Sie sind auf Seite 1von 7

ESKOM’S FLAGSHIP BATTERY ENERGY STORAGE SYSTEMS (BESS)

PROJECT

Author: P. Moyo

Eskom Holdings SOC Ltd , P O Box 1091, Johannesburg, 2000, South Africa
Technology Division
Generation Group

Abstract: The paper will discuss the flagship 360MW/1440MWh battery energy
storage systems (BESS) project that has been launched by Eskom. It will look at
storage technologies and their evolution, with particular reference to BESS of Li-
Ion, NaS and redox flow battery technologies. Energy storage programmes that are
being rolled out in the world will be outlined. The various use cases of BESS will be
covered, such as energy arbitrage, peak clipping, frequency support, volt/var
support, deferred transmission and distribution investment and quality of supply
improvement, PV smoothing, renewable energy firming, spinning reserves and
black start. Duty cycles expected of the BESS systems and the economics thereof
for customers and utilities will be explained. Finally, the paper will propose some
guidelines for the specification, testing, operation, maintenance and disposal of
BESS systems and potential for wide-spread application on the South African
power system.

Key words: BESS, Li-ion, NaS, flow batteries, storage

1. INTRODUCTION battery energy storage systems (BESS) with some


PV.
The Eskom is South Africa’s electricity utility,
responsible for 95% (220TWh) of energy supplied The sizing of the BESS would be similar to the
within the country. Eskom manages a power system energy that CSP would have generated, which is
with peak capacity of 35GW. 1440MWh per day or 525GWh per year (100MW at
60% load factor).
The power system in South Africa has evolved with
the introduction of renewable energy independent Internationally, storage programs have been
power producers (REIPPs), while at the same time launched in the USA, Europe and China. The USA
energy sent out declined at an annual rate of 0.6% program in California is called Self-Generation
(Draft IRP 2018, p18). Eskom’s share of the market Incentive Program (SGIP) and in 2013 set a target
has therefore not grown. of 1.3GW of storage by 2020. 85% of this is utility-
based with the balance being customer facing.
The latest draft integrated resource plan with an
outlook to 2030 has the following allocations – The European Union has approved plans to inject
7598MW PV and 11442MW wind. This represents a EURO200m into a program to develop battery
more than five-fold increase each for PV storage manufacturing capacity (Energy Storage
(2018:1484MW) and wind (2018: 1980). In total, it News, 14 Nov 2017), in addition to EURO150m
moves PV and wind from 7.2% installed in 2018 to already allocated.
25.6% installed in 2030, a 350% rise.
Demand is expected to rise more than eleven-fold
In its application for funding of the new large coal- by 2025 (from 10GWh to 117GWh per annum).
fired power project, the 4800MW Medupi, Eskom China is expected to trail only the US by 2022 in
committed to executing power projects utilising demand for battery energy storage
clean technologies. The 100MW Sere Wind farm (4000MW/10000MWh vs 8000MW/21000MWh).
project is one. Plans for a 100MW CSP plant were
discussed in 2015 but it was resolved in 2017 that The US DoE compiles a list of storage projects and
Eskom should roll out a project on distributed publishes them on its website
(www.energystorageexchange.org). Anyone can BESS deployment is growing internationally, with
submit their projects online. estimates at about 1GW growth per annum (see
Figure 3)

2. STORAGE TECHNOLOGIES

Energy storage solutions have been in existence for


many centuries, but electrical energy storage
development started in the second half of the 20th
century. Figure 1 shows the spectrum of solutions
ranging from high capacity mechanical solutions,
mid-range chemical solutions and through to the
new and emerging electrical solutions.

Figure 3: Growth of BESS deployment per annum

Figure 4 below shows the reduction cost of energy


storage systems.

Figure 1: Electrical energy storage systems (Fraunhofer


ISE)

BESS solutions fall within the chemical/electro-


chemical part of the spectrum. They are mid-range
solutions.

Figure 2 shows another view of storage solutions taking


into account their capacity.

Figure 4: Trends in the cost of utility-scale battery


storage systems (Navigant Research)

The CPUC SGIP programme referred to


previously has accelerated the deployment of BTM
and FOM BESS in California, triggered by their
efforts to address the excess generation of PV
during the day and extremely high ramp rates
during the peak times, a phenomenon that has
resulted in the famous ‘CAISO Duck Curve’ (see
Figure 5). 1,3GW has been approved for
implementation, which is 6.5% of a morning peak
of 20GW.

Figure 2: Electrical storage solutions capacity

It is important to note that while the Eskom project is


targeting mid-range utility-scale applications of NaS,
Li-Ion and Flow shown above, technologies are
developing very fast leading to greater capacity and
lower cost.

3. BATTERY ENERGY STORAGE SYSTEMS


Value = [energy supplied * peak rate - energy
consumed * off-peak rate] Equation 1
where
energy supplied = energy consumed * efficiency
of BESS

3.1.2 Peak Clipping

The discharge of energy at a predictable


capacity factor during peak times can be used to
Figure 5: CAISO duck curve (i) and future projections (ii) reduce peaking capacity thereby saving costs.
The general formula for value realisation over
the life of the asset is
The BESS architecture involves a battery
management module which is a chemical storage
Value = demand reduction* differential cost of
medium that is integrated into the grid using ac/dc
and dc/ac converter/inverter. Figure 6 shows that peaking generation Equation 2.1
the conversion/inversion is achieved through a PCS to the generator, or
and the overall system is managed by an energy
storage control system, sometimes called an EMS. Value = demand reduction * demand charge
(R/kWh) Equation 2.2
to the end-consumer

Figure 7 below shows both energy arbitrage and


peak shaving.

Figure 6: BESS system architecture

A balance of system installation is included that


maximises the efficiency of the BESS through Figure 7: Energy arbitrage (discharging at peak) and
HVAC systems, and provides safety features such peak shaving (new flatter profile at peak)
as fire protection.
3.1.3 Spinning/Instantaneous Reserves

3.1 BESS APPLICATIONS BESS systems have a very fast response, much
The applications of BESS are highlighted below in faster than synchronous systems. Fast
summary format. The economic value proposition deployment can have additional benefits,
for some applications is presented, with formulas. especially when coupled with traditional non-
instantaneous spinning reserves such as gas
3.1.1 Energy Arbitrage turbines that may take minutes to reach rated
output.
Energy arbitrage is where energy is stored
during low generation cost/tariff periods for 3.1.4 Frequency Support
despatch at high generation cost/tariff periods.
For as long as the system inefficiency does not BESS capacity can be used in power mode
exceed the cost differential, the business case (short duration), as a generator or load, to
may be positive. provide fast capacity support that can arrest
frequency excursions. Frequency must operate
The general formula for value realisation over within the ROCOF curve.
the life of the asset is The general formula for value realisation is
Value = investment in traditional spinning
reserves – Equivalent BESS lifecycle cost The microgrid function enables the BESS to be
Equation 4 deployed with renewable energy in a
decentralised grid arrangement.
3.1.5 Voltage Support
3.2 BESS Duty Cycles
Similarly, BESS capacity can be used in power
mode (short duration), as a generator or load, to Most BESS chemistries have a lifetime that is
provide fast voltage support that can arrest dependent on duty cycle. Li-ion batteries can
frequency excursions. This can be battery last up to 10 years, NaS last 15 years, while
capacity power or non-battery reactive power in flow batteries have a theoretically unlimited
static var compensator mode. lifecycle.
BESS duty cycles range from a few hundred
3.1.6 Quality Of Supply/Critical Power operations per year for simple functions such as
energy arbitrage, where the unit may be called
BESS can be used to ride short-duration quality upon only twice a day for weekdays, to several
of supply phenomena such as voltage dips and thousand operations per year for frequent short
flicker. duration applications such as frequency and
voltage support.
3.1.7 Capex Deferral For high duty functions such as frequency
support, it may become necessary to prepare a
BESS can be used to augment capacity and baseline of the frequency excursions in order to
support the system at critical times of the day, size the unit appropriately. Similarly, for wind
thereby avoiding what can be costly investment energy firming, annual wind profile and wind
in infrastructure upgrade. farm sizing can be used to estimate the BESS
The general formula for value realisation is duty cycle.

Value = investment in traditional infrastructure –


Equivalent BESS lifecycle cost Equation 7 3.3 BESS Specification

3.1.8 PV Smoothing 3.3.1 Procurement Specification

PV smoothing involves the storage of solar A BESS specification includes critical parameters
energy during the day for despatch at peak such container dimensions, weight, operating
times. This function enables utilities to maximise temperature range, chemistry, round-trip
the amount of solar that can be tolerated by the efficiency, fire safety systems, rated continuous
system in that both supply and storage can be power charge and discharge and communication
done. All this is subject to non-violation of protocols. The battery module, inverter and
balance of system specifications are implied in
system inertia requirements.
these parameters.
3.1.9 Wind Energy Firming Included in the specification are all requirements
for augmentation and disposal of parts.
Battery storage can be sized to complement
variable wind generation. When wind is above Service life is commonly set at 20 years.
the set limit, the BESS is charged. It is Evaluation of offers that meet technical
discharged when output reaches a lower specifications and other contract requirements is
threshold. Similarly to PV, affordable storage on the basis of lifecycle costs, being capital,
can made wind despatchable. energy inefficiency, maintenance, augmentation
and disposal costs.
3.1.10 Backup Supply
3.3.2 Testing
In UPS mode, a BESS solution can be used as Testing is prescribed in various specifications,
a back-up power supply. such as IEC 62933-2-1, IEEE 2030, etc. Factory
acceptance tests include tests for power and
3.1.11 Micro Grids energy rating, round-trip efficiency, accelerated
ageing, response time, ramp rate, auxiliary power in all. All solutions will have a primary function and
consumption and self-discharge. Site acceptance supplemental functions in the form of ‘stacked
tests include tests for grid connection, anti- benefits’, in order to maximise the value of the
islanding and quality of supply capability. BESS. As an example, a unit primarily meant for
capex deferral during peak times in winter months
3.3.3 Operation will be available for functions such as frequency
The BESS unit has a local operation mode and a support at any time and peak clipping during
remote operation mode. It relies on regular input of summer months. Peak hour discharge shall be for
set parameters to which it responds as 4 hours.
programmed, e g voltage droop.

3.3.4 Maintenance Process flow:


BESS require maintenance of the battery storage The process followed to arrive at a technical
module, the inverter and balance of system. A two- enquiry is shown in Figure 8 below:
year warranty will usually be included with the
supply of the solution. This includes responses to
1. Identification
planned (preventive) maintenance events as well as
of use cases
unplanned/faults or corrective maintenance.
There are three options for maintenance:
i. Continued maintenance by the EPC after 2. Identification
the warranty period (usually two years) of potential
ii. Warranty terms extended by a fixed period sites
(e.g. 3 years) or
iii. Maintenance taken over by the utility for the
3. Conducting
life of the asset immediately after
business case
warranty.
analysis

3.3.5 Monitoring
4. Concept designs,
Monitoring of the BESS solution is expected. This specifications and
includes the DERMS function as well as monitoring permitting
the end-of-life of critical components such as the
battery module. End of life estimation is critical in
order to correctly time the implementation of 5. Contracting
necessary interventions to maintain the intended and rollout
functionality.
Figure 8: Process Flow for the BESS project
3.4 BESS Disposal

The environmental impact of BESS is analysed


throughout its lifecycle, covering manufacture, use Step 1
and disposal. Disposal requires careful attention,
especially where the chemicals have a potential to Use cases have been extensively written about
pollute the environment. All national and and are found in key SANDIA, EPRI and IEEE
international legislation, such as the ?? Recycling is documentation (see reference list). These are
a favoured option wherever possible, and dominant covered in section 3.1 above. The most attractive
technologies such as Li-ion still have a long way t go applications are for distribution deferred
reach levels achieved by lead-acid batteries (EPRI investment and congestion management, and this
Journal, January 2016). was prioritised wherever possible.

Step 2
4 ESKOM BESS PROJECT SCOPE
Each participating OU identified potential sites.
The Eskom BESS project involves deployment of Where local benefits were not immediately
solutions at multiple sites in various OUs. available, substations sites in electrically remote
Solutions range in size from 1MW to 60MW. The Operating Units were chosen. An attempt was
average size of an installation will be made to prioritise sites that result in upstream
4MW/16MWh, which implies about 90 installations congestion and a reduction in losses. These sites
will provide losses benefits in addition to displacing provided. The scope per site is confirmed and
peak energy (kWh) and demand (kW). related technical documentation provided by
Eskom. The list of documentation to be provided
Step 3 includes, amongst others:
This step involves assessing the business benefit of i. Planning report indicating use case,
deploying BESS versus other viable options (such business case and network parameters
as new distribution/ transmission substations and ii. Arrangement diagrams for the proposed
feeders, installation of voltage regulators, additional BESS and substation yards
peaking power generators, etc), and where the iii. Various utility technical specifications
investment is recouped within a reasonable timeline.
Project justification is based on direct benefits such The evaluation criteria involves preliminary
as reduced distribution bulk purchase costs, and assessment, technical assessment and finally
indirect benefits such as reduced overall generation economic lifecycle assessment. The lifecycle
costs. phase considers capital cost, energy cost
Step 4 (inefficiency), maintenance cost,
replacement/augmentation cost and disposal cost.
The first step in this stage is conducting technical
due diligence of sites. This involves performing a
series of network planning studies such as worst 5 FUTURE AREAS OF FOCUS
case (maximum charging and discharging) load
flows, dynamic time-series studies and quality of Future areas of focus in the understanding of
supply studies. Concept layout designs for BESS, after deployment, are analytics, generation
successful sites have been conducted. These are use cases and detailed technical planning studies.
based on standard BESS yard and substation yard Analytics will involve history of deployment,
layouts but are to be finalised at detail design by the operating costs, revenue earned, ageing
successful EPC contractor. This phase also mechanisms and ageing rates. Generation use
incorporated the development and approval of the cases to be studied include provision of
following technical specifications: generation-scale instantaneous reserves coupled
i. BESS equipment to traditional non-instantaneous reserves,
ii. AC equipment emergency backup and black start capability.
iii. General BESS and substation yard On a system-wide level, a key variable to
iv. Protection and control understand is the limit of the South African power
v. DERMS system to host inverter-based generation. This is
vi. APM tool important because system inertia is always
required in order to enable the system to recover
The DERMS will be integrated into the SCADA to from faults. It is interesting that the IRP 2018 draft
provide a seamless transition between network document recognises this (p38).
conditions and BESS deployment. It will effectively
manage a ‘BESS fleet’. One opportunity that has been missed in the draft
IRP 2018 is to guide the determination of
The life management of BESS units is critical as additional energy storage. With costs declining as
some chemistries tend to degrade over time, leading they are, the document needs to prepare the
to the technical benefits not being fully realisable. It industry for these solutions. Where viable, the
is therefore important to monitor the unit, in utility and end-customers will deploy BESS even
particular the chemical storage unit, for end-of-life. with no framework in place, in particular to defray
This is achieved through the APM tool. peaking power costs. There is an opportunity for
Permitting involves sourcing land and conducting South Africa to develop an ancillary market that
environmental impact assessments in line with would make the business case for BESS more
relevant legislation. viable.

Step 5 6 CONCLUSION

The contracting phase involves completion of bid BESS has clear business value at a local and
documents (in particular the bills of quantities and network level. Various use cases have been
evaluation criteria) in line with the templates presented to indicate this. South Africa is
increasing the share of variable RE to 25% in the
draft IRP. This will result in steep ramp rates for
traditional plants and to mitigate this impact, BESS
solutions could be utilised. South Africa must
develop an ancillary market in order to stimulate
investment in solutions that will support grid
flexibility.

Allocation of inverter-based variable RE and BESS


must be limited to the minimum inertia that the
system should have. This must still be studied in
detail.

7 REFERENCES

[1] EPRI Energy Storage Technical Specification


Template, 3002006673, October 2015

[2] EPRI ESIC Energy Storage Implementation


Guide, 3002010896, December 2017

[3] EPRI Examines Environmental Aspects of Grid-


Scale Battery Deployment, Chris Warren, EPRI
Journal, January 2016

[4] IEC White Paper: Electrical Energy Storage

[5] IEEE P2030.2.1 Draft Guide for Design,


Operation, and Maintenance of Battery Energy
Storage Systems, both Stationary and Mobile, and
Applications Integrated with Electric Power
Systems, September 2017

[6] The Impact Of Battery Energy Storage Systems


On Distribution Networks, Cigre WGC6.30, 2014

[7] Department of Energy: Draft Integrated Resource


Plan 2018

[8] The Battery Will Kill Fossil Fuels—It's Only a


Matter of Time, Mark Chediak, Bloomberg, March
2018

[9] Bloomberg New Energy Outlook 2018

[10] PNNL−22010 Rev. 2 / SAND2016-3078 R:


Protocol for Uniformly Measuring and Expressing
the Performance of Energy Storage Systems, April
2016

Das könnte Ihnen auch gefallen