered advisable to being the conditions into
line with current practice. Another factor was that in many cases where the conditions are being
used for projects in developing countries, the representative of the employer did not have the
breadth of authority to delegate duties to the engineer which it had been envisaged that they
would have when the third edition was prepared and it was felt desirable to reconcile the
Considering the above fact the following were taken into account for the preparation of the
fourth edition.
(iii) Pay close attention to some specific topics such as bonds and guarantees, apportionment
of risk, insurance, claim procedures, certificates and payments and dispute procedures.
(iv) Endeavor to update the language so that it is more understandable to those charged with
There were some procedural differences in the drafting process as compared with the third
65
edition. (Refer 12).
In the preparation of the third edition, representatives of the Contractors' Associations had
participated almost as co-drafters and it had been indicated on the cover of the conditions that
the document was approved by the various contractors throughout the world. For the fourth
edition it was agreed that the contractors representatives would have consultative status during
the drafting process but the final comment would be the sole responsibility of FIDIC.
Contractors' Associations (CICA) to represent CICA in this consultative role and the EIC
In addition, during the course of the revision there was considerably more consultation with the
World Bank (WB) than had been the case in previous revisions.
The most notable changes in FIDIC fourth edition from all previous revisions are as follows
(Sawyer at el 1990).
(i) Previous revisions (First, Second and Third) did not give the employer many
duties but the fourth edition allocates certain matters to him more specifically.
Clause 2.1 in Part II lists some of the engineer's duties for which the specific
approval of the employer must be obtained before they are carried out. There are
23 occasions when the engineer must consult the employer and the contractor (For
extra works and extension of time etc.) and only one occasion when the employer
important party to the contract because it is his project and his money which
(ii) The style of the language and the layout of the clauses has been modernised to
some degree but the sequence numbering of the clauses has been preserved.
66
(iii) Part II (Conditions of particular application) has been greatly expanded by going
clauses.
(iv) Part II has been printed as a separate volume. This enables Part I (General
provides satisfactory evidence that no changes have been made therein and that
(v) The previous Part III (Dredging and reclamation works) has been incorporated
(vii) Procedures have been set out in greater detail and in an action oriented way.
(ix) Greater recognition has been made of the fact that some design of permanent
Works
4.8.1 I n t e r n a t i o n a l B u i l d i n g Construction W o r k s
In most of the countries FIDIC conditions of contract is not used for their building construction
works whereas other conditions of contracts are in practice based on their o w n or modification
of some other building contracts. Those are namely conditions of contracts in the U . K . practice,
67
of contracts based on the U.K. or the United States of America, their own standard conditions
of contracts etc. Because of these there are no evidence in the application of FIDIC conditions
of contract for international building construction works except in the middle east. (Rush
Brooke, 1983).
There are number of problems associated with a civil engineering contract in general use for
both civil engineering and building construction works. The two operations are markedly
According to Rush Brooke(Rush Brooke, 1983), FIDIC conditions of contract is not appropriate
for building construction works in the middle east and a completely redrafted equivalent of
FIDIC conditions of contract suitable for building construction work is required to avoid the
considerable, present undesirable redrafting of the engineering contract. FIDIC in also not
suitable for contracts with a mixture of multi-disciplinary activities involving mechanical and
electrical work.
Adoption o f FIDIC conditions of contract for local building construction works in the past and
present is not unusual, although it is a civil engineering contract document and the contract is
Very few projects get involved separate consultancy firms and specialised sub-contractors. The
use o f FIDIC conditions of contract in principal is acceptable among local professionals involved
in building construction works and their argument is that it will be difficult to draw a line
between civil engineering and building construction works for most of the local building
construction works. The use of FIDIC conditions of contract was in practice among most of
the private building consultancy organisations (Architectural firms), although some were using
their own or modified versions of the U.K. based building conditions of contracts.
68
4.8.3 B u i l d i n g a n d C i v i l E n g i n e e r i n g Construction W o r k s
Since the use of separate conditions of contracts and separate contract administrators (Engineers
and Architects) for both works, it will be necessary to see the notable characteristics between
the two construction works. The following are some of the notable characteristics
(ii) Civil engineering construction works contain little specialist works and some of
(iii) Building construction works consist hopefully of work fully detailed before the
work starts and with a great variety of finishes, services and sub-contractors'
work.
(iv) Civil engineering construction works frequently take place over wide areas,
perhaps already occupied by the employer or other persons and of which the
works may form only a small part, and with no readily recognisable limitations
(v) Civil engineering measurements are based on Civil Engineering Standard Method
(vi) The scope of civil engineering work is vast, and encompasses the whole of main
docks, dams, land reclamation, bridges, power stations and pipe lines are all the
responsibility of the civil engineer, together with tunnels, sea defences and
69
sewerage schemes. He will also be called upon to design and carry out the
(vii) The design and supervision of civil engineering works are usually carried out by
service.
(viii) The engineer referred in the civil engineering contract standard form will usually
a civil engineer appointed by the employer to design and supervise the works and
(ix) The services of architects on civil engineering contracts are generally required for
(x) The civil engineering contract forms do not mention by name the quantity
surveyor, but the engineer can, if he wishes, delegate his duties in regard to
measurement and valuation to a quantity surveyor but not in regard to the final
certificate. Some civil engineers still prepare their own quantities, but with the
(xi) The courts generally imply into building and civil engineering contracts the terms
that the employer will give the contractor possession of the site within a
reasonable time, that the employer will appoint an engineer or architect, that the
employer will not prevent the contractor from completing the works, and the
contractor will do the work in a good and workmanlike manner. In the standard
forms of civil engineering contract all these matters are the subject of express
terms.
70
a civil engineering project, the client is mostly government.
(xiii) Buildings are construction works in which people will work or dwell.
(xiv) Civil engineering works are more concerned with controlling the natural
(xv) Because civil engineering work is concerned with changing the natural
whereas building works are not susceptible. For example, the building of a dam
may be seriously disrupted by a sudden storm causing a flash flood. But once the
costs.
Most civil engineering schemes are large, extensive and expensive, obvious
require a high rate of expenditure during the construction stage and a high level
(xvi) Building contracts are mostly supervised by architects, it is the structural engineer
who will assist as consultant responsible for the design and inspection of the
foundation and structure. There will be other consultants for service installations,
lifts etc.
71
(xvii) Quantity surveyors either in private practice or in the public service, are almost
preliminary estimates from the sketch design to the preparation of the final
account, and will include, among other services, the preparation of the bill of
quantities, and valuations for interim certificates. The quantity surveyor receives
official recognition and his duties are partially defined in the building contract
72
CHAPTER - 5
CHAPTER 5 - B U I L D I N G C O N S T R U C T I O N I N D U S T R Y IN S R I L A N K A AND
5.1 Introduction
This chapter covers briefly the historical development of the building construction industry in
Sri Lanka from ancient time, ICTAD and its role in the local construction industry, development
works and the need for a separate conditions of contracts for local building construction works.
Of the early form of buildings in Sri Lanka, the cave monastries indicate a methodical and
man made cavity in a rock face protected by a drip ledge and a screen wall and often a lean to
roof. A wall in front of the opening consisting of a doorway and windows provided the facade
to this type of monastic building. This form of structure could be attributed to the period third
century B . C . to the first century A . D . The other forms of buildings which can be historically
authenticated are residential buildings constructed using wattle and daub techniques with a
thatched roof.
The next phase in the development in the art of construction is the extensive use of brickwork
in Sri Lanka. Historical evidence of which is available in the form of the mahastupa, the
The development of the monastic buildings around the stupas took place around the fourth
century A . D . The basic concept of the vihara was the central stupa surrounded on three or four
sides by pirivenas or residential buildings. The residential units are mostly pasadas of various
73
sizes arranged in a quadrangle around the central shrine. The architecture of the pasada is
constructed on a elevated platform with regularly placed columns. The super-structure of the
roof and of the upper storeys, if any, was of lighter and more perishable material than the brick
and stone facings of the sub-structure which is all that remains today.
T w o special developments in the materials and methods used in construction can be distinguished
in the period seventh to the tenth century. Firstly the increasing use of stone and secondly the
employment of lime mortar in brick masonry. The use of stone in extra architectural features
and such details as steps was not unknown in the earlier periods, but the overwhelming
impression of the fifth century buildings at Sigiriya were of exclusively brick and timber
architecture. From this time onwards stone was increasingly used in the base mouldings
entrance, stairs and pillars of major structures. The soft lime-stone techniques were replaced
by the much harder and more common granite around the sixth century. The wooden pillars of
the ground floor were also progressively replaced by stone columns. After the mid eighth
These construction works were done directly under the directions of kings and their Ministers
in different periods of time. The works were assigned to master craftsmen in different trades
and they had to find assistants from their castes to complete the job. It must be noted that
craftsmen belonged to different castes depending on their trades. The major work was co
ordinated by a Minister appointed by the king and in most of the projects the king himself visited
the sites to monitor the work. These craftsmen were rewarded with grants in land for the work
done by them. This system existed until the arrival of Portuguese in A . D . 1505.
(Weerakkody,1986).
Portuguese started getting the services of locals for daily wages. Firstly this system was started
in the army, and later it spread to other areas like construction. During the Portuguese and
74
Dutch periods the significant construction work comprised of the army encampments
urbanization, building construction and the Dutch canal system. In this period both brought
engineers and skilled craftsmen from their countries to construct buildings, seafortresses and
canals to transport goods, and at the same time, local craftsmen were also employed to work
The major change in the construction industry occurred during the British rule (1796-1948)
especially during the period of industrialization in England. The governments' main objectives
during this period in Sri Lanka were the preservation of law and order in the country and the
collection of revenue. Any development was, therefore, related to the increase of revenue to
Britain.
During the British rule, construction was mainly to develop roads and railways to serve the tea
and rubber plantations which were the main revenue earners and the infra-structure development
to serve those plantations were given the highest priority and was carried out using the direct
labour system. All the engineering functions were handled by the British through the following
establishments
(Balasooriya, 1992.)
The construction of houses was purely an individual effort during this period, which later
developed into a contracting system due to the increase in quantum, and the changes in
technologies adopted. The building activities were mainly in the hands of the government
departments except for traditional housing and smaller buildings of not more than two storeys
which were either owner built or built by the insignificant private sector that existed at that time.
A few large firms of British origin existed (Walkers, Browns, Colombo Commercial Co. etc.)
75
which provided for the building and other engineering needs, mainly of the plantation industry.
The Public Works Department (PWD) was responsible for the design, construction and
maintenance of all public buildings. This department was originally staffed by British engineers
who were gradually replaced by Sri Lankans who them-selves were trained in Britain. The
design for most buildings followed "Type - plans" developed in the department. (Gunasekara,
After 1948 the same (Similar to colonial period) construction system existed in this country and
some of the sizeable new buildings designed and constructed in the post - independence years
by the P W D are the office buildings for the then department of government electrical
undertakings, national savings bank building, the new central telegraph office building, all in
Colombo. The design and construction of the university scheme in Peradeniya during the same
period was the largest building project of the time. Construction works were handled mainly
by private contractors using known technologies of in-situ concrete construction and brick-work.
But, British engineers in the government sector were gradually replaced by local engineers and
technical staff. At the same time, ownership of their companies was also gradually passed on
to the locals. In addition to this, local construction companies, small scale contractors who got
The government's action after 1948, in relation to the construction industry was the outcome of
the policies of the government and was very keen to improve the agricultural sector of the
country by bringing large acres of lands under cultivation, developing major irrigation schemes
and to constructing the houses for its employees. Therefore, the government had been a client
The local authorities were engaged in construction of houses. While the government was
engaged in the construction of houses, it took some fiscal measures or policy decisions to
76
encourage the private individuals and societies to construct houses. The first action taken was
the formation of a Board with funds in 1949 and authority to grant loans for the execution of
housing schemes not to individual housing units. Societies and individuals who could put
forward housing schemes and those who could supply building materials for the execution of
From 1952, the government's objectives were the completion of large housing schemes,
irrigation works, roads and new works such as the development of the Colombo harbour and the
gal oya scheme. During the period 1950's , the government gave tax relief for the expenditure
made by the private sector on capital expenditure such as plant, machinery and buildings to
encourage the private individuals and societies to participate in construction. At the initial stage
there was no apparent increase in investment, the government further continued to extend such
reliefs to get increases in housing and building stock of the country and by which it was
expected to make a contribution to the Gross National Product (GNP) of the nation.
As a result of the government's incentive measures there was a significant change in the
roads and providing new roads, the maintenance of inland navigation, the maintenance of bridges
and also in construction and maintenance of water supply schemes and building construction.
The government also had a major role to play in the administration of housing, both in the field
of direct construction as well as regulating the housing development by private individuals and
agencies. The capital cost on housing was relatively very much higher in relation to the income
of the average citizen of Sri Lanka. Therefore, it was necessary for the state to help the people
to achieve this basic need as in food and clothing, by means of financial assistance. There are
also facts available that the government had enacted ordinances towards housing before
independence. The government after independence had taken action to construct the houses for
its employees. Hence the government had been a client in the construction industry. The
governments' monitory and fiscal policy decisions and various legislative actions had effected
77
In 1953, the policy adopted in 1949 was amended to allow a person not only to erect a house
but also to complete a partly built house or to erect an extension to a house. The first Ministry
of Housing was created in 1953, and the National Housing Department was established under
it. The new Department of Housing engaged in the building of houses and in granting loans to
With the planned industrial expansion that took place under the state sector in the post 1956
period, there was the necessity to construct many large factory buildings. It was quite rightly
decided then that the P W D or the Industries Department, which were relatively small
departments then, were not geared to deliver the goods in meeting the enormous requirements
The State Engineering Corporation (SEC) was established in 1962 under the leadership of Dr.
A . N . S . Kulasinghe to handle the design and construction of buildings and engineering works for
the numerous state sector industrial development projects launched under the then Ministry of
Industries. Subsequently, the SEC expanded its services to other areas including office
buildings, housing, hospitals, new town development, hydropower projects, etc. During the
early days, such as the central bank building, Colombo, were designed and constructed by
foreign consultants and contractors. The PWD then, was probably not considered proficient
enough to be entrusted with such works. The Buildings Department, carved out subsequently
form the P W D in 1969 continued with very conventional buildings for the public sector. A few
tall buildings appeared in Colombo during the period (1968-80) and some of the more notable
ones then were the insurance building, people's bank building, SEC building, CECB building,
national housing secretariat, labour secretariat and inland revenue building. These building
structures were designed and constructed by the local engineers working in various
Private sector consultancy firms which were commissioned in the early 1960's were limited to
architectural practice only. There existed however a couple of individual structural engineers
who provided the structural design and drawings to some architects and architectural firms and
78
carried out general supervision of structural construction on an adhoc basis. With the change
in government in 1965, there was a change in policy. Local consultants were entrusted with
civil engineering consultancy assignments for the fist time. The first formal private engineering
consultancy practice was started in 1968 was Engineering Consultants Limited. (Balasooriya,
1991).
Also in the late 1960's there were certain amount of private sector consultancy firms
commissioned to a limited extent for the large volume of state sector projects in the architectural
practice. Several consulting engineering firms were established in the late 1960's and it was
then thought that private consultancy practice had taken root. By the year 1970 all forms of
government financed construction works were highly developed towards the use of contracting
systems. However, with another change of government in 1970 the consulting engineering firms
that were established during the period 1965-1970 took a nose drive in 1970-1971 with many
of the firms putting up their shutters and the principals of such firms seeking employment
abroad. Except for a few architectural firms, most of the other consultancy organisations went
out of business. It was indeed a big sleep as far as consulting engineering was concerned during
the period 1971-1977 with little or no development work being done. What little development
work that was being done, both consultancy and construction, during the period 1971-1977 were
carried out by the public sector, except for a few building projects entrusted to favoured
architectural firms. During this period (1971-1977) the government policy was that the
using direct labour, which condition existed until 1977. (Balasooriya, 1992), (Zylva at el 1989)
A s a result of the change of government in 1977 and its "open economy" policy and foreign aid
and grants to finance the new development plans, the then government received W B and
International Monitory Fund (IMF) support and formulated Public Investment Programme (PIP).
Under the first 1977 PIP three of the major projects initiated were
79
(i) One thousand housing programme
(Zylva at el 1989).
All of these involved massive civil engineering and building works. A change of policy in 1977,
resulted in reverting back once again to contracting systems for all forms of government financed
building and civil engineering construction, due to the inability of the system of construction by
government agencies using direct labour to cope up with the massive development programmes
In accordance with the general trends in the historical changes in the industry, management
during the colonial times was through the Ministry of Public Works. The government by cabinet
decision decided to entrust a part of the heavy development programme to the Ceylon Chamber
Consortium (SLCC) which was established in 1980 for this purpose recommended a consultant
for the design through construction supervision and a contractor for the execution of the works
based on the consultants plans and specifications which were often approved by the client. Due
to this, apart from agencies responsible for the construction of buildings in Sri Lanka under the
public sector such as purely public sector department (Dept. of Buildings) and public sector
corporations, with the execution of works placed on the private sector organisations the scenario
in the building industry changed drastically. At this time the private sector organisations as well
as public sector organisations were ill-prepared to, and incapable of undertaking on their own,
the large development projects, viz, multi storey housing, shopping and market complexes,
university expansion and large office complexes. Since the foreign loans and grants were used
to finance these massive projects, foreign consultants and contracting companies were brought
in to various large projects, tied to "Aid" packages. For the design and construction of some
very ordinary office buildings for the government, foreign agencies were commissioned
organizations being set up to undertake design and/or construction supervision. Some of these
80
consultancy organizations did neither have the capability nor the expertise of undertaking
challenging consultancy assignments. During this period, even though the government awarded
the contracts on competitive bidding due to the influx of work, not much effort was required
from the contractors to procure jobs. Furthermore, during 1977, the SLCC started assigning
work to both contractors and private consultants registered with them. SLCC contracts were
executed on a cost + basis. The contract sum was negotiated with the technical committee of
the then Ministry of Local Government, Housing and Construction, on the basis of basic cost
+ 35% allowance for overheads and profits. The Consortium received 3 % service charge
deducted from payment to contractors. The other notable problems due to massive development
arised in this period among the private sector organisations were, weakness in their competence
and capability, viz, timeless of performance, quality of performance, reliability of cost estimates,
After 1977, a few private sector consulting engineering firms have been set up to provide
specialised engineering services in structural engineering, water supply and drainage engineering,
and management services. During the post 1977 period to-date, existing consulting firms grew
and many new practices have appeared on the scene some of which have now established
As a result of the return to contracting system, it was necessary to register contractors. The
system which was adopted for utilizing private contractors to handle work on a priority basis is
on negotiated rates, rather than on a tender system. Contractors registered with the SLCC.
However, it has been decided to reverse back to the tender system, and contractors are now
For large building projects, such as markets, administrative complexes, and large housing
projects, contractors are registered for the specified jobs based on their experience, and short
For jobs which could be handled by local contractors open tendering systems were used and it
81
is generally found that only local contractors would apply for the jobs, since the overheads of
foreign contractors prevent them form being able to provide competitive jobs.
In the post 1977 period (1977-1987) large investments in buildings arising from the policy
changes, also generated much more building activity in the private sector - hotel industry, office
buildings, housing development, factories for the Free Trade Zone, etc. This period was a
boom period for the construction industry in Sri Lanka. (Fernando, 1986), (Joachim, 1988) and
(Balasooriya, 1992).
A s stated in 5 . 2 , the period from 1977 to 1987 was a boom period for the local construction
intervention to protect in the first place, and thereafter develop and strengthen the construction
In the beginning of 1980, the government of Sri Lanka made a positive attempt to develop the
domestic construction industry with a firm commitment supported by the W B and the United
In January 1981 the Construction Industry Training Project (CITP) under the then Ministry of
Local Government, Housing and Construction was established and initiatives were taken to
establish the Association of Construction Contractors of Sri Lanka (ACCSL). Some of the main
(i) Establish an unified modular training system for construction related trades to improve
the productivity and earning capacity of construction workers and provide opportunities
(ii) Improve the operations and maintenance of construction plant and equipment by training
82
(iii) Increase the effectiveness of work planning and supervision by training middle and upper
(iv) Improve and streamline the methods and procedures relating to the construction industry,
(v) Strengthen the agencies and institutions involved in training for the construction industry.
(Refer 17)
This project was partly financed by the International Development Agency (IDA) and was
supported by consultants from the British Council. A national steering committee for the
construction industry was established under this project to co-ordinate activities under (iii), (iv)
and (v) above. Since 1981 CITP has been in the forefront providing assistance to contractors
During the period from 1981 to 1986, the government concentrated on the training of
construction skills to meet the project demands created by the construction boom. In addition
to the training function, CITP was also expected to "Implement standardisation of construction
In April 1986 the CITP was transformed into ICTAD as a permanent institution under U D A to
re-structure the construction industry (i.e. to face up to challenges that had emerged with the
I C T A D has three divisions under its umbrella namely construction development division, training
The construction industry development division of ICTAD has three sub-divisions. These are
83
(i) Technology development unit
This unit was set up to transfer information on methods, materials and equipment available to
owners as well as in promoting the use of local materials and familiarisation with appropriate
(ii) C o n s t r u c t i o n economics u n i t
This is concerned with the improvement of the operating environment of the construction
industry and would be involved in the quantitative and qualitative analysis of special problems
affecting the construction process and recommending changes in building procedures, contract
requirements, etc.
(iii) I n d u s t r y development u n i t
This is primarily concerned with improving the management capability of national contractors
and developing various project and programmes to improve the efficiency of contractors.
From 1986, the ICTAD took several measures to address its attention to the development of the
By about 1986, local contractors were of the opinion that there was a heavy under utilization of
capacities in the construction industry due to a shortage of work. The disturbed civil conditions
and resultant uncertain investment climate were major causes for the contraction in construction
activity. This sense of insecurity was further aggravated by the feeling that foreign contractors
A report complied by the ICTAD notes "The basic problem is a lack of defined long term policy
for the development of the local industry. Infact, it is not even treated as a industry in policy
84
formation. The state should formulate a strategy for the long term development of the industry".
As a result the government in mid 1987 appointed a high powered four member committee to
study and identify the problems affecting the local construction contractors to enable the
This committee made an in-depth study and after one year of deliberation, identified six main
areas that affected the development of domestic contractors and the industry. They were
(iv) The need for the ACCSL to expand its membership and its activity and establish
industry.
It is generally accepted that, inadequacy of working capital is among the serious problems
of the domestic contractors. Each of the above were then analyzed in more detail and several
proposals were made under each head for consideration of the government. These proposals
were formulated, elaborated on and presented in the from of recommendations for the
consideration of the cabinet of ministers by the then Hon. Prime Minister and Minister of
Housing and Construction. These recommendations were approved by the cabinet on 10-08-
1988.
By recognizing the difficulties faced by the local construction industry, the ICTAD started a
number of projects to develop the local construction industry. Some of them are
(iv) Obtaining cabinet approval for issues which help to improve the local construction
85
industry.
them was one of the major tasks handled by ICTAD during the year 1989. According to this
grading system the contractors have been graded under categories of five engineering fields.
Grade Capacity
2 Rs. 15 M - 50 M.
3 Rs. 5 M - 15 M.
4 Rs. 1 M - 5 M.
5 Rs. 2 5 0 , 0 0 0 - 1 M.
Furthermore, by a cabinet memorandum, dated 14-06-1988, the cabinet also divided that one of
the pre-requisites for a contractor to take a government job is that the contractor must be a
I C T A D also had developed and had intention to develop the standard conditions for
86
5.4 I C T A D Conditions of C o n t r a c t
Publication No S C A / 1
As stated in 5 . 3 , one of the objective of the CITP and its successor ICTAD was preparation of
the standard form of conditions of contract and its revision of the effective contract management
The national steering committee, which was established under the CITP project, through an
agreement of a subject area sub-committee and working groups had prepared conditions of
contract for works of building and civil engineering (With forms of tender and agreement),
regulation for tender procedures and several specifications in the field of civil engineering to
meet Sri Lankan conditions and requirements. The Sri Lanka conditions of contract (First
edition) for works of building and civil engineering had been originally prepared by a five
This document had been recommended by the national steering committee for the construction
industry and adopted by the secretaries' committee of the construction industry in 1986. (Refer
17).
The ICTAD conditions of contract (First edition) was based purely on FIDIC conditions of
contract (Third edition) with little modifications made to suit the local construction industry.
Upto this period (Before 1986) there was no standard form of contract for all agencies, each
agency generally had its own contract form for jobs of a non specific nature.
While for jobs of specific nature, specific contract documents are studied and approved by the
The legal system available to the construction industry is very broad based and has to be drawn
87
out from the civil procedure code. Except common law no special law exists, defined as law
of building contracts or law of construction contracts. This leads to the situation that both
clients and contractors have got to, at every turn, retain legal advisors to identify the areas of
law that cover a particular issue arising out of a contract. (Ganeshan, 1991) and (Zylva at el
1989).
Publication N o . S C A / 1
As stated in 5 . 3 , the cabinet of ministers approved on 10-08-1988, the memorandum dated 14-
of Local Government, Housing and Construction (Cabinet paper 116 of 1988 continuation 71)
By considering the above, the ICTAD conditions of content had been revised to incorporate the
recommendations. The government had also approved the adoption of the ICTAD conditions
of contract for works of building and civil engineering and further directed the ministries,
government departments, corporations and other state sector agencies to adopt the ICTAD
The revised edition of the ICTAD conditions of contract also had been based mainly on FIDIC
conditions of contract (Third edition). However, there are few sub-clauses based on FIDIC
conditions of contract (Fourth edition) and ICE conditions of contract (Fifth edition). Following
88
Clause N o Description
to 7 calendar days.
(vii) 65 (5) Special risks - Riot, whether directed against the state, persons or
- property is included.
days.
For projects with total domestic funding and meant entirely for local tendering, ICTAD
conditions of contract is used by most of the institutions in Sri Lanka from 1989 onwards.
ICTAD had also taken steps in 1991 to review the revised edition of the conditions of contract
by comparing the FIDIC conditions of contract (Fourth edition) under the Chairmanship of Dr.
From the survey carried out, it has been able to find out that various conditions of contracts have
been used by the private sector consultants (Architects). The following table gives a summary
89
Table 5.1 V a r i o u s conditions of contracts in use in S r i L a n k a
1989
Private Sector (i) RIBA conditions of contract
modification)
After
Private Sector (i) ICTAD conditions of contract
1989
(ii) RIBA conditions of contract
modification)
90
5.6 N e e d f o r a S e p a r a t e Conditions of C o n t r a c t f o r B u i l d i n g C o n s t r u c t i o n W o r k s
As stated in earlier chapters in the U.K. and in some other countries separate conditions of
contracts are used for building and civil engineering construction works. However, ICTAD
conditions of contract had been recommended for both building and civil engineering
It is necessary to study whether there is a need for a separate conditions of contract for building
construction works.
construction w o r k s
(i) The base document for ICTAD conditions of contract is the FIDIC conditions of contract
(Third edition). In the revision of the FIDIC 3 , the ICE conditions of contract (Fifth
edition) had a significance influence. Both FIDIC conditions of contract (Third edition)
and ICE conditions of contract (Fifth edition) are to be used for civil engineering
construction works. Hence there are doubts, about the efficiency of I C T A D conditions
(ii) Rush Brooke had reported (Rush Brooke, 1983) about many problems faced in the
Middle East building construction works for using FIDIC conditions of contract (Third
edition). H e is of the view that the FIDIC conditions of contract (Third edition) should
(iii) Building and civil engineering construction works have many differences and hence use
of the same conditions of contract may not be correct. (Rush Brooke, 1983).
91
(iv) In many countries separate conditions of contracts are used for building and civil
(v) A study initiated by ICTAD, undertaken by Dr. S. Ganeshan had recommended that
I C T A D should review its conditions of contract (Revised edition, 1989) and then
formulate separate conditions of contract for building construction works, in the public
sector, private sector and also for sub-contract works. (Ganeshan, 1991).
(vi) For the private sector, ICTAD should support the initiative of the Institute of Architects
to work out standard conditions of contract. ACCSL and others may be associated with
92
CHAPTER - 6
CHAPTER 6 - VIEWS OF THE CONSTRUCTION INDUSTRY O N T H E ICTAD
CONDITIONS OF CONTRACT
6.1 Introduction
The questionnaire (See Appendix A) developed to get views of the construction industry on the
involved in the building construction works with a view to get their responses. Subsequently
A few professionals responded immediately and the majority had to be reminded several
times. Details of the sample surveyed are given below. In addition to the questionnaire survey
personnel interviews and discussions were held among some of the professionals.
The data and information gathered were analysed under the following areas
(i) Problems encountered while using the ICTAD conditions of contract for building
(ii) V i e w s about having separate conditions of contract for building and civil engineering
construction works.
93
(iii) Problems encountered while using the FIDIC conditions of contract for building
construction works.
(iv) Views about the cabinet decision for having one conditions of contract for both building
(v) Major differences between the RIBA conditions of contract and the I C T A D conditions
of contract.
6.2.1 Problems encountered while using the I C T A D conditions of contract for building
construction works
(ii) 0 4 responded that the ICTAD conditions of contract is often modified by the
client/consultant to safeguard their interests. The modifications are mainly done in part
II to negate the effect of part I. They have also mentioned some clauses for
modification.
94
Table 6.1 ICTAD clauses for modification.
Clause Description N o . of
No. responses
acceleration)
contract(Fourth edition)
56 Joint measurements 1
60 Advance payment 10
60 Retention money 2
67 Arbitration 6
70 Price fluctuation 5
Some of the professionals indicated that it is difficult to comment on the use of ICTAD
conditions of contract for building construction works, without studying the document in detail.
There were also views expressed by some professionals that the ICTAD conditions of contract
is based on the FIDIC conditions of contract and it is a civil engineering document. Therefore,
the I C T A D conditions of contract will not be appropriate for the building construction works.
They have also indicated that in other countries separate conditions of contracts are being used
approved document.
95
6.2.2 V i e w s a b o u t h a v i n g separate conditions of contract f o r b u i l d i n g a n d civil engineering
construction w o r k s
(ii) 07 responded that there should be separate conditions of contracts for both construction
works.
(iii) 02 responded that it is too early to have separate conditions of contracts for both
construction w o r k s
(i) All 2 0 responded that there is no problem while using FIDIC conditions of contract.
(i) 11 responded that there should be one conditions of contract for both construction works
(ii) 0 7 responded that there should be separate conditions of contract for both construction
works.
96
6.2.5 M a j o r differences between the RIBA conditions of contract a n d t h e I C T A D
conditions of contract
Few selected senior architects were interviewed in this connection and they told that, the RIBA
conditions of contract stresses more on building construction works than civil engineering works.
Also the RIBA form is more British oriented and it is not really suited for Sri Lanka. Compared
understand.
The following are the summary of the views of the professionals on the I C A T D conditions of
(ii) If the I C T A D conditions of contract is used without any negate effect on the content by
any modifications to part I or part II, the real problems could be identified.
(iii) The problems identified by the professionals are general and common for the construction
industry.
(iv) Drawing a line between the building work and civil engineering work is difficult unless
(v) Having separate conditions of contract will not be an appropriate step at this stage.
consultants, clients and contractors based on the experience obtained after using for a
(vi) The present ICTAD conditions of contract is not proper as it is and there are some errors
(vii) Contractors should be taught and allowed to comment freely on any changes made by the
(viii) There is no national policy to use or follow the ICTAD conditions of contract. Therefore,
97
the private sectors cannot be forced to use.
(ix) There should be separate conditions of contract for major works and minor works.
(x) N o major complaints were reported from the departments and state sector organisations
From the questionnaire survey interviews and discussions with building industry professionals
it was revealed that the present ICTAD conditions of contract can be used with little
modifications to some clauses mentioned in 6.2. However, a detailed analysis should be carried
out by comparing building conditions of contract with the ICTAD conditions of contract before
a revision is undertaken.
The findings of the surveys presented in this chapter are taken into account in chapter 7
98
CHAPTER - 7
CHAPTER 7 - COMPARISON OF SELECTED CONDITIONS O F CONTRACTS
7.1 Introduction
Comparison of a few widely used conditions of contracts is a necessity to find out how various
aspects of building construction contracts are covered. This comparison will enable us to
identify necessary revisions, additions and omissions to be made to the ICTAD conditions of
The following widely used conditions of contracts were compared in this study.
(i) FIDIC conditions of contract (International) for works of civil engineering construction,
Parts I, II and III, Form of Tender, Appendix and Form of Agreement. (FIDIC 3)
(ii) FIDIC conditions of contract for works of civil engineering construction, Fourth edition,
September 1987.
Parts I and II, Form of Tender, Appendix and Form of Agreement (FIDIC 4)
(iii) ICTAD conditions of contract for works of building and civil engineering - Sri Lanka.
Parts I and II, Form of Tender, Appendix and Form of Agreement ( I C T A D 89)
(iv) Joint Contracts Tribunal (JCT) standard form of building contract 1980 edition (Local
Incorporating amendments of 1984 and 1986, London, RIBA publication Ltd, 1987.
( J C T 8 0 ).
(v) General conditions of contract for building and civil engineering. GC/WORKS/1
In addition, for the comparison of selected conditions of contracts, ICE conditions of contract
(Fifth edition) and ICTAD conditions of contract for building construction works in Sri Lanka
In the comparison the FIDIC 3 was selected as the base document since the I C T A D 89 is based
on the FIDIC 3 .
99
The summary of the comparison is presented in Appendix B and the presentation is explained
in 7 . 2 . The analysis and necessary modification to the ICTAD 89 based on the comparison,
The summary of the detailed and thorough comparison of the five selected conditions of
below.
modifications.
In addition, the footnotes describe the variations in contents of each clauses from the FIDIC 3
clause.
Footnotes are given only for the clauses which are marked in 'A' and 'B' in the remarks
column.
Footnotes for other clauses which are marked in ' C in the remarks column incorporate in the
modification/revision presented in 7 . 3 .
The comparison reveals that in order to improve the ICTAD 89 for building construction works;
(i) 25 clauses of the ICTAD 89 can be used without any modification (Marked in ' A ' in the
remarks column).
100
The clause numbers are 5 , 9 , 1 3 , 1 5 , 1 8 , 2 4 , 3 1 , 3 2 , 3 5 , 3 8 , 4 1 , 4 3 , 4 5 , 4 7 , 5 4 , 5 5 , 5 6 , 5 7 , 5 8 , 6 1 ,
6 2 , 6 4 , 6 5 , 6 6 , and 7 1 .
(ii) 12 clauses of the ICTAD 89 have to be replaced fully by the relevant clause of FIDIC
(iii) 35 clauses of the ICTAD 89 have to be modified/revised (Marked in ' C in the remarks
column).
(iii) Views expressed by the senior professionals involved in building construction works.
(Through interviews).
The modifications/revisions proposed for each of the clauses identified (Marked in ' C in the
Clause 1
Any notices to be given under the contract shall be in writing. They may be given to the
101
contractor by delivery to his agent or may be posted to the registered office or last known place
of business of the contractor. A postal notice shall be deemed to have been served on the date
(GCW1)
Clause 2
If within 7 days after receipt of a written notice from the consultant requiring compliance
with an instruction the contractor does not comply therewith, then the employer may
employ and pay other persons to execute any work whatsoever which may be necessary
to give effect to such instruction; and all costs incurred in connection with such
employment may be deducted by him from any monies due or to become due to the
contractor under this contract or may be recoverable from the contractor by the employer
as a debt.
12 Clerk of Works.
The employer shall be entitled to appoint a clerk of works whose duty shall be to act solely as
inspector on behalf of the employer under the directions of the consultant and the contractor
shall afford every reasonable facility for the performance of that duty. If any direction is given
to the contractor by the clerk of works the same shall be of no effect unless given in regard to
a matter in respect of which the consultant is expressly empowered by the conditions to issue
instructions and unless confirmed in writing by the consultant within 2 working days of such
direction being given. If any such direction is so given and confirmed then as from the date of
102
Clauses 3 a n d 4
(a) Written consent should be extended to both parties, (i.e. Employer and contractor)
(JCT 80).
(b) Where the contract bills provide that certain work measured or otherwise described in
those bills and priced by the contractor must be carried out by persons named in a list
annexed to the contract bills. The list must comprise not less than three persons. Either
the employer (or consultant on his behalf) or the contractor shall be entitled with the
consent of the other, which consent shall not be unreasonably with held, to add additional
persons to the list at any time prior to the execution of a building sub-contract agreement.
(JCT 80)
(c) The employment of the domestic sub-contractor under the sub-contract shall determine
immediately upon the determination of the contractor's employment under this contract.
(JCT 80).
(d) N o part of the sub-contract work shall be further sub-let without the consent of the
Clause 6
(i) Unless it is strictly necessary for the purposes of the contract, the drawings,
shall not without the consent of the consultant, be used for any other contract or
(ii) Upon the issue of defects liability certificate the contractor shall return to the
(iii) If the permanent work is designed by the contractor, then he has to supply 4 copies of
such drawings to the consultant. The contractor shall supply any further copies of
drawings and other documents as the consultant may request in writing for the use of tiie
103
1
employer, who shall pay the cost of such additional copies. (FIDIC 4 ) .
The consultant shall after due consultation with the employer and the contractor
(iv)
determine the delay. (FIDIC 4)
Clause 7
I n a d d i t i o n t h e f o l l o w i n g sub-clauses have to be a d d e d .
(i) The consultant shall provide without charge to the contractor with two sets of further
The contractor and the consultant, if either one so requests, shall jointly prepare a
schedule subject to change from time to time in accordance with the progress of the
work, fixing the dates at which the various detail drawings will be required, and the
consultant shall furnish them in accordance with the schedule. Also schedule can be
prepared for beginning of manufacture and installation of materials and for the
The contractor shall prepare at his own expense and submit with such promptness as to
cause no delay in his own work or in that of any other contractor doing work on the
same building, two copies of all shop or setting drawings, templates, patterns and
104
I I
models, as well as schedule required for the work of the various trades, and the
consultant shall pass upon them with reasonable promptness, making desired corrections.
The contractor shall make any corrections required by the consultant in the submitted
copies.
Before submitting shop drawings for approval, the contractor shall check drawings of all
(v) Identification
Shop drawings shall be numbered consecutively and represent with all relevant details.
containing name of project, contractor's name, serial number of drawings and titles.
The contractor shall submit 3 sets of prints of shop drawings to the consultant for
approval. One copy of the satisfactory shop drawings shall be returned to the contractor.
Should shop drawings be disapproved by the consultant one set of such shop drawings
shall be returend to the contractor with necessary corrections and changes to be made as
1
indicated.
(a) The contractor shall make required corrections and changes and re-submit shop drawings
(b) Upon receipt of approval, the contractor shall insert date of approval on tracings and
(c) N o work called for by shop drawings shall be executed until the consultant's approval
(d) If shop drawings show variation from contract requirements because of standard shop
practice or other reasons, the contractor shall make specific mention of such variations
105
Approval of shop drawings will be general. It shall not relieve the contractor of
responsibility for accuracy of such shop drawings nor for proper fitting and construction
of work, nor for furnishing of materials or work required by the contract and not
shall not relieve the contractor from responsibility for deviations from drawings or
specifications, unless he has in writing called the consultant's attention to such deviations
at the time of submission and secure his written approval, nor shall it relieve him from
Clause 12
T h e f o l l o w i n g sub-clauses have to be a d d e d .
(i) Written notice shall be given to the consultant with a copy to employer regarding
obstructions. The consultant shall, after due consultation with the employer and the
(ii) The contractor shall forward his proposals with the notice to the consultant in regard to
Clause 14
T h e f o l l o w i n g sub-clauses have to be a d d e d .
(i) The contractor shall submit a detailed cash flow estimate in quarterly periods, of
all payments to which the contractor will be entitled under the contract. (FIDIC
4).
(ii) The contractor shall submit two copies of the master programme free of charge
to the consultant and within 14 days of any decisions by the consultant regarding
extension of time, the contractor has to submit two copies of any amendments and
(iii) The programme should contain the temporary works, method of work, and labour and
Clause 16
T h e f o l l o w i n g sub-clause has to be a d d e d .
106
(i) The contractor shall not make changes in personnel named in his tender in connection
with the contract without the prior approval of the consultant, other than for causes
outside the contractor's control, which shall not be unreasonably withheld by the
Clause 17
T h e f o l l o w i n g sub-clauses have to be a d d e d .
(i) All the details to be given to setout the works, shall be at the ground level. (JCT 80)
(ii) Any discrepancies in or divergences between documents formed by the contractor shall
Clause 19 v
IWM1
T h i s has to be replaced f u l l y by clauses 1 9 . 1 a n d 19.2 of F I D I C 4 .
(i) Statutory regulation should be complied in respect of storage and use o f a l l things which
Clause 2 0
contractors.
I n a d d i t i o n t h e f o l l o w i n g sub-clauses have to be a d d e d .
(i) If the contractor is unable or unwilling to carryout promptly any emergency work required
by the consultant the employer may make arrangements for that work to be carried out. If the
work carried out by the employer shall be such as the contractor is liable under the contract to
carry out or execute at his own expense then the contractor shall reimburse any costs incurred
by the employer and any loss suffered by the employer, because the contractor has not carried
107
(ii) Existing utilities, if damaged due to negligence or fault of the contractor shall be repaired
(iii) In an emergency during the execution of the works or during any maintenance period
affecting the safety of life or of the work or of adjoining property, the contractor without
to act, at his discretion, to prevent such threatened loss or injury any he shall so act
Clauses 2 1 a n d 2 5
I n a d d i t i o n t h e f o l l o w i n g sub-clauses have to be a d d e d .
(ii) Insurance cover period should be modified as end of maintenance period or upto
(iii) Contractor shall give written notice both to the consultant and to the employer in the
(iv) Additional premium involved in the case of extension of time should be included.
(JCT 80).
80).
(vi) Responsibility of the employer and the contractor in regard to the existing
Clause 22
I n a d d i t i o n t h e f o l l o w i n g sub-clause has to be a d d e d .
(i) Loss of profits or loss of use suffered because of any loss or damage should be included.
(GCW 1).
Clause 2 6
108
T h e f o l l o w i n g sub-clauses have to be a d d e d .
(i) Where there is any divergence between the statutory requirements and all or any of the
contract document or between the statutory requirement and any instruction of the
consultant requiring a variation then the contractor shall immediately give to consultant
a written notice. Then the consultant within 7 days on receipt of the notice has to issue
the instruction in relation to the divergence. If any works vary in regards to instructions,
then those instructions will be treated as variation orders issued by the consultant (JCT
80)
(ii) In any emergency compliance, the contractor has to comply with the statutory
requirements and inform the consultant, and this work shall be treated as a variation
Clause 2 7
(i) The contractor shall inform the consultant or the clerk of works of the discovery
(ii) The consultant shall issue instructions in regard to what is to be done concerning
an object reported by the contractor and such instructions may require the
party. Any such third party shall be deemed to be a person for whom the
(iii) If in the opinion of the consultant compliance with this clause or with an instruction
issued under this clause has involved the contractor in direct loss and/or expense for
which he would not be reimbursed by a payment made under any other provision of this
contract then the consultant shall himself ascertain the amount of such loss and/or
(iv) If and to the extent that it is necessary for the ascertainment of such loss and/or
expense the consultant shall state in writing expense the consultant shall state in
(v) If any materials found from the excavation shall be used for permanent works,
109
those will be assessed by the consultant and that amount shall be deducted from
Clause 2 8
(i) All royalties or other sums payable in respect of the supply and use in carrying
out the works shall be deemed to have been included in the contract sum. (JCT
80).
(ii) All royalties or other sums payable with the consultant's instructions shall be
(iii) The employer shall reimburse the contractor the amount of any royalty etc, which
(b) was not reasonably contemplated under the contract. (GCW 1).
Clause 3 0
Clause 3 4
(i) The employer shall has the power to inspect the wages books and time sheets of the
contractor's employees and the contractor shall recognise the freedom of his work people
Clause 3 7
110
(i) When the work is to be so prepared in workshops or other places of a domestic sub
contract so far as possible secure a similar right of access to those workshops or places
for the consultant and his representatives for inspection. (JCT 80).
Clause 4 4
(i) The extension of time shall be granted with due consultation of employer and the
contractor and shall be notified the contractor with a copy to employer. (FIDIC
4).
(ii) The extension of time claim shall be made in writing to consultant by the
(iii) The extension of time claim shall be rejected by the consultant if no notification is made
(iv) Final decision on extension of time shall be made within 60 days after issuing the
(vi) The consultant shall fix the new completion date within 60 days from the receipt
(vii) Any dissatisfaction of the consultant's decision by the contractor should be notified within
(viii) N o requests from the contractor shall be made for extension of time after completion of
Clause 4 6
Ill
(i) If the contractor wants to work at night or on holidays to cover the delay then the
additional supervision charges shall be recovered by the employer from the contractor.
The charges shall be determined by the consultant with due consultation with employer
Clause 4 8
(i) The contractor shall give the written notice to th consultant with a copy to the
(ii) The contractor shall request the consultant to issue a certificate of practical
completion to any part of the permanent works which the employer has elected
(iii) The contractor or the employer shall inform the insurers in regard to storage of the
employer's goods or partial possession and any additional premium involved in this shall
Clause 4 9
(i) The "certificate of completion of making good defects" shall be issued by the consultant.
(JCT 80).
(ii) In the case of partial possession by the employer, the insurance premium shall be
deducted with due consultation with the consultant and the contractor. (JCT 80).
Clause 5 0
112
T h e following sub-clause has to be added to this clause.
(i) Any defects not rectified by the contractor shall be rectified by another party appointed
by the employer. The cost involve in this shall be recovered from the contractor. (GCW
1).
Clause 51
(i) Change any specified sequence or timing of construction of any part of the works.
(FIDIC 4).
(a) Access to the site or use of any specific parts of the site.
(d) The execution or completion of the work in any specific order. (JCT 80).
Clause 52
Clause 5 3
termination.
113
(ii) 5 4 . 6 of FIDIC 4 - Costs in the case of termination.
(iii) 5 4 . 7 of FIDIC 4 - The contractor shall, where entering into any sub-contract for the
contractor's equipment, temporary works or materials brought on to the site by the sub
contractor.
(iv) Any materials or goods included in any interim certificate shall be employer's
property and the contractor shall remain responsible for loss or damage to the
(v) The contractor shall furnish the schedule of proposed plant and equipment and
their substitutions prior to the signing of the contract for the approval. After
(vi) Although the plant and equipment schedule is approved by the consultant, the
responsible.
(vii) The temporary or trail usage by the employer of any mechanical device, machinery,
apparatus, equipment or any work or materials supplied under contact before final
completion and written acceptance by the consultant shall not be constructed as evidence
(viii) The contractor shall furnish and maintain all equipment such as temporary stairs, ladders,
ramps, scaffolds, run ways, derricks, chutes and the like, as required for proper
execution of work by all trades. All such apparatus, equipment, and construction shall
meet all requirements of labour law and other local laws applicable thereto.
Clause 5 9
114
I n a d d i t i o n to this t h e following sub-clauses have to be a d d e d .
(i) In the definition of nominated sub-contractor (i.e. 59.1 of ICTAD 89) the supply of plant
(ii) Provisional sums and prime cost sums has to be included. (JCT 80).
(iii) The contractor shall not grant to any nominated sub-contractor any extension of time
within which the sub-contract works without the written consent of the consultant. (JCT
80).
(iv) If any nominated sub-contractor fails to complete the sub-contract works within
the period specified in the sub-contract or within any extended time granted by
the contractor with the written consent of the consultant, and the contractor so
provided that if the consultant is satisfied to grant extension of time then he shall
so certify in writing to the contractor not later than 30 days from the date of
notification. Immediately upon the issue of such a certificate the consultant shall
(v) The consultant shall issue a certificate of practical completion to the nominated
(vi) If the original nominated sub-contractor fails to rectify any defect, shrinkage or
other fault in the sub-contract works then the consultant shall appoint another sub
contractor to rectify those defects, the cost involved in this shall be recovered
(vii) The contractor shall not be responsible to the employer in respect of any nominated sub
115
(viii) Provision should be made for re-nomination. (JCT 80).
(ix) The contractor shall not determine any nominated sub-contract without an
Clause 6 0
6 0 . 1 - Advance payment of 20% of the contract sum shall be made at one stage following the
guarantee acceptable to the employer for the full value of the advance payment.
6 0 . 4 - Combined bond should cover the full value of the retention money and the performance
bond.
60.11 To be deleted.
(i) Any cost incurred by the contractor shall not be subjected to retention. (JCT 80).
(ii) Any amount allowable by the contractor to the employer shall not be subjected to
(iii) Provision should be made to include off-site materials or goods. (JCT 80).
(iv) Final statement should be submitted by the contractor not later than 5 6 days after
116
Clause 63
(i) Written notice shall be given by registered post or recorded delivery specifying
(ii) If the contractor shall have offered or given or agreed to give to any person any
gift or consideration of any kind as an inducement or reward for doing the job,
as a bribe, then the employer shall be entitled to determine the employment. (JCT
80)
(iii) The employer shall pay any supplier or sub-contractor (Nominated or domestic) for any
materials or goods delivered or works executed for the purposes of this contract (Whether
before or after the date of determination) in so far as the price thereof has not already
(iv) If the employer appoints a new supplier, new nominated or domestic sub
any reasonable objection to any further assignment thereof by the employer. (JCT
80).
(v) The employer shall pay to the contractor any amounts due within a reasonable
Clause 67
(i) Provision should be made in the contract for either party in the event of disagreement
with the consultant and after referring a dispute to the consultant for his final decision
117
(ii) I C T A D 89 clause contents should be replaced by FIDIC 4 clause contents, except the
Clause 6 9
(i) Continuous suspension of work shall be considered for determination by contractor. (JCT
80).
(ii) The reasonable cost of removal of materials or goods from site shall be paid by the
(iii) The total value of work completed and additional works carried out at the date of
respect of direct loss and/or expense shall be paid by the employer. (JCT 80).
(v) The cost of materials or goods properly ordered for the wok for which the
contractor shall have paid or for which the contractor is legally bound to pay and
on such payment by the employer any materials or goods so paid for shall become
(vi) The contractor shall with all reasonable dispatch and in such manner and with
such precautions as will prevent injury, death or damage of the classes in respect
118
(vii) The contractor shall give written notice by registered post or by recorded delivery to the
Clause 7 0 .
(ii) Price adjustment formula method shall be used by using the ICTAD indices. ICTAD
should take steps to review the indices to cover all the works.
119
CHAPTER - 8
CHAPTER 8 - CONCLUSIONS AND RECOMMENDATIONS
8.1 Conclusions
into
Various types of contracts of the above two methods are described in detail in
chapter 2.
2. In Sri Lanka, the traditional bill of quantities (Measure and pay) types of
contracts are widely used in both the public and private sector in procuring
in the U.K. for different types of procurement methods. The important feature is
that the building and civil engineering contracts use different conditions of
4. FIDIC 3 although intended for measure and pay type civil engineering works,
have been used for building construction works as well in other countries.
5. Problems arising from using FIDIC 3 for building works have been documented.
120
(ii) Tenders advertise locally:- Conditions of contract is I C T A D 89.
7. Building construction works of the private sector in Sri Lanka uses a modified
conditions of contract.
(i) About 55% think that the separate conditions of contract for building and
civil engineering construction works are not required. But 35% think
other way.
are the general clauses cover for both building and civil engineering
(iv) Some consultants have not faced much problems with ICTAD 89. It may
works.
10. Building and civil engineering construction works have some different notable
121
In building construction works
(v) Design and supervision works are usually carried out by chartered
(iv) Design and supervision works are usually carried out by chartered civil
engineers
122
(i) 25 clauses of the ICTAD 89 can be used without any modifications.
clause of FIDIC 4.
72.
8.2 Recommendations
1. ICTAD should take steps to introduce, explain and solve problems arising of the ICTAD
2. Periodic seminars should be held to discuss experiences and to identify revisions required
(i) Local practices and views of the professionals involved in building construction
123
works.
(iv) Studying other conditions of contract (Make use of the comparison done in this
study).
4. Contractors should be taught and allowed to comment freely on any changes made by the
5. There should be a national policy to use ICTAD conditions of contract without changing
6. There should be separate conditions of contract for major and minor building construction
works.
consultants, clients and contractors in association with the ACCSL, the I C T A D , the
Surveyors.
124
REFERENCES
REFERENCES
Austen, A.D. and Neale, R.H.(1990). "Managing Construction Projects - A Guide to Processes
and Procedures". Genova, International Labour Office, pp 5-33.
Balasooriya, B.M.A. (1992). "Historical aspects of the building industry in Sri Lanka".
Proceedings of a seminar on engineering research and development, Faculty of Engineering,
University of Peradeniya, (Jubilee 1942-92).
Dickason, Ivan (1985). "JCT 80 and the builder an introduction", CIOB publication.
Fernando, C.C.T.(1986). "Consulting practice in Sri Lanka". Lecture note delivered at the
(World bank/UNDP/FIDIC/The Association of Consulting Engineers, Sri Lanka) seminar held
in Hotel Galadari Meridian, Colombo.
FIDIC conditions of contract for works of civil engineering construction, FourUi edition,
September 1987, FIDIC publication.
10. Ganeshan, S.(1991). "Development of the national construction industry - A case study of Sri
Lanka". An ICTAD publication in association with the world bank.
11. General conditions of contract for building and civil engineering- GC/WORKS/1 (Edition 3),
(Lump sum with quantities)(December 1989, Revised edition 1990),HMSO, Department of the
Environment Property Holdings, London.
12. "Guide to the use of FIDIC" (Fourth edition),(1989). Conditions of contract for works of civil
engineering construction, FIDIC publication.
13. Gunasekara, Mervyn. P. (1990) "Procuring construction projects in Sri Lanka - Contractor's view
point". Seminar notes on construction management of Asian Productivity Organisation conducted
by the ICTAD and the NI13M.
14. Hugh Clamp and Stanley Cox. (1990). Which contract? choosing the appropriate building
contract, RIBA publications.
15. ICE conditions of contract and forms of tender, agreement and bond for use in connection with
works of civil engineering construction, Filth edition (June 1973) (Reprinted January 1986).
16. ICTAD conditions of contract for building work, Sri Lanka. Unpublished document (Draft).
17. ICTAD conditions of contract (First edition - September 1986), CITP Publication No. SCA/1.
18. ICTAD conditions of contract (Revised edition - January 1989), ICTAD Publication No. SCA/1.
19. JCT Standard form of building contract 1980 edition (Local authorities with quantities), RIBA
publications Ltd, London.
20. Joachim, M.E.(1988). Survey report on construction industry in Sri Lanka (Phase 1)., Asian
Productivity Organisation.
21. Jones, Glyn P.(1979). " A new approach to the international civil engineering contract". New
York, The Construction Press Ltd.
22. Kulasinghe, A.N.S. (1986). "The Development of Consulting Engineering Practice in Sri Lanka".
Lecture note delivered at the (World bank/UNDP/FlDIC/ The Association of Consulting
Engineers, Sri Lanka) Seminar held in Hotel Galadari Meridian, Colombo.
23. Kumarasinghe, Jaliya and Kumarasinghe, Ananda (1990). "Country paper on the construction
industry in Sri Lanka". Seminar notes on construction management of Asian Productivity
Organisation conducted by the ICTAD and the NIBM.
24. Ramus, J.W.(1989). "Contract Practice for Quantity surveyors". Second edition,
U.K.,Heinemann, Newnes.
25. Ratnayake, A.(1991). "Contract administration practices in Sri Lanka". Seminar notes on
engineering consultancy and contracting practices in the SAARC region held in Colombo,
Organised by the Institution of Engineers Sri Lanka with Federation of Engineering Institutions
of South and Central Asia.
26. Rush Brooke, P.L. (1983). Working with FIDIC", A practical approach to its use in the Middle
East, CIOB publication.
27. Sawyer, John.G. and Arthur Gillott, C. (1990). "The FIDIC Digest - Contractual relationships,
responsibilities and claims under the fourth edition of the FIDIC conditions". First edition,
London, Thomas Telford Ltd.
28. Spiers, G.S.(1983). "The standard form of contract in times of change", CIOB publication.
29. Tissera, CH.de.(1990). "ICTAD Profile". Ministry of Policy Planning and Implementation.
30. Wallace, Duncan I.N. (1974). "The international civil engineering contract". First edition,
London, Sweet and Maxwell Ltd.
31. Weerakkody, Felix (1986). "Historical background of the construction industry in Sri Lanka".
Research paper submitted to the master of business administration degree at University of Sri
Jayawardanapura on managerial analysis of the construction industry in Sri Lanka.
32. Zylva, Eddie De., Weddikkara, Chitra., and Emmanuel, M.P.R.(1989). "Sri Lanka construction
industry in the 80's". (Project SRL/86/001-IDA/UNDP/ILO).
INTERVIEWS AND DISCUSSIONS
Professionals Participated in the Interviews a n d Discussions
A T T E N T I O N OF
Dear Sirs,
Therefore I will be very much grateful to you, if you could give information by filling
the attached questionnaire at your earliest convenience and send it to my Colombo address. For
your convenience, I am enclosing a self-addressed stamped envelope.
Since no telephone facilities are available at my working place, it will be very difficult
to contact you over the telephone during working hours.
Please also note that all information provided by you will be treated strictly confidential
and used solely for the specific purpose of the survey.
I hope your kind co-operation and assistance to make this survey a success.
Thanking you,
Yours faithfully,
(signed)
N . Logeswaran
R E S E A R C H PROTECT QUESTIONNAIRE FOR M.Eng. D E G R E E IN C O N S T R U C T I O N
M A N A G E M E N T . D E P A R T M E N T O F CIVIL E N G I N E E R I N G . U N I V E R S I T Y O F
MORATUWA
(i) The types of conditions of contracts used in Sri Lanka, in the past
and the present.
(ii) The necessity to modify the ICTAD conditions of contract to suit
local building construction works.
1.0 GENERAL
1.4 Discipline of work:- (If you do work in more than one discipline please indicate the
order of priority)
1.5 Name, designation, contact address and telephone number of the officer
responding :-
NAME:-
DESIGNATION:-
CONTACT ADDRESS:-
T E L E P H O N E NO:-
2.0 CONDITIONS OF CONTRACTS
2.1 What were/are the types of conditions of contract for building construction works you
or your organisation has used in the past and what are presently being used?
(Eg. FIDIC 3 , FIDIC 4, ICTAD 89, JCT 80 etc., with or without modification or any
other)
(a) What are the problems you or your organisation encounter while using ICATD
conditions of contract for building construction works?
(b) What are the clauses in the ICTAD conditions of contract do you consider to require
modification with regard to building construction works?
(c) H o w could the ICTAD conditions of contract be modified for the local building
construction works?
(For eg. Based on some other conditions of contract or your own)
(a) Why the ICTAD conditions of contract is not used for building construction works?
(b) What are the changes to be made to ICTAD conditions of contract in your opinion
to use for building construction works?
2.4 What are your views about having separate conditions of contract for building and civil
engineering construction works?
2.5 ICTAD conditions of contract is the modification of the FIDIC conditions of contract
(Third edition) and the FIDIC is meant only for civil engineering construction works
whereas the ICATD conditions of contract is meant for both building and civil
engineering construction works.
2.6 If you have mentioned the FIDIC conditions of contract at 2.1 above.
What are the specific problems you or your organisation encounter while using it for
building construction works?
2.7 What are your views about the cabinet decision for having one conditions of contract
(ICTAD) for both building and civil engineering construction works?
2.8 If you have mentioned the RIBA conditions of contract at 2 . 1 , what are the main
differences between the RIBA and the ICTAD conditions of contract?
APPENDIX - B
APPENDIX B
COMPARISON OF CONDITIONS OF CONTRACTS WITH CLAUSE NUMBER AND DESCRITPION
No. FIDIC conditions of contract ICTAD conditions of FIDIC conditions of JCT 80(Local GC/Works/1 (Edition Remarks
(Third edition) = FIDIC 3 contract (Revised edition contract(Fourth Authorities with 3) =GCW1
1989)=ICTAD 89 edition) = FIDIC 4 Quantities)=JCT 80
No. FIDIC conditions of contract ICTAD conditions of FIDIC conditions of JCT 80(Local GC/Works/1 (Edition Remarks
(Third edition)=FIDIC 3 contract (Revised edition contract(Fourth Authorities with 3) =GCW1
1989)=ICTAD 89 edition) = FIDIC 4 Quantities) = JCT 80
ASSIGNMENT AND SUB ASSIGNMENT AND SUB ASSINGMENT AND SUB 19 Assignment and
LETTING LETTING CONTRACTING Sub- Contracts
3 3 Assignment 3 Assignment 61 Assignment
3.1 Assignment of Contract 19.1 Assignment C
62 Sub-letting
4 4 Sub-letting 4 Sub-letting 19.2 Sub-letting-
4.1 Sub-Contracting Domestic
4.2 Assignment of Sub Sub-Contractors.-
-Contractor's Obligations Architect's/
Supervising
Officer's consent
19.3 Sub-letting-list in
Contract Bills
19.4 Sub-letting
-Determination
of Employment of
Domestic Sub
-Contractor
6 6.1 Custody of Drawings 6.1 Custody of Drawings 6.1 Custody and Supply of 5. Contract Documents - 2 Contract Documents c
6.2 One Copy of Drawings to 6.2 One Copy of Drawings to be Drawings and Documents other documents - issue of
be kept on Site kept on Site 6.2 One Copy of Drawings to be certificates
6.3 Disruption of Progress 6.3 Disruption of Progress kept on Site 5.1 Custody of Contract Bills
6.4 Delays and cost of delay of 6.4 Delays and Cost of Delay of 6.3 Disruption of Progress and Contract Drawings
Drawings Drawings 6.4 Delays and Cost of Delay of 5.2 Copies of Documents
Drawings 5.3 Descriptive Schedules etc-
6.5 Failure by Contractor to Master Programme of
Submit Drawings Contractor
5.5 Availability of certain
documents
5.6 Return of Drawings etc.
5.7 Limits to use of
documents
7. 7. Further drawings and 7. Further drawings and 7.1 Supplementary drawings and 5.4 Drawings or details No clause c
instructions instructions instructions.
10 10. Performance Bond 10. Performance Bond 10.1 Performance Security No clause No clause B
D* 10.2 Period of Validity of
Performance Security
10.3 Claims under
Performance Security
F4.10*
11 11. Inspection of Site 11. Inspection of Site 11.1 Inspection of Site No clause 7.1' Conditions B
D* D* 7.2 . affecting
7.6 Works
E*
12 12. Sufficiency of Tender 12. Sufficiency of Tender. 12.1 Sufficiency of Tender No clause 7.3") Conditions C
Adverse Physical Adverse Physical 12-2. Adverse Physical 7.4( affecting
Conditions and Artificial Conditions and Artificial Obstructions or Conditions 7.5j Works
Obstructions Obstructions
13 13. Work to be to the 13. Work to be to the 13.1 Work to be in Accordance 2.1 Contract Documents No clause A
Satisfaction of Engineer Satisfaction of Engineer with Contract E*
D* * F4.13
33 Programme C
14 14 Programme to be 14 Programme to be 14.1 Programme to be Submitted 5.3.1.2
Furnished Furnished 14.2 Revised Programme Descriptive
14.3 Cash Flow Estimate to be Schedules etc-
Submitted Master Programme
14.4 Contractor not Relieved of of Contractor
Duties or Responsibilities
t-4.8* - Clearly explained and covers more conditions.
JC.8* - Not clearly covered as FIDIC 3 .
E* - Similar to FIDIC3.
D* - No change.
F4.10* - Clearly explained and covers more conditions.
F4.13* - No change, but only the heading differs.
Continued.
16 16. Contractor's Employees 16. Contractor's Employees 16.1 Contractor's Employees 8.5 Exclusion from 6 Contractor's C
16.2 Engineer at Liberty to the Works of employees
Object persons employed
thereon
17 17. Setting-out 17. Setting-out 17.1 Setting out 7. Levels and setting 9. Setting-out C
out of the Works
and clause 2
(extracts)
18 18. Boreholes and Exploratory 18. Boreholes and Exploratory 18.1 Boreholes and No clause No clause A
Excavation Excavation Exploratory Excavation
D* D*
D* - No change.
IC.15* - 15.1 is a new clause, all others are similar to FIDIC 3.
JC.10* - Differs from FIDIC 3 .
GC.5* - Similar to JCT 8 0 .
Continued.
19 19. Watching and lighting 19. Watching and lighting 19.1 Safety. Security and No Clause 13 Protection of C
Protection of the Works
Environment
14 Nuisance and
19.2 Employer's pollution
Responsibilities
20 20.1 Care of Works 2 0 . 1 . Care of Works 20.1 Care of Works No Clause 54 Emergency C
Work
20.2 Excepted Risks 20.2. Excepted Risks 20.2 Responsibility to Rectify
Loss or Damage
21. 21. Insurance of Works, 21. Insurance of Works, 2 1 . 1 . Insurance of Works 22. Insurance of 8. Insurance C
etc. etc. and Contractor's the Works
Equipment 22A. Erection of
F3.21* IC.21* 21.2. Scope of Cover new buildings
21.3. Responsibility for - Al! Risks
Amounts not Insurance of
Recovered the Works by
21.4. Exclusions the Contractor
22B Erection of
new
buildings
- All Risks
Insurance of
the
Works by the
Employer
22C. Insurance of
existing
structures
- Insurance of
Works or
extensions to
existing
structures
2 2 D . Insurance for
Employer's
ikftftlt*^. loss
of liquidated
* s % damages
I ill
Continued.
22 22.1 Damage to Persons 22.1 Damage to Persons 22.1 Damage to Persons 20 Injury to persons 19 Loss or Damage C
and Property and Property and Property and property and
22.2 Indemnity by 22.2 Indemnity by 22.2 Exceptions indemnity to
Employer Employer 22.3 Indemnity by Employer Employer
23 23.1 Third Party Insurance 23.1 Third Party Insurance 23.1 Third Party Insurance 21 Insurance against 8 Insurance B
23.2 Minimum Amount of 23.2 Minimum Amount of (Including Employer's injury to persons or
Third Party Insurance Third Party insurance Property) property
23.3 Provision to 23.3 Provision to 23.2 Minimum Amount of
Indemnify Employer Indemnify Employer Insurance
23.3 Cross Liabilities
D* F4.23* E* E*
TJ* - No change.
F4.23* - Similar to FIDIC 3 , but this says that the insurance should be in the joint names of the Employer and the Contractor.
E* - Similar to FIDIC 3 .
Continued.
24 24.1 Accident or Injury to 24.1 Accident or Injury to 24.1 Accident or Injury to 21 Insurance against 8 Insurance A
Workmen Workmen Workmen injury to persons
24.2 Insurance against 24.2 Insurance against 24.2 Insurance against or property
Accident, etc., to Accident, etc., to Accident to
Workmen Workmen Workmen
JC.21* GC.8*
D* D*
25 25 Remedy on Contractor's 25 Remedy on Contractor's 25.1 Evidence and Terms of No clause No clause C
Failure to Insure Failure to Insure Insurances
25.2 Adequacy of Insurances
F3.25* IC.25* 25.3 Remedy on Contractor's
Failure to Insure
25.4 Compliance with Policy
Conditions
D* - No change.
JC.21* and GC.8* - Partly covers the FIDIC 3 contents.
F3.25* and IC.25* - Refer clause 2 1 .
Continued.
26 26.1 Giving of Notices and 26.1 Giving of Notices and 26.1 Compliance with Statutes, 6 Statutory 11 Statutory C
Payment of Fees Payment of Fees Regulations, etc. obligations, notices
notices, fees and
26.21 Compliance with Statutes, 26.2") Compliance with Statutes, charges
28 28 Patent Rights and 28 Patent Rights and 28.1 Patent Rights 9 Royalties and 12 Patents C
Royalties Royalties 28.2 Royalties patent rights
29 29 Interference with Traffic 29 Interference with Traffic 29.1 Interference with Traffic No clause No clause B
and Adjoining Properties and Adjoining Properties and Adjoining Properties.
D* F4.29*
30 30.1 Extra ordinary Traffic 30.1 Avoidance of Damage to 30.1 Avoidance of Damage to No clause No clause C
30.2 Special Loads Highway, etc. Roads
30.3 Settlement of Extra 30.2 Transport of 30.2 Transport of Contractor's
ordinary Traffic Claims Constructional Plant Equipment or Temporary
30.4 Water borne Traffic 30.3 Water bome Traffic Works
30.3 Transport of Materials or
Plant
30.4 Water borne Traffic
D* - No change.
F4.29* - No change, but FIDIC4 covers for execution and completion of the works.
Continued.
31 31. Opportunities for Other 31.1 Facilities for Other 31.1 Opportunities for Other 29 Works by 65 Other works A
Contractors Contractors Contractors Employer or
31.2 Delay and Extra work 31.2 Facilities for Other persons employed
Contractors or engaged by
IC.31* Employer
E*
E* E*
32 32. Contractor to keep Site 32.1 Contractor to keep Site 32.1 Contractor to keep Site No clause 34.2 Commencement A
Clear Clear Clear and Completion
D* D*
33 33. Clearance of Site on 33 Clearance of Site on 33.1 Clearance of Site on No clause 34.2 Commencement B
Completion Completion Completion and Completion
• D* F4.33*
D* - No change.
IC.31* - Similar to FIDIC 3, but 31.2 is a new clause from ICE conditions of contract (5th edition).
F4.33* - Little elaborated. Even contractor shall be entitled to retain on site upto the end of the defects liability period.
Continued.
34 34.1 Engagement of labour 34.1 Engagement of Labour 34.1 Engagement of Staff and 19A Fair Wages 15 Returns C
34.2 Supply of Water 34.2 Supply of Water Labour
34.3 Alcoholic Liquor or 34.3 Alcoholic Liquor or
Drugs Drugs
34.4 Arms and Ammunition 34.4 Arms and Ammunition
34.5 Festivals and Religious 34.5 Festivals and Religious
Customs Customs
34.6 Epidemics 34.6 Epidemics
34.7 Disorderly Conduct, 34.7 Disorderly Conduct,
etc. etc.
34.8 Observance by Sub 34.8 Rates
-Contractors 34.8 Observance by Sub
34.9 Other Conditions -Contractors
affecting Labour and 34.9 Other Conditions
Wages affecting Labour and
Wages
36 36.1 Quality of Materials and 36.1 Quality of Materials and 36.1 Quality of Materials, Plant 8 Materials, goods No clause B
Workmanship and Tests Workmanship and Tests and Workmanship and Tests and workman
36.2 Cost of Samples 36.2 Cost of Samples 36.2 Cost of Samples ship to conform
36.3 Cost of Tests 36.3 Cost of Tests 36.3 Cost of Tests to description,
36.4 Cost of Tests not 36.4 Cost of Tests not testing and
Provided for, etc. Provided for inspection
IC.36* 36.5 Engineer's Determination 8.1 Kinds and
where Tests not Provided standards
for 8.2 Vouchers -
materials and
F4.36* goods
8.3 Inspection-tests
8.4 Removal from
the site-work.
materials or
goods
JC.8*
37 37 Inspection of Operations 37 Inspection of Operations 37.1 Inspection of Operations 11 Access for 31.4 Quality C
37.2 Inspection and Testing Architect/ 31.5 -do-
37.3 Dates for Inspection and Supervising 31.6 -do-
Testing Officer to the 31.7 -do-
37.4 Rejection works
37.5 Independent Inspection
38 38.1 Examination of Work 38.1 Examination of Work 38.1 Examination of Work 8.3 Inspection-tests 16 Foundations A
before Covering up before Covering up before Covering up 17 Covering work
38.2 Uncovering and Making 38.2 Uncovering and Making 38.2 Uncovering and Making
Openings Openings Openings JC.8.3* GC. 16/17*
F4.38*
D*
39 39.1 Removal of Improper 39.1 Removal of Improper 39.1 Removal of Improper 8.4 Removal from 53 Non B
Work and Materials Work or Materials Work or Materials or Plant the site-work, -compliance with
39.2 Default of Contractor in 39.2 Default of Contractor in 39.2 Default of Contractor in materials or Instructions
Compliance Compliance. Compliance goods
D* F4.39* GC.53*
-
JC.84 *
SUSPENSION
40 40.1 Suspension of Work 40.1 Suspension of work 40.1 Suspension of Work No clause 40.2g PM's B
40.2 Suspension Lasting more 40.2 Suspension lasting more 40.2 Engineer's Determination Instructions
than 90 days ' than 90 days following Suspension
D* 40.3 Suspension Lasting more GC.40*
than 84 Days
F4.40*
D* - No change-
F4.38* - Similar to FIDIC 3 , but the name Engineer is used throughout.
F4.39* - Similar to FIDIC 3, but the plant and the Contractor's design is also included here.
F4.40* - Similar to FIDIC 3, only the days differ.
JC.8.3* and JC.8.4* - Not clearly covered as FIDIC 3.
GC.53*, GC.40* and GC. 16/17* - Not clearly covered as FIDIC 3.
Continued.
D* D*
42 42.1 Possession of Site 42.1 Possession of Site 42.1 Possession of Site and 23.1 Date of 34.1 Commencement B
42.2 Wayleaves, etc. 42.2 Wayleaves, etc. Access thereto Possession - and Completion
42.2 Failure to Give Progress to
Possession Completion Date GC.34*
D* 42.3 Wayleaves and Facilities
F4.42* JC.23*
43 43 Time for Completion 43 Time for Completion 43.1 Time for Completion
D* D* No clause No clause A
44 44 Extension of Time for 44.1 Extension of Time for 44.1 Extension of Time for 25 Extension of 36 Extensions of C
Completion Completion Completion time time
44.2 Assessment of Extension 44.2 Contractor to Provide
During the Course of Work Notification and Detailed
44.3 Assessment of Due Date Particulars
for Completion 44.3 Interim Determiantion of
Extension
45 45 No Night or Sunday Work 45 No Night or Sunday Work 45.1 Restriction on Working No clause No clause A
Hours
D*
F4.45*
D* - N o change.
F4.45* - Similar to FIDIC3,but (a) The wording Sunday is removed here, and
(b) Engineer's Representative is replaced by Engineer.
Continued.
47 47.1 Liquidated Damages for 47.1 Liquidated Damages for 47.1 Liquidated Damages for 24 Damages for 55 Liquidated A
Delay Delay Delay non-completion Damages
47.2 Reduction of Liquiated 47.2 Reduction of Liquidated 47.2 Reduction of Liquidated
Damages Damages Damages 18.1.4 Liquidated E*
47.3 Bonus for Completion 47.3 Bonus for Completion F4.47» damages -
D* relevant part
E*
48 48.1 Certification of 48.1 Certification of 48.1 Taking-Over Certificate 17.1 Certificate of 37 Early C
Completion of Works Completion of Works 48.2 Taking Over of Sections Practical Possession
48.21 Certification of 48.2] Certification of or Parts Completion
4 8 . 3 \ Completion by Stages 48.3 Completion by Stages 48.3 Substantial Completion of 18.1 Employer's
48.4J 48.4. Parts wish-
48.4 Surfaces Requiring Contractor's
Reinstatement consent
23.3 Possession by
Contractor-use or
occupation by
Employer
D* - No change.
F4.47* - No change, but the bonus clause is omitted here.
Continued.
50 50 Contractor to Search 50 Contractor to Search 50 Contractor to Search 8.3 Inspection - tests 21 Defects in C
17.3 Defects etc. - Maintenance
Architects Periods
/Supervising
Officers instructions
c S «
% £ W
Continued.
54 54 Approval of Materials > 54 Approval of Materials, 54.8 Approval of Materials No clause No clause A
etc., not implied etc., not implied not Implied
D* E*
D* - N o change.
E* - Similar to FIDIC 3 .
Continued.
D* D* E*
56 56 Works to be Measured 56 Works to be Measured 56.1 Works to be Measured 13.6 Contractor's right to 18 Measurement A
be present at
D* D* measurement GC.18*
JC.13.6*
TJ' - No change.
IC.57* - Similar to FIDIC 3 , but the Contractor has to submit a cashflow statement
within 28 days to Engineer for approval of all Lump Sum items .
JC.13.6* - Similar to FIDIC 3 , but not fully covered.
GC.18* - Similar to FIDIC 3 , but not fully covered.
F4.57* - Similar to FIDIC 3 .
Continued
PROVISIONAL SUMS PROVISIONAL SUMS PROVISIONAL SUMS 13.3 Instructions on 64 Provisional Sums
58 58.1 Definition of 58.1 Definition of 58.1 Definition of provisional sums
"Provisional Sums" "Provisional Sums" "Provisional Sums"
58.2 Use of Provisional 58.2 Use of Provisional 58.2 Use of Provisional
Sums Sums Sums
58.3 Production of 58.3 Production of 58.3 Production of
Vouchers, etc. Vouchers, etc. Vouchers, etc.
IC.58* F4.58*
1C.58* - Similar to FIDIC J, but the construction managment services are also included here.
F4.58* - Similar to FIDIC 3 > u t only the wordings differ.
Continued.
60 60.1 Certificates and 60.1 Advance Payment 60.1 Monthly Statements 30 Certificates and Payments 47 Finance Charges C
Payment 60.2 Monthly Statements 60.2 Monthly Payments 48 Advances on Account
60.2 Advances on 60.3 Monthly Payments 60.3 Payment of Retention 49 Final Account
Constructional Plant 60.4 Payment of Retention Money 50 Certifying payments
and Materials Money 60.4 Correction of 51 Recovery of Sums
60.3 Payment in Foreign 60.5 Correction and Certificates 52 Cost Savings
Currencies Withholding of 60.5 Statement at
Certificates Completion
60.6 Final Account 60.6 Final Statement
60.7 Time for Payment 60.7 Discharge
60.8 Currency Account 60.8 Final Certificate
and Rates of Exchange 60.9 Cessation of
60.9 Payments to Employer's Liability
Contractor 60.10 Time for Payment
60.10 Payments to the
Employer
60.11 Advances on
Constructional Plant
and Materials
60.12 Payments in Foreign
Currency
62 62.1 Maintenace Certficate 62.1 Maintenace Certficate 62.1 Defects Liability No clause No clause A
62.2 Cessation of 62.2 Cessation of Certificate
Employer's Liability Employer's Liability 62.2 Unfulfilled
62.3 Unfulfilled Obligations 62.3 Unfulfilled Obligations
Obligations
F4.62*
D*
64 64 Urgent Repairs 64 Urgent Repairs 64.1 Urgent Remedial 33 War damage 54 Emergency Work A
D* Work
F4.64* JC.33* GC.54*
65 65.1 No Liability for War, 65.1 No liability for War, 65.1 No Liability for 32 Outbreak of hostilities No clause
etc., Risks etc.. Risks Special Risks
65.2 Damage to Works, 65.2 Damage to Works, 65.2 Special Risks
etc., by Special Risks etc., by Special Risks 65.3 Damage to Works by
65.3 Projectile, Missile, 65.3 Projectile, Missile, Special Risks
etc. etc. 65.4 Projectile, Missile,
65.4 Increased Costs 65.4 Increased Costs etc.
arising from Special arising from Special 65.5 Increased Costs
Risks Risks arising from Special
65.5 Special Risks 65.5 Special Risks Risks
65.6 Outbreak of War 65.6 Outbreak of War 65.6 Outbreak of War
65.7 Removal of Plant on 65.7 Removal of Plant on 65.7 Removal of
Termination Termination Contractor's
65.8 Payment if Contract 65.8 Payment if Contract Equipment on
Terminated Terminated Termination
65.8 Payment if Contract
IC.65* Terminated
F4.65* St-32*
IC.65* - Special Risks include whether riot is directed against the State, persons or property.
F4.65*- Special risks exclude loss or damage due to (a) the use or occupation by the Employer of any section and (b) the Engineer's design of the works.
IC.32* - Partly covers FIDIC 3 contents.
Continued.
66 66 Payment in Event of 66 Payment in Event of 66.1 Payment in Event of 32 Outbreak of Hostilities No clause A
Frustration Frustration Release from
D* Performance JC.32*
F4.66*
68 68.1 Service of Notices on 68.1 Service of Notices on 68.1 Notice to Contractor N o clause 1.3 Definitions etc.
Contractor Contractor 68.2 Notice to Employer
68.2 Service' of Notices on 68.2 Service of Notices and Engineer
Employer or Engineer on Employer or 68.3 Change of Address
68.3 Change of Address Engineer
68.3 Change of Address F4.68* GC.l*
69 69.1 Default of Employer 69.1 Default of Employer 69.1 Default of Employer 28 Determination by No clause
69.2 - do- 69.2 - do - 69.2 Removal of Contractor
69.2 - do- 69.2 - do- Contractor's
Equipment
69.3 Payment on
Termination
69.4 Contractor's
Entitlement to
Suspend work
69.5 Resumption of Work
M . 6 8 * - No change, but in addition the cable, telex or lacsimile transmission is included here.
G C . l * - Partly covers FIDIC 3 contents.
Continued.
F4.71*
IC.71*
F4.72*
rrf\
iocs / Oi \&'A
!*. - &\ t \
! 8
A i|
^ Is
I C 7 1 * , I C 7 2 * , F4.71* and F4.72* - Number of days are changed from 30 to 28.