Beruflich Dokumente
Kultur Dokumente
7, Karimnagar.
District : Karimnagar Category: EPC
No. of tests to be
Total QC Total quantity
Progress during the month in Crores/ No. of inspections conducted / actual
Certificat executed during
Agreement Expenditure details during the month tests conducted by
es upto the month in Cum
Value/ Revised Extention of QC Staff
Package No., & Name of Executing last
S. No Name of Work Agreement time granted Remarks
Agency Circle month/
Value (In up to
During
Crores)
Concrete
Concrete
the
Balance
Up to During the
Soil
Soil
Cumulative month AEE DEE EE
last Month Month
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
Package No.5
1.Pump house, Surgepool
IFFC
excavation, CC for tunnel
IFFC - Pkg-5 : Lift from Thotapally Circle,
3 366.26 31/03/2019 1.82 5.12 6.94 359.32 1 / 1 8 6 2 640 - 2 / 4 0 / 0 bed lining, Vertical
Reservoir to Gouravelly Reservoir. LMD
M/s.MEIL. shafts(3No's) excavation
Colony.
is in progress.
Package No.6
Raising Embankment,
IFFC
Weir Body wall, SLRB
IFFC - Formation of Gouravelly Circle,
4 583.274 28/12/2019 396.61 0.00 396.61 186.66 27 / 0 13 10 2 1882 735786 4 / 6 48 / 52 Sub Structure, Rock toe
Reservoir M/s. BVSR LMD
and revetment work is in
Construction, P.LTD Colony.
progress.
IFFC-Pkg -8 IFFC
IFFC - Pkg-8 : Construction of
Circle, Work Stand Still due to
6 Gandipally Reservoir with allied 50.00 31/12/2017 23.91 0.00 23.91 26.09 27 / 0 0 0 - 0 0 0 / 0 0 / 0
Ratna & MEIL & KBL LMD Re-Engineering.
works
(JV) Colony.
PCLIS-Pkg-8
Electro-Mechanical Works
of Unit-6 & 7 are in
Kaleshwara
Kaleshwaram Progress.
7 4900.39 m Circle 30/09/2017 4137.96 11.05 4149.01 751.39 84 / 1 20 6 2 0 0 0 / 0 0 / 0
Project-DR.BRAPCSS Pkg-8 MEIL-SEW-MAYTAS- (Inner Top cover of Unit-
LMD, KNR
BHEL (CONSORTIUM) 7&shaft Combined
alignment of Unit-6)
Pages}
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
Pages}
Progress Report for the Month of June - 2019 of Sub Division No. 1, LMD Colony of QC&I Division No. 7, Karimnagar.
Cumulative
During
Concrete
Concrete
Balance
crores) Up to
Dy.EE
During the
AEE
Soil
Soil
last EE
the Month month
Month
1 2 3 4 5 6 7 8 9 10 11 12 14 15 16 17 18 19
13
Flood flow canal from SRSP phase-II
- Construction of Link Canal from Link Canal
IFFCC Circle,
Canal Lining is in
1 Km.0.00 (MMR R / S Canal @ Km 101.65 LMD, 15/11/2017 101.53 0.00 101.53 0.12 31 / 0 8 4 - 1200 - 3 / 5 0 / 0
36.125 i.e. end of package-II) to Km M/S.SMSL – Progress
Karimnagar.
6.900 SRRCIPL(JV)
Page 3 of 12
QC &I. Sub Division No.1, QC &I. Sub Division No.1,
LMD Colony, Karimnagar LMD Colony, Karimnagar
Page 4 of 12
Progress Report for the Month of May - 2019 of Sub Division No. 1, LMD Colony of QC& I Division No. 7, Karimnagar.
District : Karimnagar Category: Minor Irrigation
Total quantity
Total QC No. of tests to be
Agreement Date of Progress(Expenditure) during the No. of inspections executed
Package No., Certificates conducted / actual tests
Value/ Revised Executing Completion/ month in Crores during the month during the
S. Agreement Value upto last conducted by QC Staff
Name of Work Agreement Circle/ Extended month in Cum Remarks
No (In Crores) & Name month/
Value (In Division Date of
of Agency During the
crores) Completion
Balance
Up to During month
Cumula Concre
last the AEE Dy.EE EE Soil Concrete Soil
tive te
Month Month
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
MI-MK-Phase-III-MTB,
M. T. B.
Kothapalli(V), Karimnagar(M), Irrigation
Work Stand
1 Karimnagar District M/s KRMR 3.23 Circle, 15/11/2017 1.41 0.00 1.41 1.82 1 / 0 1 0 - 0 0 0 / 0 0 / 0 Still.
Constructions, Karimnagar
Hyderabad
MI-MK-Phase-II-MTB,
Manakondur (V&M), Karimnagar M. T. B. Irrigation
2 District. 4.68 Circle, 30/04/2018 3.11 0.00 3.11 1.57 4 / 0 0 0 - 0 0 0 / 0 0 / 0 Work standstill.
Sri.K.Prabhakar Karimnagar
Reddy
MI-MK-Phase-II-MTB,Huzurabad
M. T. B. Irrigation
(V&M), in Karimnagar District
3 2.74 Circle, 16/02/2018 1.94 0.00 1.94 0.80 1 / 0 0 0 - 0 0 0 / 0 0 / 0 Work standstill.
Sri.G.Swamy Reddy. Karimnagar
Page 5 of 12
Total quantity
Total QC No. of tests to be
Agreement Date of Progress(Expenditure) during the No. of inspections executed
Package No., Certificates conducted / actual tests
Value/ Revised Executing Completion/ month in Crores during the month during the
S. Agreement Value upto last conducted by QC Staff
Name of Work Agreement Circle/ Extended month in Cum Remarks
No (In Crores) & Name month/
Value (In Division Date of
of Agency During the
crores) Completion
Balance
Up to During month
Cumula Concre
last the AEE Dy.EE EE Soil Concrete Soil
tive te
Month Month
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
MI- Check dam/ Anicut across Local
Check Dam Irrigation
stream near Mallial(V),
8 0.64 Circle, 19/09/2017 0.20 0.00 0.20 0.44 1 / 0 0 0 - 0 0 0 / 0 0 / 0 Work standstill.
Jammikunta(M), Karimnagar Karimnagar
Thanniru Anjaiah
District
MI- Check dam/ Anicut across Local
Check Dam
stream near Patharlapalli vagu near Irrigation
9 0.87 Circle, 19/09/2017 0.48 0.00 0.48 0.39 1 / 0 0 0 - 0 0 0 / 0 0 / 0 Work standstill.
Patharlapalli(V), Jammikunta(M), M/s Poorna Karimnagar
Karimnagar District Constructions.
MI- Check dam/ Anicut across
Manair Vagu near Korkal Check Dam Irrigation
10 (V),Veenavanka(M), Karimnagar 10.39 Circle, 27/04/2019 7.61 0.00 7.61 2.78 2 / 0 3 1 - 621 28000 2 / 4 2 / 3 Work standstill.
District Sri.K. Bala Narsimha Karimnagar
Reddy.
MI- Check dam/ Anicut across
Manair Vagu near Vilasagar Check Dam
(V),Jammikunta (M), Karimnagar Irrigation
11 District 10.57 Circle, 19/05/2019 9.24 0.00 9.24 1.33 3 / 0 0 0 - 0 0 6 / 7 0 / 0 Work standstill.
M/s. BLG Projects Karimnagar
Ltd..
Page 6 of 12
Total quantity
Total QC No. of tests to be
Agreement Date of Progress(Expenditure) during the No. of inspections executed
Package No., Certificates conducted / actual tests
Value/ Revised Executing Completion/ month in Crores during the month during the
S. Agreement Value upto last conducted by QC Staff
Name of Work Agreement Circle/ Extended month in Cum Remarks
No (In Crores) & Name month/
Value (In Division Date of
of Agency During the
crores) Completion
Balance
Up to During month
Cumula Concre
last the AEE Dy.EE EE Soil Concrete Soil
tive te
Month Month
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
LMD Colony, Karimnagar LMD Colony, Karimnagar
Page 7 of 12
Abstract for Progress of works of Quality Control & Inspection Sub Division No. 1, LMD Colony for the Month of June - 2019
District : Karimnagar
2 Medium Irrigation - - - - - - - - - - - - - -
4 TSIDC - - - - - - - - - - - - -
Page 8 of 12
Report of abstract for details of progress of works of Quality Control & Inspection Sub-division No.1, LMD Colony for the month of June - 2019
District : Karimnagar
No.of tests to be
Total Quantity conducted/actual tests
Progress during the month/ Expenditure Total QC Certificates No. of inspections during
executed during the conducted by QC staff
Detail(in Crores) issued the month
month in Cum
Total no of
S. Total No. Concrete Soil
Category works in Remarks
No of works
progress
Cumulative
conducted
conducted
conducted
conducted
Concrete
actually
actually
Balance
Up to Up to
During During the
to be
to be
Soil
last last AEE Dy.EE EE
the Month Month
Month Month
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
1 Major Irrigation
i EPC works 7 5 4820.90 28.51 4849.40 1419.64 279 4 51 26 6 3252 737986 9 16 49 53
ii Non-EPC works 4 4 195.28 10.26 205.54 99.79 38 2 21 12 2 3534 0 17 15 0 0
2 Medium Irrigation - - - - - - - - - - - - - - - -
4 TSIDC - - - - - - - - - - - - - - - -
TOTAL 24 9 5054 38.77 5093 1541 340 6 80 39 8 7407 765986 34 42 51 56
Page 9 of 12
Statement showing the Quality Conrol Audit Reports
Circle:QC&I Circle Hanmakonda Month : Jun-19
Division:QC&I Division No:7 Karimnagar
Sub-Division: QC & I Sub-Division:1, LMD Colony.
No. of Inspections / Dimensional checks by Remarks/Defects notified with
No. of Tests Conducted
the QC Staff with date description
Soil / Concrete / Others ATRs
Un
No. of tests to No. of received
attended Deduction
Name of Work with Package No be conducted tests on the
S.No No. of tests During the Remarks/ s made (in Remarks
and Agreement Details EE DEE AEE/AE Total executed as per conducted Cumulative Remarks/
conducted month Defects Rs)
quantity code/manual/ by Defects
by QC Staff notified
circulars Constructi
etc., on Staff
1 2 3 4 5 6 7 8 9 10
IFFC - Pkg-2: MMR R/S canal from
1 km.17.750 to 36.700 and including 27 4,22,27 2200 / 110 2/7 2/7 1/2 Nil - - - -
Thotapally online reservoir
1,3,4,7,10,11,12,
Kaleshwaram Project- DR.BRAPCSS 10,20,21,25, 13,14,17,18,20,2
5 10,21 0 / 0 0/0 0/0 0/0 Nil - - - -
Pkg-8 29 1,22,24,25,26,
27,28,29
Flood flow canal from SRSP phase-II -
Construction of Link Canal from
3,4,6,12,14,19,22
6 Km.0.00 (MMR R / S Canal @ Km 3,12,22,27 0 / 1200 0/30 0/30 0/5 Nil - - - -
36.125 i.e. end of package-II) to Km ,27
6.900
SRSP- Stage- I - Modernisation of
Main Canal from Km. 146.000 to Km. 2,4,7,11,13,18,21
7
191.000 of Kakatiya Main Canal in
7 2,7,11,21,26 0 / 1150 0/25 0/25 0/6 Nil - - - -
,26,28
below LMD, SRSP (Phase-II)
Kakatiya Canal - Modernisation of
Main Canal from Km. 191.000 to Km.
8
234.000 of Kakatiya Main Canal in
7 2,7,21 2,7,13,21 0 / 1184 0/25 0/25 0/4 Nil - - - -
below LMD, SRSP-I (Phase-II)
Page 10 of 12
SRSP - Stage-I - Providing stone
pitching, plastering to chute drains on
LF and RF earth dam from (-)22.00 to
119.00 and 140.00 to 325.00 and
9
drilling 76mm dia (NX) core holes in
0 0 0 0 / 0 0/0 0/0 0/0 Nil - - - -
foundation holes in Gallery of Prof. G.
V. Sudhakar Rao Lower Manair Dam,
Karimnagar Dist.
Page 11 of 12
Asst. Executive Engineer, Dy Executive Engineer,
QC&I Sub Divn No 1, QC&I Sub Divn No 1,
LMD Colony LMD Colony
Page 12 of 12