PROJECT NOTICE

SDOT Permit Number(s): SDCI Permit Number(s):


412415

PROJECT INFORMATION

Name of Project 26th Ave Pavement Investigation

Address of Project 26th Ave SW, between Roxbury St. and Barton St.

Project Website N/A

Project Description We will be drilling 6 geotechnical boreholes in the roadway to investigate


cause of failing pavement and cause of reported vibrations in homes from
bus traffic.
Anticipated Project Start Date December 2, 2019

Anticipated Project End Date December 4, 2019

Duration of Project 3 days

PROJECT CONTACT

24-Hour Contact Name Seth Pemble

Phone Number 206-794-3126

Email spemble@hwageo.com

ASSOCIATED RIGHT-OF-WAY CLOSURES

ROW closures (e.g., Duration of Hours of


Street Between sidewalk, parking lane, etc.) closure closure

&
26th Ave SW Lane Closure 6 hours 9AM-3PM
Roxbury St

Cambridge

&
26th Ave SW Lane Closure 2 hours 9-11AM
Cambridge

Barton

&

&

If you wish to report safety or mobility concerns at any time, please call 684-ROAD (7623).