CHAPTER 1
INTRODUCTION
HCL Infosystems Limited is India’s premier IT System Integration company, with a strong
legacy and over thirty years of experience in this domain, HCL offers System Integration
services as a single-window turnkey solution, that integrate best-in-class products and
solutions to meet the business needs of enterprise.
HCL Infosystems wanted to implement a new System Integration Vertical in the automation
sector citing their competency in the hardware, software and networking domains. HCL
Infosystems wanted to implement SCADA as their new vertical and I had to conduct a
market feasibility study in order to suggest certain Go-to market strategy for HCL
Infosystems to enter the market.
Lack of a Clear Business Case to justify investments on SCADA Systems dampens market
potential. With increasing power requirements and improved economic forecasts in India,
utilities are elevating the priority of grid management technologies such as supervisory
control and data acquisition (SCADA) systems. However, a significant restraint on the
market is the frequent inability of utility personnel to clearly justify to approving officers of
the need for investments on these systems. Consequently, vendors need to refashion
approaches to SCADA system justification and work closely with SCADA personnel at
different utilities to develop convincing business plans. Besides tangible benefits, many
unquantifiable or unanticipated benefits can also be identified to add value to the investments
and help demonstrate the importance of SCADA technology as a strategic tool for operations.
This research analyses the Indian markets for power transmission SCADA systems. The
study reveals important differences between the various electric utility segments and non-
utility segments with power transmission application, thus providing a deeper understanding
of the markets and its opportunities. It further provides a review of Government of India’s
Eleventh 5 year plan on the automation sector supporting SCADA systems.
Page 1
Business credibility of System Integration in ICT domain using SCADA
CHAPTER 2
LITERATURE SUPPORT
SCADA is an acronym that stands for Supervisory Control and Data Acquisition. SCADA
refers to a system that collects data from various sensors at a factory, plant or in other remote
locations and then sends this data to a central computer which then manages and controls the
data.
SCADA is a term that is used broadly to portray control and management solutions in a wide
range of industries. Some of the industries where SCADA is used are Water Management
Page 2
Business credibility of System Integration in ICT domain using SCADA
Systems, Electric Power, Traffic Signals, Mass Transit Systems, Environmental Control
Systems, and Manufacturing Systems.
There are many parts of a working SCADA system. A SCADA system usually includes
signal hardware (input and output), controllers, networks, user interface (HMI),
communications equipment and software. All together, the term SCADA refers to the entire
central system. The central system usually monitors data from various sensors that are either
in close proximity or off site (sometimes miles away).
For the most part, the brains of a SCADA system are performed by the Remote Terminal
Units (sometimes referred to as the RTU). The Remote Terminal Units consists of a
programmable logic converter. The RTU are usually set to specific requirements, however,
most RTU allow human intervention, for instance, in a factory setting, the RTU might control
the setting of a conveyer belt, and the speed can be changed or overridden at any time by
human intervention. In addition, any changes or errors are usually automatically logged for
and/or displayed. Most often, a SCADA system will monitor and make slight changes to
function optimally; SCADA systems are considered closed loop systems and run with
relatively little human intervention.
One of key processes of SCADA is the ability to monitor an entire system in real time. This
is facilitated by data acquisitions including meter reading, checking statuses of sensors, etc
that are communicated at regular intervals depending on the system. Besides the data being
used by the RTU, it is also displayed to a human that is able to interface with the system to
override settings or make changes when necessary.
SCADA can be seen as a system with many data elements called points. Usually each point is
a monitor or sensor. Usually points can be either hard or soft. A hard data point can be an
actual monitor; a soft point can be seen as an application or software calculation. Data
elements from hard and soft points are usually always recorded and logged to create a time
stamp or history.
Page 3
Business credibility of System Integration in ICT domain using SCADA
A SCADA system includes a user interface, usually called Human Machine Interface (HMI).
The HMI of a SCADA system is where data is processed and presented to be viewed and
monitored by a human operator. This interface usually includes controls where the individual
can interface with the SCADA system.
Page 4
Business credibility of System Integration in ICT domain using SCADA
HMI's are an easy way to standardize the facilitation of monitoring multiple RTU's or PLC's
(programmable logic controllers). Usually RTU's or PLC's will run a pre programmed
process, but monitoring each of them individually can be difficult, usually because they are
spread out over the system. Because RTU's and PLC's historically had no standardized
method to display or present data to an operator, the SCADA system communicates with
PLC's throughout the system network and processes information that is easily disseminated
by the HMI.
HMI's can also be linked to a database, which can use data gathered from PLC's or RTU's to
provide graphs on trends, logistic info, schematics for a specific sensor or machine or even
make troubleshooting guides accessible. In the last decade, practically all SCADA systems
include an integrated HMI and PLC device making it extremely easy to run and monitor a
SCADA system.
SCADA systems are an extremely advantageous way to run and monitor processes. They are
great for small applications such as climate control or can be effectively used in large
applications such as monitoring and controlling a nuclear power plant or mass transit system.
SCADA can come in open and non proprietary protocols. Smaller systems are extremely
affordable and can either be purchased as a complete system or can be mixed and matched
with specific components. Large systems can also be created with off the shelf components.
SCADA system software can also be easily configured for almost any application, removing
the need for custom made or intensive software development.
In the first generation, computing was done by mainframe systems. Networks didn’t exist at
the time SCADA was developed. Thus SCADA systems were independent systems with no
connectivity to other systems. Wide Area Networks were later designed by RTU vendors to
communicate with the RTU. The communication protocols used were often proprietary at
Page 5
Business credibility of System Integration in ICT domain using SCADA
that time. The first-generation SCADA system was redundant since a back-up mainframe
system was connected at the bus level and was used in the event of failure of the primary
mainframe system.
The processing was distributed across multiple stations which were connected through a
LAN and they shared information in real time. Each station was responsible for a particular
task thus making the size and cost of each station less than the one used in First Generation.
The network protocols used were still mostly proprietary, which led to significant security
problems for any SCADA system that received attention from a hacker. Since the protocols
were proprietary, very few people beyond the developers and hackers knew enough to
determine how secure a SCADA installation was. Since both parties had vested interests in
keeping security issues quiet, the security of a SCADA installation was often badly
overestimated, if it was considered at all.
These are the current generation SCADA systems which use open system architecture rather
than a vendor-controlled proprietary environment. The SCADA system utilizes open
standards and protocols, thus distributing functionality across a WAN rather than a LAN. It is
easier to connect third party peripheral devices like printers, disk drives, and tape drives due
to the use of open architecture. WAN protocols such as Internet Protocol (IP) are used for
communication between the master station and communications equipment. Due to the usage
of standard protocols and the fact that many networked SCADA systems are accessible from
the Internet; the systems are potentially vulnerable to remote cyber-attacks.
SCADA systems are used to automate complex industrial processes where human control is
impractical — systems where there are more control factors, and more fast-moving control
factors, than human beings can comfortably manage.
Around the world, the most typical implementation of SCADA systems include:
Page 6
Business credibility of System Integration in ICT domain using SCADA
Electric utilities use SCADA systems to detect current flow and line voltage, to monitor the
operation of circuit breakers, and to take sections of the power grid online or offline.
State and municipal water utilities use SCADA to monitor and regulate water flow, reservoir
levels, pipe pressure and other factors.
Facility managers use SCADA to control HVAC, refrigeration units, lighting and entry
systems.
• Manufacturing:
SCADA systems manage parts inventories for just-in-time manufacturing, regulate industrial
automation and robots, and monitor process and quality control.
• Mass transit:
Transit authorities use SCADA to regulate electricity to subways, trams and trolley buses; to
automate traffic signals for rail systems; to track and locate trains and buses; and to control
railroad crossing gates.
• Traffic signals:
SCADA regulates traffic lights, controls traffic flow and detects out-of-order signals.
There is a trend for PLC and HMI/SCADA software to be more "mix-and-match". In the mid
1990s, the typical DAQ I/O manufacturer supplied equipment that communicated using
proprietary protocols over a suitable-distance carrier like RS-485. End users who invested in
a particular vendor's hardware solution often found themselves restricted to a limited choice
of equipment when requirements changed (e.g. system expansions or performance
improvement). To mitigate such problems, open communication protocols such as IEC
60870-5-101 or 104, IEC 61850, DNP3 serial, and DNP3 LAN/WAN became increasingly
popular among SCADA equipment manufacturers and solution providers alike. Open
architecture SCADA systems enabled users to mix-and-match products from different
Page 7
Business credibility of System Integration in ICT domain using SCADA
vendors to develop solutions that were better than those that could be achieved when
restricted to a single vendor's product offering.
Towards the late 1990s, the shift towards open communications continued with individual
I/O manufacturers as well, who adopted open message structures such as Modbus RTU and
Modbus ASCII (originally both developed by Modicon) over RS-485. By 2000, most I/O
makers offered completely open interfacing such as Modbus TCP over Ethernet and IP. The
North American Electric Reliability Corporation (NERC) has specified that electrical system
data should be time-tagged to the nearest millisecond. Electrical system SCADA systems
provide this Sequence of events recorder function, using Radio clocks to synchronize the
RTU or distributed RTU clocks.
SCADA systems are coming in line with standard networking technologies. Ethernet and
TCP/IP based protocols are replacing the older proprietary standards. Although certain
characteristics of frame-based network communication technology (determinism,
synchronization, protocol selection, environment suitability) have restricted the adoption of
Ethernet in a few specialized applications, the vast majority of markets have accepted
Ethernet networks for HMI/SCADA.
With the emergence of software as a service in the broader software industry, a few vendors
have begun offering application specific SCADA systems hosted on remote platforms over
the Internet. This removes the need to install and commission systems at the end-user's
facility and takes advantage of security features already available in Internet technology,
VPNs and SSL. Some concerns include security, Internet connection reliability, and latency.
SCADA systems are becoming increasingly ubiquitous. Thin clients, web portals, and web
based products are gaining popularity with most major vendors. The increased convenience
of end users viewing their processes remotely introduces security considerations. While these
considerations are already considered solved in other sectors of internet services, not all
entities responsible for deploying SCADA systems have understood the changes in
accessibility and threat scope implicit in connecting a system to the internet.
Page 8
Business credibility of System Integration in ICT domain using SCADA
SCADA systems come in a myriad of types, sizes, and applications. They may
monitor/control only a few hundred points or tens of thousands of points. For the scope of
this report, only SCADA systems that apply to electrical transmission, distribution, water
treatment, traffic control, mass transit system and generation and were of substantial size
were evaluated. EMS contains a suite or modularized set of applications such as AGC, outage
coordination, load forecasting, remote clients, and business applications.
Frequently, many vendors enter or leave the SCADA market based on corporate buy outs.
Figure (a) shows the percentage of manufacturer use from the respondents of a recent
survey on existing systems.
Page 9
Business credibility of System Integration in ICT domain using SCADA
Figure (b) identifies future vendors being considered for new EMS procurements. The
term
“EMS” in Figure (b) represents a consolidation of the existing installations (SCADA, DMS,
EMS, etc.) shown in Figure (a). The number of vendors in the legend of Figure (b) is less
than shown in Figure (a) due to industry consolidation and vendors no longer providing
SCADA systems.
The following are vendor profiles of the top six SCADA suppliers shown in Figure (b).
Company: Advanced Control Systems (ACS)
Background and Strengths: ACS was founded in 1975 to supply real-time control systems
and equipment to the electric utility industry. ACS has delivered more than 470 SCADA,
SCADA/AGC, DMS, and EMS masters and 11,000 RTUs. Their current masters are based
on UNIX software and workstations or workstations and servers using RISC processors in an
open network environment. A full line of RTUs is supplied, all with IED interface
capabilities and various communications protocols, including DNP 3.0. A full line of
substation equipment is offered from legacy RTUs to protocol’s converters/data
concentrators to substation automation systems with or without graphical user interface
Company: Siemens
Page 10
Business credibility of System Integration in ICT domain using SCADA
Background and Strengths: Siemens Power Transmission and Distribution was formed to
focus specifically in the operations and needs of domestic and international electric utility
markets. Siemens provides a complete range of products. Siemens is a supplier of SCADA
and automation systems to the electric, water, and gas utility industries as well as to industrial
customers worldwide. TeleGYR is now part of Siemens. Other products include SICAM
controllers and RTUs.
Company: QEI
Background and Strengths: Founded in 1960 as Quindar Electronics, QEI designs and
manufactures SCADA equipment and systems. The company supplies industries such as
water, gas, power, petroleum, pipeline, railroad, steel, communication, traffic control, and
telemetry. Products include the TDMS 2000 and RTUs.
Company: ABB
Background and Strengths: ABB is one of the world’s largest suppliers of automation
systems for the electric power industry. The ABB network management specializes in
SCADA/DMS/EMS applications software. Major products include the RANGER system.
ABB also integrates their own microprocessor-based relays with SCADA systems. They have
installed more than 5,000 substation automation systems worldwide.
Company: Alstom ESCA
Background and Strengths: Alstom provides small- and large-scale SCADA/EMS/DMS
systems. Primarily focused on the electric power industry, they provide hardware and
software in substation automation and real-time energy information systems. They are a
worldwide industry leader in SCADA technology. Products include e-terra Global energy
solutions.
Page 11
Business credibility of System Integration in ICT domain using SCADA
Substation and control center hardware, once removed, is typically discarded or stored
indefinitely in a warehouse or back room. One utility in fact gave its old RTU cabinets to its
employees to use as smokers, which apparently works quite well.
CHAPTER 3
METHODOLOGY OF STUDY
Page 12
Business credibility of System Integration in ICT domain using SCADA
What’s more, these examples don’t show how deep and complex SCADA data can be. In
every industry, managers need to control multiple factors and the interactions between those
factors. SCADA systems provide the sensing capabilities and the computational power to
track everything that’s relevant to your operations.
Maybe you work in one of the fields listed in the previous section; maybe you don’t. But
think about your operations and all the parameters that affect your bottom-line results:
• Do you need to know — in real time — the status of many different components and
devices in a large complex system?
• Do you need to measure how changing inputs affect the output of your operations?
• Where are you lacking accurate, real-time data about key processes that affect your
operations?
SCADA can do a lot for the clients — but how can the clients make sure that you’re really
getting the full benefits of SCADA? Evaluating complex systems can be tricky — especially
if you have to learn a new technology while still doing your everyday job.
But you’ve got to be able to make an informed decision, because the stakes are incredibly
high. A SCADA system is a major, business-to-business purchase that your company will
live with for maybe as long as 10 to 15 years. When you make a recommendation about a
permanent system like that, you’re laying your reputation on the line and making a major
commitment for your company.
And as much as SCADA can help you improve your operations, there are also some pitfalls
to a hasty, unconsidered SCADA implementation:
• You can spend a fortune on unnecessary cost overruns
Page 13
Business credibility of System Integration in ICT domain using SCADA
• Even after going way over budget, you can STILL end up with a system that doesn’t
really meet all your needs
• Or just as bad, you can end up with an inflexible system that just meets your needs
today, but can’t easily expand as your needs grow
Although you need sensors, control relays and a communications network to make a
complete SCADA system, it’s your choice of a master station and RTUs that really determine
the quality of your SCADA system.
Sensors and control relays are essentially commodity items. Yes, some sensors are better than
others, but a glance at a spec sheet will tell you everything you need to know to choose
between them.
An IP LAN/WAN is the easiest kind of network to work with, and if you don’t yet have LAN
capability throughout all your facilities, transitioning to LAN is probably one of your long-
term goals. But you don’t have to move to LAN immediately or all at once to get the benefits
of SCADA. The right SCADA system will support both your legacy network and LAN,
enabling you to make a graceful, gradual transition.
Your SCADA RTUs need to communicate with all your on-site equipment and survive under
the harsh conditions of an industrial environment. Here’s a checklist of things you should
expect from a quality RTU:
a) Sufficient capacity to support the equipment at your site … but not more capacity
than you actually will use. At every site, you want an RTU that can support your
expected growth over a reasonable period of time, but it’s simply wasteful to
spend your budget on excess capacity that you won’t use.
b) Rugged construction and ability to withstand extremes of temperature and
humidity. You know how punishing on equipment your sites can be. Keep in
Page 14
Business credibility of System Integration in ICT domain using SCADA
mind that your SCADA system needs to be the most reliable element in your
facility.
c) Secure redundant power supply. You need your SCADA system up and
working 24/7, no excuses. Your RTU should support battery power and, ideally,
two power inputs.
d) Redundant communication ports. Network connectivity is as important to
SCADA operations as a power supply. A secondary serial port or internal modem
will keep your RTU online even if the LAN fails. Plus, RTUs with multiple
communication ports easily support a LAN migration strategy.
e) Non-volatile memory (NVRAM) for storing software and/or firmware. NVRAM
retains data even when power is lost. New firmware can be easily downloaded to
NVRAM storage, often over LAN — so you can keep your RTUs’ capabilities up
to date without excessive site visits.
f) Intelligent control. As I noted above, sophisticated SCADA remotes can control
local systems by themselves according to programmed responses to sensor inputs.
This isn’t necessary for every application, but it does come in handy for some
users.
g) Real-time clock for accurate date/time stamping of reports.
h) Watchdog timer to ensure that the RTU restarts after a power failure.
Your SCADA master should display information in the most useful ways to human operators
and intelligently regulated your managed systems. Here’s a checklist of SCADA master
must-haves:
a) Flexible, programmable response to sensor inputs. Look for a system that
provides easy tools for programming soft alarms (reports of complex events that
track combinations of sensor inputs and date/time statements) and soft controls
(programmed control responses to sensor inputs).
b) 24/7, automatic pager and email notification. There’s no need to pay personnel
to watch a board 24 hours a day. If equipment needs human attention, the SCADA
master can automatically page or email directly to repair technicians.
Page 15
Business credibility of System Integration in ICT domain using SCADA
c) Detailed information display. You want a system that displays reports in plain
English, with a complete description of what activity is happening and how you
can manage it.
d) Nuisance alarm filtering. Nuisance alarms desensitize your staff to alarm
reports, and they start to believe that all alarms are nonessential alarms.
Eventually they stop responding even to critical alarms. Look for a SCADA
master that includes tools to filter out nuisance alarms.
e) Expansion capability. A SCADA system is a long term investment that will last
for as long as 10 to 15 years. So you need to make sure it will support your future
growth for up to 15 years.
f) Redundant, geo diverse backup. The best SCADA systems support multiple
backup masters, in separate locations. If the primary SCADA master fails, a
second master on the network automatically takes over, with no interruption of
monitoring and control functions.
g) Support for multiple protocols and equipment types. Early SCADA systems
were built on closed, proprietary protocols. Single-vendor solutions aren’t a great
idea — vendors sometimes drop support for their products or even just go out of
business. Support for multiple open protocols safeguards your SCADA system
against unplanned obsolescence.
1. Does the SCADA package integrate with both existing and new hardware?
More often than not you have an existing infrastructure such as programmable logic
controllers (PLCs) and remote terminal units (RTUs) to which you need to add new devices
to optimize your automation system. The SCADA package that you choose must be able to
communicate with legacy hardware as well as the latest hardware, such as programmable
automation controllers (PACs). While OLE for process control (OPC) has become the de-
facto industry standard to communicate to automation devices, there are still many sensors
and instruments that require their own drivers. The ability to write your own drivers within
your SCADA environment becomes a key factor in your ability to use existing hardware with
new hardware.
Page 16
Business credibility of System Integration in ICT domain using SCADA
In addition to OPC client functionality, Modbus is another popular industrial protocol that is
often used to access registers on RTUs and sensors. TCP/IP and UDP are some of the other
low-level protocols that you can use to communicate with different hardware. With a truly
open SCADA system, you can communicate with any existing hardware while adding the
newest hardware as your system progresses.
Figure: Typical open architecture HMI/SCADA system connecting to both legacy and
the latest hardware.
Most SCADA vendors charge based on the number of tags you use while developing your
SCADA system. A decent-sized application easily ends up using a few thousand tags. With
the SCADA vendors charging a premium for each tag used, you typically develop your
application with an eye toward the number of tags you have used up so far. If you do reach
the limit, you have to go through the painful process of getting another purchasing order
Page 17
Business credibility of System Integration in ICT domain using SCADA
approved and devoting time toward all the overhead associated with it instead of
concentrating on developing your application.
Once the development is complete, even during the deployment phase, vendors charge by the
number of tags for their run-time systems, which can lead you to exceed your budget if you
do not plan properly in the beginning. To reduce costs, investigate packages that do not
charge by the number of tags but still deliver the performance requirements.
3. How flexible is the SCADA package when the customer wants to add advanced
analysis features?
While automation systems are designed to optimize by improving uptime and yield, SCADA
systems are often required to perform advanced analysis and be flexible to implement
features not typical of traditional SCADA systems. For instance, if you are acquiring
vibration data and want to perform fast Fourier transform to discern if your system vibration
is above the specified limits, you typically turn to separate analysis packages or, at best,
invoke a programming language such as Visual Basic or even C from within your SCADA
package.
If your SCADA package is flexible enough to double as a programming language to
implement custom features and perform advanced analysis functions, you greatly reduce the
development time and training costs associated with having to learn different packages to
meet your final system specifications.
Page 18
Business credibility of System Integration in ICT domain using SCADA
4. Can the customer program both the controller logic and its HMI/SCADA
functionality in the same environment?
Many times you prefer to buy most of your hardware and software from a single vendor.
Except for the convenience of a single purchase order, you could buy equipment from
different vendors as long as the specifications meet your requirements. However, if you can
program both your control hardware logic and the SCADA in the same environment, you can
minimize your development time considerably. You can also save on training costs because
you do not have to be proficient in two different environments.
5. Which operating systems can the customer use to run the SCADA application?
Page 19
Business credibility of System Integration in ICT domain using SCADA
All HMI/SCADA systems typically run on Windows XP and now Windows Vista operating
systems. However, with Windows CE and Windows XP Embedded gaining popularity
because of their relatively lower costs and smaller software footprints, touch panel
manufacturers have developed many touch panels to support these operating systems. A great
option to keep the cost of the total system down is to use this low-cost software where
possible. To do this, you need to make sure that the SCADA system can run on different
operating systems. Linux and Macintosh OSs are not as popular in this field but should be
considered nevertheless.
At the heart of the issue of SCADA system security are three major misconceptions that are
commonly held by utility managers. The report points to the misconceptions, listed on the
following page, as the major obstacles to the implementation of the best possible information
security strategies.
Most SCADA systems were originally built before and often separate from other corporate
networks. As a result, IT managers typically operate on the assumption that these systems
cannot be accessed through corporate networks or from remote access points. Unfortunately,
this belief is usually fallacious.
In reality, SCADA networks and corporate IT systems are often bridged as a result of two
key changes in information management practices. First, the demand for remote access
computing has encouraged many utilities to establish connections to the SCADA system that
enable SCADA engineers to monitor and control the system from points on the corporate
network. Second, many utilities have added connections between corporate networks and
SCADA networks in order to allow corporate decision makers to obtain instant access to
critical data about the status of their operational systems. Often, these connections are
implemented without a full understanding of the corresponding security risks. In fact, the
security strategy for utility corporate network infrastructures rarely accounts for the fact that
access to these systems might allow unauthorized access and control of SCADA systems.
Page 20
Business credibility of System Integration in ICT domain using SCADA
Many of the interconnections between corporate networks and SCADA systems require the
integration of systems with different communications standards. The result is often an
infrastructure that is engineered to move data successfully between two unique systems. Due
to the complexity of integrating disparate systems, network engineers often fail to address the
added burden of accounting for security risks. As a result, access controls designed to protect
SCADA systems from unauthorized access through corporate networks are usually minimal,
which is largely attributable to the fact that network managers often overlook key access
points connecting these networks. Although the strategic use of internal firewalls and
intrusion detection systems (IDS), coupled with strong password policies, is highly
recommended, few utilities protect all entry points to the SCADA system in this manner.
The above misconception assumes that all attackers of a SCADA system lack the ability to
access information about their design and implementation. These assumptions are
inappropriate given the changing nature of utility system vulnerabilities in an interconnected
environment. Due to the fact that utility companies represent a key component of one of the
nation’s critical infrastructures, these companies are likely targets of coordinated attacks by
“cyber-terrorists”, as opposed to disorganized “hackers.” Such attackers are highly motivated,
well-funded, and may very well have “insider” knowledge. Further, a well-equipped group of
adversaries focused on the goal of utility operations disruption is certain to use all available
means to gain a detailed understanding of SCADA systems and their potential vulnerabilities.
Furthering this risk is the increasing availability of information describing the operations of
SCADA systems. To support competition in product choices, several standards for the
interconnection of SCADA systems and remote terminal units (RTUs) have been published,
as have standards for communication between control centres, acceptance of alarms, issuance
of controls, and polling of data objects. Further, SCADA providers publish the design and
maintenance documents for their products and sell toolkits to help develop software that
implements the various standards used in SCADA environments.
Page 21
Business credibility of System Integration in ICT domain using SCADA
Finally, the efforts of utility companies to make efficient use of SCADA system information
across their company has led to development of “open” standard SCADA systems. As a
result of this development, SCADA system security is often only as strong as the security of
the utility’s corporate network. While the RTUs on a network may be difficult to access
outside of the dedicated serial lines, it is only moderately difficult to penetrate the control
panel for the SCADA manager through the corporate network and quickly ‘learn’ commands
by watching actions that are carried out on the screen. Attacks on highly complex systems
become much easier when attackers first penetrate the workstations of SCADA operators.
Page 22
Business credibility of System Integration in ICT domain using SCADA
8. SCADA Vendor should carry out regular employee training programs for regular
up-gradation of the knowledge and skills of the employees.
1. SCADA Vendor should have acquired ISO-9000 certification for the product
broadly, for which approval is being sought
2. SCADA Vendor should have the system of easy tractability of the product from
the raw-material stage to the finished product stage to the finished product stage is
available
3. SCADA Vendor should have a system of monitoring the supplied product
complaints.
4. SCADA Vendor should have an effective quality control system to monitor
quality control.
• Inward raw material
Page 23
Business credibility of System Integration in ICT domain using SCADA
• Stage inspection at various assembly stages such as PCB inspection before and
after soldering inspection, IC functionality check, Transducer testing, modem
functionality test etc.
• Inspection of the final assembled product to confirm adherence to the
requirement / specification
• Test equipment to test designed feature of SCADA system, MODEM and
simulators to simulate field signals, Current injection set, Variable and
stabilised ac voltage source, Variable PF source of adequate range.
1. SCADA Vendor should have the Quality assurance plan for the product detailing
following aspect:
• Organization chart.
• Flow process chart.
• Stage inspection details.
• Various parameters to maintain the control over the manufacturing.
1. The Quality manual of SCADA Vendor indicating the extent of control over
production and testing should be available.
2. A degree/diploma holder should be the head of the inspection / testing / final
control section with 5 years of experience in the relevant fields.
3. The System of documentation in respect of following should be available.
• Rejection at the customer and its warranty replacement e.g. documentation of
problems reported from field, corrective action taken thereof,
monitoring/validation of the action taken.
• Incoming raw material with the reference of suppliers as well as internal test.
• Details regarding stage inspection and test results.
• Details regarding the final testing and dispatch to the customer in proper
packed condition.
• System for calibration of testing and measuring instruments.
Page 24
Business credibility of System Integration in ICT domain using SCADA
As described in the previous section, corporate networks and SCADA systems are often
linked, which means that the security of the SCADA system is only as strong as the security
of the corporate network. With pressure from deregulation forcing the rapid adoption of open
access capabilities, vulnerabilities in corporate networks are increasing rapidly. The
following section outlines several common system vulnerabilities found on SCADA and
corporate networks that impact the relative security of SCADA systems:
Page 25
Business credibility of System Integration in ICT domain using SCADA
➢ Network connections with corporate partners are not secured by firewall, IDS,
or virtual private network (VPN) systems consistent with other networks
➢ Dial-up modem access is authorized unnecessarily and maintenance dial-ups
often fail to implement corporate dial access policies
➢ Firewalls and other network access control mechanisms are not implemented
internally, leaving little to no separation between different network segments
3.4.2.1 ATTACKS
Attacks on electronic systems have become a reality for many companies and electric
utilities implementing SCADA are no exception. This section discusses the types of
attacks typically seen and the defence tools used to ward off these attacks. This survey
is not focused on the electric utility industry (4% of respondents were from utilities),
it does provide a baseline for the types of attacks perpetrated and damage done by
unauthorized users in almost all the SCADA implementation. According to the
survey, approximately 56% of respondents reported unauthorized computer use in the
past 12 months, slightly less than the numbers reported in the previous 4 years. Figure
shows the data gathered from the survey.
The downward trend in reported attacks may be somewhat misleading. The report
also shows an increasing trend toward not reporting unauthorized use of computer
systems. Respondents cited fear of negative publicity or exploitation by competitors
as primary reasons for not reporting. Figure shows the actions taken by respondents
when they were attacked.
Page 26
Business credibility of System Integration in ICT domain using SCADA
Page 27
Business credibility of System Integration in ICT domain using SCADA
➢ Password Crackers
The term password cracker is basically self explanatory. The intent of this software is
to try multiple login attempts, typically using one of two methods, dictionary or brute
force. Dictionary attack tools use common words or phrases that often appear in
passwords. Brute force attack tools simply try every possible character combination
that could be entered as a password. Brute force attacks can obviously take longer but
also have the ability to crack more passwords. A bevy of password cracking programs
is available free on the internet. Lophtcrack is a commercially available program that
costs about $250 and is capable of performing brute force and dictionary attacks.
➢ War Dialers
War dialers use a single modem or a bank of modems to dial a range of numbers to
determine whether a particular phone line has a modem connected to it. If this is the
case, the attacker can then attempt to gain access to this modem using a password
cracker or other tool. Like password crackers, war dialers can also be downloaded
from the internet. Examples include ToneLoc and THC-Scan. PhoneSweep is a
commercially available program that can differentiate between modems and faxes.
Cost for this program is approximately $1,000.
Ping sweep and port scan programs work on TCP or UDP networks. Ping sweep
programs work similarly to war dialers, except instead of dialing phone numbers they
ping ranges of IP addresses to determine which ones are used. Port scan programs can
then be used to determine which ports are being used. Nmap is an example of a tool
that can do ping sweeps and port scans. It is freely available on the internet and works
on Windows-based machines. Ethereal is a UNIX/LINUX version that is also freely
available.
Page 28
Business credibility of System Integration in ICT domain using SCADA
receiver. Protocol analyzers take raw packet data and attempt to determine the
protocol used and the information being transmitted by each packet. Like other tools,
many products are available freely from the internet. Ethereal, mentioned in the
previous section, also performs sniffing and protocol analysis.
Denial of service (DOS) attack tools work by flooding a network with either
legitimate or malformed packets of data, thereby effectively locking out legitimate
traffic. Some tools come with several malformed packet types known to cause certain
systems to crash. Examples of these tools are smurf, fraggle, and SYNflood.
SYNflood sends connection requests (SYN packets) to the intended target, but never
acknowledges the connection so that many ports are left open on the target
machine(s).
As shown in the previous section, there are several ways to gain access to a
networked system. Once a system has been penetrated, an attacker has several options
to choose from if his or her target is an electric utility.
He or she could:
1. Take direct control of devices in substations and/or generation plants,
shutting these facilities down.
2. Plant malicious code or a “logic bomb” that executes on a given event or at
a preselected time to disrupt the system.
3. Plant code that opens a “back door” to allow easy access in the future.
4. Change data such as billing information to disrupt financial operations.
5. Perform a “man in the middle” attack to intercept and change data to
deceive system operators into thinking the system is in a condition that it is
not (e.g., circuit overload). The operators may therefore take unnecessary or
damaging action to mitigate this condition.
6. Change protective device settings to make a protective relay trip when it
shouldn’t, not trip when it should, or both, thus taking the system out of
service and/or causing damage to equipment.
Page 29
Business credibility of System Integration in ICT domain using SCADA
7. Take resources hostage for other purposes (e.g., game hosting), degrading
performance of the system for the tasks it was designed to do.
Of course, system penetration is not necessarily even required. An attacker could
initiate a denial of service (DOS) or distributed denial of service (DDOS) attack that
basically ties up all network resources and prevents legitimate traffic from getting
through a network.
Several tools are also available to defend systems. These tools include passwords,
firewalls, intrusion detection systems, virtual private networks, and access control.
The following sections provide a brief description of each of these tools.
➢ Passwords
Passwords can be an effective security method. Two factors that influence their
effectiveness are whether the passwords are strong passwords and whether they
are encrypted. Strong passwords are defined as passwords of six characters or
more, with at least one special character or digit and mixed-case character, that do
not form a pronounceable word, name, date, or acronym.Table shows a
comparison of the time it takes a password cracking program to crack passwords
of different lengths for strong passwords (require brute-force cracking) and for
dictionary passwords. Dictionary passwords in this case are based on the 25,143-
word UNIX spell-check dictionary that contains words, numbers, common names,
and acronyms. Strong passwords are based on a 90-character set of letters,
numbers, and special characters.
Page 30
Business credibility of System Integration in ICT domain using SCADA
As one can see from the table, strong passwords, especially those of six characters or
longer, are almost impossible to crack using brute force methods. Of course, if a
potential intruder can sniff a network and see the password in clear text, the strongest
password is no better than a weak password. It is therefore important that passwords
not be transmitted in clear text. Several tools are available for password encryption
for workstations and servers. Intelligent devices in substations, on the other hand,
often do not support a full character set for passwords, nor do they support password
encryption.
➢ Firewalls
Page 31
Business credibility of System Integration in ICT domain using SCADA
➢ Access Control
Access control can include the control of physical access to computer systems. It
can also refer to electronic access. For electronic access, control measures are
identified as one, two, or three factor authentication. The three factors are:
○ Something you have (e.g., ID card)
○ Something you know (e.g., password)
○ Something you are (e.g., fingerprint)
Obviously the most secure authentication and access control would incorporate all
three, but this is seldom the case in actual systems. Two-factor authentication is
sometimes used, but single-factor authentication is still commonplace for many
systems. RSA security is a leader in two-factor authentication systems. According
to the RSA website (http://www.rsasecurity.com/), their SecurID cards are the
most popular two-factor identification systems in the world.
Biometrics is the term typically used to describe the third factor. Several methods
of using biometrics to verify identity are available. Factors checked by various
systems include fingerprints, retinas, iris, face patterns, hand geometry, signature,
or voice recognition. Although costs for these devices are decreasing, they do not
appear to be used widely. Perhaps one of the reasons is that at least some of them
are quite easy to spoof. According to a recent PC Magazine article, fingerprint
Page 32
Business credibility of System Integration in ICT domain using SCADA
scanners could be spoofed by simply breathing on the sensor, making the last
fingerprint reappear. Some face recognition sensors could be spoofed by a still
photo. Iris sensors could similarly be fooled by placing a photograph of a person’s
eye on someone else’s face.14 Newer products are addressing some of these
problems but it appears for the most part that biometric devices are not quite ready
for prime time.
Respondents to the survey report use several tools to defend against attacks (see
Figure). Most common among these are anti-virus software, firewalls, access control,
and physical security. Intrusion detection is also becoming a more commonly used
tool, as well as encrypted files. Most of the technologies in Figure in the previous
section are fairly self explanatory.
Page 33
Business credibility of System Integration in ICT domain using SCADA
As mentioned previously, NERC has been involved with the security of electric utility
systems. Its Urgent Action Standard 1200, which was issued in August 2003, is an
attempt to standardize and enforce compliance with cyber-security principles. The
standard mandates that every entity involved with the generation, transmission, or
distribution of electric power must perform several steps, including:
1. Identify its critical cyber assets.
2. Identify its physical and electronic perimeters.
3. Implement physical and electronic access controls.
4. Monitor physical and electronic access.
5. Identify response actions for physical and electronic incidents.
6. Identify recovery plans in the case of an attack.
Physical security at electric power substations and generation facilities varies from
installation to installation depending on level of risk, level of impact, and cost of
implementation. Cost is a particularly important factor as a result of the competitive pressures
brought on by deregulation. IEEE Std. 1402-2000, “IEEE Guide for Electric Power
Page 34
Business credibility of System Integration in ICT domain using SCADA
Substation Physical and Electronic Security,” is available as a resource for planning and
implementing security measures. The main categories of physical security at electric power
substations are physical barriers and electronic barriers. Examples of physical barriers
include fences, walls, and locks. Examples of electronic barriers include photo-
electric/motion sensing, video surveillance systems, building systems, computer security
systems, passwords, dial-back verification, selective access, virus scans, encryption, and
encoding. Examples of other types of security measures are lighting, landscaping, buildings,
patrols, communications, and internal and external information restrictions.
Table identifies three sample electric power utilities and their implementation of IEEE Std.
1402-2000. The three utilities are a hydro-electric utility, a utility performing transmission,
distribution, and generation, and a utility performing transmission and distribution only.
Table: Three sample electric power utilities and implementation of IEEE Std. 1402-
2000
Page 35
Business credibility of System Integration in ICT domain using SCADA
A security survey was performed and documented in IEEE Std. 1402-2000. The survey
results, shown in Table, provide an indication of the effectiveness of security methods used
by respondents in an urban substation. One general observation is that lights, signs, and
special locks are the most common security methods employed. Although generally effective
according to the majority of the respondents, these methods were not found to be completely
effective and can be defeated. Some of the methods used least often (alarms systems, motion
detectors, and electronic protection) were reported to be completely effective. The
respondents were from various utilities.
Page 36
Business credibility of System Integration in ICT domain using SCADA
The entire power requirement in India is basically met by the following three methods:
• Hydro Stations
• Thermal Stations
• Nuclear Generation
From the pie chart we can clearly conclude that the major portion of the requirement of the
power is met using the Thermal generation technique.
Subsequently the total cost of production for the Thermal power generation is the maximum
followed by Hydro stations and the Nuclear generation in the end. One of the reasons for the
low contribution of the Nuclear sector is that it is relatively a new domain and currently the
production is only under the control of the Central Government.
Per Unit cost for Thermal power generation is maximum closely followed by Nuclear power.
Whereas the per unit cost of Hydro power generation is the least. But however due to the lack
of proper projects on the river beds across India, there is a lot of emphasis on the production
of electricity using the Thermal stations even though it is very costly. In the Eleventh Five
year plan the Government of India has given a lot of emphasis on the Hydro electric power
stations.
Page 37
Business credibility of System Integration in ICT domain using SCADA
In the Eleventh Five year plan (2007-2012) the Government of India plans to clearly increase
the capacity of all the three Power generation sectors i.e. Thermal, Hydro and Nuclear in
order to satisfy the ever increasing requirement of the Urban and the Rural India. This clearly
indicates that there will be an increase in the number of projects to meet the requirement
which will provide a clear opportunity for the SCADA implementation as these projects will
involve a lot of automation.
Page 38
Business credibility of System Integration in ICT domain using SCADA
Wind power and Hydro electric power stations are the two most cheap way of producing
energy to satisfy the requirement of the Urban and Rural masses across India. Therefore the
Government of India has given the maximum subsidies to the projects in these sectors to
encourage energy production.
Due to the limited infrastructure across the river beds in India the total capacity production of
Hydro power stations is not adequate to meet the requirements of the Indian population.
There exists a great potential in the Wind power stations for generating energy and meet the
requirements.
The subsidies provided by the Government of India encourage the projects in the Wind
power sector. However being a relatively new sector there are fewer projects in this domain
but it is slowly increasing.
India has been heavily relying on the Small hydro power stations for satisfying the energy
requirement and hence the total number of projects is maximum in this particular sector.
India has also started concentrating on the generation of energy using Biomass and Urban
waste as it is one of the cheapest ways and is environmental friendly.
Page 39
Business credibility of System Integration in ICT domain using SCADA
The increase in the participation of the private sector over the years for the production of
energy provides an opportunity for HCL to provide infrastructure support as well as to
implement SCADA for the automation related processes in the project and provide an end to
end support. HCL has a tremendous potential to tap the Thermal and the Hydro projects
across India and thus give a boost to its SCADA domain.
3.5.3.1 THERMAL
3.5.3.2 HYDRO
Page 40
Business credibility of System Integration in ICT domain using SCADA
5.3.3 NUCLEAR
However Nuclear sector being a relatively new and a niche domain is solely under the
control of the Central Government. All the projects of Nuclear energy production is
managed by the Central Government and HCL does not have an opportunity in this
particular domain. The production of energy has gone down tremendously for 2007-
08 to 2009-10 due to the restrictions introduced for the nuclear energy production by
the Indo-US nuclear deal.
There are basically three major players involved in the production of the Natural Gas and Crude Oil
as a Secondary source of Commercial energy provider. These players are:
• ONGC
• OIL
• Joint Ventures/ Private Companies
Page 41
Business credibility of System Integration in ICT domain using SCADA
The overall production projects of Crude Oil are basically under the Central Government
organizations ONGC and OIL. However there are around 25 % of projects under the private
sector which again throws up an opportunity for HCL to provide infrastructure support and
implement SCADA in its automation processes.
Whereas in the production of the Natural Gas around 50% of the total projects are under the
private sector thus opening up another opportunity for HCLs SCADA implementation.
This centrally sponsored scheme includes the continuing schemes related to Flood
Management Works in Ganga Basin/Brahamaputra & Barak Basin and improvement
of drainage in Brahamaputra, flood management and anti erosion works being
executed by Brahamputra Board, feasibility studies of channelization of Brahamputra
etc. This scheme will also include activities to be taken up in all the other basins
Page 42
Business credibility of System Integration in ICT domain using SCADA
throughout the country such as Flood proofing programme, critical flood control and
anti erosion works including sea erosion, improvement in drainage in critical areas,
inundation modeling of flood disaster preparedness, Grant-in-Aid to Brahamputra
Board and Ganga Flood Control Commission, Strengthening of Flood Management
Organisation, CWC, setting up of National Flood Management Commission, share
cost for flood component in multi-purpose water resources development projects etc.
A provision of Rs. 8500 crore has been kept for this scheme under Central sector in
XI Plan. Out of this Rs.7000 crore is for the Centrally Sponsored Programme and
Rs.1500 crore is meant for the Central Sector Schemes of GFCC, Brahamputra
Board and CWC.
Page 43
Business credibility of System Integration in ICT domain using SCADA
• Hydrology project:
The scheme will cover all activities related to ground water management studies with
an objective to evolve sustainable strategies including exploration, investigations,
artificial recharge to ground water, conjunctive use of surface and ground water
resources, geogenic contamination etc. The scheme will include existing scheme of
Ground Water Survey, Exploration & Investigations, Artificial Recharge of ground
water and Central Ground Water
Authority. A provision of Rs. 515 crore has been kept for this scheme under Central
sector in XI Plan
• Flood Forecasting:
The scheme will include the activities of collection of Hydro-meteorological data and
issue of Flood Forecasts in India and will include the continuing scheme related to
Strengthening & Modernization of FF & HO network in Brahamaputra & Barak basin
and Establishment and Modernization of flood forecasting network in India including
inflow forecasts.A provision of Rs.150 crore has been kept for this scheme under
Central sector in XI Plan.
• Infrastructure development:
Page 44
Business credibility of System Integration in ICT domain using SCADA
This scheme will include the activities related to lands & building and IT
Development and will include the continuing schemes related to Land and Buildings
of CWC, Lands and Buildings of GFCC, Lands and building of CGWB, IT
Development of MoWR, Upgradation and Modernisation of Computerisation and
Information system of CWC etc. A provision of Rs.125 crore has been kept for this
scheme under Central sector in XI Plan.
Page 45
Business credibility of System Integration in ICT domain using SCADA
iii. Fibre Optic embedded Raman Scattering Technique or any other alternate
technology for scanning of Boiler Tube Metal Temperature.
Technologies are available for boiler condition assessment. However the major issue
involved is to make it suitable & approachable, when it comes to real life situation in
a boiler. The main deliverable for the project is to demonstrate these technologies in
an integrated manner for true assessment of boiler condition.
Robotic based Corrosion mapping system for water wall tubes through Magnetic
Inductance Bridge based robotic system. The water wall tubes in the primary pass of
thermal power plant boiler are subjected to severe corrosion problems especially in
the burner zones leading to loss in thickness. The wall thickness of each tube needs to
Page 46
Business credibility of System Integration in ICT domain using SCADA
be monitored during annual shutdown periods for ascertaining their suitability for
continued service and schedule for replacement if necessary. In view of the short shut
down periods, it is not possible to measure the thickness of all tubes using
conventional ultrasonic technique. In a robotic based system, the probe/magnetizing
coil is supported on robotic device which can crawl along the whole length of the
water wall tubes and maps the corrosion thickness. The high temperature boiler tube
during service forms coherent oxide layer on the outer surface due to oxidation. The
presence of this oxide layer on the outside of tubes interferes with ultrasonic wall
thickness measurement and prevents proper sound coupling during conventional UT
technique. The application of EMAT probes permits enables direct measurement
without any surface cleaning of the boiler. When coupled with a robotic device, large
number of tubes and different elevations can be covered in a short shut down period.
Phased array technique is a specialized type of testing that utilizes multi element array
transducers and software controls for steering the ultrasonic beam. In view of
complexity in shape & geometry of component of turbine components such as blades,
rotor steeple and disk rim attachments, the conventional techniques suffer by
reliability, accuracy & reproducibility. The advanced linear phased array ultrasonic
technology wherein multiple UT probes mounted in a single holder is used to for this
purpose and reported that the reliable and redundant results can be obtained in respect
of defect detection, sizing and shape. HP / IP rotors suffer in-service degradation from
rotor material temper embrittlement. The rotor material fracture toughness, which
governs the size of the critical flaw for fracture, is hence adversely affected. A
reliable assessment of the fracture toughness properties of steam turbine rotor requires
sampling of material from inservice rotor. A miniature sample removal and small
punch testing technique for direct estimation of fracture toughness provides a rational
basis for reduction of conservatism during RLA of rotor. The remote eddy
current/CCTV system is capable of examining the trailing and attachment areas of L-
0 and L-1 turbine blades without turbine disassembly. Eddy current tests have also
been successfully used to detect cracks in the area of the satellite wear strips on the
leading edge of last stage blades and for inspection of turbine casing bolt and bolt
holes. Critical turbine components must be evaluated to assure safe operation during
Page 47
Business credibility of System Integration in ICT domain using SCADA
their lifetime. The adoption of advanced RLA methodologies leads to the emergence
of sophisticated practice in RLA with reliable and upgraded assessment technologies
in the short time available during periodic maintenance, application of Robotics,
improved deterministic routes and evolution of technology options. The project
envisages development of state-of-art technology in the area and adopts them in a few
thermal power stations. The project will support a number of spin off research in the
related area.
• Combustion modelling and technologies for utilization of fly ash unburnt carbon
in pressurized fluidized bed gasifier
Page 48
Business credibility of System Integration in ICT domain using SCADA
The advantages of VSC based HVDC system can be best utilized for applications
like:
• Deep river crossings
Page 49
Business credibility of System Integration in ICT domain using SCADA
• Power supply to isolated loads (supply to distant town, mine, island or even
production platform in the sea needing power from main land),
• Feeding Power from small isolated generation (wind, small hydro, tidal solar
etc.) to a grid or to a separate load without affecting power quality of receiving
network.
The implementation of technology developed in the area of power distribution is also
envisaged. Here, power electronics devices such as DVR, STATCOM etc. based on
VSC based converters would be developed. These would be included in the feeders to
improve power quality. These demonstration systems would have suitable AMR
system to monitor energy supplied to customers. The deliverables from the project
would result in demonstration of high quality power distribution systems. The
selection and development of suitable power electronics devices and a field show
casing as stated above forms an integral part of the project.
The project would pave the way for design of future rural energy network, where
distributed generation sources are likely to be deployed and would act as a
benchmark.
Sr PROJECTS ALLOCATION
No.
1. Coal Liquefaction Project by OIL Rs.250 Crore
Upstream 159,161
Refining 81,545
Gas 13,079
Marketing 6,080
Page 50
Business credibility of System Integration in ICT domain using SCADA
TOTAL 269,049
The above investments are based on the information received from various companies and
does not include investment in the oil and gas sector by the private sector. However, these
investments may undergo some change at the time of finalisation of the Annual Five Year
Plans.
SWOT analysis is a tool for auditing an organization and its environment. It is the first stage
of planning and helps marketers to focus on key issues. SWOT stands for strengths,
weaknesses, opportunities, and threats. Strengths and weaknesses are internal factors.
Opportunities and threats are external factors.
Page 51
Business credibility of System Integration in ICT domain using SCADA
Strengths
a) A SCADA system can help industry to save time and money through
standardisation of technology.
c) SCADA software enables you to monitor the operations in real time thus
reducing the operational costs and improves the efficiency of any automation
set up.
Page 52
Business credibility of System Integration in ICT domain using SCADA
d) Reduced incident risks through the reduction in the number and severity of
operational incidents and improved capability to respond once an incident has
occurred (remote monitoring, remote control, and ability to control groups of
assets)
e) Standardize operating procedures and better utilization of staff and the auto-
generated reporting system can ensure compliance with regulatory principles.
1. Capabilities of HCL
a) HCL has a well established and reputed brand name in the market in both
primary sector requirements for SCADA implementation
i. IT domain
b) HCL thus can have a competitive advantage over other existing niche players
in the market by providing end-to-end solutions by itself.
c) HCL keeps up its pace with the changing trends in the technology. Therefore
the clients can be assured of the solution provided by HCL will not become
obsolete.
d) HCL Infinet- the Networking service provider has received MAIT's 'Level II
recognition for Business Excellence'. HCL Infinet has also received the
ELCINA award for quality in networking solution.
Weaknesses
HCL Infinet while providing the networking solution for SCADA might adopt the
standardized technologies with known vulnerabilities because of the constraints on the use of
existing security technologies and practices which may give rise to the security
vulnerabilities.
Page 53
Business credibility of System Integration in ICT domain using SCADA
a) Denial of Service (DoS) attack to crash the SCADA server leading to shut
down condition (System Downtime and Loss of Operations)
b) Delete system files on the SCADA server (System Downtime and Loss of
Operations)
c) Planting a Trojan and take complete control of system (Gain complete control
of system and be able to issue any commands available to Operators)
f) Change data points or deceive Operators into thinking control process is out of
control and must be shut down (Downtime and Loss of Corporate Data)
g) Modify any logged data in remote database system (Loss of Corporate Data)
Opportunities
1. Market developments
Page 54
Business credibility of System Integration in ICT domain using SCADA
ii. Oil & Gas industry – 9.3% over the next five years
iii. Electric Power industry – 5.5% over the next five years
a) Customization of the PLCs through the use of Software is a market which has
remained aloof from the existing players. HCL has the capability to explore
this opportunity in a profitable manner and can use it as a potential entry
point.
1. New Verticals
b) HCL can also target operations in niche segments like Nuclear and
Radioactive processing industry which is a booming sector in India due to the
recent Indo-US nuclear deal.
c) SCADA integration with GIS - HCL can also plan to integrate SCADA with
the existing System Integration vertical of HCL-Vehicle Tracking Signal for
proper Traffic Signal control and Congestion Management System.
a) HCL can go for key strategic alliances with established core automation
sector players in the market and provide them with the required hardware,
software and networking technologies for SCADA implementation.
Page 55
Business credibility of System Integration in ICT domain using SCADA
b) HCL can also go for the acquisition of some small SCADA implementing
firms and thus need not worry about acquiring new projects.
Threats
1. Existing players
a) A number of domestic and international players in the Indian market can pose
a great challenge and competition for HCL.
1. Insurmountable weakness
a) Security threat which is a weakness of the SCADA system both internal and
external, are the biggest threat that HCL might face while developing and
implementing the SCADA system
a) Thin clients, web based products and web portals which provides low cost
solution for SCADA implementation can pose a threat for new entrant like
HCL
CHAPTER 4
Page 56
Business credibility of System Integration in ICT domain using SCADA
4.1.1 WIPRO
Page 57
Business credibility of System Integration in ICT domain using SCADA
• High Performance Computing such as high volume data analysis, GIS Systems,
Simulation
For the implementation of the SCADA successfully Wipro has gone into a number of
strategic alliances with the leading players in this particular domain.
• Honeywell
• Yokogawa
• Intellution
• Cimplicity
Page 58
Business credibility of System Integration in ICT domain using SCADA
Page 59
Business credibility of System Integration in ICT domain using SCADA
Wipro will market and deliver Schneider Electric's solutions including Manufacturing
Execution Systems (MES) and Supervisory Control And Data Acquisition (SCADA) in
India.
Page 60
Business credibility of System Integration in ICT domain using SCADA
To begin with, Wipro shall provide Schneider Electric’s Ampla MES Solution to the mining,
mineral processing and metals industries.
Wipro’s System Integration capabilities and Schneider Electric’s reach in the SCADA market
will promote the synergy and alliance. Wipro's matured consulting practice and proven
delivery model for large and complex projects will help Schneider Electric’s collective
customers make the most of their energy.
GE Fanuc Automation entered into a Solution Provider go-to-market agreement with Wipro
Technologies, the global IT services business of Wipro Limited (NYSE:WIT). The two
companies will work together globally to better serve manufacturing enterprises in the
Automotive, Pharmaceutical, Food & Beverage and Consumer Packaged Goods industries
with solutions in the Production Management area.
This relationship will provide significant value to customers looking to integrate their
Production Management and ERP systems by leveraging Wipro’s knowledge of GE Fanuc
Production Management solutions and their expertise in ERP.
The scope of the agreement covers services, point solution development and joint go-to-
market activities. Wipro’s knowledge of supply chain, plant floor operations, enterprise
technologies and business processes will enable timely and effective deployment of GE
Fanuc Production Management solutions which include the Proficy family of products:
Proficy Tracker, Proficy Plant Applications, Proficy HMI/SCADA CIMPLICITY and iFIX,
as well as Proficy Historian, Proficy Change Management and Proficy Real-Time
Information Portal products that encompass an integrated suite of applications providing
execution, logistics, quality, tracking, reporting and visibility throughout all of a company’s
plant operations.
Page 61
Business credibility of System Integration in ICT domain using SCADA
Page 62
Business credibility of System Integration in ICT domain using SCADA
The following pie chart shows the segment wise performance of ABB in the year 2008 and
2007. The revenue from all the other segments of ABB in 2008 other than the Power System
shows a significant increase in the performance from the year 2007.
2008 2007
Orders Received 25608 30029
Revenues 23054 22514
Central Government’s focus on the power sector reforms and introduction of the National
Electricity policy in past few years is reflected in increasing investments in capacity addition,
development of transmission network and power distribution improvements. However due to
the exceptional global liquidity crunch, economic downturn and increase in capital costs
resulted in the postponement and implementation of several power projects, especially those
which has been taken up by industrial houses. The rescheduling of few power projects and
Page 63
Business credibility of System Integration in ICT domain using SCADA
Company’s decision to exit Rural Electrification projects due to safety and cash flow
concerns has resulted in lower orders received as compared to the previous year.
The exit of ABB from the Rural Electrification projects presents an opportunity in front of
HCL to grab these projects and thus enter the market in automation projects and provide end
to end solution to the Government of India.
2008 2007
Orders Received 24062 20433
Revenues 20492 16321
Buoyancy in the transmission sector and the distribution sector continued during the year
with higher level of investment in this sector until the middle of the year. The orders
somehow slowed down during the second half of the year due to liquidity crunch and
slowdown in the global market. However as per the current indications in the Eleventh five
year plan the Government of India is planning towards the implementation of the power
generation, distribution and transmission projects. The stimulus package announced by the
Government of India of around Rs.20 crore shows the seriousness of the Government of India
towards this sector.
Thus the impetus of the Government towards this sector can be perceived by HCL as a
positive indicator and can use this as an opportunity to enter the market.
Page 64
Business credibility of System Integration in ICT domain using SCADA
2008 2007
Orders Received 15659 14600
Revenues 13334 10665
The Industrial climate in the country remained buoyant during the first half of the year with
strong growth indicators from various verticals. The global market meltdown affected the
second half of the year with some of the proposed investments being deferred or postponed
indefinitely. The industry has significant opportunities for investments looking at the trend of
increasing per capita consumptions of steel, cement etc. Also the setting of industrial plants
by steel majors like POSCO and Arcelor-Mittal provides an opportunity for this sector to
grab new projects.
HCL can plan acquisitions or a strategic merger with Siemens and acquire mechanical OEMs
in the metal sector and then put effort to consolidate this acquisition with their own
automation solutions for metals to provide an end to end solution to the customer
2008 2007
Orders Received 20679 15395
Revenues 17376 13333
Page 65
Business credibility of System Integration in ICT domain using SCADA
A positive market environment particularly in the first half of the year coupled with strategic
thrust on capacity and product range expansion and focused marketing efforts depending
upon the industry verticals helped the segment in registering a growth of 34% in orders
received and 30% increase in the revenues during the year. There was a strong marketing
focus on the original equipment manufacturer (OEM) segment including HVAC, pumps,
compressor, boiler machinery, wind energy, waste water management.
Building up of capacities by the segment and increase in competition coupled with reduction
in the demand in the market on account of the slow down posed challenges for the growth in
business volumes. Capacity expansion planned in infrastructure sector like water, roads,
railways, wind and water management projects are expected to grow.
HCL can plan major marketing activities in potential growth areas like railways, water, waste
water, maintain efficient distribution network and continuous range expansion in order to
establish itself in the market.
Page 66
Business credibility of System Integration in ICT domain using SCADA
Page 67
Business credibility of System Integration in ICT domain using SCADA
2009 2008
$1,723. $2,419.
Sales 5 7
Segment Operating
Earnings 223 584.7
Segment Operating Margins 12.90% 24.20%
(in millions, except
percentages)
Sales
Page 68
Business credibility of System Integration in ICT domain using SCADA
Architecture & Software sales decreased 29 percent in 2009 compared to 2008 as plant
shutdowns occurred and production slowed across many industries. Organic sales decreased
24 percent, as the effects of currency translation contributed approximately 5 percentage
points to the decline.
Operating Margin
Architecture &Software segment operating margin decreased by 11.3 points to 12.9 percent
in 2009 compared to 2008. The decrease was primarily due to significant declines in sales
volume. The unfavorable impact of currency exchange rates and restructuring charges also
contributed to the decrease, partially offset by cost reductions.
Page 69
Business credibility of System Integration in ICT domain using SCADA
2009 2008
2,609.0 3,278.1
Sales 0 0
Segment Operating Earnings 206.7 440.5
Segment Operating Margins 7.90% 13.40%
(in millions, except
percentages)
Sales
Control Products & Solutions sales decreased 20 percent in 2009 compared to 2008. Organic
sales decreased 15 percent as the effects of currency translation contributed 5 percentage
points to the decrease.
Page 70
Business credibility of System Integration in ICT domain using SCADA
Control Products & Solutions segment operating margin decreased by 5.5 points to 7.9
percent in 2009 compared to 2008. The decrease resulted primarily from significant declines
in sales volume. Inflation, the unfavorable impact of currency exchange rates and
restructuring charges also contributed to the decrease.
Competitors
• The major competitors of our Architecture & Software operating segment include
Siemens AG, Mitsubishi Corp., ABB Ltd, Honeywell International Inc., Schneider
Electric SA and Emerson Electric Co.
• The major competitors of our Control Products&Solutions operating segment include
Siemens AG, ABB Ltd, Schneider Electric SA, Honeywell International Inc. and
Emerson Electric Co.
Page 71
Business credibility of System Integration in ICT domain using SCADA
4.1.4 SIEMENS
Page 72
Business credibility of System Integration in ICT domain using SCADA
Segment information :
The primary and secondary reportable segments are business segments and geographical
segments respectively.
Business Segments: The business of the company is divided into eleven segments. These
segments are the basis for management control and hence, form the basis for reporting. The
business of each segment comprises of:
Revenue
Inter
segmental
External sales sales Total
2008 2007 2008 2007 2008 2007
Automation and 1,59,78, 1,34,10, 50,69,6 31,44,8 2,10,48, 1,65,55,
drives 711 663 40 16 351 479
Industrial solutions 1,17,95, 92,37,92 2,34,00 2,91,05 1,20,29, 95,28,98
and services 420 8 9 2 429 0
67,08,85 34,67,42 67,08,85 34,67,42
Transport 8 4 0 0 8 4
Building 10,19,59
technologies 0 9,84,319 0 35,274 0 3
4,15,42, 4,17,79, 8,35,46 12,28,2 4,23,78, 4,30,08,
Power 879 906 5 49 344 155
Healthcare and 60,53,46 52,46,93 60,53,46 52,46,93
other services 0 1 0 0 0 1
Real estate 6,44,530 4,95,568 0 0 6,44,530 4,95,568
Information and 14,41,88 14,69,96
communication 0 0 0 28,088 0 8
12,03,43 12,03,43
Automotive 2,31,596 7 0 0 2,31,596 7
• Power
Provides automation solutions for a wide range of applications in power plants,
focusing on a complete range of medium and high voltage switchgears, medium
Page 73
Business credibility of System Integration in ICT domain using SCADA
voltage switchboards, protection and control systems for sub-stations, power system
control and energy management systems, meters, transformers and industrial turbines.
Page 74
Business credibility of System Integration in ICT domain using SCADA
• Transport
Provides solutions for rail automation, railway electrification, light and heavy rail,
locomotives, trains, turnkey projects and integrated services.
• Building Technologies
Executes projects for providing Integrated Building Management Systems including
Building Automation Systems, Fire Alarm/Access Control/Security Systems.
Siemens India has discontinued the operations in the Building Technologies sector in
2008. This is clearly evident from the fact that the sales in the year 2008 was zero.
Page 75
Business credibility of System Integration in ICT domain using SCADA
• Real estate
Provides comprehensive real estate management.
• Automotive
Manufacturing and trading of dashboard instruments, tachographs and other allied
equipments for the automobile.
Page 76
Business credibility of System Integration in ICT domain using SCADA
4.1.5 HONEYWELL
Honeywell manages their operations basically through four major businesses that are reported
as operating segments:
• Aerospace
Page 77
Business credibility of System Integration in ICT domain using SCADA
Page 78
Business credibility of System Integration in ICT domain using SCADA
Solutions
Specialty Materials 605 721 658
Transportation Systems 156 406 583
Corporate (145) (204) (189)
(dollars in millions) $ 4097 $ 4845 $ 4654
• Aligning inventory, production and research and development with customer demand
and production schedules;
• Continuing to design equipment that enhances the safety, performance and durability
of aerospace and defense equipment, while reducing weight and operating costs;
• Delivering world-class customer service and achieving cycle and lead time reduction
to improve responsiveness to customer demand; and
Page 79
Business credibility of System Integration in ICT domain using SCADA
• Continue to develop new processes, products and technologies that address energy
efficiency, renewable energy sources, global warming, security regulations and
position the portfolio for higher value;
• Commercialize new products and technologies in the petrochemical, gas processing
and refining industries;
• Drive sales and marketing excellence and expand local presence in fast growing
emerging markets;
• Execution of awarded government stimulus projects and pursuit of additional projects;
• Manage exposure to raw material commodity fluctuations; and
• Prioritize critical investment to increase plant reliability and attainment, productivity,
quality and operational excellence.
Page 80
Business credibility of System Integration in ICT domain using SCADA
• Maintaining the high quality of current products while executing new product
introductions;
• Increasing global penetration and share of diesel and gasoline turbocharger OEM
demand;
• Aligning cost structure with current economic outlook, and successful execution of
repositioning actions;
• Aligning development efforts and costs with new turbo platform launch schedules;
and
Page 81
Business credibility of System Integration in ICT domain using SCADA
Page 82
Business credibility of System Integration in ICT domain using SCADA
Segment Operations
Our five segments are focused on the broad markets they serve:
• Energy Infrastructure
• Technology Infrastructure
• NBC Universal
• Capital Finance
• Consumer & Industrial
Revenues
2009 2008 2007
Energy Infrastructure 37,134 38,571 30,698
Technology Infrastructure 42,474 46,316 42,801
NBC Universal 15,436 16,969 15,416
Caital Finance 50,622 67,008 66,301
Consumer & Industrial 9,703 11,737 12,663
Segment Profit
2009 2008 2007
Energy Infrastructure 6,842 6,080 4,817
Technology
Infrastructure 7,489 8,152 7,883
NBC Universal 2,264 3,131 3,107
Caital Finance 2,344 8,632 12,243
Page 83
Business credibility of System Integration in ICT domain using SCADA
Energy Infrastructure
Energy Infrastructure segment revenues decreased 4%, or $1.4 billion, in 2009 as higher
prices ($1.3 billion) were more than offset by lower volume ($1.6 billion), the stronger U.S.
dollar ($0.7 billion) and lower other income ($0.5 billion), primarily related to lower earnings
from associated companies and marks on foreign currency contracts. The increase in price
was primarily at Energy. The decrease in volume reflected decreased equipment sales at
Energy, partially offset by increased equipment sales at Oil & Gas. The effects of the stronger
U.S. dollar were at both Energy and Oil & Gas.
Segment profit increased 13% to $6.8 billion, compared with $6.1 billion in 2008, as higher
prices ($1.3 billion) and lower material and other costs ($0.5 billion) were partially offset by
lower other income ($0.7 billion), primarily related to lower earnings from associated
companies and marks on foreign currency contracts, and lower volume ($0.2 billion). Lower
material and other costs were primarily at Energy. Lower volume at Energy was partially
offset by higher volume at Oil & Gas.
Technology Infrastructure
Technology Infrastructure revenues decreased 8%, or $3.8 billion, in 2009 as lower volume
($4.1 billion), the stronger U.S. dollar ($0.4 billion) and an update at Transportation of our
estimate of product service costs in maintenance service agreements ($0.3 billion) were
partially offset by higher prices ($0.5 billion) and higher other income ($0.5 billion),
primarily including gains on the ATI-Singapore acquisition, dissolution of the joint venture
with FANUC Ltd. and the Times Microwave Systems disposition. The decrease in volume
Page 84
Business credibility of System Integration in ICT domain using SCADA
was across all businesses in the segment. The effects of the stronger U.S. dollar were at
Healthcare, Enterprise Solutions and Aviation. Higher prices, primarily at Aviation, were
partially offset by lower prices at Healthcare. Segment profit decreased 8% to $7.5 billion in
2009, compared with $8.2 billion in 2008, as the effects of lower volume ($1.0 billion) and
lower productivity ($0.4 billion) were partially offset by higher prices ($0.5 billion) and
higher other income ($0.4 billion), primarily including gains on the ATI-Singapore
acquisition, dissolution of the joint venture with FANUC Ltd. and the Times Microwave
Systems disposition. The decrease in volume was across all businesses in the segment. Lower
productivity at Transportation and Enterprise Solutions was partially offset by Aviation.
NBC Universal
NBC Universal_ revenues decreased 9%, or $1.5 billion, in 2009 as lower revenues in our
broadcast television business ($1.1 billion), reflecting the lack of a current-year counterpart
to the 2008 Olympics broadcasts and the effects of lower advertising revenues, lower
revenues in film ($0.8 billion) and lower earnings and higher impairments related to
associated companies and investment securities ($0.4 billion) were partially offset by the gain
relating to A&E Television Network (AETN) ($0.6 billion) and higher revenues in cable
($0.3 billion). Segment profit of $2.3 billion decreased 28%, or $0.9 billion, as lower
earnings in film ($0.6 billion), lower earnings and higher impairments related to associated
companies and investment securities ($0.4 billion), lack of current-year counterpart to 2008
proceeds from insurance claims ($0.4 billion) and lower earnings in our broadcast television
business ($0.2 billion) were partially offset by the gain related to AETN ($0.6 billion) and
higher earnings in cable ($0.2 billion).
Capital Finance
Page 85
Business credibility of System Integration in ICT domain using SCADA
Capital Finance revenues decreased 24% and net earnings decreased 73% compared with
2008. Revenues in 2009 and 2008 included $3.0 billion and $0.4 billion of revenue from
acquisitions, respectively, and in 2009 were reduced by $4.8 billion as a result of
dispositions, including the effect of the deconsolidation of Penske Truck Leasing Co., L.P.
(PTL). Revenues in 2009 also decreased $14.1 billion compared with 2008 as a result of
organic revenue declines, primarily driven by a lower asset base and a lower interest rate
environment, and the stronger U.S. dollar. Net earnings decreased by $6.3 billion in 2009
compared with 2008, primarily due to higher provisions for losses on financing receivables
associated with the challenging economic environment, partially offset by lower selling,
general and administrative costs and the decision to indefinitely reinvest prior-year earnings
outside the U.S.
During 2009, GE Capital provided $72 billion of new financings in the U.S. to various
companies, infrastructure projects and municipalities. Additionally, we extended $74 billion
of credit to approximately 54 million U.S. consumers. GE Capital provided credit to
approximately 14,200 new commercial customers and 40,000 new small businesses during
2009 in the U.S. and ended the period with outstanding credit to more than 346,000
commercial customers and 174,000 small businesses through retail programs in the U.S.
Consumer & Industrial_ revenues of $9.7 billion decreased 17%, or $2.0 billion, in 2009
compared with 2008, as lower volume ($2.2 billion) and the stronger U.S. dollar ($0.1
billion) were partially offset by higher prices ($0.2 billion). The decrease in volume primarily
reflected tightened consumer spending in the European and U.S. markets. Segment profit
increased 10% in 2009 as higher prices ($0.2 billion) and lower material and other costs ($0.2
billion) were partially offset by lower productivity ($0.3 billion) and lower other income
($0.1 billion).
4.2 COMMISSIONING/VALIDATION
Page 86
Business credibility of System Integration in ICT domain using SCADA
Commissioning is the formal process of verifying and documenting that the installed SCADA
system complies with and performs in accordance with the design intent, as defined in the
design documentation. Commissioning should be identified as a specific activity requiring its
own planning, scheduling, management and monitoring during the design and construction
process. A commissioning team should be assembled including representatives of all
involved parties.
b. Roles and responsibilities of the various parties within the commissioning process
may vary with the agency and the type of project. In some cases, an independent
engineer may be brought in to coordinate and oversee the commissioning process. If
an independent engineer is not used, the design engineer should be retained to oversee
the commissioning process. In either case, certain key components of the program
that must be included for a successful outcome:
(1) A clear definition of the process and the parties’ roles and responsibilities
(Commissioning Plan).
(2) Integration of commissioning activities into the overall project schedule.
(3) An organized system of commissioning documentation.
(4) Development of written testing and verification procedures for every
critical aspect of system performance.
Page 87
Business credibility of System Integration in ICT domain using SCADA
A factory acceptance test and demonstration should be required in which the controller(s),
I/O, and HMI hardware and software are verified to the extent possible without the actual
field devices.
Pneumatic lines should be pressure tested per ISA RP 7.1 and checked for obstructions.
Electrical conductors should be tested for continuity and insulation resistance according to
industry standards for their voltage ratings.
4.2.4 CALIBRATION
Page 88
Business credibility of System Integration in ICT domain using SCADA
Instrument and actuator calibration should be completed prior to loop checkout or startup of
systems. The calibration program should include the following:
The wiring of each control loop should be physically verified from the field device terminals
to the controller.
Cable, conductor, terminal board and terminal designations should be verified and marked off
as such on a copy of the loop diagram or equivalent schematic or wiring diagram.
Verification should be by signal tracing, continuity verification, or “ringing out”. Tags and
labels placed during construction should not be considered adequate verification.
Page 89
Business credibility of System Integration in ICT domain using SCADA
b. All analog loops should be tuned for optimum response using a closed-loop tuning
method and the resulting gain, reset and rate recorded on the loop checkout sheet.
c. A Control Loop Checkout sheet should be completed for each loop.
Performance testing of all systems should be performed to verify compliance with the
specified sequences of operations and control diagrams. Functional performance testing
consists of executing written step-by step procedures in which a condition is initiated or
simulated and the response of the system is noted and compared to the specified response.
Functional performance tests must verify the following:
a. Manual and automatic control modes.
b. Normal system conditions and modes of operation.
c. Contingency conditions and modes of operation.
d. Effect of all operator controls.
e. Operation of all interlocks and permissives.
f. Confirmation of failure state of all outputs.
g. Physical and information security measures.
4.2.8 RE-COMMISSIONING
Page 90
Business credibility of System Integration in ICT domain using SCADA
Prior to functional performance testing, all sensors and instruments should be calibrated and
documented using an Instrument Certification Sheet. Each Instrument Certification Sheet
should include four sections:
a. Description of the Instrument such as Tag Number and Description;
b. A table to record the calibration of Transmitters and Indicators;
c. A table to record the calibration of Process Switches;
d. A list of the Calibration equipment used.
e. Instrument Description: The Instrument Description section should include the
following information:
(1) Project name
(2) Project location
(3) Project number
(4) Certifier’s name
(5) Certification date
Page 91
Business credibility of System Integration in ICT domain using SCADA
Page 92
Business credibility of System Integration in ICT domain using SCADA
(3) Span: the difference between the Maximum and Minimum value of the
instrument
(4) Error: [(Output – Input) / Span] x 100%
Valve actuators and other final control elements should also be calibrated and documented. A
final control element certification sheet should include four sections:
a. Description of the final control element such as tag number and description
b. A table to record the calibration of the I/P (current to pneumatic) converter, if
applicable
c. A table to record the calibration of the final control element
d. A list of the calibration equipment used
e. The final control element description section should include the following
information.
(1) Project Name
(2) Project Location
(3) Project Number
(4) Certifier’s Name
(5) Certification Date
(6) Control Loop Number
(7) Drawing References (such as P&ID, Wiring Diagram, etc.)
(8) Control Valve Tag Number
(9) Control Valve Description
(10) Control Valve Location
(11) Control Valve Manufacturer
(12) Control Valve Model Number
(13) Control Valve Serial Number, if applicable
(14) Control Valve Actuator (Pneumatic or Electric)
(15) Control Valve Positioner (Direct or Reverse), if applicable
(16) Control Valve Positioner Input and Output Signal, if applicable
(17) Control Valve I/P Converter Input and Output Signal, if applicable
Page 93
Business credibility of System Integration in ICT domain using SCADA
(18) Control Valve Failure Mode (open or close) on air failure, if applicable
(19) Control Valve Failure Mode (open or close) on power failure, if
applicable
f. A record of the I/P (current to pneumatic) converter calibration should contain the
following data for both increasing and decreasing inputs at 0, 25, 50, 75 and 100
percent of span:
(1) Input value
(2) Output value
(3) Error
g. A record of the final control element calibration should contain the following data
for both increasing and decreasing signals at 0, 25, 50, 75 and 100 percent span:
(1) Input value
(2) Output travel (position)
(3) Error
h. The certification sheet should include the following information on the calibration
equipment used.
(1) Type of Device
(2) Manufacturer and Model Number
(3) Accuracy
(4) NIST Traceability (Yes/No)
i. Definitions:
(1) Input: the control signal from the controller (PLC)
(2) Output: the measured value of the valve controller to the valve
(3) Travel: the valve percent open (not all valves are linear)
(4) Error: [(Output – Input) / Span] x 100%
The control system integrator should perform loop checkouts for each control loop in the
system and provide suitable documentation certifying that the loop is tuned and operating
properly. The control loop checkout sheet should have a section verifying each of the six
Page 94
Business credibility of System Integration in ICT domain using SCADA
steps described below. When this has been verified and signed off, the functional
performance testing (FPT) can be started.
Page 95
Business credibility of System Integration in ICT domain using SCADA
g. The software logic and HMI/OIT should have been verified during the factory
acceptance test.
h. The Control Loop Checkout Sheet should have a section verifying each of the steps
describe above.
When this has been verified and signed off, the Functional Performance Testing can
be started.
The SCADA system should be part of the overall preventive maintenance (PM) program for
the facility. Preventive maintenance schedules for SCADA components and subsystems
should be coordinated with those for the mechanical/electrical systems they serve to
minimize overall scheduled downtime.
Page 96
Business credibility of System Integration in ICT domain using SCADA
a. Many components of SCADA systems, such as dead-bus relays, are not required to
function under normal system operating modes. For this reason the system should be tested
periodically under actual or simulated contingency conditions. These tests should approach as
closely as possible the actual off normal conditions in which the system must operate. For
example, SCADA for standby generator plants should be tested by interrupting the utility
source as far upstream of the normal service as possible.
b. Periodic system testing procedures can duplicate or be derived from the functional
performance testing procedures.
c. The SCADA software maintenance should include timely updates of any new versions
from the supplier and testing to verify proper installation on the SCADA computer. In
addition, software antivirus updates should be maintained. This should be performed any
time after the computer is connected to the Internet. Normal operation requires that the
SCADA computer not be connected to the Internet.
Page 97
Business credibility of System Integration in ICT domain using SCADA
d. Electrical power systems, both AC and DC, serving SCADA systems should be
maintained in accord with the requirements of TM 5-692-1 and NFPA 70B.
Page 98
Business credibility of System Integration in ICT domain using SCADA
The design agency should perform an O&M analysis to determine the O&M data required to
support maintenance of the SCADA system by the using government agency. This analysis
should be coordinated with the using government agency to determine maintenance
parameters and O&M data that are available to the using government agency. Typical O&M
data requirements include the following items:
a. System documentation as defined in chapter 10.
b. Minimum spare parts list.
c. Recommended spare parts list.
d. Recommended onsite test equipment.
e. Recommended O&M training.
f. Recommended O&M to be performed by contract.
An adequate on-site stock of spare parts is essential to obtaining high availability of SCADA
systems.
Reliability calculations demonstrating compliance with “six nines” criteria typically use
repair times based on “replace with spare” which are shorter than those for “repair failed
component”. If on-site stocks are inadequate, actual availabilities will be significantly less
than these calculated values.
a. Minimum recommended stocking levels include the following. These quantities
may need to be increased for components which are used in large numbers in the
facility:
(1) Manufacturer’s recommended spare parts list.
(2) One each of all line replaceable boards or modules.
(3) Six each power and control fuses used in the system.
(4) Tools required to terminate coaxial on fiber optic cables.
b. Specifications should also require that the following be furnished with each
system:
(1) Laptop computer loaded with software required to access controllers.
(2) Licenses for all software installed on the system.
(3) Permission to modify program code.
Page 99
Business credibility of System Integration in ICT domain using SCADA
The design agency should specify functional areas of the operating system and/or equipment
where a technical representative will be furnished by the manufacturer for training, test,
checkout, validation, or pre-operational exercises. Ongoing O&M of SCADA system
software may require technical support from the system vendor or from agency technical
personnel not located at the facility. Commercial SCADA software typically has provisions
for remote modem access that permit this type of support from the vendor’s location or an
agency central engineering group. Such remote access provisions represent a vulnerability to
“hacking” and must be used with great caution. They should be monitored when in use and
physically disconnected when not in use. PLC suppliers have indicated that they are unable to
provide a firewall that will protect the controller program in the event of unauthorized access
to the HMI processor.
Password protection policies for all SCADA systems, including PLC’s, shall be in
compliance with established DoD policies. The DoD policy is established by the Chairman of
the Joint Chiefs of Staff Instruction (CJCSI) 6510.01 D, Information Assurance (AI) and
Computer Network Defense (CND).
These policies require that the default password that came from the control supplier be
changed when placed into operation at the facility.
4.4.1 GENERAL
Page 100
Business credibility of System Integration in ICT domain using SCADA
Individual control loops should be identified by loop number following the convention
established by ISA S5.1. Each instrument, actuator and control point should have a unique
tag number incorporating the loop number and identification letters per table 1 of ISA S5.1.
All equipment and instruments should be consistently identified by their complete tag
number on all drawings and points lists.
P&IDs should be provided for all mechanical systems. P&IDs should depict all components
of mechanical systems including vessels, pumps, compressors, chillers, heat exchangers,
Page 101
Business credibility of System Integration in ICT domain using SCADA
piping, valves and instruments and the control relationships between them. Symbols used
should comply with ISA S5.1 – Instrumentation Symbols and Identification and ISA 5.3 -
Graphic Symbols for Distributed Control/Shared Display Instrumentation, Logic and
Computer Systems.
Page 102
Business credibility of System Integration in ICT domain using SCADA
Loop diagrams define the physical wiring for each loop from each instrument or actuator to
the controller. All field devices, terminal boards, junction boxes, etc. are depicted along with
the signal type and range. These drawings are the basis for verification of all SCADA system
field wiring, instrument calibration, and loop tuning. All devices, terminals, cables and
conductors must be completely identified on the loop diagrams per ISA S5.4 – Instrument
Loop Diagrams.
Binary logic diagrams are flowcharts that depict all discrete logic using Boolean logic
symbols. Logic diagrams should comply with ISA S5.3 – Binary Logic Diagrams.
Control schematics show the interface between the SCADA system and the internal wiring of
related equipment such as motor starters, pump control panels, generator control panels, etc.
Proper development of control schematics requires a significant effort on the part of the
SCADA system integrator because the standard drawings provided by manufacturers of these
related system drawings are typically inconsistent in format, symbols and content, requiring
that they be redrafted by the integrator to provide an integrated documentation package.
Symbols used on control schematics should comply with the previously referenced ISA
standards and ANSI Y14.15. – Electrical and Electronic Diagrams.
All SCADA documentation should include creation date, issue date, revision data, and
revision history in a format that is consistent across all documents. A document database or
spreadsheet should be maintained that provides a current listing of all documents and their
revision status.
Page 103
Business credibility of System Integration in ICT domain using SCADA
CHAPTER 5
CONCLUSIONS
SCADA Software can be installed in many hospitals and research facilities in order to
ensure the continuous monitoring of all medical devices providing a steady and controlled
temperature (refrigerators, freezers, ..) and to guarantee the conservation for a long time
of special tissues and materials; any operational abnormal condition is immediately
recognized and filtered according to user settings; in case of persistent anomalies an
alarm is created that, depending on its gravity, can be related with a local signal (siren,
Page 104
Business credibility of System Integration in ICT domain using SCADA
lamp, ...) or broadcast via SMS to a maintenance technician cellular phone; a TCP/IP
network can provide all data related to devices functionality and organic material
conservation to one or more client analysis stations; at defined time interval or at user
request.
HCL offers end-to-end turnkey solutions to our customers in the 'Healthcare' domain.
Listed below are the areas on which we provide our services as a System Integrator.
Hospital Management Information Software (HMIS) Application:
➢ Design, Development & Customization of HMIS application as per approved SRS
& BPR document.
➢ Deployment of Integrated HIS with Data mining tool.
➢ Data Migration/Porting from Existing/Legacy Application (HIS)
➢ Support during Warranty
5.1.1.2INFRASTRUCTURE
➢ Airports
Page 105
Business credibility of System Integration in ICT domain using SCADA
• SCADA System can also be used for the airport fuelling system that
handles barge and ship receiving, mainline pump control, tank inventory,
valve manifold control, ESD, jetty mainline metering/proving, interface to
leak detection system, distribution pump control, hydrant and truck rack,
fire and safety systems.
➢ Railways
Indian Railways can use SCADA system for monitoring and control of Traction
Power system which is responsible for providing power to the electric trains. The
following railways specific applications can be implemented:
• Auto Fault Localization
• CB Tripping reports
• Power Block
• Maximum demand handling
Page 106
Business credibility of System Integration in ICT domain using SCADA
SCADA Systems can be used for the Homeland Security in the following areas:
Fleet Management
Fleet management is an all-inclusive urban public transit management solution which
enables you to plan your operations on strategic level, model routes and schedules
while providing you with intuitive insight into the status of routes in progress – just
what you need to improve the efficiency and timeliness of daily operations.
City Surveillance
It is the process of monitoring the behavior of people, objects or processes within city
for conformity to expected or desired norms in trusted systems for security or social
control. The purpose of the project is to investigate and generate better public
understanding of the practices, programs and systems used to screen in order to assess
the scope and depth of their concrete impacts on civil liberties, privacy rights and
mobility rights. This basically makes the security personnel to be OMNIPRESENT in
places where they do not need to be physically.
SCADA System is important for maintaining good traffic and road conditions,
improve the monitoring of traffic flow, as well as rush hour traffic management,
safety signs and emergency alarm systems.
Page 107
Business credibility of System Integration in ICT domain using SCADA
Firstly, the SCADA System has to provide a fast and reliable, high quality, data
transfer solution over long geographical distances. The second key factor was to
overcome the mountainous area around the Indian terrain. Wireless SCADA System
is the best and the most cheap option for the implementation of the SCADA System.
SCADA System can also be used for keeping a track of the efficient management of
the Toll Plaza.
Page 108
Business credibility of System Integration in ICT domain using SCADA
Page 109
Business credibility of System Integration in ICT domain using SCADA
5.2.1.2 INITIATION
1. Validate project need
2. Establish concepts and scope
3. Establish Summary Work Breakdown Structure
4. Conceptual estimate (-30 to +50%)
At this stage some small amount of funding has been approved to undertake the
preliminary investigations, and prepare a preliminary project management plan. It will be
necessary to firm up on the scope, identify the main technologies to be used, and gain
agreement and approval of the potential users of the system. Sufficient work needs to be
done to enable a cost estimate to be prepared that is accurate to within -30 to +50%.
Page 110
Business credibility of System Integration in ICT domain using SCADA
Similarly sufficient work needs to be done to establish the benefits of the system to
enough accuracy to convince management to give approval to proceed to the next phase.
A common mistake at this point is to go into too much technical detail. It is surprising
how often detailed I/O listings for example are produced at this stage. The work at this
stage should be concentrating on the functional (or user) requirements, and the
technological requirements should only be looked at to the point of enabling cost
estimates to be produced (and only to within -30 to +50%).
The emphasis should be on ensuring that there is a common understanding within the end
users of what functionality the system will provide. If the system is being introduced to
improve productivity, then it is important that user management understand how they can
use the SCADA system to change work practices.
It is important at this stage that the project team include someone from the end user part
of the organisation to begin to build a sense of ownership of the system. This involvement
should continue throughout the project so that the system can be handed over on
completion to an operator who is committed to using it to its full potential.
Although the work should be concentrating on the functional requirements, it is necessary
to keep an eye on the technical capabilities offered by suppliers as "off the shelf" in your
industry. Restricting the amount of custom software that the system will require is
probably the biggest single action you can take to reduce costs, risks, and minimise the
project timeframe.
Some preliminary idea of the contracting strategy will have been developed e.g. to use
consultants, to use design and construct contracts (recommended) and so on. This can
have a substantial impact on costs and in particular a decision to use consultants requires
funding to proceed to the next phase.
The decision to use consultants must be taken with care. A consultant may have
preconceived ideas as to how the project should be managed. Some decisions such as the
use of design and construct contracts may not be in consultants interests, as they may
wish to carry out the design for example. They can normally point to a track record of
"success" for their approach. Care must be taken in the selection of the consultant to
ensure that you get what you want. Therefore you must be clear as to what your priorities
are before selecting the consultant. Do you want to take a low risk approach to your
Page 111
Business credibility of System Integration in ICT domain using SCADA
5.2.1.3 DEFINITION
Page 112
Business credibility of System Integration in ICT domain using SCADA
As the project is about to proceed to design, it is important that the contracting strategies
are firmed up. The trends are towards increasing use of design and construct contracts.
These are highly recommended, and will reduce costs substantially. In the past it has been
common to engage a consultant (or to do "in-house") to do the design, and then tender for
a system based on this design. This meant the SCADA supplier was told how the system
was to be put together, and in effect he was somewhat absolved of responsibility. If it
didn't work, then it was an additional cost for him to fix up someone elses mistakes.
Bundling all parts of the system into a single contract (communications, instrumentation,
RTU's and SCADA system ) and using a design and construct approach can substantially
reduce costs and increase the chance of the project being delivered on time. In effect you
are minimising the numbers of interfaces between designer and supplier, between
communications and SCADA, etc, and allowing the SCADA supplier to organise the
project in the most efficient manner for him. It is important that if you are going to use
design and construct contracts, you still don't do the design. Your contract for example
should not mandate the communications design to be used, but should lay down some
guidelines eg must be radio, x numbers of RTU's per repeater, reliability required, must
have diagnostic facility built in, and so on. The so-called "go-no go" decision at the
completion of this phase is probably the last serious chance that the project can be
stopped.
5.2.1.4 DESIGN
• Design Reviews
• Definition Report Reviews
• Funds Justification
• Design Estimate -10%+10%
If using a design and construct approach, then this phase normally involves preparing the
specification, and developing tender evaluation plans. It is probable that a prequalification
phase could proceed at this time to overlap the tender preparation, and the
prequalification phases. (Prequalification is used to preselect reputable tenderers who
have a proven track record in this field, and should always be undertaken.
Prequalification allows the selection of potential suppliers before they have submitted a
Page 113
Business credibility of System Integration in ICT domain using SCADA
5.2.1.5 ACQUISITION
Page 114
Business credibility of System Integration in ICT domain using SCADA
The following key personnel or their representatives make up the recommended project
implementation team. Although time commitment and degree of involvement will vary with
the stage of the project, all team members should be involved from the planning stage and
Page 115
Business credibility of System Integration in ICT domain using SCADA
remain in the communications loop throughout the duration of the project. It is a mistake to
delay the involvement of maintenance staff or the commissioning agent until the end of the
design stage or the construction stage; making changes at this late stage based on their input
will undoubtedly impact schedule and cost.
a. Project manager
b. Facility manager
c. Operations and maintenance manager
d. Controls technician
e. Mission commander
f. Utility system designer(s)
g. SCADA system designer
h. Physical security specialist
CHAPTER 6
RECOMMENDATION
The far-reaching impact of new technologies and quantum change in the way companies are
restructuring and streamlining business processes are transforming the global Supervisory
Control and Data Acquisition (SCADA) market. The worldwide market for SCADA systems
for the oil and gas industry is expected to grow at a compounded annual growth rate (CAGR)
of 9.3% over the next five years. The market was nearly $850 million in 2007 and is
forecasted to be over $1.3 billion in 2012, according to a new ARC Advisory Group study.
The latest SCADA systems encompass a new generation of technology components. These
new generations of SCADA components are easier to integrate and provide vastly improved
capabilities and functionalities. SCADA systems are now being considered in a wide range of
applications and true business processes for a variety of purposes, including business
Page 116
Business credibility of System Integration in ICT domain using SCADA
performance management thus providing ample opportunity for a new player to exploit the
profits in the different verticals related to this sector.
ARC has analyzed the SCADA market by geographic region, project size, and component
type, including hardware, software, and services. The worldwide SCADA market is
expanding as upstream development and new production occurs in remote and newly
developed regions, and the existing energy infrastructure utilizes the enhanced functionalities
of SCADA to improve its core business processes of managing global disparate assets.
Global demand for energy in the form of oil and gas is driving both exploration and
production activities of the oil and gas industry. New SCADA technology enables energy
companies to conduct their business in remote and increasingly hostile environments.
Exploration activities and new production fields are developed, monitored, controlled, and
optimized globally using advanced technologies including SCADA.
The energy sector in developed regions is using SCADA as a core technology to support new
business processes in response to changing industry dynamics. Developing regions are seeing
increased exploration and production activities for which SCADA is used to link the
geographically separated facilities. SCADA will be at the core of technology adoptions as the
world economy strengthens and as the industry moves to improve business processes to meet
growing energy demand and economic challenges. In both the upstream and midstream
portions of the oil and gas industry, SCADA will play an increasingly important role in the
real-time dissemination of knowledge and management control of assets.
Strategic planning for energy investments and the transition of the operation and management
of existing assets to incorporate new advances in technology is critical. Challenges and issues
the energy industry must address include:
• Tightening integration of business processes to midstream oil and gas operational
systems such as SCADA;
• Migration planning to enable efficient transition of legacy systems to meet new
demands from all stakeholders;
Page 117
Business credibility of System Integration in ICT domain using SCADA
• Updating and automating older fields, the coming of age of the digital oilfield, and the
proliferation of intelligence to all levels of physical assets on a global basis;
• Implementation of Asset Lifecycle Management programs and regulatory compliance
initiatives such as integrity management, and
• Increasing concern over security and environmental issues.
Energy industry operating firms are seeking ways to become more responsive to the demands
of all stakeholders. SCADA suppliers can play a major role by providing solutions. SCADA
systems are an enabling technology that can help to change the way energy companies
restructure business processes to respond to market dynamics with real-time knowledge flow.
With change come opportunities. There are a number of strategies that ARC recommends to
suppliers and users of SCADA systems and components to maximize their potential in the
changing marketplace. Here is a closer look at three of the strategies.
Suppliers must develop a SCADA system that can be fully integrated with corporate business
systems. Energy companies are increasingly looking for a total solution, integrating SCADA
systems with other systems at the plant level and with higher level corporate business
systems. SCADA system design must go beyond plant systems that are open, modular, and
provide for simplified connectivity to other control systems.
For a SCADA system to be marketable, it is becoming necessary to be able to communicate
with business systems throughout a company. These systems include an ever-expanding
number of outside systems that typically reside in an extended supply chain. To be
competitive, suppliers must show how their SCADA systems can provide appropriate real-
time data to systems across this extended supply chain, both now and in the future.
SCADA has evolved into a more robust technology capable of serving as the channel for
information flow to a number of higher level applications, including supply chain
applications. The midstream segment of the oil and gas industry, with its focus on transport
(pipelines), is particularly supply chain-centric. SCADA, long associated with operations
management of pipelines, must now have the functionality to provide supply chain systems
with real-time information.
Page 118
Business credibility of System Integration in ICT domain using SCADA
Just as the upstream and downstream portions of the energy industry have become more
sophisticated in integrating operations management with business processes, so too will the
midstream portion. The supervisory control portion of SCADA is already transitioning to
better accommodate a collaborative production management approach. This collaboration is
closely tied to supply chain and other business processes, with linkage to upstream and
downstream industry workflows.
Most of the issues that pipeline management programs address may also be viewed in the
context of creating an efficient supply chain. Functions such as custody transfer, accounting,
and transactional management, batch tracking, nominations, and terminal management all
reside in both the operations management and supply chain domains.
There's also increasing need to operate the midstream portion of the industry as a value-add
business and to generate increased revenue from existing assets. Business drivers for
implementing supply chain management initiatives include clean fuels regulatory issues, an
increasing product mix, increasing market volatility, and tightened regulatory constraints.
The net result is a more complex set of scheduling and inventory management issues that are
forcing the adoption of more efficient business processes.
Emerging SCADA systems should have the capability to be both fully compatible with IT
and to communicate with internal and external enterprise systems.
They should also include an expanding number of applications that typically reside in the
extended supply chain, such as:
• Strategic network planning
• Replenishment planning/inventory management
• Distribution planning and optimization
• Scheduling movements
• Execution management
Page 119
Business credibility of System Integration in ICT domain using SCADA
When evaluating the lifecycle of a SCADA system, it's important to note that the components
that comprise a complete system have distinctly different lifecycles. While some
owner/operator firms have RTUs that are more than 25 years old, it is doubtful the software
applications that connect to business or IT systems would be viable for that length of time.
Migration planning is the interface for merging the automation and IT worlds. There are a
number of perspectives and issues to consider. Software is continually being developed to
reflect the changing demands of business processes and workflows. Companies must employ
a SCADA system that provides a flow of data and information to support these evolving
workflows. This often requires an upgrading of SCADA systems. Proper migration planning
is critical.
The principal issues are deficiencies in the functionality of legacy systems, component
obsolescence, and increasing security concerns. SCADA's role is changing dramatically in
response to changing business processes. More information is demanded more frequently by
additional functional groups, both internal and external to an enterprise.
Legacy SCADA system components may still function as designed. However, new
operational and business processes often require new, higher-level functionality not included
in the original components. This makes SCADA migration planning critical.
HCL should look for a comprehensive SCADA professional's certification program that
enables the measurement of SCADA knowledge, skills and abilities, and also serves to
enhance the standing of SCADA professionals in the industry.
Page 120
Business credibility of System Integration in ICT domain using SCADA
HCL SCADA consulting services can accelerate the productivity of the prospective channel
partners as well as our prospective end users. HCL Quality Process Consulting is a niche
service offering as a part of the suite of Transformation Services. HCL Quality Process
Consulting offers process improvement services that span the entire continuum ranging from
Process definition, implementation & training to Process assessments for Model and non-
model based improvement initiatives. HCLs System Integration team has an impressive track
record, offering first-hand experience working for channel partners in mission-critical
industries including oil & gas, power, transportation and water. Thus HCL can become only
the second organization in India after Reliance to provide both IT Consultancy and SCADA
Consultancy to the end user.
• Custom application development
HCLs consulting team would have a wealth of vertical industry experience that they
can bring to bear on partner and end user efforts to develop specialized applications.
Our consultants can help customers develop the specialized software in applications
such as power generation and distribution, gas and liquids pipelines, rail and metro
transportation and water/wastewater applications.
HCL’s Consulting team will be leveraged to provide Quality Consulting Services to HCL’s
clients. HCL’s Quality Consulting strength lies in the skills and rich experience of our
consultants, who have experience in Energy sector. They bring with them practical
Page 121
Business credibility of System Integration in ICT domain using SCADA
implementation experience of various processes that best fits client’s SCADA environment.
HCL can form a Global Strategic Alliance with some of the leading SCADA players and thus
combine its IT expertise with the SCADA domain knowledge of the leading players to
provide an end to end solution to the prospective customers.
As part of this alliance, HCL can focus on providing full-solution system integration services
in established markets, while the prospect partner will be responsible for the marketing and
sales of both companies HMI/SCADA products.
However it needs to be ensured that the target markets for both companies are oil and gas
production, water and wastewater, power and utilities industries, and environment change
tracking industry.
Some of the potential partners of HCL in the SCADA domain are listed below:
• ABB
• Siemens
• Larsen & Toubro
• GE
• Honeywell Automation India Ltd
HCL can also acquire a pre established small firm in the SCADA domain and thus be assured
of gaining a sure entry in to the market and provide an enhanced end to end solution to the
established clients. By doing this HCL can actually showcase its capability in the SCADA
domain and this will help HCL to acquire new projects.
Fig: Perceptual map showing the potential entry point in the SCADA domain
Page 122
Business credibility of System Integration in ICT domain using SCADA
Scalability is a constant challenge in IT. Acquiring new capacity may necessitate expansion
of IT staff, software licenses, floor space, power and more. Contracts change. Markets shift.
And managers face the possibility of either constantly buying or underutilizing IT resources.
How can players across the industry keep SCADA data and other mission-critical
applications safe without wasting money? To stay out of the fire-fighting mode it is better for
niche SCADA players to outsource functions like managing data centres, monitoring basic
security and ensuring fundamental network and application performance. HCL thus can
provide turnkey IT infrastructure to a number of energy-related companies.
Page 123
Business credibility of System Integration in ICT domain using SCADA
• Don't rush into a Service Level Agreement. Define what you really need. Get the
details of what they're guaranteeing, how it will be measured and what penalties apply
if you step outside the lines.
• Get grassroots support. Make sure non-executive SCADA staff understands that these
measures will help them, not undermine them. Involve them in the selection process.
• Draft up an exit strategy, just in case.
Page 124