Beruflich Dokumente
Kultur Dokumente
ravikantswami@gmail.com 11
The Design Core Market
Assessment
Specification
MANUFACTURE
Concept
Plant location Design
Plant layout
Detail
Production scheduling Design
Sell
ravikantswami@gmail.com 22
Plant Location
Possible Factory Location
A B C D E
Criterion Weighting
PR Skilled labour 7 2 14 3 21 0 0 1 7 4 28
OXI
A pool of unskilled labour 8 5 40 2 16 0 0 4 32 2 16
MIT
Y A motorway 7 3 21 2 14 1 7 3 21 4 28
TO: An airport 4 1 4 3 12 4 16 2 8 2 8
The sea / a river 0 2 0 5 0 5 0 2 0 1 0
Housing 5 4 20 3 15 0 0 3 15 4 20
Amenities 5 3 15 2 10 0 0 2 10 3 15
Potential for expansion 7 2 14 1 7 5 35 3 21 2 14
Availability of grants/incentives 8 1 8 2 16 5 40 1 8 3 24
Safety 2 3 6 2 4 5 10 2 4 2 4
Planning constraints 5 2 10 3 15 5 25 4 20 2 10
Environmental impact 4 3 12 2 8 4 16 1 4 2 8
TOTAL 164 138 149 150 175
ravikantswami@gmail.com 33
‘Functional’ Plant Layout
•
Common for a large
L L M M
variety of products in
batch volumes. L L M M
•Similar processes are Material 1
grouped together.
•Inefficient: Long material Material 2
transport routes from D D
dept. to dept. Work in ASSEMBLY
progress is high. Tracking 1
D D
of orders can be difficult.
Product 1
•Advantages: Specialist
labour and supervision.
Flexibility as material can Product 2
be rerouted in any G G
ASSEMBLY
sequence. 2
G G
ravikantswami@gmail.com 44
‘Product’ Plant Layout
•
Mass production where
variety is small and
L M D G
production volumes are very
high.
• AKA ‘flow’ or ‘line’ layout. A
•More efficient, but less S
flexible than ‘functional’ S
layout. E
L M D G M
•Work in progress is B
minimised, and jobs are easily L
tracked. Y
•Investment in specialised
capital equipment is high, so
a reliable and steady demand
L M D G
is required.
•Very sensitive to machine
breakdown or disruption to
material supply. ravikantswami@gmail.com 55
‘Cellular’ Plant Layout
• AKA ‘Group Technology’
•Each cell manufactures products L M ASSEMBLY
belonging to a single family.
D G CELL 1
•Cells are autonomous
manufacturing units which can
produce finished parts.
•Commonly applied to machined
parts. M M ASSEMBLY
•Often single operators supervising D G CELL 2
CNC machines in a cell, with robots
for materials handling.
•Productivity and quality maximised.
Throughput times and work in
progress kept to a minimum. L L ASSEMBLY
• Flexible. L G CELL 3
•Suited to products in batches and
where design changes often occur.
ravikantswami@gmail.com 66
Designing a ‘Cellular’
Layout
A company produces 16 specialist tools.
The company is planning to relocate and reorganise production with a
‘cellular’ layout, with cells containing 5-7 machines each.
Production involves 10 types of machine: L1, L2, L3, D1, D2, M1, M2, G1,
G2, F.
4 machines of each type are used, except D2 of which there is only 1.
ravikantswami@gmail.com 77
Designing a ‘Cellular’
Layout
Construct a dendrogram based on pairs of
Draw-up a machine-part incidence matrix
closely related machine routes
Machine
L1 L2 L3 D1 D2 M1 M2 G1 G2 F ‘Proximity’ between
Part
machines/clusters
1 1 1 1 1 1 1
2 1 1 1 1 8
3 1 1 1 1 1
4 1 1 1 1
5 1 1 1 1
6 1 1 1 1 1
1 1
7 1 1 1 1 1 1
8 1 1 1 6
9 1 1 1
10 1 1 1 1 1
1
11 1 1 1 1 1
12 1 1 1 1 1 1
13 1 1 1 1
1 4
14 1 1 1 1
15 1 1 1 1
16 1 1 1 1 1 1
1
‘Proximity’ between machines
1
n 2
d pq = ∑ apj − aqj
1
1
1 a=1 used
j =1
a=0 not used
1
e.g. p=1, q=2
1 then d12=3 (L2,G1,G2)
0
1 7 16 12 3 4 6 2 13 9 10 11 14 8 5 15
ravikantswami@gmail.com 88
Designing a ‘Cellular’
Layout 8
L1 L2 M1 L1 L3
8
L2 M2 D2
Cell A Cell C 8 8
D1 M1
Routes 1, 7, 16 Routes 2, 13, 9
L1 G1 8 G2 8
F G1 M2 F G2 D1 Cell E
Routes 8, 5, 15
Total 37 32
ravikantswami@gmail.com 99
Other Plant Layouts
‘Random’ Layout
• Very inefficient
‘Process’ Layout
• Process industries, e.g.
LABOU MATERI
steelmaking. R AL
• The process determines layout.
COMPONEN
TS
ravikantswami@gmail.com 1010
Single Machine Scheduling
Shortest Processing Time (SPT) Others
Henry L. Gantt, Frankford Arsenal, USA
Schedule ABC Minimise average
processing time
I.
A B C WSPT Schedule in
Time
2 6 7 order of weighted
Schedule CAB shortest processing time
II.
C A B
Time Minimise average
1 3 7
+ 1 h delivery time to customer
delay
Average customer waiting time: EDD Schedule in
I. (3+7+8)/3 = 6 h order of earliest due
II. (2+4+8)/3 = 4 2/3 h date
Shortest jobs before longer jobs
ravikantswami@gmail.com WEDD Schedule in
1111
Scheduling Operations in
Series
Sample: A B C D E Schedule ABCDE
Time to prepare Prep.
(h) A B C D E Time
6 7 4 6 2
Time to 6 13 17 23 25
photograph (h) Phot.
5 6 6 3 4 A B C D E
6 11 13 19 25 28 32
Johnson’s Algorithm
ravikantswami@gmail.com 1212
Scheduling Machines in
A
Parallel 31
B 5 Machine 1
C 25
A F I H Time
D 7
31 43 55 61
E 10
F 12 Machine 2
G 28 G J E B L
H 6 28 45 55 60 64
I 12
Machine 3
J 17
K C K M D
21
25 46 54 61
L 4
Time
Required
Operation (h) Predecessors Earliest finish time of Earliest
predecessors Start
A 3 - - 0
B 3 A 3(A) 3
C 1 - - 0
D 2 C 1(C) 1
E 8 A, D 3(A), 1+2(D) 3
F 4 - - 0
G 1 F 4(F) 4
H 4 - - 0
I 12 C 1(C) 1
J 6 B, E, G 3+3B, 3+8(E), 4+1(G) 11
K 4 H, I, J 4(H), 1+12(I), 11+6(J) 17
ravikantswami@gmail.com 1414
Critical Path Analysis
H Allowable slack
0 17 Critical path
Earliest Latest
4 start finish
Operation period
time time
C I K
A
0 1 1 17 17 21
C
1 D 12 4
F
1 3
Operatio H
2 E n time
A D
3 11
0 3 I
8 J
3 B 11 17 B
3 11 E
6
3 G
F G J
0 10 4 11 K
4 1
8 16 Time (h)
ravikantswami@gmail.com 1515
Materials Requirement
Planning (MRP)
Master
Production Bill of Current
Schedule Materials Inventory
Material
Purchasing Manufacturing
Control
Schedule Schedule
Schedule
ravikantswami@gmail.com 1616
Master Production Schedule
(MPS)
production plan showing period by period anticipated production of finished item
N.B. It is not a sales forecast, though expected sales are a consideration
Week 5 6 7 8 9 10 41 42
Product P65 10 0 20 0 20 0 20 0
Product K92 15 20 20 25 15 20 20 20
Product U37 30 35 5 45 30 30 30 30
Current week
Week 5 6 7 8 9 10 41 42
Forecast
10 10 10 10 10 10 10 10
demand
MPS 10 0 20 0 20 0 20 0
Orders
8 8 5 0 2 0 0 0
accepted
Available to
4 0 15 0 18 0 20 0
promise
(Current stock + MPS) – (Total orders to next production run) = Stock available to promise
10 + 10 - 8 + 8 = 4
ravikantswami@gmail.com 1818
Master Requirements
Planning (MRP)
Product P65 Planning
Current stock on hand = 10 period
Week 1 2 3 4 5 6 37 38
Gross
10 20 10 30 0 10 20 20
requirements
Scheduled
10 25
receipts
Net
25 10 20 20
requirements
Planned order
35 40
receipts
Planned order
35
releases
Projected
10 10 15 5 10 10 0 20 0
inventory
ravikantswami@gmail.com 1919
Economic Order Quantity
Q
Let
C0 = Cost of placing an order,
CH = Cost (per year) of holding a single unit in stock
D = Demand rate (no. units per year)
T = O + H Q * (1 + δ ) 2
Q 2 1/ 2 1/ 2
C D C C (1 + δ ) 2COD
= O H + H
(1 + δ ) 2DCO 2 CH
1/ 2
DCOCH 1
= + 1+ δ
Holding costs alone 2 1 + δ
, r ae y r e pt s oc l at o T
1/ 2
DCOCH
= (1 − δ + δ − δ ... + 1 + δ )
2 3
Q
2
Demand is never truly predictable.
What happens if we get the value of Q
slightly wrong? So, T ≈ (2DCOCH )1/ 2 (1 + δ 2 / 2)
Even if we over-order by 10%, the
cost of the stock is only increased
ravikantswami@gmail.com 2121by
about 0.5%.
Just in Time Manufacture
(JIT)
A system of organising manufacturing, the essence of which is to
remove waste, particularly in the waste of time and resources
associated with stocks held at different stages of the manufacturing
process.
• Reduction of batch sizes
Large batch sizes are costly to produce (large amounts of stock, long
time to produce the whole batch before reaping a return). JIT philosophy
is to reduce batch sizes towards unity.
• Reduction of set-up times
Each batch is costly in set-up time. Achieving small batch sizes requires
the strive towards reduced set-up times. Achieved with, e.g.
reprogrammable equipment, quick change tooling, storage of tooling
close to machine etc.
• Reduction of buffer inventories
Materials, sub assemblies, part processed parts etc. in queues/storage
are costly and inefficient. They cost money rather than make money.
• Frequent deliveries and long term relationships with
suppliers
Reduced batch sizes and buffer inventories require small, but frequent
deliveries often on demand. Suppliers viewed as partners rather than
adversaries.
ravikantswami@gmail.com 2222
Just in Time Manufacture
(JIT)
A system of organising manufacturing, the essence of which is to
remove waste, particularly in the waste of time and resources
associated with stocks held at different stages of the manufacturing
process.
• Reduction of batch sizes
Large batch sizes are costly to produce (large amounts of stock, long
time to produce the whole batch before reaping a return). JIT philosophy
is to reduce batch sizes towards unity.
• Reduction of set-up times
Each batch is costly in set-up time. Achieving small batch sizes requires
the strive towards reduced set-up times. Achieved with, e.g.
reprogrammable equipment, quick change tooling, storage of tooling
close to machine etc.
• Reduction of buffer inventories
Materials, sub assemblies, part processed parts etc. in queues/storage
are costly and inefficient. They cost money rather than make money.
• Frequent deliveries and long term relationships with
suppliers
Reduced batch sizes and buffer inventories require small, but frequent
deliveries often on demand. Suppliers viewed as partners rather than
adversaries.
ravikantswami@gmail.com 2323
Just in Time Manufacture
• Short lead times
(JIT)
Results in increased responsiveness to customer requirements and
therefore increased competitiveness.
• Simple material flows and reduced floor space
‘Product’ or ‘cellular’ plant layouts are essential to ensure smooth flow of
material through the factory. The ‘functional’ layout results in too much
work in progress.
• Teamwork and a motivated workforce
The sensitivity of the system to down-time requires that problems are
solved quickly, and by all concerned. Problem solving and continual
improvement cannot be achieved without consultation and involvement
of the workforce who are the people on the shop floor that know the
operations best.
• Workers responsible for the quality of their own work
Workers on the shop floor should think of themselves as making parts
rather than just operating a machine. ‘Non-productive’ costs such as
education of the workforce should be viewed as necessary.
• Visibility of performance
Simple flow of material allows each member of the workforce to see how
their work fits into the rest of the factory, and therefore allows rapid
problem solving.
ravikantswami@gmail.com 2424
Material Control in JIT:
Kanban
Kanban
A card or docket that authorizes either processing of a part at a
particular workstation, or movement of parts between workstations.
ravikantswami@gmail.com 2525
A Kanban System
Kanban authorizing Kanban authorizing move
production at from workstation A to
workstation A workstation B
P P M P
Workstati Workstati
on on
A B
P P M
M
P M
Production transaction
Containers Parts waiting to
waiting to be be processed Move transaction
moved to at workstation
ravikantswami@gmail.com
workstation B B
2626
The Kanban System
Specification
SELL Concept
Design
Manufacture
Sell
ravikantswami@gmail.com 2828