DESCRIPTION : INSPECTION AND TEST PLAN FOR ELECTRICAL - GENERAL
Legend
H - Hold Point: A stage of inspection work where the inspection party has to certify the work before commencement of the next W - Witness Point: A stage of inspection of work where all inspection party will be
activity. informed “without holding” the commencement of next stage of work.
R - Review : Provision of document of all the work that require review / approval M - Monitoring : Designated part is required to monitor the work which is on progress
SUB-
Applicable Acceptance Inspection SAMSUNG C&T
CONTRACTOR
No Quality Activity Remark
Document Criteria Record
Signature Signature Signature Signature
1 PREPARATION
Material Receiving
2.1 Material Receiving Inspection Inspection
H R
Pre-Installation check
3.1 R R R
- Foundation and setting bolts
CLIENT :
PROJECT : OWNER LOGO
DESCRIPTION : INSPECTION AND TEST PLAN FOR ELECTRICAL - GENERAL
Legend
H - Hold Point: A stage of inspection work where the inspection party has to certify the work before commencement of the next W - Witness Point: A stage of inspection of work where all inspection party will be
activity. informed “without holding” the commencement of next stage of work.
R - Review : Provision of document of all the work that require review / approval M - Monitoring : Designated part is required to monitor the work which is on progress
SUB-
Applicable Acceptance Inspection SAMSUNG C&T
CONTRACTOR
No Quality Activity Remark
Document Criteria Record
Signature Signature Signature Signature
Cable Termination
- Tightness
4.3 H W W
- Identification marking
- Visual Check
5 INSTALLATION OF EQUIPMENT
Equipment Installation
- Location, Alignment & Levelling Inspection
5.3 - Torque of Nuts & Bolts H W W
- Earthing Check
- Visual check
Page : 4 Of: 6
SID-10-YE_-QPH-SCT-001 Rev. : 0
Date : DD-MMM-YYYY
CLIENT :
PROJECT : OWNER LOGO
DESCRIPTION : INSPECTION AND TEST PLAN FOR ELECTRICAL - GENERAL
Legend
H - Hold Point: A stage of inspection work where the inspection party has to certify the work before commencement of the next W - Witness Point: A stage of inspection of work where all inspection party will be
activity. informed “without holding” the commencement of next stage of work.
R - Review : Provision of document of all the work that require review / approval M - Monitoring : Designated part is required to monitor the work which is on progress
SUB-
Applicable Acceptance Inspection SAMSUNG C&T
CONTRACTOR
No Quality Activity Remark
Document Criteria Record
Signature Signature Signature Signature
Earthing
- Proper installation of buried cable
- Checking protection of cable on surface
6.2 - Cable Termination (checking tightness) H W W
- Installation and connection of test pit and
test link with rod
Lightning
- Proper installation of lightning rod
6.3 H W W
- Checking tightness of support
- Checking proper insulation of cable
Testing
6.4 H W W
- Earth Resistance Test
7 Lighting and Small Power System
Equipment Installation
- Light, Switch, Socket, Junction Box
7.3 H W W
- Earthing Check
- Visual check
Cable laying & Termination
- Checking proper cable laid
7.4
- Cable Termination
- Visual Check
Page : 5 Of: 6
SID-10-YE_-QPH-SCT-001 Rev. : 0
Date : DD-MMM-YYYY
CLIENT :
PROJECT : OWNER LOGO
DESCRIPTION : INSPECTION AND TEST PLAN FOR ELECTRICAL - GENERAL
Legend
H - Hold Point: A stage of inspection work where the inspection party has to certify the work before commencement of the next W - Witness Point: A stage of inspection of work where all inspection party will be
activity. informed “without holding” the commencement of next stage of work.
R - Review : Provision of document of all the work that require review / approval M - Monitoring : Designated part is required to monitor the work which is on progress
SUB-
Applicable Acceptance Inspection SAMSUNG C&T
CONTRACTOR
No Remark
Document Criteria Record
Quality Activity Signature Signature Signature Signature
8 Communication System
Equipment Installation
- Panel Installation
- CCTV, PA, Phone
8.2 - Field Cabinet H W W
- Junction Box
- Earthing Check
- Visual check
Cable Laying & Connection
- Check the cable types
8.3 - Clamping & supporting, space allowance H W W
- Identification marking
- Visual Check
Testing
8.4 - Continuity Check H W W
- Power loss check of FO ( optional)
9 Transformer Erection (GSUT, UAT)
Equipment Installation
- Location, Alignment & Levelling Inspection
9.3 H W W
- Earthing Check
- Visual check
CLIENT :
PROJECT : OWNER LOGO
DESCRIPTION : INSPECTION AND TEST PLAN FOR ELECTRICAL - GENERAL
Legend
H - Hold Point: A stage of inspection work where the inspection party has to certify the work before commencement of the next W - Witness Point: A stage of inspection of work where all inspection party will be
activity. informed “without holding” the commencement of next stage of work.
R - Review : Provision of document of all the work that require review / approval M - Monitoring : Designated part is required to monitor the work which is on progress
SUB-
Applicable Acceptance Inspection SAMSUNG C&T
CONTRACTOR
No Quality Activity Remark
Document Criteria Record
Signature Signature Signature Signature
10 FINAL INSPECTION
Final inspection / Conformity check
10.1 H W W
(Cleanliness check)
As Built Drawing
11.2 As Built / Red Mark Drawing availability Red Mark Drawing
R R R