Beruflich Dokumente
Kultur Dokumente
(Reaffirmed 2002)
Indian Standard
METHODS OF MEASUREMENT OF BUILDING
AND CIVIL ENGINEERING WORKS
PART 1 EARTHWORK
( Fourth Revision )
UDC 69.003.12:69.021.13:624.13
Q BIS 1992
Indian Standard
METHODS OF MEASUREMENT OF BUILDING
AND CIVIL ENGINEERING WORKS-
PART 1 EARTHWORK
C Fourth Revision )
1 SCOPE 2.6 The following works shall not be measured
separately and allowance for the. same,shall be
This standard (Part 1 ) covers the method of deemed to have been made in the description of
measurement of earthwork in building and civil main item:
engineering works.
4 Setting out works, profiles, etc;
2 GENERAL RULES b) Site clearance, such as cleaning grass and
vegetation;
2.1 Clubbing of Items c) Unauthorized battering or benching or
excavation;
Items may be clubbed together provided that the
break-up of the clubbed items is agreed to be on 4 Forming (or leaving) ‘dead men’ and
‘tell tales’ in borrow pits and their removal
the basis of the detailed description of the items after measurements;
stated in this standard.
4 Forming ( or leaving ) steps in sides of deep
2.2 Booking of Dimensions excavation and their removal after
measurements;
In booking dimensions. the order shall be con- f ) Excavation for insertion of planking and
sistent and generally in the scquence.of length, strutting;
breadth or width and height or depth or
thickness.
g) Unless otherwise specified, removing slips
or falls in excavations; and
2.3 Measurements h) Bailing out or pumping of water in
excavation from rains.
Unless otherwise stated hereinafter all work shall
be measured net in decimal system, as fixed in 2.7 Special pumping other than what is required
position as given below: for conditions given in 2.4 (a) and included
in 2.6 ( h ) and tube well/well point dewatering
a) Each dimension shall be measured’ to the where resorted to, shall each be measured
nearest 0’01 m; separately for all stages of pumping, including
intermediate stages unless otherwise stated, in
b) Areas shall be worked out to the nearest’
K.W. Hrs, or HP Hrs, against separate specific
0’01 m”; and provision(s) made for the purpose.
c) Cubical contents shall be worked out to
the nearest 0’01 m3. 3 CLASSiFICATION
The materials to be excavated shall be classified
2.4 Work to be Measured Separately
as follows unless otherwise specified.
.
Work executed in the following conditions shall a) ‘SoftlL.oose Soil - Generally any soil which
be measured separately: yields to the ordinary application of pick
and shovel, or to PHA WRA. rake or other
a) Work in or under water,
ordinary digging implement; such as vege-
b) Work in or under foul situations, table or organic soil, turf, gravel, sand,
silt, loam, clay peat, etc.
c) Work under tidal conditions, and
b) Hard/Dense Soil - Generally any soil
d) Work in snow. which requires the close application of
picks, or jumpers or scarifiers to loosen;
2.4.1 The levels of high and low water tides such as stiff clay, gravel, cobblestone,
where occurring, shall be stated. water bound macadem and soling of roads.
NOTE - Cobblestone is the rock fragment usually
2.5 Bills of Quantities rounded or semi-rounded having maximum
diameter in any one direction between 80 mm and
300 pm.
The bills of quantities shall fully describe the
materials and workmanship, and accurately 4 Mud - A mixture of soil and water in
represent the work to be executed. fluid or weak solid state.
w . . . .
IS 1200 ( Part 1 ) : 1992
2
IS 1200 ( Part 1) : 1992
4.2.5 In case of the following works, authorized 4.6 Surface Excavation
quantities ( calculated on the basis of authorized
working space ) or those actually excavated, Excavation exceeding 1’5 m in width as well as
whichever, are less, shall be measured: IO m2 on plan but not exceeding 300 mm in
depth shall be described as ‘surface excavation’
a) In work which requires formwork; and measured in square metres.
3
IS 1200 ( Part 1 ) : 1992
5.1.1 The description of items shall include 6.1.3 Where tightly driven close butt jointed
loading and unloading. sheeting is necessary as in the case of running
sand, the item shall be measured separately and
5.1.2 If spoil heaps requiring re-handling have the packing of cavities behind sheeting with
become consolidated due to passage of time or suitable material shall be included in description
any other reason, it shall be so stated and such of the item
heaps shall be measured separately.
6.1.4 Planking and strutting required to be left
5.1.3 For the purpose of measurements of lead, permanently in position shall be measured
the area excavated shall be divided into suitable separately.
blocks and for each block the distance from the
centre of the block to centre of placed earth
7 REMOVING TREES AND HEDGES
pertaining to this block shall be taken as lead.
7.1 Clearing of shrubs, brushwood, small trees
5.2 Lift
not exceeding 300 mm girth shall be measured in
Lift shall be measured from ground level. square metres, and shall deem to include removal
Excavation up to 1’5 m depth below ground and disposal. The girth shall be measured at
level and depositing excavated material on the 1 m above ground level.
ground shall be included in the item of earthwork
for various kinds of soil. Extra lift shall be 7.2 Cutting down hedges and removal of fences
measured’ in unit of 1’5 m or part thereof. shall be fully described and measured in running
Obvious lifts shall only be measured; that is lifts metres and shall deem to include removal and
inherent in the lead due to ground slope shall not disposal.
be measured ( except for lead up to 250 m ).
When earth has to be carried over a bank/ 7.3 Cutting down trees of 300 mm girth and over
obstruction and dumped beyond it, the lift shall up to 1 000 mm girth shall be enumerated as one
be the difference in level between the centre of item. The cutting down of trees exceeding
gravity of the excavated earth and the top of 1000 mm in girth shall be enumerated stating
bank/construction. the girth. The girth shall be measured at one
metre above ground level. The item shall include
6 PLANKING AND STRUTTING lopping of branches and removal and disposal.
6.1 The planking and strutting required to 7.4 Digging out of roots including stacking shall
uphold the face of excavated earth, etc, shall be be measured separately and enumerated.
IS: 1200 ( Part II ) -1974
( Reaffirmed 2007 )
Indian Standard
METHOD OF
MEASUREMENT OF BUILDING AND
CIVIL ENGINEERING WORKS
PART II CONCRETE WORKS
(Third Revision)
UDC 69.003.12:693.5
© Copyright 1975
BUREAU OF INDIAN STANDARDS
MANAK BHAVAN, 9 BAHADUR SHAH ZAFAR MARG
NEW DELHI 110002
March 1975
III 1200 ( Part D ) • 1174
issued in different parts which will be helpful to the specific users in various
trades. This part covering method of measurements of concrete works
applicable to building as \\'('11 as civil engineering works was, therefore,
issued as a second revision in 1968.
0.6 This part is, therefore, intended to provide comprehensive guidance for
measurement of concrete construction in wide field of building and civil
engineering works including bridkcs, industrial structures, etc, taking into
account in a large measure advanced practice of concrete construction.
This, third revision, has been done so as to keep the provision as per latest
practices.
0.7 For the purpose of deciding whether a particular requirement of this
standard is complied with, final value, observed or calculated, expressing
the result of a measurement, shall be rounded off in accordance with
IS : 2-1960·. The number of significant places retained in the rounded
off value should be same as that of the specified value in this standard.
I. SCOPE
1.1 This standard ( Part II ) covers the method of measurement of concrete
works in building and civil engineering works.
NOTE - The method of measurement of concrete work in roads, piling, wells and
tunneling is covered respectively in J~: 1200 ( Part XVII ir, IS: 1200 ( Part XXIII ):,
IS: 1200 ( Part XXIV)I and IS: 1200 (Part XXV )~.
2. GENERAL RULES
2.1 ClubbiDI of Items - Items may be clubbed together provided the
break-up for such items is agreed to be on the basis of the detailed descrip-
tion of items stated in this standard.
2.2 Bill of Q,uaDtides/ltems of Work - Items of work shall fully
describe the materials and workmanship to represent work to be executed.
2.3 De8criptio. of Items - The description of each item shall, unless
otherwise stated, be held to include where necessary, conveyance and
delivery, handling, unloading, storing, fabrication, lowering, hoisting, all
*Rules for rounding off numerical values ( .., vis,d).
fMethod of nleas'4l"('mtnt of building and civil enlineerinl works: Part XVII Road
work including airfield pavements ( "eoltd "v;S;tm ).
~Method of measurement or building and civil engineerin. worb: Part XX)II Pili. .
( 1,",lId rev;,io" ).
Il\f~thod of measurement of building and civil cnginceriq works: Part XXIV Well
foundations ( sIro"d r,,';,sitm ).
'Meth~ of measurement nf building and civil enllneerin. works: Part XXV TUOnclinl
( l,tDnd "VUfDII ).
4
JlII_(Put D)-1174
labour for finishing to required shape aDcIlize, setting. fitting and fixing in
position, straight cutting and waste, diJpoIaI of packings, etc.
2.t DIm...I. . . - Unless otherwise ltated all work shall be measured
net in decimal system as fixed in its place as given in 2.~.1 to 2.4.3. Any
work done extra over the specified dim_olll than be ignored.
2.4.1 Dimensions shall be measured to nearest 0·01 m except for the
thickness of slab which shall be measured to nearest 0·005 m,
2.4.2 Areas shall be worked out to nearest 0·01 square metre.
2.4.3 Cubic contents shaD be worked out to nearest 0·01 cubic metre.
2.5 Booldal or Dime••Io•• - In booking dimensions, order shall be
consistent and generally in sequence of length, width and height or depth
or thickness.
2.6 Work. to be Me.....eet Separately- Worb executed in following
conditions shall be measured separately:
a) Work in or UDder water.
b) Work in liquid mud,
c) Work in or under foul poIitions,
d) Work under tides, and
e) Work in snow.
2.&.1 In the case or work under tides the levela of high and low water
tides shall be stated.
2.7 M t ill 8taae-- Worb shall be measured under the
following categories in convenient stages stating the height or depth:
a) Below ground/datum level. and
b) Above ground/datum level.
NOTa- The ground/datum levellball be dcfiDed in each cue.
. r.
F'////////Al
.'.1
~---,l 1
l-- IE ----l
A I--IF --I A
•
L
I-----aIG --I
--r•
J OJ
I---I HA--.l I"
1
FlO. 1 SHADED PORTION SHOWING SIIALL v oms
f.2 a.laforceci/plala c....t eoacrete (C••t I. S;",)
~.2.1 Concrete cut ill ,i'"
shall be classified as follows:
a) Foundations, footings, bases for columns;
7
J8: 1210( pa..t u )• 1974
b) Walls (any thickness) including attached pilasters, buttresses,
plirnh and string courses, fillets, etc;
c) Slabs, supported on wall/beams/columns, landings, balconies,
canopies, bridge slabs;
d) Slabs other than those specified in (e);
e) CHAJJAS including portions bearing on the wall;
f) Lintels, shelves, beams and bressumers;
g) Columns, piers, abutments, pillars, posts and struts;
h) Staircase including stringer beams but excluding landings;
j) Balustrades, newels and railing;
k) Spiral staircases ( including landing );
m) Ar... hes
n) Domes, vaults;
p) Shell roof, arch rib and folded plates;
q) Chimneys and shafts;
r) Canal lining;
I) Ballast walls, retaining walls, return walls;
t) Concrete filling to precast components;
u) Kerbs, steps and the like;
v) String or lacing courses, parapets, copings, bed block, anchor
blocks, plain, window sills and the like;
w) Cornices and moulded window sills; and
y) Louvers, fins, fascia.
Non - All proj~tion~J etc, shaU be included in the main items.
10
18 I 1200 ( Part II ) • 197..
4....1 Concrete in structural members, such as columns, beams and slabs
shall each be measured separately.
".f.l.1 Memben cast In section, (that is not in one continuous
operation) shall be fully described.
4.~.2 Forming and groutinR or sealing ducts or ~roovcc; shall be measured
in running metres fully describing size and other particulars of sleeves ( or
aheathing), temporary supports required in formation of ducts and
composition of grout.
......3 Forming and grouting the air-holes at ends) middle or sides or in
any other position of ducts shall be included in the devcription of item.
4.4.4 Filling.n the jacking or anchoring recesses shall be described
stating finish to exposed surface or filling and measured separately in cubic
metres.
t.t.5 Supplying, fixing and tensioning steel wiresIstrands jor cables
(measured between anchorages ) shall he measured in kilograms stating
ultimate strength and proof stress and size of wire or cable. Each size shall
be measured separately, No allowance shall be made for extra lengths
in anchorages or elsewhere. The number of strands in each cable» type
of central core, and type of sheathing if any to wires shall be stated.
De-greuinp. straightening, cutting to lengths and assembling wires
and cables, cones, wedges, anchor-plates, spacers. distance pieces and other
expandable items shall be deemed to be included with main item.
t.5 P....r...... CoDerea. - Preca8t - Prestressed concrete precut
worb shall be fully described.
• .5.1 Formwork or moulds for precast units and for forming anchorage
pockets ahan be deemed to be included with items.
4.5.2 Precast units shall be enumerated stating number, size, length,
method of fixing and bedding. Unless otherwise stated, hoisting, tranl-
portation, auembly and setting in position shall be included in item. The
cluaification shall be as follows:
a) Pre-tensioned in the mould;
b) POit-tensioned on ground after casting;
c) Cut in section, assembled and post-tensioned before erection;
d) POit-tensioned after hoisting but capable of self-support;
e) Cut in sections for assembly in iiII' and post-tensioned after
erection; and
f) PCllt-tenaioned after hoiltins but requiring support until teDlion-
inI it completed.
11
IS I 1200 ( Part II ) • 1974
".5.3 Cores, wires, strands and cables for post-tension members shall be
measured as in 4.4.5. In case of pre-tension members, these items shall be
included in the main item.
4.6 Mi8ceUaaeoas Items
4.6.1 Expansion Jo;nt~f - Expansion joints in floors, roofs and walls shall
be described as including all formwork and labour necessary to form joint
and shall be measured iQ running metres stating depth and width of joint.
Alternatively, these may be measured in square metre stating the width of
the joint.
4.6.1.1 Material used in filling and or for covering shall be fully des-
cribed and measured separately in running metres.
4.6.1.2 Where sheet of copper, brass, aluminium or of any other
material is used, it shall be fully described and measured in running metres,
4.6.2 Damp-proof course in concrete shall be described and measured in
square metres stating thickness. Item shall include formwork and fair
finish to edges and also levelling and preparing of brickwork or stone
masonry to receive damp-proof course. Horizontal and vertical damp-
proof courses shall each be measured separately.
4.&.3 Watt,p,ol!ri".~ Concrete
4.6.3.1 Waterproofing material used for waterproofing or concrete
shall be described stating quantity of material to be used and measured
separately in litres or kilograms.
4.&.3.2 Surface treatment of concrete shall be measured in square
metre. stating number of coals or dressings and proportion of waterproofing
material to water.
4.6.4 Gunitira; - Guniting shall be fully described and finished surface
measured in square metres.
.....5 PaekI Pr,sm" Groutin,
4.6.5.1 Grout Hoi,s - The length of grout holes drilled either for pack
grouting or pressure grouting through concrete shall be measured in
running metres. Grout holes drilled through plate steel liners shall.
however, be enumerated separately.
~.6.5.2 Grout Pi/JIs and Fittings - Grout pipes and fittings provided for
grouting shall be measured in kilograms and weight of all pipes and
fittinp shall be derived either by actual weighment or from known weights
and lengths.
4.6.53 W.", P",SU" T,sti", - Measurement for water prellure
teltiDc thall, where necesaary, be made aeparately for each hole aDd
enumerated.
12
IS : 1200 ( Part 0 ) • 1974
4.6.5.4 Measur ement for grouting shall be made on basis of the weight
of cement in grout actually forced into holes. Stone dust and .other
additions, if used, shall be measured separately In loose dry state before
mixing and shall be measured by boxes of approved size and desizn.
4.6.6 (;,oullng Stanchion Bases - Cement grouting undci plates of stan-
chien or precast concrete column or stet"I grillages shall be measured in
square metres and its mix stated.
4.6.7 Iloldi1l,g Doiun Bolts - Grouting in of holding down bolts and the
temporal ~ boxings ot wedges to form holes for the same shall be enume-
rated. Depth and height of the hole and mix shall be slated and grouting
included in description.
4.6.8 Cutting in Concret«
4.6.8.1 Work involving cutting, or sinking into existing' concrete shall
be classified as follows:
a) Grooves, chases and hke shall be' measured in 1 unning metres
stating gil th; and
b) I Joles, 11101 tires and openings shall be measured per centimetre of
depth of cutting and shall be classified as follows
1) Up to 250 <"In! in area, and
2) Exceeding 250 em' and up to and including 0'1 m~ area.
NOT~ - Area shall be reckoned as the net area required and not nccessarslv the area
actually cut.
4.6.8.2 Cutting opening exceeding 0·1 m 2 in area shall be measured
in cubic metre and items shall include provision for fixing and removal of
existing support and temporary support.
4.6.8.3 Cutting of existing reinforced cement concrete surfaces anti
exposing reinforcement without damaging the same shall be measured in
square metres stating depth.
4.6.9 Toothi", and Bonding - Where new concrete walls are bonded to
existing walls an item of labour and material in cutting, toothing and
bonding shall be measured in square metres.
13
IS :1200 ( Partlll) -1976
(Reaffirmed
( Reaffirmed 2002)
1992 )
Indian Standard
METHOD OF
MEASUREMENT OF BUILDING AND
CIVIL ENGINEERING WORKS
PART III BRICKWORK
( Third Revision)
Third Reprint AUGUST 1993
‘_ ,,.
I
_---
0 Copyrfgghl1976.
BUREAU OF INDIAN STANDARDS
MANAK BHAVAN, 9 BAHADUR SHAH ZAFAR MARG
NEW DELHI 110002
Gr 3 September 1976
- _s
/
pw_--. 1._- _.._^_..^_-_
0.5 Since various trades are not related to one another, the Committee
decided that method of measurement for each trade as given in IS : 1200-
1964* be issued separately as a different part, which will be helpful to
specific users in various trades. This part covering method of measure-
ment of brickwork applicable to building as well as civil engineering
works was, therefore, issued as a second revision in 1970.
0.6 In the course of use of this standard in the past five years based on
suggestions received, certain amendments were issued to this standard.
This third revision has been prepared to incorporate these amendments.
0.7 For the purpose of deciding whether a particular requirement of this
standard is complied with, the final value, observed or calculated,
expressing the result of a measurement, shall be rounded off in accordance
with IS :2-1960t. The number of significant places retained in the
rounded off value should be the same as that of the specified value in
this standard.
1.. SCOPE
1.1 This standard ( Part III ) covers the method of measurement of
brickwork in buildings and civil engineering works.
NOTE- The method of measurement of refractory brickwork is covered in IS : 12@)
( Part VI )-1974$
2. GENERAL
2.1 Clubbing of Items- Items may be clubbed together provided that
break up of clubbed items is on the basis of detailed descriptions of items
as stated in this standard.
2.2 Booking of Dimensions -In booking dimensions, the order shall
be consistent and generally in the sequence of length, breadth or width
and height or depth or thickness.
2.3 Measurement-All work shall be measured net in the decimal
system, as fixed in place, as given below:
a) Dimensions shall be measured to the nearest 0.01 m,
b) Areas shall be worked out to the nearest 0.01 m*, and
c) Cubic contents shall be worked out to the nearest O-01 rns.
4
IS : 1200 ( Part III ) - 1976
2.7.1 Levels of high and low water tides, where these occur, shall be
stated.
3. BRICKWORK GENERAL
3.1 Bricks and,mortar to be used for brickwork shall be fully described.
Where it is proposed to specify a bond other than English bond, it shall
be so stated.
5
(S 8 1200 ( Part XII) - 1976
4 Footings;
b) Battered (measured net). Battered surfaces shall, however, be
measured, separately in square metres as an extra-over;
4 Eaves or beam fillings, no deduction being made for joists, rafters,
etc;
4 Brickwork ( excluding refractory brickwork ) in chimney breasts,
chimney stacks, smoke or air flues (except independent chimney
shaft as in factories for steam boilers ); and
e) Pilasters, plain copings and sills.
NOTE - In the case of receding courses of panels, recess shall not be deducted.
4. MEASUREMENT
4.1.1 Walls one brick thick and less shall each be measured separately
in square metres stating thickness.
6
Lh---.---. I_~.._ _..... _I. .. .
4.1.2 Walls exceeding one brick thick but not exceeding three bricks in
thickness shall be measured in multiples of ha&brick which shall be
deemed to be inclusive of mortar joints. Where fractions of half-brick
occur due to architectural or other reasons, measurement shall be taken
as follows:
a) Up to t brick - actual measurement, and
b) Exceeding i brick- full half-brick.
Cl.3 For walling which is more than three bricks in thickness actual
thickness of wall shall be measured.
Cl.4 No deductions or additions shall be made on any account for the
following:
n
9. CIRCULAR BRICKWORK
5.1 Brickwork circular on plan to a mean radius not exceeding 6 m &all
be measured separately and shall include all cutting and’ waste and
‘templates.
5.1.1 Brickwork circular on plan to a mean radius exceeding 6 m shall
he measured separately and included with general brickwork.
6. BACKING TO MASONRY
6.1 Brickwork in backing to masonry shall be measured separately stating
average thickness; description shall include. all cutting and waste for
bonding.
7. HONEYCOMB BRI’CKWORK
7.1 Honeycomb brick walling shall be measured in square metres stating
thickness and pattern of honeycombing. Honeycomb opening shall not
be deducted.
9. CAVITY WALLS
9.1 Forming of cavity shall be measured in square metres stating width
of cavity and shall include ties and their ,number per square metre.
Material, size and shape of ties shall be described.
9.3 Labour‘and material for closing cavities at jambs, sills and heads of
openings shall be described and measured separately in running metros.
9?4 Use of cores for keeping cavity clear and forming requisite weep and
vent holes shall be described.
8
IS: 1200 (Part III ) - 1976
14. UNDERPINNING
14.1 Brickwork .in underpinning shall be measured separately and an
item for extra labour and material in wedging up on top of underpinning
shall be measured in square metres as length multiplied by width of top
course.
*Method of measurement of building and civil engineering works : Part VIII Steel
work and iron work ( third revision ).
tMethod of measurement of building and civil engineering works : Part XXI Wood-
work and joinery ( second reuision ).
$Method of measurement of building and civil engineering works : Part V Form wotk
( second r&s&2 ).
9
rS : 1200 ( Part III ) - 1976
10
IS : 1200 ( Part III ) - 1976
11
lS*l2OO(PartlV)-197&
( Reaffii
( Reaffirmed 1992
2002) )
Indian Standard
METHOD OF MEASUREMENT OF BUILDING
AND CIVIL ENGINEERING WORKS
PART IV STONE MASONRY
( Third Revision 1
UDC 69.003.12:'693.1
@ Co/@& 1976
0.5 Since various trades are not related to one another, the Sectional
Committee decided that method of measurement for each trade as given
in IS : 1200-1964* be issued separately as a different part, which will be
helpful to specific users in various trades. This part covering method of
measurement of stone masonry applicable to buildings as well as civil
-engineering works was, therefore, issued as a second revision in 1970.
0.6 In the course of use of this standard in the past five years, based on
suggestions received, certain amendments were issued to this standard by
the Sectional Committee and the third revision has been prepared so as to
incorporate such amendments.
,0.7 For the purpose of deciding whether a particular requirement of this
standard is complied with, the final value, observed or calculated,
expressing the results of a measurement, shall be rounded off in accord-
ance with IS : 2-1960t. The number of significant places ‘retained in
rounded off value should be the same as that of the specified value in
this standard.
1. SCOPE
1.1 This standard ( Part IV) covers method of measurement of stone
masonry in buildings and civil engineering works.
‘2. GENERAL
2.1 Clubbing of Items - Items may be clubbed together provided
that break-up of clubbed items is on the basis of detailed descriptions
of items as stated in this standard.
2.2 Booking of Dimensions - In booking dimensions, the order shall
be consistent and generally in the sequence of length, breadth or width
and height or depth or thickness.
~2.3 Measurements - All work shall be measured net in the decimal
system, as fixed in its place, unless otherwise stated herein, as given
below:
a) Dimensions shall be measured to the nearest 0.01 m.
b) Areas shall be worked out to the nearest 0.01 m2, and
c) Cubic contents shall be worked out to the nearest 0.01 ms.
2.4 Description of Item - Description of each item shall, unless
otherwise stated, be held to include, conveyance, delivery, handling,
unloading, storing, waste, returning of packings, scaffolding, tools and
tackle, as necessary.
2.7.1 Levels of high and low water tides, where these occur, shall be
stated.
3. WALLING
3.1 Type of stone, kind of walling and mix of mortar shall be described:
Item of general walling shall be deemed to include the following:
a) Bond stones;
b) Raking out joints for plastering or for pointing, done as a
separate process or finishing joints flush as work proceeds;
c) Preparing top of existing wall and the like for raising;
d) Rough cutting and waste for forming gables, cores of arches,
splays at eaves and the like and all rolrgh cutting in the body of
walling;
5
3S : 1200 (Part IV) - 1976
4. MEASUREMENT
6
IS : 1200 ( Part IV ) - 1976
5. STONE NOGGING
7
IS t 1200 (Part IV)-1976
7. UNDERPINNING
8. LEVELLING UP
9. FACINGS
9.1 If facing stones are the same as those used in body of walling,
additional work involved in dressing stones shall be described as ‘extra-
over ’ walling.
9.1.2 If facing stones are different from those used in body of walling,
facings may be stated as ‘stone and labour in facing’. Type of such
facing and average bed shall be described, and bonders, if any, shall also
be described and number per square metre stated. Bonding to stone
walling and to brick work shall be measured separately.
*Method of measurement of building and civil engineering works: Part XXI Wood-
work and joinery.
tMethod of measurement of building and civil engineering works: Part V Formwork.
8
IS : 1200(Part IV) - 1976
9
IS : 1266 ( Part IV ) - 1976
10
IS t 1200 (Part IV) - 1976
11
IS : 1200 ( Part V ) - 1982
1. SCOPE
2. GENERAL RULES
4
IS : 1200 ( Part v ) - 1982
2.5.1 The levels of high and low water tides, where occurring, shall be
stated.
2.5.2 Where sprin;, requiring pumping are likely to be encountered,
the work shall be maajured against a separate specific provision made
for the purpose ( see 2.5.3 ).
2.5.3 Special pum%nz, where resorted to, shall be measured separately
for all stages of pumping, includinq intermediate stages, unless stated
otherwise, in kilowatt hours or HP hours, against specific provision made
for the purpose.
2.6 Bills of Quantities - The bills of quantities shall fully describe
the materials and workmanship, and accurately represent the work to be
executed.
2.7 Measurement in Stages - Work shall be measured under the
following categories in convenient stages stating the height or depth:
a) Below ground/datum level, and
b) Above ground/datum level.
NOTE - The ground datum level shall be specified in each case.
3. DESCRIPTION OF FORMWORK
4 Bolts, wire ties, clamps, spreaders, nails or any other items to hold
the sheathing together;
4. TYPE OF FOBMWORK
4.1 Separate items shall he provic’ed for fcrmwork with type of contact
surface, such as:
b) Flat surfaces, such as soffits of foors, roofs landing and the like;
where floors exceed 200 mm in thickness the formuork shall be
measured separately stating the thickness;
e>Arches
i) up to 6 111 span
ii) above 6 m span
4 Spiral staircases;
t) Chimneys and shafts;
u) Elevated water reservoirs;
8
IS : 1200 (Part 6) -1974
( Reaffirmed 2007 )
Indian Standard
METHOD OF MEASUREMENT OF
BUILDING AND CIVIL ENGINEERING WORKS
PART 6 REFRACTORY WORK
( Second Revision)
Fifth Reprint JANUARY 2000
( Incorporating Amendment No. I )
© Copyright 1980
BUREAU OF INDIAN ST ANDARDS
MANAK BHAVAN, 9 BAHADUR SHAH ZAFAR MARG
NEW DELHI 110002
Gr 2 April 1974
III 1_ ( Put VI)- 1174
0.5 For the purpose of deciding whether a particular ~uirement of this
ltandard is compliedwith, the final value, observed.or calcUlated, expreuihg
the result of a meuurement, .h.11 be rounded off' in accordance with
IS : 2·1960·. The Dumber ofsipificant places retained in the rounded off
value should be the same as that of the specified value in this standard.
I. SCOPE
1.1 This standard (Part VI) coven the method of measurement of
refractory work.
2. 0ENBIlAL ItULBI
2.1 ChaWtIaI oIlteIDa - Items may be clubbed together provided that
the br:eak up of the clubbed items is agreed to be on the basis of the detailed
description Ofthe items atated in this standard.
2.2 .oId-,elDIm_.t. . - In booking dimensionl, the order shall be
CODIiItent and generally in the sequence of.lengtll, breadth or width and
height or depth or thickness.
2.1 _ - Unless otherwise stated hereinafter all work ,hall be
measured net in the decimal system, as fixed in place, as given in 2.3.1 to
2.1A.
2.1.1 DimeaUoI1l shall be measured to the nearest 0·01 m,
2.1.2 Areal shaD be worked out to the nearest 0·01 mi.
2.3.3 Cubic contentishaU be worked out to the nearest 0-01 mi.
2.3•• Weight sball be worked out to the nearest 0-001 tonne.
2.t DMatpdoa 011.... - The description of each item iliaD, UBless
otherwise ltated be deemedto include, where necessary, conveyance, delivery,
bandliag, unloading» .toring watel !etum of PMking, necessary scafFoldingl,
platforms, walkways, tools and taCkles, stacking item wise, opening of pack.
agesand disposal Ofwood,straw etc. This shall.1so include useof necessary
equipmenu, safety applianees,lighting at place of work, ventilatioD facilities,
where necessary.
2.5 W.... - AU measurement of cutting shaU, unless otherwise stated, be
deemed to include conaequent wastap.
2.1 Dell. . . . - Where a minimum area is defined for the deduction of
opening voids or both, such area shall refer onlyto oporainpor voids within
die space measured.
•1luIeI for rouDdiDa 08'auaaerica1 val... ("""').
4
18 I 1200 ( Part VI ) • 1974
2.7 W.-k .. be Mea. . . . ~t.1y- The refractory work to be
carried out in hot conditions shall be 10 specified indicating range of
temperature and work shall be measured separately.
2.1 . . of Q.taaaddH - The bills of quantities shan fully describe the
materials and workmanship and accurately represent the work to be
executed.
3. METHOD or MEASUREMENT
3.1 The items of work wherever nec~"ary and unless otherwise stated shall
be deemed to include the following:
. a) Dressing of the brick.'1/blocks including cutting, grinding and
chipping to achieve proper thickness of joint and alignment as
required in the drawings for all classes of work.
b) Dressing of bricks/blocks including cutting, grinding and chipping
wherever necessary for expansion joints, sliding joints, binding
joints, etc, to ensure proper curvature and keying in arches,
curved surface, etc.
c) Forming of expansion joints, sliding joints, etc, excluding filling
(for filling s" 3.8 ).
d) Finishing, pointing, clearing and cleaning of masonry joints, gaps,
hollows, cavities, opening passages, ducts etc.
3.2 The refractory and insulation bricks and blocks, types of mortars and
powden to be used shall be fully described. Other auxiliary and fi1lin8
materials, such as paper, cardboard, asbestos materials, mineral wool, water
glass, coke pitch, carbon mass.speeia! sands, crumbs, powders) admixtures anel
plasticizers required to be in('drporated in the works shall also be described.
3.3 All refractory work wl1eas otherwise specified shall be measured in
cubic metres. The measurement shall be inclusive of mortar joints
expansionjoints and sliding joints. Deductions for voids, openings, etc, shall
be made only when the area of each such opening and voids exceeds a·or
square metre.
3.4 The method of measurement on volumetric basis as specified in 3.3 shall
also apply for eastable refractory work or refractory concreting, rammed,
mass filling; filling of loose insulation materials, such as mica crumbs, slag
wools, asbestos powders, fil-eclay mass and carbon mass.
3.5 Where the brick/blocks lining is separated from the shell 01" wall surface
by the usc of asbestos, cardboard, etc, such insulating material shall be fully
described and measured separately in square metres,
3.8 Where intulation plaster is applied over the refractory surface. the same
shall be fullv described and measured ~c~pa1"at(~I\' in square metres.
5
11,1- 'PurVl)-1174
1.7 llehctoty ~t work shall be tully clelcribecl uul meuurecl ill cubic
metreI 011 the bUis or theoretical volume to be srouted.
1.8 Fillinlof ~on jointl, aliclina joints with pa~, cardboarcI, etc,
shall be fiiIIy cleIcribecl and measured aeparately in numiDg tquare metres.
1.1 Unleu otherwile ltated fixina of anchon, ~ and IU~ • •
members for the rehctory. briCkwork shall be lIepar_tely mOun r'"
IS: 1200 (Part VIII) - 1974* l.
3.10 Unl. otherwise ltated painting of finished muonry with cement or
fireclay mortars. water IIua. ete.1baIl be ~ured aaparately ( ",IS: 1200
(Part KIlll-1976t J.
6
IS : 1200 ( Part VII ) - 1972
( Reaffirmed 2007 )
Indian Standard
METHOD OF MEASUREMENT OF
BUILDING AND CIVIL ENGINEERING WORKS
PART VII HARDWARE
( Second Revision)
© Copyright 1977
BUREAU OF INDIAN STANDARDS
MANAK BHAVAN, 9 BAHADUR SHAH ZAFAR MARG
NEW DELHI 110002
Gr 2 July 1972
IS .1200 ( Put VB ) • 1972
1. SCOPE
1.1 This standard (Part VII) coven the method of measurement of
hardware in buildings and civil -engineering works.
2.GBNERAL
2.1 ne.c:rIpdOD 01 lum - The description of each item shall, unless
otherwise stated, be held to include, wherever necessary, conveyance and
delivery, handling, unloading, storing and all labour for fitting and fixing
in poaition t cutting and waste, return of packing, etc.
2.2 LImJt. 01 Meu....m ••t - The dimensioDi shall be measured net
in decimal system nearest to 0-01 m,
~.3 BID. 01 Q,. . .dd. - The bills of quantities shall fully describe the
materials and workmanship and accurately represent the work to be
executed.
2.4 Mode df M.8aremeDt. - The various kinds of builders hardware
shall be described and measured separately according to the material,
finish, size, pattern and method offixing.
2.4.1 All builden hardware shall be fully described and enumerated
except the following which mall be measured in running metres:
a) Curtain roda or poles, stating the outer diameter;
b) Curtain Raila - Curtain runnen, brackets and stops shall be
described and included with the item Itating the number per
metre of rail;
c) Rails for .liding luhes stating the size of the rail j and
d) Suh Linea - The girth or diameter thall be ltated.
2.5 Fixing of hardware items ahaIl include aU fittings, cutting, ainkm"
boring and momcing, the supply of screws ( or bolts, nuts and waahen In
the case of hardware made for fixing with bolts), to match.
2.& Hardware fixeel to wood and metal ahall each be meuured aeparately.
2.7 Hardware fixed Bush shall be 80 delClibed.
9) Latches (SuR""lk or Nor- The dimensions of the plate (havinl the bow
folk) handle) and the liztt number
8) t...')('k~ drawer
9) Locks furui1 ure 'Chc Inaximum diamt"lcr of the knob
10) Cleall helayinl Straight distance between two endl of cleat
11 ) Catrbf'l, .prinS (for r"l- The 8at overallsi.e in elevatioD oC the plate- with
light) "prins catch excludiDI the Itrikin. plate
12) Faat«-nen, cocupur The lenlth or handle from the ce-ntre of piYOt or
hiDled joint
13) Fa.t~nerl and Itnys ExtrMDe lenlth ir.tiudinl thickneaa of back plate
(curment)
14) Pivotl and aocketl The dimensions of each pia te
Ii) Star.' quadrant (for fan- The shortelt Itra.bt length between the extreme
ilht) ~nd. of the quaCirant atay
( ConlillUltl)
IS I 1200 ( Put VB ). 1172
29) Door c10ser ( bydraullc:aUy The, wellht and the width oCthe door 1o which it
replated) II latcRdecl to be &ueclalaaU be Itated
10) ri.... pwe, The len,th, wldtb and tlalcbell otthe pI.lft
31) SlIdia, door bolt (Aldrop) Lenltb ~ the bolt
52) J'Joot door ItoppH wida 1.eaIth 01ill plate
pl••
II) Boob and..,. Lealstb ul the houk . .lIurccI out to ou&
6
IS 1200 (Part 8) : 1993
(Reaffirmed 2002)
~TlT 8 i~qT({m q ~m
( :qT~r '!'fUef11T )
Indian Standard
METHODS OF MEASUREMENT OF
BUILDING AND CIVIL ENGINEERING WORKS
PART 8 STEELWORK AND IRONWORK
( Fourth Revision)
C DIS 1993
Indian Standard
METHODS OF MEASUREME.NT OF
BUILDING AND CIVIL ENGINEERING WORKS
PART 8 STEELWORK AND IRONWORK
( Fourth Revision )
1 SCOPE 3.3 Description of Items
This standard ( Part 8 ) covers the method of The description of each item, which covers
measurement of steelwork and ironwork in both fabrication and erection, shall include
buildings and civil engineering works. conveyance and delivery, handling, unloading,
storing, hoisting and all labour for finishing to
NOTE - The method of measurement for roof
covering; pipe Iines, etc for water supply and required shape and size. Alternatively, in each
sewerage; and pipe Jines, etc for gas and oil are item of work fabrication or erection shall be
covered in IS J200 (Part 9 ) : 1973, IS J200 described and measured separately.
(Part 16): 1979 and IS 1200 (Part 20):1981
respectively. 3.4 Bill of Quantities
2 REFERENCES Items of work shall fully describe the materials
The following Indian Standards are necessary and truly represent the work to be executed.
adjuncts to this standard: 3.5 Dimensions
IS No. Title Unless otherwise stated all works shall be
1200 Method of measuremen t of measured net in decimal system, a.. fixed in its.
( Part 9 ) : 1973 building and civil engineering place, as given in 3.5.1 and 3.5.2.
works: Part 9 Roof covering
( including cladding) ( second 3.5. t Cross-sections and thicknesses shall be
revision) taken from relevant Indian Standards. Length
and breadth shall be measured to nearest
1200 Method of measurement of ·0·00 I m except for reinforcement which shal L
(Part 16 ): 1979 building and civil engineering be measured to nearest 0·005 m,
works: Part 16 Laying of
water and sewer lines includ- 3.5.2 Areas shall be worked out to nearest
ing appurtenant structures 0'001 m t •
( third revision)
3.6 The priming coat shall be described and
1200 Method of measurement of included in item of fabrication.
( Part 20 ) : 1981 building and civil engineering
works: Part 20 Laying of gas 3.7 The mass of steel sheet, plate and strip:
and oil pipe line-, ( third rolled steel sections. steel rods, steel reinforce-
revision) ments, and steel strips; forged steel, steel cast ..
l23-.) Mild steel tubes, tubulars and iog, and steel tubes shall be taken from relevant
( Part 1 ) : 1979 other wrought steel fittings : Indian Standards.
Part 1 Mild st eel tubes (fourth 3,7.1 The final mass of individual categories/
revision) sections calculated based on dimensions arrived
3 GENERAL RULES at in 3.5.1 and 3.5.2 and mass arrived at as
per 3.7, shall he worked out to nearest I kg.
3.1 Clubbing of Items
3.8 Unless otherwise specified an addition of
Items may be clubbed together provided that 2' 5 percent of the mass of structure shall be
break-up of clubbed items is agreed to be on the made for shop and site rivet heads in riveted
basis of detailed description of items, stated in steel structures.
1hJS standard.
3.9 Unless otherwise specified, in the case of
3.2 Booking of Dimensions welded steel structures no allowance shall be
made for the weld metal.
1n booking dimensions, order shall be consistent
and generally in sequence of length, width and 3.10 Wedging-up, under stanchion bases or steel
height or depth or thickness. grillages shall be described and enumerated.
2-66 BIS/NO/07
18 1200( Part 8 ) : 1'"
4 STEEI4WORK portion), running bars for doors and
fencing posts and struts;
4.1 Various items of steelwork shall be classified
and measured separately under following v) Framed work, such as grills, gratings,
categories. Work in each classification shall be framed guard bars, ladders, walkways,
described. Bolted, riveted and welded structures railings, brackets and similar work;
shall be described as such and measured w) Straps, hooks, clamps, holdfasts, wall ties,
separa tely: insets, knee pieces, and similar works;
y) Ornamental work as in grills, balustrades,
a) Rolled sections (joist, channel, angle or and curved, ramped and scroll portion of
tee) fixed independently without con- cores for handrails; 'and
necting plates;
z) Steelwork for:
b) Rolled sections fixed with connecting
plate or angle cleats as in main and cross- 1) doors,
beams, hip and jack rafters, purlins 2) hydraulic gates, and
connected to common rafters and the 3) cassions and well curbs,
like.
NOTES
c) Rolled joists, with or without stiffeners in
grillages ( the weight of stiffeners shall be 1 In composite construction shear connectors. If
any. will form part of structural steelwork.
added to the mass of joists );
2 The above classification with suffix B, R or W
d) Compound girders; shall be indicated in bills of Quantities to denote
e) Plate girders (stating type and overall bolted, riveted or welded construction
height of girder ); respect i ve Iy.
f) Lattice girders, aerial masts, tank stag ing 4.2 The stee lwork shall be measured by ma.ss
and like ( stating details of members and except otherwise mentioned,
overall height of structure );
4.3 Unless otherwise specified, mass of cleats,
.g) Single stanchions composed of rolled brackets, packing pieces, bolts, nuts, washers,
joists or channels with caps, bases, splices, distance pieces, separators, diaphragm, gussets
angle brackets, etc; ( taking overall rectangular dimensions), fish
11) Compound stanchions with caps, bases, plates, etc, shall be added to the weight of
splices, angle brackets, etc; respective ite D1S. In riveted work, allowance i~
j) Trusses and trussed purlins ( stating spans to be made for mass of rivet heads ( see 3.1 ).
and overall heights ); No deduction shall be made for rivet or bolt
holes ( excluding holes for anchor or holding
k) Framing of cladding and glazing;
down bolts ). Deduction in case of rivet or bolt
m) Crane gantry rails including fastenings: hole shall, however, be made if its area exceeds
n) Staircases including stringers, treads, 0·02 ro l and for notch if its area exceeds 0,05 m t .
landings, handrails, etc; For other type of openings like holes for service
pipe etc, deduction shall be made if its area
p) Plates ( plain or chequered ), square cut
exceeds 0'1 mi.
or notched, holed ( ordinary or counter-
sunk) without any attachments; 5 TUBULAR STRUCTURES
<I) Plates of classification ( p) above with
The tubular structures shall be described and
riveted, bolted or welded attachments;
measured by weight.
r) Running rails and girders for sliding
doors; 6 CABLES/GUY WIRES
s) Platework with or without stiffeners for: The cables and guy wires shall be described and
1) bunkers, measured in running metre stating the diameter
2) chutes, or by weight.
3) chimneys including ladders, 7 BEARINGS
4) tanks with or without covers including These shall be classified as roller, rocker, sliding,
stays but excluding stagings, etc, and fully described and enumerated.
5) gutters and downpipes, and 8 PIPES FOR FLUES
'6) furnace shell.
8.1 Flue pipes of steel sheeting shall be
x) Anchor bolts, holding down bolts including measured overall in funning metres and describ-
all fittings and sag rods; ed as including all short lengths, cutting and
11) Wind ties to roofs, strakes for wooden waste. The" method of jointing and fixing shall be
bridges, cores for handrails (straight described. Support s shall be measured separately,
2
IS 1200 ( Part 8 ) : 1993
3
18'1200 ( Part 8 ) : 1993
4
GMGIPN-58 BIS/ND/07-200
IS : 1200 (Part IX) - 1973
(Reaffirmed 2007)
Indian Standard
METHOD OF MEASUREMENT OF
BUILDING AND CIVIL ENGINEERING WORKS
PART IX ROOF COVERING (INCLUDING CLADDING)
( Second Revision)
Tenth Reprint JUNE 2008
(Incorporanng Amendment No.1)
© Copyright 1978
BUREAU OF INDIAN STANDARDS
MANAK BHAVAN, 9 BAHADUR SHAH ZAFAR MARG
NEW DELHI 110002
Gr 3 March 1973
ISI~ (PanIX)-lI7S
issued separately as a dift'ereIlt part. This will also be helpful to u~en
in using the specific standard.
0.5.1 Pfhis part coven method of measurement 4)f roof eovttilt~
( including cladding) applicable to buildings as well as to civil eng,,~r.-~t ...
ing works.
0.6 For the purpose of deciding whether a particular requirement of this
standard is complied with, the final value, observed or calculated,
expressing the result of a measurement, shall be rounded off in accord-
ance with IS: 2-1960*. The number of sign~cant places retained in
the rounded off value should be the same as that of the specified value
in this standard.
1. SCOPE
1.1' This standard (Part IX) covers the method of measuremmt of roof
coVCring (including cladding) for buildings and civil engineering worb.
2. GENERAL RULES
2.1 Clabbial olltem- - Items may be clubbed together provided that
the break-up of the clubbed items is agreed to be on the basis of the
detailed description of the items stated in this standard.
2.2 Booldac of Dlme. .1.... - In booking dimensions, the order shall
be consistent and generally in the sequence of length, breadth or width
and height or depth or thickness.
2.3 DeIIcdpdoa 01 Ite1D8 - The description of each item shall, unless
otherwise stated, be held to include, where necessary, canveyance and -,
delivery, handling, unloading, storing, fabrication, hoisting, all labour
for finishing to reCfuired shape and size.
2.4 M~u - Unless otherwise stated hereinafter all works
lball be measured net in decimal system, as fixed in its place, as given in
1.4.1 and"2.4.2 4
4
IS 11200 (Part IX) ·1973
2.8 Bib. of QJaaadtln - The bills of quantities shall fully describe the
materials and workmanship, and accurately represent the work to be
executed.
2. '1 The superficial area of roof coverings and cladding as laid shall be
measured on the flat in square metres without allowance for laps and
corrugations, if any.
2.7.1 Portions of roof covering overlapped by ridge or hip, etc, shall be
included in the measurements of the roof except where otherwise
stated. fII •
2.8 Any opening not exceeding 0·4 rn l shall not be deducted and form-
ing such openings requiring cutting shall be enumerated.
2.' Any opening exceeding 0-4 m l shall be deducted and cutting requi-
red shall be measured in running metres,
2.10 Cutting across corrugations shall be measured on the flat and not
girthed.
2.11 No additions shall be made for laps cut through.
2.12 Sheeting curved or bent to curvature shall be measured separately.
2.13 'The woodwork and steelwork shall be measured separately under
the relevant part of this standard.
'7.4: Special ridge and hip tiles shall be described stating the kind, pattern,
quality and size as also the mortar in which bedded and pointed.
Coloured mortar (to match the coloured tiling, if required to be used
for pointing) shall be described.
7.5 Hip hooks shall be enumerated stating the size and whether black or
galvanized.
7.6 Eaves tiles bedded in mortar on walls shall be measured in running
metres as extra for eaves describing the mortar and width of bedding.
7.7 Filling ends and spaces between tiles at eaves with mortar shall be
measured in running metres and described stating the depth of filling.
7.8 Filling to single and double tiling shall be measured separately.
7.9 Screwing eaves tiles to battens shall be measured in running metres
stating type, size, spacing of screws and washers. Drilling holes in the
tiles shall be included in the description.
7.10 Half tiles or one and a half tiles at verges shall not be measured
separately, but straight cutting and waste at verges shall be allowed for
the full length of the verge and measured in running metres.
7.11 Tiles at verges bedded in mortar on walls shall be measured in
running metres as 'extra over' for verges describing the mortar and width
of tile bedding.
7.12 Country tiling shall be described as including all cutting and
waste.
7.13 Special ventilating tiles and glass tiles shall be enumerated as
'extra over' only over roof tiling.
8. ROOF SlDNGLES
1.1 Wood shingles to roof shall be measured in the same way as in the
case of roof tiling (s" 7 ).
9. 1\oop SLA'rING
'.1 Slate roofs shall be measured in the same way as in the case of roof
tiling <. see 7 ).
10. TERRACED ROOFING
10.0 The size and quality of burnt bricks, brick tiles, stone slabs and
similar materials for terraced roofing, method of laying, jointing, point-
ing and mix and type of mortar shall be described, stating the number of
layers of bricks tiles, etc.
7
IS: 1200 (Part IX ) -1973
9
t\1GIPr - 162 Deptt of HIS/2008 200 Books
IS : 1200 (Part X) - 1973
(Reaffirmed 2007)
Indian Standard
METHOD OF MEASUREMENT OF
BUILDING AND CIVIL ENGINEERING WORKS
PART X CEILING AND LININGS
( Second Revision)
Fifth Reprint JUNE 2008
(IncorporatingAmendmentNo. 1 and Including AmendmentNo.2)
© Copyright 1979
BUREAU OF INDIAN STANDARDS
MANAK BHAVAN, 9 BAHADUR SHAH ZAFAR MARG
NEW DELHI 110002
Gr 2 March 1973
IS, 1200 (Part X)-l91'
issued separately as a different part. This will abo be helpful to usen In
using the specific standard.
0.5.1 This part covers method of measurement of ceiling and linings
applicable to buildings as well as to civil engineering works.
0.6 For the purpose of deciding whether a particular requirement of this
standard is complied with, the final value, observed or calculated, express-
ing the result of a measurement, shall be rounded off in accordance
with IS: 2-1960·. The .number of significant places retained in the round-
ed off value should be the same as that of the specified value in this
standard.
1. SCOPE
1.1 This standard (Part X) covers the method of measurement of ceilings
and linings for buildings and civil engineering works.
2. GENERAL RULES
2.1 Clubbing or IteDl8 -- Items may be clubbed together provided that
the break-up of the clubbed items is agreed to be on the basis of the de-
tailed description of the items stated in this standard.
2.2 B~oldDg or DimeD.loD8 - In booking dimensions, the order shall be
consistent and generally in the sequence of length, breadth or width and
height or depth or thickness.
2.3 DescriptioD or Items - The description of each item shall, unless
otherwise stated, be held to include where necessary, conveyance and
delivery, handling, unloading, st.oring, fabrication, hoisting, all labour for
finishing to required shape and size.
2.4 Me••lIremeat. - Unless otherwise stated here-in-after all worb
shall be measured net in decimal system, as fixed in itl place, as giYal
in 1.4.1 and 1.4.2.
2.4.1 Dimension shall be measured to the nearest ()eOI m ..
2.4.2 Areas shall be worked out to the nearest 0·01 mi.
2.5 Bills of Q,aaadtie. ~ The bills of quantities shall fully describe the
materials and workmanship, and accurately represent the work to be
executed.
5
IS : 1200 ( Part XI)- 1977
(Reaffirmed 2007)
Indian Standard
METHOD OF MEASUREMENT OF
BUILDING AND CIVIL ENGINEERING WORKS
PART XI PAVING, FLOOR FINISHES, DADO AND SKIRTING
( Third Revision )
Second Reprint JANUARY 1989
UDC 69.003.12:693.7+69.025.3
© Copyright 1977
BUREAU OF INDIAN STANDARDS
MANAK BHAVAN, 9 BAHADUR SHAH ZAFAR MARG
NEW DELHI 110002
Gr 3 December 1977
lB. 1200 ( Part XI) .1977
0.5 Since various trades are not related to one another, the Committee
decided that each type of trade as given in IS: 1200-1964* be issued
separately as a different part, which will be helpful to specific users in
various trades. This part covering method of measurement of paving
and floor finishes applicable to building as well as civil engineering works
was, therefore, issued as a second revision in 1971.
0.6 In the course of use of this standard in the past 6 years) a number of
suggestions were received and accordingly certain amendments were issued
to this standard. This third revision incorporates all such amendments
besides making other provision up-to-date.
0.7 For the purpose of deciding whether a particular requirement of this
standard is complied with, the final value, observed or calculated, express-
ing the result of a measurement, shall be rounded off in accordance with
IS: 2-1960t. The number of significant places retained in the rounded
off value should be the same as that of the specified value in this standard.
1. SCOPE
1.1 This standard (Part XI) covers the method of measurement of
pavings, floor finishes, dado and skirting in buildings and civil engineering
works.
NOTE - The method of measurement of airfield pavements is covered in IS: 1200
( Part xvu )-1969:.
2. GENERAL
2.1 Clubbing 01 Items - Items may be clubbed together provided that
the break-up of the clubbed items is agreed to be on the basis of the
detailed description of the items.
2.2 Bookiog of DilDeosiou& - In booking dimensions, the order shall
be consistent and generally in the sequence of length, breadth or width and
height or depth or thickness.
2.3 De8criptioD of Items - The description of each item shall, unless
otherwise stated, be held to include wherever necessary conveyance and
delivery, handling, unloading, storing, fabrication, hoisting, aJJ labour for
finishing to required shape and size, setting, fitting and fixing in position,
straight cutting and waste, return of packings, and other incidental
operations.
4
IS I 1200 (Part XI) .1177
2.t DimeaBloD - All work shall be measured net, as laid, in the decimal
I)'Item as under, unless otherwise stated hereinafter:
a) Dimensions shall be measured to the nearest 0-01 m, and
-b) Areas shall be worked out to nearest 0-01 mi.
2.S 8m. 01 Q,aaadtie. - Items of work shall fully describe the materials
,and workmanship and accurately represent the work to be executed.
2~6 Catda._ - All cuttings shall unless otherwise stated be held to include
the consequent waste.
2.7 Mode 01 Measaremeat - All work shall be measured in square
metres unless otherwise stated. Deductions for ends of dissimilar materials
or other articles embedded shall not be made for areas not exceeding 0-1 mi.
2.7.1 Work in isolated width not matching with the general finish shall
be measured as below:
a) Width 30 em and below in running metres (the description to
include for cutting to edges if any), and
b) Width above 30 cm in square metres.
2.8 Expansion and dummy joints shall be described and measured
separately in running metres stating depth and width of joints. The filler
mall be described and included in the description of item.
2.9 Work in repairs shall be so described and preparation of old surfaces to
receive such work shall be included in the description.
2.10 Work in isolated areas not exceeding I n12 each shall be so described
stating the nature thereof
2.11 Work to a pattern or in more than one colour shall be so described
stating the nature thereof.
2.12 Curved work, conical work and spherical work shall be described
separately stating the radius.
2.12.1 Labour in such works shall be so described and Jn~a'iured
separately.
3. IN S/1 U FINISHES
3.1 In situ finishes shall be classified according to the kind of material
( for example, granolithic, terrazzo, mosaic, etc ) and measured separately.
The following particulars shall be given for each classification:
a) Composition and mix;
b) Thickness, which shall be exclusive of keys, grooves a nrt open
joints;
5
III 1200 ( Put XI ) • It77
c) Number of coats;
d) Nature of surface treatment (tor esaD1ple, steel trowelled, wood
floated, polished. sprinkled with carborundum powderJ etc ) j
e) Nature of base and any special treatment to the same; and
f) Situations, for example, whether in flooring or in dado/skirting.
3.2 Work executed to imitate atone slab, or atone blocb shall be 10
described ltating the average size or the alabl or blocks, the surface fiDiah
(for example, plain, .rough, etc) •
• .3 Wark to floon laid in bays and work to Soon laid in panels betWeeD
dividing Itrips shall be so described lta~ the size of bay or area of panel
or bay. The dividing strip shall be measured separately (,t, 3.13).
3.4 Work in Boon laid in one operation with the base concrete shall be 10
dacribed.
3.5 No deduction shall be made for yoids Dot exceeding CY2 mi.
J.6 Work in treads, riletS and edael of landings shal1 be measured iD
Iquare metres, Work in landinp abaU ~ included in the main item.
1.7 ·Wark to wall strings and open Jtrinp..ahall be measured in Iquare metrel.
Ea.., angles, ramps and wreathed coraen shall be included WIth the item,
,.I Moulded nOlinga shall be meuured in running metres] returned
moulded ends and angles to mouldinglaball be included in the description.
,.I Dado! (including raking dadOl) ahall be measured in square metres,
Skirting (including raking skirtiDg) shall be measured in running metrel
stating the height. Mitree, ItOpa, returned ends and the like ahall be
included with the item.
S.10 Work to kerbs ,hall be meaaured in running metres stating the girth
on face. Raking kerbl and vertical kerbt shall each be so deecribed,
ArriaeI, rounded edges and coyea Iball be included in the dalCriptioD~
Angles and intenectiODI thalJ be enumerated separately.
S.ll Forming channels shall be J;DeaSUred in running metres as extra over
the finishings in which they occur ItatiDg the girth on face. Arriles shan
be included in the deacriptiODe EDcb, angIeI, interaectioDS and outlet.
than each be enumerated separately.
3.12 Lining to channels shall be measured in running metres .tating the
Birth OD face. Anises and coves shaD be included in the description. Endsl
angles, intersections and outletllhall each be enumerated separately.
3.13 Dividing strips shall be described stating aize and thickness and
measured separately in rwming metres. DescriptiO!! shan include foJ'
__, ansles aDd intenectiona and method of fbUng~ embetldiDg. etc.
"
IS I 1200 ( Part XI ) • 1m
f. TILE, SLAB OR BLOCK FINISHES
t.l Particulan of the following shall be given:
a) Kind of tile. slab or block units (for example, precast concrete,
precast terrazzo, brick, natural stone. cast stone, slate, marble.
Woodblocks, cork, rubber, etc);
Non - In cue of precut concrete work» the mix to be atated.
b) Thickness and size of tile, slab or block units;
c) Shape of unit. where other than rectangular;
d) Nature of surface finish (for example, glazed, rubbed, polished,
type of dressing in case of stone, etc);
e) Bedding or other method of fixing units;
f) Grouting, pointing or other finish to joints;
g) Nature of base (for example, wood, screeded bed, concrete,
brickwork, etc );
h) Situations, for example. whether in flooring or in dado/skirting; and
j) Layout ofjointl.
4.2 Temporary moulds for precast tile, slab or block units shall be deemed
to be included with the item.
4.' No deduction sha)) be made for 'Voids not exceeding 0-2 mi.
4.f Square cutting at joint and at boundaries shall be deemed to be
included with the items.except as provided in 4.5. Raking, cutting and
curved cutting shall eacl he measured separately in running metres except
where occurring within a pattern. In case of work laid to diagonal
patterns, straight cuttiJl8 at boundary ( measured around the peri metre of
each area) shall be measured in running metres.
"'5 Fair edges. rebated edges, rounded edges, chamfered edges, splayed
edges, bevelled edges and the like shall be measured separately in running
metres including ends, angles, mitres, intersections, etc.
...6 Moulded edges, grooves, flutes and the like shall each be measured
separately in running metres. Ends, angles and intersections shan each
be enumerated separately.
f." Cutting and fitting around steel stanchions and the like (grouped
together) shall be described and enumerated.
• .& Cutting and fitting around pipes. tubes. ban, cables, conduits and
the~Ukc shall be described and enumerated.
tel Cutting and fitting around profile of steps shall be enumerated.
7
IS .1200(PanXl)-1977
f.IO Cutting and fitting around dueting brackets, newels. we pedes.
vents, soot-doors and the like (grouped together) shall be enumerated
.tating the size in stages of 25 em girth.
f.11 Dividing Itrips shall be described stating size and thickness and
meuured separately in running metres. Description shall include fot
ends, angles and intenections and method of fixing, embedding, etc.
4.12 Dadoa (including raking dado! ) shall be measured in square metres.
Skirting ( including raking skirting) shall be measured in nmniDl metres
Itatins the height. Mitres. stops, returned ends and the like Ihall be
included witb tile item.
4.13 Channels and lining to channels shall each be measured separately
in running metres describing the section and average depth. Channell
to falls ahall be so described. Rounded edges shall be included in the
description. Ends, angles, intersections and outlets shall each be enumer-
ated aeparately.
4.14 Kerbs shall be measured in runnIng metres describing the section
and shall include rounded edges coves, etc.
f.15 8pe,ciaI tiles and special slabs to form coved internal an,l~ of any
radiUl, rounded external angles, architraves. mouldings, Ceiling ribs,
comiceP and the like shall each be measured in running metres separately
according to size and shape.
Ll& Work to treads. risen and edges of J~diDgs shall be measured
teparately in Iquare mctrea. Work in landings shall be includt;d in the
main item.
5. SHEBT PINISBE8
5.1 Particulars- of the following shall be glven~
a) Kind of sheeting (linoleum, cork, rubber, etc) j
b) Thickness and quality of sheeting;
c) Method of fixinR and joining; and
d) Nature of base,
5.2 Laps and seams shall be included in the description stating the lap
and type ofaeam and lhall not be measured separately.
U Sheet finishea to vertical mCdned and horizontal surfaces shall bel
measured separately.
5.4 No deduction thaD be made tor voids not exceeding 0-2 mi.
8
IS I 1200 ( ·Part XI ) • 1977
5.5 Raking cutting and curved cutting shall each be measured separately
in running metres except where occurring within a pattern (se~ 2.11 ).
Forming rounded external angles and coved internal angles shall each be
measured separately in running metres stating the girth.
5.6 Cover strips over joints of finishes shall be described stating the size
and measured in running metres. Description shall include for ends
angles and intersections. J
5.7 Cutting and fitting around steel stanchions and the like (grouped
together) shall be described and enumerated.
5.8 Cutting and fitting around pipes, tubes, bars, cables, conduits and the
like shall be described and enumerated.
5.9 Cutting and fitting around profile of steps shall be enumerated.
5.10 Cutting and fitting around ducting brackets, newels, we pedestals,
vents, soot-doors and the like (grouped together) shall be enumerated
stating the size in stages of 25 em girth.
6. BEDDING AND BACKINGS
-6.1 Particulars of the following shall be given:
a) Composition and mix;
b) Thickness which shall be exclusive of keys, grooves, open joints; and
c) Nature of base and any treatment of the same.
6.2 Screeded beds for all floor finishes shall be described and measured.
6.3 No deduction shall be made for voids not exceeding 0-2 m 2 •
6.4 Bedding and backing laid in bays or laid in panels between dividing
strips shall be so described stating the size of bay or area of panel or bay.
6.5 Bedding and backing in treads, risers and edges of landings shall each
be measured separately in square metres. Work in landings shall be
included in the main item.
6.6 Bedding and backing In skirtings and dados shall be measured
separately.
6.'7 Forming channels in beds shall be measured in running metres as extra
over the beds in which they occur stating the girth on face. Arrises,
rounded edges, coves, ends, angles, intersections, outlets and the like shall
be included with the itCH1S.
IS : 1200 ( Part XII ) - 1976
( Reaffirmed
( Realkued 2002
1997 ) )
Indian Standard
r METHOD OF MEASUREMENT OF BUILDING
AND ClVIL ENGINEERING WORKS
PART XII PLASTERING AND POINTING
( Third Revision )
0 Copyright r976
Gr 3 June 1976
IS t 1200 ( Part XII) - 1976
0.5 Since various trades are not related to one another, the Committee
decided that each type of trade as given in IS: 1200-1964’ be issued
separately as a different part which will be helpful to specific users in
various trade>. This part covering method of measurement of plastering
and pointing appiicable to building as well as civil engineering works
was, therefore, issued as a second revision in 1971.
0.6 In the course of use of this standard in the past five years based on
the suggestions received, certain amendments were issued to this
standard. This third revision also incorporates all those amendments.
0.7 For the purpose of deciding whether a particular requirement of
this standard is complied with, the final value, observed or calculated,
expressing the result of a measurement, shall be rounded off in
accordance with IS : 2-1960t. The number of significant places retained
in the rounded off value should be the same as that of the specified
value in this standard.
1. SCOPE
1.1 This standard ( Part XII ) covers the method of measurement of
plastering and pointing for buildings and other civil engineering works.
2. GENERAL RULES
2.1 Clubbing of Items-IItems may be clubbed together provided
detailed drawings or specifications or both are prepared for such items
and method of measurement is agreed to be on the basis stated in the
standard.
2.2 Booking of Dimensions-In booking of dimensions, the order
shall be consistent and generally in the sequence of length, breadth or
width and height or depth or thickness.
2.3 Description of Items--Description of each item shall, unless
.otherwise stated, be held to include, wherever necessary, conveyance;
delivery; handling; unloading; storing; necessary scaffolding; protective
cover; cleaning stains from floors, walls, return of packings, etc; and
other incidental changes.
2.4 Dimensions-- All work shall be measured net as executed in the
decimal system, as given below:
a) Dimensions shall be measured to the nearest 0.01 m, and
b) Areas shall be worked out to the nearest 0’01 ma.
4
IS: I200 (Parr XII ) - 1976
3. PLASTERING
3.1 Plaster work shall be classified according to the material used and
each classification shall be measured separately. The following parti-
culars shall be given for each classification:
4 Mix of mortar;
b) Number of coats and thickness of each coat;
4 Nature of surface treatment,
4 Nature of base;
4 Curved work, conical work, spherical work and eliptical work
stating the radius; and
f> Any special treatment of base.
3.1.1 Description shall include arrises, internal ’ rounded angles,
external chamfers and/or rounded angles not exceeding 80 mm in girth.
NOTE - For work exceeding 80 mm girth, scc 3.4.
5
W t 1269 ( Part XII ) - 4976
3.8 D&jnactions
3.8.1 For jambs, soffits, sills, etc; for openings not exceeding 0.5 m2
each in area, for ends of joists, beams, posts, girders, steps, etc, not
exceeding 65 ms each in area, and for openings exceeding 0’5 ma and
not exceeding 3 ma rin each area, deductions and additions shall be made
in the following manner:
a) No deduction shall be made for ends of joists, beams, posts, etc,
and openings not exceeding 0.5 ms each and no addition shall
be made for reveals, jambs, soffits, sills, etc, of these openings
nor for finish to plaster around ends of joists, beams, posts, etc.
b) Deductions for openings exceeding 0.5 m2 but not~exceeding 3 ma
each shall be made as follows and no addition shall be made for
reveals: jambs, soffits, sills, etc, of these openings:
1) When both faces of wall are plastered with same plaster,
deduction shall be made for one face only.
2) When two faces of wall are plastered with different types of
plaster or if one face is plastered and the other pointed,
deduction shall be made from the plaster or pointing on the
side on which width of reveals is less than that on the other
side but no deduction shall be made on the other side. Where
widths of reveals on both faces of wall are equal, deduction
of 50 percent of area of opening on each face shall be made
from areas of plaster and/or pointing as the case may be.
3) -When only one face is plastered and the other face is
not, full deduction shall be made from plaster if width of
reveal on plastered side is less than that on unplastered
side hut if widths of reveal on both sides are equal or
width of reveal on plastered side is more, no deduction shall
be made.
4) When width of door frame is equal to thickness of wall or
is projecting beyond thickness of wall, full deduction for
opening shall be made from each plastered face of the wall.
3.8.2 In case of openings of area above 3 m* each, deduction shall
be made for opening on each face but jambs., soffirs and sills shall be
measured.
NOTE -In calccdating areas of openings, the extra width of rebated reveals, if
any, shall be excluded.
6
IS 81200 ( Part XXI ) - 19%
3.13 Length shall be measured in running metres at the centre .of girth.
Girth shall be measured along curve of moulding.
3.14 Moulded cornices and coves shall be measured in square metres, the
area being arrived at by multiplying length by girth.
3.16.3 Size of laths, their distance apart and the kind of timber shall
be stated in the case of wood lathing.
3.16.4 Connector lathing shall be measured separately.
7
IS: 1200 ( Part XII) - 1976
4. POINTXNG
4.1 Proportions of materials shall be described. Varioustypes of pointing
shall be measured separately. Pointing on different types of walls,
floors, roofs, etc, shall be IrLeasured separately, Type and material of
surface to be pointed shall be described.
4.2 Pointing in single detached joints as for flashings shall be measured
in running metres.
4.3 Pointing brick and tile work with mortars of matching shades shall
be measured separately.
4.4 Pointing shall be measured in square metres.
4.5 Removing pointing by raking or otherwise shall be measured in
square metres.
4.6 Deductions
4.6.1 For jambs, soffits, sills, etc, for openings not exceeding 0.5 mr
each in area; for ends of joists, beams, posts, girders, steps, etc, no:
exceeding 0’5 ma each in area; and for openings exceeding 0.5 ma and
not exceeding 3 ma each, deductions and additions shall be made in the
following manner:
a) No deduction shall be made for ends of joists, beams, posts, etc.
and openings not exceeding 0.5 ms each, and no addition shall
be made for reveals, jambs, soffits, sills, etc, of these openings
nor ~for finish around ends of joists, beams, posts, etc.
b) Deductions for openings exceeding 0.5 m* but not exceeding
3 m2 each shall be made as follows and no addition shall be
made for reveals, j,ambs, s&its, sills, etc, of these ‘openings:
1) When both faces of wall are pointed with the same type of
pointing, deduction shall be made for one face only.
2) When two faces of wall are pointed with different types of
pointing or if one face is. plastered and the other pointed,
deduction shall be made in the plaster or pointing on the side
on which the width of. reveals is less than that on the other
side, but no deduction shall be made from plaster or pointing
on the other side. Where widths of reveals on both faces of
wall are equal, deduction of 50 percent of area of opening
on each face shall be made from areas of plastering and/or
pointing as the case may be.
8
IS:1200( Part XII)- 1976
4) When only one face is pointed and the other face is not
pointed, full deduction shall be made from pointing if width
of reveal on the pointed side is less than that on unpointed
side, but if widths of the reveals on both sides are equal or
width of reveal on pointed side is more, no deduction shall
be made nor any addition shall be made for reveals, jambs,
soffits, sills, etc.
I
4.6.2 In case of openings of area above 3 mz each, deduction shall be
nade for opening on each face but jambs, soffits and sills shall be
measured.
NOTE- In calculating are& of openings, extra width of rebated reveal, if any,
shall be excluded.
'JfRrftzr 1fPICfi
~ ~s:tlol 3tR ~ ~\ifl~1I~ cnrm cnIlWR ~
mTJ 13 1fCR ~ qft ~, ~~, ~-&A:I,< q "W'R
(r/ir:rcrr Tffierur)
Indian Standard
METHODS OF MEASUREMENT OF BUILDING
AND CIVIL ENGINEERING WORKS
PART 13 WHITE WASHING, COLOUR WASHING, DISTEMPERING AND
PAINTING OF BUILDING SURFACES
( Fifth Revision)
Fifth Reprint JULY 2008
(Including Amendment No. I)
© BIS 1994
BUREAU OF INDIAN STANDARDS
MANAK BHAVAN, 9 BAHADUR SHAH ZAFAR MARG
NEW DELHI 110002
March 1994 Price Group 2
IS 1200 ( Part 13 ) : 1994
Indian Standard
METHODS OF MEASUREMENT OF BUILDING
AND CIVIL ENGINEERING WORKS
PART 13 WHITE WASHING. COLOUR WASHING, DISTEMPERING AND
PAINTING OF BUILDING SURFACES
( Fifth Revision)
1 SCOPE 2.6.2 Preparatory work on old treated surfaces
shall be described and included in the main
1.1 This standard ( Part 13 ) covers the methods item.
of measurement of white washing, colour wash-
ing, distempering and painting of building 2.7 Classification
surfaces in civil engineering works.
Various decorative treatments shall be measured
2 GENERAL RULES separately under the various classification as
given below and materials and type of surfaces
2.1 Clubbing of Items to be treated shall be fully described:
Items may be clubbed together provided these a) Whitewash, colour wash, etc;
are on the basis of detailed description of item,
stated in this standard. b) Non-washable distemper;
c) Washable distemper;
2.2 Booking of Dimensions
d) Waterproof paint ( colour/colourless );
In booking of dimensions the order shall be con-
sistent and generally in the sequence of length, e) Chalk whiting to cloth or hessian surface;
breadth or width and height. f) Linseed oil and cement to steel and iron
2.3 Description of Items work: and
g) Cement slurry wash.
Description of each item shall unless otherwise
stated, be held to include, where necessary, con- 2.7.1 Priming and alkali neutralizing treatments,
veyance; delivery; handling; unloading; storing; scrapping of surface, washing surfaces spoilt by
waste; return of packings; necessary scaffolding; smoke soot, removal of oil and grease spots,
protective cover; and cleaning stains from floors, treatment for disinfection with efflorescence,
walls, glass panes, etc. moulds moss, fungi, algae and litchen shall be
measured separately and materials described.
2.4 Bills of Quantities
1.8 Walls, Ceilings, etc
Item of work shall fully describe materials and
workmanship, and accurately represent the work Work on walls, ceilings and sloping roofs shall
to be executed. each be measured separately.
2.9 Old Treated Surfaces
2.5 Number of Coats
Work on old treated surfaces shall be measured
Decorative treatment shall be fully described separately and so described.
stating the number of coats in each case.
3 MEASUREMENT
2.6 Preparatory Work
3.1 All work shall be measured net in square
Preparatory work, such as brooming down, steel metres, the decimal system as executed and as
wirc brushing, scrapping washing and rubbing given below:
down, shall be described and included in the
main item. a) Dimensions shall be measured to the-
nearest 0·01 m, and
2.6.1 Preparatory work on new surfaces and
primary coats, if any, shall be described and b) Areas of individual items shall be worked
included in the main item. out to the nearest 0'01 nl:!.
IS 1200 ( Part 13 ) : 1994
Indian Standard
METHOD OF MEASUREMENT OF
BUILDING AND CIVIL ENGINEERING WORKS
PART 14 GLAZING
( Third Revision)
Fourth Reprint JUNE 2008
(Including Amendment No.1)
© Copyright 1985
BUREAU OF INDIAN STANDARDS
MANAK BHAVAN, 9 BAHADUR SHAH ZAFAR MARG
NEW DELHI 110002
Gr 2 February 1985
IS : 1200 ( Part 14 ) • 1984
I. SCOPE
1.1 This standard ( Part 14 ) covers the method of measurement of glazing
n buildings and civil engineering works.
2. GENERAL RULES
2.1 Clubbing of Items - Items may be clubbed together provided these are
on the basis of the detailed dcsc tion of items stated in this standard.
2.5 Bills ofQu8ntities - The bills of quantities shall fully describe the
4
IS : 1200 ( Part 14 ) - 1984
1.7 Work in wood, metal concrete and the like shall be measured
separately,
a) Front and back putty and sprigged or fixed with glazing pins,
b) Bedded in putty and fixed with beads. and
c) Bedded in rubber or velvet and fixed with beads (wherever
required).
3. i\1~l'HOD OF MEASUREMEN'f
3.4 Hacking-out old broken glass and preparing for new glass shall be
measured in square metres.
J.S Holes drilled in work shall be enumerated stating diameter of the hole.
type and thickness of the glass/sheet and size of the pane.
3.6 Grinding, polishing and rounding off edges of glass or glazing sheet
shall be described and measured in running rnctres.
5
IS : 1200 (Part 15) -1987
(Reaffirmed 2007)
Indian Standard
METHOD OF MEASUREMENT OF
BUILDING AND CIVIL ENGINEERING WORKS
PART 15 PAINTING, POLISHING, VERNISHING, ETC
( Fourth Revision)
Fourth Reprint JUNE 2008
(Including Amendment No. 1)
© Copyright 1987
BUR E AU OF I NDI AN S TA N D A R D
MANAK BHAVAN, 9 BAHADUR SHAH ZAFAR MARG
NEW DELHI 110002
Gr 3 October 1987
IS : 1200 ( Part 15 ) - 1987
0.5 Since various trades are not related to one another, the Committee
decided that each type of trade as given in IS: 1200-1964* be issued
separately as a different part, which will be helpful to specific users in
various trades. This part covering method of measurement of painting,
polishing, varnishing, etc, applicable to building as well as civil engineer-
ing works was, therefore, issued as a second revision in 1968 and third
revision in 1976.
0.6 In the course of use of this standard in the past ten years, suggestions
for improvement of some of the clauses were received. This fourth revision
covers modifications in respect of painting of steel work and inclusion of
painting of flush doors, besides updating the requirement so as to bring it
in line with revisions of relevant Indian Standards.
0.7 For the purpose of deciding whether a particular requirement of this
standard is complied with, the final value, observed or calculated, expres-
sing the result of a test or analysis, shall be rounded off in accordance with
IS : 2-1960t. The number of significant places retained in the rounded oIT
value should be the same as that of the specified value in this standard.
1. SCOPE
1.1 This standard (Part 15 ) covers the method of measurement of paint-
ing, polishing, varnishing, etc, in buildings and civil engineering works.
NOTE - Method of measurement of painting of building surfaces are covered in
IS : 1200 ( Part 13 ).
2. GENERAL RULES
2.1 Clubbing of Items -- Items may be clubbed together provided these are
on the basis of detailed description of items stated in this standard.
4
IS : 1200 ( Part 15 ) - 1987
2.4 Measurement - All work shall be measured net in the decimal system,
as executed and as given below:
a) Dimensions shall be measured to the nearest 0-01 m, and
b) Areas shall be worked out to the nearest 0-01 m 2 •
2.5 Bill of Quantities -- Items of works shall fully describe materials and
truly represent the work to be executed.
2.6 Preparatory work, such as knotting, priming, stopping and rubbing
down, burning off or stripping shall be described and the number of coats
shall be stated, Work on surfaces previously painted shall be measured
separately.
2.6.1 Where: special colours or other special finishes are required, it shall
be so stated.
2.7 Work on different surfaces shall be measured separately classified
as follows and the preparatory work shall be described and included in the
items:
a) Non-absorbent surfaces, such as on steel and other metals; and
b) Semi-absorbent surfaces, such as wood, fibre-board.
3. MEASUREMENT OF PAINTING
3.1 Painting, except where otherwise stated, shall be measured in square
metres.
3.1.1 No deduction shall be made for openings not exceeding 0'5 m 2
each, and no addition shall be made for painting to beading, moulding,
edges, jambs, soffits, sills, etc, of such openings.
3.2 In case of fabricated structural steel and iron work, priming coat of
paint shall be included with fabrication. Subsequent coats of paint shall
be measured separately on the basis of weight of steel work and iron work
or in square metres. The weight/area of steel sheet, plate and strip; rolled
steel sections, steel rods and steel strips forged steel, steel castings and steel
tubes shall be taken from relevant Indian standards. If rivet heads, bolt heads
( with or without washers), nuts ( with or without washers and including
projecting portion of shank) are picked out in a tint different from that of
adjacent work, these shall be enumerated and measured as extra over.
NOTE - No addition shall be made to the weight calculated for the purpose of
measurement of steel and iron work for the paint applied either in shop or at site.
3.3 Painting work up to 10 cm in width or in girth and not in conjunction
with similar painted work shall be measured in running metres and shall
include cutting to line where so required.
5
IS : 1200 ( Part 15 ) - 1987
3.3.1 Cutting to line, where not included in the item, shall be measured
separately in running metres.
3.4 Small articles up to 0·1 m 2 of painted surface, where not in conjunction
with similar painted work, shall be enumerated.
3.5 Painting on different types of work shall be kept separate and surfaces
to be painted shall be described. It shall be stated whether measurements
are flat or girthed. Alternatively, different surfaces may be grouped into
one general item, areas of uneven surfaces being converted into equivalent
plain areas in accordance with Table I.
3.6 Corrugated sheet surfaces and Nainital pattern roof surfaces shalt be
included with plain surfaces after increasing their areas by the following
percentages:
a) Corrugated sheets 14 percent
b) Nainital pattern roof ( plain sheets with rolls) 10 percent
c) Nainital pattern roof with corrugated sheets 25 percent
d) Asbestos cement sheets, corrugated 20 percent
e) Asbestos cement sheets, semi-corrugated 10 percent
3.7 Painting on eaves-gutters, rain-water pipes, soil and ventilating pipes
and steel poles shall be measured in running metres stating the size or
girth. Fittings, such as bends, shoes, branches, heads, etc, shall be included
in the length.
3.8 Painting on small articles, such as gate and turn straps, metal ceiling/
roses, metal switch-blocks, heads and nuts or bolts, articles of builder's
hardware and the like when picked out in different tint or not in conjunc..
tion with similar painted work shall be enumerated.
3.9 Flag staffs, chimneys, aerial masts ( not latticed ), water tanks, flood
light towers, over-head electric masts, spires and the like requiring special
scaffolding shall be measured separately stating the size, height and average
girth.
3.10 Painting in repair work up to 1 m2 shall be enumerated in the follow-
ing categories:
a) Not exceeding 0'1 m2 ,
b) Exceeding 0·1 m2 and Dot exceeding 0·5 m2, and
c) Exceeding 0·5 m2 and not exceeding 1 m2 •
NOTE - Areas exceedil1l 1 m' shall be measUred as in 2.~.
6
IS : 1200 ( Part 15 ) • 1987
7
IS : 1200 ( Part IS ) - 1987
8
IS : 1200 ( Part 15 ) - 1987
4. VARNISHING
4.1 Application of sizmg, staining and varnishing on wood-work shall be
measured in accordance with the work provisions contained in 3.
5. POLISHING
5.1 Polishing on wood-work shall be described ali including all preparatory
work and bodying.. in and shall be measured in square metres in accordance
with the provisions contained in 3. Alternatively, articles shall be described
and enumerated.
6. PRESER\TATIVE TREATMENT
6.1 Surface application of wood preservatives shall be measured in square
metres irrespective of girth or size, and the provisions contained in 3 shall
be followed.
7. TARRING
7.1 Tarring shall be measured as for painting in accordance with the
provisions contained in 3.
8.1 Letters, figures and similar items shall be enumerated stating height
and form or style, namely, block, italics, etc; stops, commas, hyphens and
the like shall be deemed to be included in the item.
9
IS : 1200 ( Part XVI ) - 1979
Reaffirmed 1992
((Reaffirmed 1
2002)
Indian Standard
METHODS OF MEASUREMENT OF
BUILDING AND CIVIL ENGINEERING WORKS
PART XVI LAYING OF WATER AND SEWER LINES
INCLUDING APPURTENANT ITEMS
( Third Revision )
FourthReprintFEBRUARY 1998
8 Copyright 1979
Gr 2 November 1979
.
IS: 1200 (&rt XVI)- 1979
0.5 sCt&e measurement of each type of trade is not related to one another,
and &is&,to facilitate the second revision of IS: 1200-1964*, the Sectional
Committee decided that each type of trade as given in IS : 1200-1964* be
iWt%l separately as different parts. This will also be helpful to the specific
~rs in various trades in using the standard. This part covering the
method of measurement of laying of water and sewer lines including
appurtenant items applicable to building as well as civil engineering works
was therefore issued as a second revision 1969. The third revision has been
taken up so as to keep the provisions conform to the latest practice.
0.6 For the purpose of deciding whether a particular requirement of this
standard is complied with, the final value, observed or calculated, expressing
the result of the measurement, shall be rounded off in accordance with
IS : 2-1960t. The number of significant places retained in the rounded off
value should be the same as that of the specified value in this standard.
1: SCOPE
1.1 This standard ( Part XVI ) covers the method of measurement of laying
of water and sewer lines; and other appurtenant items of work, involved in
the execution of water suppiy and sewerage projects.
N~TB - The method of measurement of water supply, plumbing and drains is
covered in IS:1200 (Part X1X)-1970$.
2. GENERAL RULES
2.1 Clubbing of Items - Items may be clubbed together, provided these are
on the basis of detailed description of items as stated in the standard.
2.2 Booking of Dimensions-In booking dimensions, the order shall be
consistent in the sequence of length, breadth or width, and height or depth
or thickness.
2.3 Description of Items -The description of each item shall, unless
otherwise stated, be held to include wherever necessary conveyance and
delivery, handling, unloading, storing, fabrication, hoisting, all labour for
finishing to the required shape and size, setting, fitting and fixing in
position, straight cutting and waste, and other incidental operations.
2.4 Dimensions-All work shall be measured net as fixed, to the nearest
0.01 metre, unless otherwise stated hereinafter.
2.5 Bills of Quantities -Items of work shall fully describe the materials
and workmanship, and accurately represent the work to be executed.
*Method of measurement of building works ( revised ).
tRules for rounding off numerical values ( revised ).
fMethod of measurement of building works: Part XIX Water supply, Iplumbing,
drains and sanitary fittings.
4
IS:1200 (Part XVI)-1979
3.2 Suspended Dips and vertical pipes shall be so described and the
supports and other fixing arrangement ( see 3.4.2 ) measured separately.
3.4.1 The valve cistern, public fountain platforms, fire hydrants, etc, shall
be fully described and enumerated.
4.1 Sewer lines shall be classified according to their diameter, length of each
pipe, kind of material, the quality of pipe and the method of jointing, and
shall be measured in running metres inclusive of all joints. The measure-
n)ent shall be taken along the central line of the sewers and fittings or
specials. All fittings or specials shall be enumerated separately as ‘extra-
_..__, rL_
“VW . ^__.^
_^ LUrrUlg
Ulc DCWCIS. fi..*c:.., ilL1U
,..A ,“‘L’L”‘&
:,.:..r:,, .l., na..,arn .a
LUGDGWGIJ “..,.I. Urr,rrl;J
L” JUtill fit,:,,” “1
,._ n,,&-.:n,r
JpGti,olJ
shall be deemed to be included with the item of fittings or specials.
6
IS : 1200 (Part XVI)- 1979
7
1s: a200( Put XVIII ) - 1974
( Reaffhmed
(Reaffirmed 1992)
2002)
Indian Standard
METHOD OF MEASUREMENT OF BUILDING
AND CIVIL ENGINEERING WORKS
PART XVIII DEMOLITION AND DISMANTLING
Third Revision )
UDC 69.003.12:69.059.62
related to one another, the Sectional Committee decided that each type of
trade as given in IS : 1200-1964* be issued in different parts which will be
helpful to specific users in various trades. This part covering method of
measurement of demolition and dismantling applicable to building as well as
civil engineering works was therefore issued as second revision in 1971.
The third revrston incorporates all the changes decided by the Sectional
Committee in the past 3 years including the provision of dismantling of
masonry and concrete met during excavation.
1. SCOPE
1.1 This standard ( Part XVIII) covers the method of measurement of
demolition and dismantling in buildings and civil engineering works.
NOTE - For the purpose of this standard the term ‘ dismantling ’ implies care_
fully taking up or down and removing without damage. The articles rhPll be
passed by hand, whrre necessary, and lowered to the ground, and not thrown, and
where these are fixed by nails, screws, bolts, etc, theseshall be taken out with proper
tools and not by tearing or ripping off and the term ‘ demolition ’ implies trrking up
or down, or-breaking up.
2. GENERAL RULES
2.3 Measurements
2.3.1 Measurement of all work, except hidden work, shall be taken
before demolition or dismantling and no allowance for increase. in bulk shall
be made.
2.3.2 All work shall be measured net in the decimal system as fixed in its
place, as given in 2.3.2.1 to 2.3.2.3.
*Method of measurement of building works (jirsf rrzrision).
tRules for rounding off numerical values ( revised ) .
4
IS : 1200( Part XVIII ) - 1974
2.7 Rtcaudonm
2.7.1 Attention shall be drawn to any neces&y precautions to be taken
for the protection of the public and the owner’s property,
2,X2 Temporary shoring for the safety of portions not required to be
pulled’down or of adjoining property, and temporary enclosures or partitions
shall be included in the main item. 1
5
IS : 1200( Part XVIII ) - 1974
The distance for removal shall be measured over the shortest pm&cable
route and not necessarily the route actually taken.
2.9.1 Distances exceeding 100 m and up to 1 km shall be measured in
units of 100 m and those exceeding 1 km in units of 500 m.
2.10 Works laid dry and with mortar shall be measured
type of mortar shall be stated. Framed and unfram
measured separately.
2.U Disconnccting/MaintainIng of Services-Attention shall be
directed to any necessary diinnecting or maintaining of services, whether
temporary or permanent; and an item shall be provided fm making good if
required.
3. WALLS AND PIERS
3.1 Walls, independent piers, columns and their footing and foundation of
brick, stone or concrete shall .be described and measured in cubic metrea.
All copings, corbels, cornices and other projections shall be included with
the wall measurements.
3.1.1 In measuring the thickness of plastered walls, the thickness of the
plaster shall be excluded.
3.2 Ashlar face stones, dressed stone work, precast concrete articles, etc, if
required to be taken down in tact, shall be so stated and measured separately
in cubic metres.
3.3 Honeycomb work and hollow block walling of bricks, stone or eoncrete
shall be measured as solid.
3.4 Cleaning of bricks and stacking them for measurement, lncludi all
extra handling and removal and disposal of rubbish as stated, shz 1 be
enumerated in thousands of cleaned bricks.
3.5 Cleaning of stone obtained from demolished/dismantled stone masonry
of any description including ashlar facing, dressed stonework, stone slabs or
flagging and precast concrete blocks including all extra handling and dispo-
sal of rubbish as stated shall be measured in cubic metres of cleaned at&e.
5. ROOFS
5.1 Roof coverings generally including t&tens, boarding mats, bamboo
JAFFARI, other subsidiary support, shaU be measured in squap n,etres
stating the thickness and size or gauge. Ridges, hips and vallevb shall be
girthed and included with the roof area. C:orru,:atcd ahd semicorrugated
s@&ces shall be measured flat and not girthed.
5.2 Mud on roofs shall be measured in cubic metros.
5.3 Lead sheets in roofs shall be measured in kilograms and hips, valleys,
ilashings, linings to gutters, etc, shall be included in this weight.
5.1 Supporting members, s*_uzhas rafters, purlins, beams, joists and trusses,
. of wood, shall be measured in cubic metres and where of steel or iron
where
sectmu, in kilograms. If the span exceeds 10 m, it shall be so stated.
6. CEILINGS
6.1Stripping
of ceiling shall be measured in square metres and described.
62 Sfipporting joists,beams, etc, shall be measured in cubic metres or in
kilograms aa specified in 5.4.
10.WOODWORK
18.1 Ballies shall be measured in running metres.
lo*2 All other woodwork under 40 cm2 in section shall be measured in
running metres and average 40 cm2 and over in cubic mrires.
Is: 1200(Pmt XVIII)- 1914
15. GLAZING
15.1 Taking out any description of serviceable glass, except polished plate,
from old sashes, skylights, etc (any thickness, weight or size ) raking out
old putty, etc, shall be measured in square metres.
15.2 Irregular or circular plans shall be measured as rectangular or square.
8
__~.___.-.-.. -~..
ISr1200(PartXVIII)-W4
16.6 Ventilating shafts, guiley traps, flushing cisterns and other appurtenant
items ofwork shall be enumerated.
9
IS:12oo(P8rtxl2L)-l981
(Reatllmd 2002)
(Reaffirmed 1997)
Indian Sthiard
METHOD OF
MEASURRMBNT ‘OF BUILDING
AND CIVIL ENGINEERING WORKS
FART XIX WATER SUPPLY, PLUMBING AND DBAINS
( Third Revision )
Fourth Reprint MARCH 1999
UDC ~9.003.12:696.11/.14
1. SCOPE
1.1 This standard ( Part XIX ) covers the method of measurement of
water supply, plumbing and drains in buildings and civil engineering
works.
NATE - The method of measurement of laying of water and sewer lines, etc, is
covered in IS : 1200 ( Part XVI ) - 1979$.
2. GENERAL RULES
4
IS : 1200 ( Part XIX ) - 1em
2.4 Dimensions - All work shall #be tieasurcd net as fixed, to, the
nearest 0’01 metre unless otherwise stated hereinafter.
2.6.1 The levels of high and low water tides, where occurring, shall be
stated.
2.6.2 Where special pumping due to causes other than rains and
subsoil water is resorted to, the same shall be measured separately,
unless otherwise stated, in kilolitres of water against a separate specific
provision(s) made for this purpose [ see 2.7 of IS : 1200 ( Part I )-
1974* J.
2.7 Measurement in Stages - Work shall be mewed under the
following categories in convenient stages stating the height or depth:
a) Below ground/datum line, and
b) Above ground/datum line.
NOTE - The ground/datum line shall be specified in each case.
3. GENERAL
3.1 All pipes and fittings shall be classified according to their nominal
diameter, kind of material, quality and the method of jointing and shall
be measured in running metres unless otherwise specified. The method
of laying, jointing and fixing shall be fully described.
NOTE - The nominal diameter is as defined in relevant Indian Standard.
3.1.1 The item shall include all cutting and waste of pipes and also
cutting threads where necessary.
3.2 In the case of fittings of unequal diameter, it shall be designated
by largest diameter.
-
*Method of measurement of building and civil engineering works: Part 1 Earthwork
( third ruuirion ).
5
f
LL-.._......__ _ __
3.3 ,The testing of water supply, drains and plumbing shall be included
inthe description of the item.
,3.4 Lead caulked joints shall be enumerated separately.
3.5 Pipes laid or fixed in ducts, chases, trenches, embedded in floor,
fixed to walls, ceilings, etc, with supports shall be measured separately.
3.6 The method of measurement for excavation of trenches for laying
pipelines and other allied works and refilling of the trenches, etc, shall be
as per IS : 1200 ( Part I )-1974*.
3.7 Concrete beds, haunchings and coverings, including any form-
work required, shall be described and measured in running metres
stating size of the pipe, dimensions and mix of concrete.
3.8 Cutting through walls, floors, etc, and making good shall be included
with the item. This shall, however, not include concealed pipe work in
which case the cutting of chase and making good shall be measured
separately in running metres.
3.3 Lengths of pipes not exceedin Q one metre, other than running
lengths, shall be measured separately in running metres and described as
in short length.
4. WATER SUPPLY
4.8 Standard fittings like elbows, bends, tees, connectors, unions,
diminishing sockets shall be included along with the pipes.
4.1 Caps, callers, plugs, stopped ends and similar items of the pipe shall
bc described and enumerated.
4.2 Sluice valves, hydrants, stop-cocks, covers, surface boxes and water
meters shall be described and enumerated .and shall be measured
separately according to the diameter. The jointing to pipe on either
side shall be described.
4.3 The connection to the water main shall be described and enume-
rated.
4.4 Boilers, Cisterns and Cylinders - Boilers, cisterns and cylinders
shall be enumerated stating the type, size, location, method of fixing,
working and test pressure and the type and size of the connections for
pipes. Perforations for connections shall be enumerated.
4.4.1 Insulahg Coverings to Boilers, Pipes, etc - Insulating coverings
shall be fully described and measured in square metres in the case of
6
L. _.. __.. . .-.
boilers, cylinders and tanks and in running .metres in the case of pipes
stating the diameter. No deduction shall be made for manholes, hands,
holes, pipes, etc, passing through insulation, nor shall any extra be
measured for finishing insulations around such openings.
4.4.2 Insl,llation to bends, elbows, tees, valves and the like shall be
enumerated as extra over.
5. PLUMBING
5.1 Plumber’s Work - Locks, taps, valves, pillar-cock, stop-cock, ball
valves, caps and linings, also cleaning eyes with screw caps, ferrules,
thimbles, unions, waste washers, perforated gratings and the like shall be
described and enumerated. The joints and thr fixing shall also be
described and included in the item.
5.2 Bends, elbows, tees, branches, inspection or access doors, swan necks,
enlarged sockets, etc, for soil waste and bent pipes shall be enumerated
as extra over.
5.2.1 Wire guards and ventilating cowls over tops of pipes shall be
described and enumerated and measured separately according to the bore
of the pipe.
5.3.1 Standard fittings like elbows, bends, tees, connectors, unions and
diminishing sockets shall be enumerated.
5.4 Traps shall be described and enumerated. Joints at both ends shall
be included in the item.
7
“_.__.
“-,-- __._- __._^...
.-_.
r
I_
6. DRAIN
6.1 Drain Pipes -The pipes shall be classified according to their
nominal diameter, the quality of pipe, kind of material and the method
of jointing and shall be measured in running metres, inclusive of all
joints. The measurement shall be taken along the central line of the
pipes and fittings or specials. All fittings or specials shall be enumerated
separately as extra over the pipes Cutting and jointing the pipes to
such fittings or specials shall be deemed to be included with the item of
fittings or specials.
6.1.1 Alternatively,- the pipes shall be classified according to the
nominal diameter, quality, kind of material and shall be measured in
running metres. The measurement shall be taken along the central line
of the pipes and in between the fittings or specials. All joints, fittings,
or specials shall be described and enumerated separately. Cutting of
pipes for jointing to such fittings or specials shall be deemed to be
included with the item of fitting or specials.
6.2 The manholes and inspection chambers shall be measured in detail
as per relevant parts of this Indian Standard.
6.2.1 Alternatively, the manholes and inspection chambers shall be
described and enumerated. They shall be classified into different
groups depending upon the depth, such as up to half metre depth, half to
one, qne to two, two to three and so on. The depth of the manhole
shall be the distance between the top of the manhole cover and the invert
of the main drain.
___~. .__ _. _-
Indian Standard
METHOD OF
MEASUREMENT OF BUILDING AND
CIVIL ENGINEERING WORKS
PART XX LAYING OF GAS AND OIL PIPE LINES
( Third Revision)
UDC 69.003.12:696.2:621.644
@ Copyri,ht 1981
1. SCOPE
1.1 This standard ( Part XX ), covers the method of measurement of
laying of gas and oil pipelines.
2. GENERAL RULES
2.1 Clubbing of Items - Items may be clubbed together, provided these
are on the basis of detailed description of items as stated in the standard.
2.2 Booking of Dimensions - In booking dimensions, the order shall
be consistent and generally in the sequence of length, breadth or width
and height or depth or thickness.
2.3 Description of Items - The description of each item shall, unless
otherwise stated, be held to include, where necessary, conveyance and
delivery, handling, loading, storing, fabrication, hoisting, all labour for
finishing to required shape and size, setting, fitting and fixing in position,
straight cutting and waste, return of packings and other incidental
operations.
2.4 Dimensions - All work shall be measured net as fixed to the
nearest 0-01 metre, unless otherwise stated hereinafter.
2.5 Bills of Quantities - Items of work shall fully describe the
materials and workmanship, and accurately represent the work to be
executed.
*Method of measurement of building and civil engineering works ( rruirrd).
tRules for rounding off numerical values ( rnirrd ).
4
IS : 1200 ( Part XX ) - 1981
2.6.1 The levels of high and low water tides, where occurring, shall
be stated.
2.6.2 Where special pumping due to causes other than rains and sub-
soil water is resorted to, the same shall be measured separately, unless
otherwise stated, in kilolitres of water ao;ainst a separate specific pro-
vision(s) made for this purpose [see 2.7 of IS : I200 ( Part I ) l974* 1.
2.7 Measurement in Stages - Work shall he measured under the
following categories in convenient stages stating the height or depth:
a) Below ground/datum line, and
b) Above ground/datum line.
NOTE - Tlrc=ground/datum line shall be sprcifird in each CHSC.
3.1 Gas and oil pipelines shall be classified according to their diameter,
length of each pipe, kind of material, the quality of pipe and the method
of joining and shall be measured in running metres inclusive of all
joints. The measurement shall be taken along the central line of the
pipes and fittings or specials. All fittings or specials shall be enumerated
separately as ‘extra over’ the pipes. Cutting and jointing the pipes to
such fittings or specials shall be deemed to be included with the item of
fittings or specials.
3.1.1 Alternatively, gas and oil pipes shall be classified according to
their diameter, kind of material, quality of the pipe and shall be
measured in running metres. The measurement shall be taken along the
central line of the pipes and in between the fittings or specials. All
joints, fittings or specials shall be fully described and enumerated se-
parately. Cutting of pipes for jointing to such fittings or specials shall
be deemed to be included with the item of fitting or specials.
3.2 Components for supporting pipes, like hangers, chairs, pillars, etc,
shall be fully described and enumerated separately.
5
IS : 1200 ( Part XX ) - 1981
3.3 Pipes laid or fixed in ducts, trenches and chases shall be so described
in each case.
3.4 Pipes embedded in floor screed shall be so described.
3.5 Excavation of Trenches - Method of measurement for excavation
of trenches for laying pipelines and other allied works and refilling the
trenches, etc, shall be as given in IS : 1200 ( Part I )-1974*.
3.6 Concrete beds, haunchings and coverings, including any formwork
required, shall be described and measured in running metres stating size
of the pipe, dimensions and mix of concrete.
3.7 Heat Treatment - Heat treatment shall be fully described .and
enumerated separately unless otherwise stated.
3.8 Tests - Hydrostatic tests and radiographic tests shall be separately
described and measured in running metrcs for hydrostatic tests and per
centimctre length for various sixes of pipes for radiographic tests.
3.9 Pigging, Pickling and Purging - Pigging, pickling and purging
with inlet gases shall be separately enumerated.
3.10 Insulation
3.10.1 All insulation to pipe work shall be fully described and measur-
ed inrunning metres, unless otherwise stated, stating the type and size
of the pipes. The measurement shall be taken along the central line of
the pipes and fittings or specials. No separate measurement shall be made
for bevelling of insulation at ends flanges, etc.
3.10.2 Insulation around valves, and other ancillaries and to pipe
fittings shall be fully described and enumerated separately, as ‘exfru
over’ the insulation to pipe work.
( Second Revision)
ThJrd Rf'prrnt (J( rr}HEH I',H7
\ rfit li I P I rn ~
I I '\ "1 ( n d HH t1! 01. f
Gr J
d I 1200 ( Part XXI ) - 1973
0.5.1 This part coven method of measurement of woodwork and
joinery; applicable to buildings as \vel.l as to civil cnJrinceriol works.
0.6 In reporting the result of a measurement made in accordance with
this standard, jf the final value, observed or calculated, is to be rounded
off, it shall be done in accordance with IS : 2·1960.
I. SCOPE
1.1 This standard (Part XXI >- covers the method of measurement or
woodwork and joinery in buildings and civil engineering works.
2. GENERAL RULES
4
II a 1200( Pan XXI ). 1171
2.1 . . . • 1 Q,aaadd.. - Bills or quantities shall fully describe materiaIJ
aDd workmanJhip, and accurately represent the work to be executed.
s. GENERAL
'.1 The description and type or the wood to be. used shall be stated; eaeh
kind of wood shall be measured separately.
3.2 The work shall be measured in cubic metres unless otherwise stated
hereinafter.
3.3 The \\'ork shall be measured separately for • fixed • and 'framed and
fixed'. 'Framed and fixed' work shall be that which involve mortice and
tenon or dove-tailed joints.
S.4 All work shan include nails. \Vork ' secret fixed " 'fixed with screws'
or fixed with screws and cups' or 'Jix~d with bolts and washen • shan be
C
measured separately and shall include ahootinl the jointt to proper aplay•
...2.5 In cale of boarded floor. the width of board., the method of
jointing and nailinl shall be described; if 800... are to be travened or
fiDilbed for polilbiu,. it ahall be 10 ltated.
t.2.6 In cue of weather boardin,. width and thicmeu or boards and
lap ,ball be ltated. In cue of feathereedpcl boardl..,. thickDea mall be
the maximum thicJmeu.
4.2.1.1 All chamfering. rebatiD" etc, to edge. of weather boardins
.ball be dacribed.
t.I Batten work shall be described and meuured in rUDDing me~rCl.
4.4 Trellis work shaD be meuured in square meuea 1tatins lize oflalb,
and .pacing.
t.4.1 ODe-way and two-way trcllia work .hall each be meuured
aeparately.
4.4.2 Posts. rail., stiles, brace. and other lupporta for trellis work anel
for door. and windoWi frame. in trellis work sball be meuured aeparatel,.
4.t.3 Doon and wiDcIowa formed in trellia work ,baD be meuurecl
aJongwith trcllia work.
• .5 . . ., .... I ~ -ShaM, and .truttiD, timben (use
and wute ) shaD be measuredlD cubic metra and Ihall mdude neceuary
1
11,1_ ( Part XXI ) .1'73
bolts. wedges, dOl-lpikes , nails, putting together, erecting, maintaining
in position for the required period, striking an'd removal.
4•• Ball)' Work - Bally work shall be measured in running metres stating
mean diameter.
NOTa- Mean diameter shall be the aver..e or diameters at the end••
4.7 Stalrca••• - Work to staircases shall be measured under a leparate
heading and measured in detail as in 4.7.1 to 4.7.1'. Where detailed
working drawings are available ltaircas~. may be measured as an omnibu.
item fully described stating the tread area in square metres.
~.7.1 Landings including bearer, .hall be measured as for boarded
floon.
4.7.2 Treads and risers shall be measured in square metres, the area
being obtained by multiplying the lengeh of tread by the exposed width
or tread plus the rise from step to step. Winders and riser shall be
included with the item.
~.7.3 Housing of treads, risers, ftiers and winders shall be included in
the descril!tion, ali also all labours, such as cross-tonguing, croos-grooving,
erOl.·reba~ng) framing and gluing, wedging and blocking.
4.7.1 Cut strings shall be measured a! for outer Itrinp and shall
inoJude cutting of upper edge for treads.
4.7.1 Ramped, circular and wreathed portion shall be measured
aeparately and 10 deseribed•
.a.7.11 Hand-raill shan be measured in running metres along top centre
line stating estrcme section of straight portions and whether rounde. or
moulded.
4.7.11 Circular level, ramped and wreathed hand-rails shall be meuur-
ed aeparatcly. Quadrants. short ramps and wreaths and scroll ends shall
be enumerated.
8
Ilal_(Put XXI).I'7S
4.1.12 Mitres, housing joints and hand-railscrewa arid dowell at jUIl~
tion of circular part with strai.ht one shall be enumerated.
4.7.13 Balusters .han be deacribed and enumerated ltaun. . . aacl
shall include framinp or houliDi at end•.
4.7.14 Newell shall be described and measured in runnin, metrea ltat.
in, the section, and if turned, the length of turniJll shall be ltated.
4.7.15 Sunk panels and mouldings planted-on houaecl·ja to neweJa IhaII
be ltated.
4.7.18 Newel caps and pendants .hall be described and enumerated.
4.1 ea.ee1 Fram.. 01 Vertical SIkIia, WI"'. . . - Cued frame. 01
vertical lliding windows shall be described and Iheuured in runnlq
metres J a1on, t~e outer' edge•
... IIdrtIap, CorDIe.., Plctan .act Dado aau.. etc - Sartin...
cornices. picture rails, dado rails and similar mauldin.. m.ll be dacribecl
includin. method of fixing and measured in runnio. metra.
t.11 Trap Doo... - Trap doora .hall be described and enumerated -
• extra--over' relevant item.
4.11 Pelmet boxes ,hall be described and measured in runninl metres
along the aides and r~ce planking.
4.12· T.ra_ WOI'k- Turned work shall be measured in rwmio. meuea
Itating the Jirth.
4.13 . . . .ri.. - The fallowinl typel or work shall be fully described and
enumerated:
a) Wardrobel and cupboards;
b) Draining boards;
c) Plate racks;
d) Curtain brackets;
e) Towel rails;
f) Toilet fixtures;
I) Back board. to cisterna; and
h) Small fittinp, such u door and window It• •
t
( Reaffirmed 2002 )
IS : 1200 ( Part XXII ) - 1982
1. SCOPE
1.1 This standard ( Part XXII ) covers the method of measurement of
materials normally used in buildings and civil engineering works.
2. GENERAL
2.1 Description of Item - Description of each item shall, unless other-
wise stated, include, wherever necessary, conveyance and delivery,
,~__J,?__ .__,__J:__ _&.._I__ _A^
nanaung, unwaaulg, JLOI-~II~,
C;CI;
4
IS t 1200 ( Part Xxi1 ) - 1982
Boards
Plywood, etc In rns, statingtype and thickness
Blocks (Building, Clay, Cement. Stone, etc) Enumerated stating size, type and grade
if any
Distemper In kg
Glass Sheets ( Plain/Pin Head/Frosted/ Wired/ In ms, stating type, thickness and size
Splinter proof)
Marble Dust In kg
J:
IS : 1200 ( Part XXII ) - 1982
SteCl
Mild steel sheets In tonnes, stating size and thickness
Mild steel expanded metal In mJ and described
Wire fabric/chain fabric In ma and described
Hoop iron/boits/rivets/barsjstructural In kg or tonnes and described
sections/rails/mild steel pipes
stone
Boundary stone/kilometre stone Enumerated, stating size and type
Kerb stone Enumerated, staling size
Fioor stone slabs In rn2 and described
Soling stone, boulders, rubble In rns, after making a deduction of
i5 percent from gross stack measure-
ments, stating nominal size and type
Sanitary Fiftings
Cisterns / clamps / cocks / ferrules,‘foot- Enumerated and described
rests / gratings / hydrants Itraps/bath
tubsjurinais ivaivesjwash basins/‘WC
pans/showers/towel rails/bidets
Tiles Enumerated, stating type and size
Timber
Blocks/baulks Enumerated, stating type and size
Ballies Enumerated, specifying diameter and
described ( diameter shall be measured
at !*5 m from the thick end )
( Confinued )
1s t 1200 ( Part SXrl ) - 1982
Wall Tiles/False Ceiling Tilts/Roofing Tiles Enumerated, statirlg type and size
*
IS:l2OO(Part23)-1988
(Reaffirmed 2002)
Indian Standard
METHOD OF
MEASUREMENT OF BUILDING AND
CIVIL ENGINEERING WORKS
PART 23 PILING
( Fourth Revision)
Second Reprint DECEMBER 1996
UDC 69.003.12:624.155
@ Copyright 1989
*_
ISr12oO(Part23)-1908
Indian Standard
METHOD OF
MEASUREMENT OF BUILDING AND
CIVIL ENGINEERING WORKS
PART 23 PILING
( Fourth Revision )
0. FOREWORD
0.1 This Indian Standard (Part 23 ) ( Fourth one another, the Sectional Committee during
Revision) was adopted by the Bureau of Indian its second revision decided that each trade as
Standards on 16 November 1988, after the given in IS : 1200-1964* shall be issued separa-
draft finalized by the Method of Measurement tely as a different part as it would be helpful
of Works of Civil Engineering ( Excluding River to users in using the specific standard. This
Valley Projects ) Sectional Committee had part covers the method of measurement of
been approved by the Civil Engineering Division piling work applicable to buildings as well as
Council. to civil engineering works was published sepa-
rately in the year 1971 and further revised in
0.2 Measurement occupies a very important 1977. In view of the large number of comments
place in the planning and execution of any civil received on this part, the Sectional Committee
engineering work from the time of first estimates decided to issue a fourth revision incorporating
to the final completion and settlement of pay- the changes to keep the latest method as being
ments of project. Methods followed for measure- followed by most of the organizations. The
ment are not uniform and considerable differ- principal modifications are in respect of rein-
ences exist between practices followed by forced cement concrete sheet, timber sheet, and
different construction agencies and also between bored piles.
various Central and State Government Depart-
ments. While it is recognized that each system 0.4 For the purpose of deciding whether a
of measurement has to be specifically related to particular requirement. of this standard is
administrative and financial organizations complied with,’ the final value, observed or
within a department responsible for the work, a calculated, expressing the result of a measure-
unification of the various systems at technical ment, shall be rounded off in accordance with
level has been accepted as very desirable IS : 2-1960*. The number of significant places
specially as it permits a wider range of operation retained in the rounded off value should be the
for civil engineering contractors and eliminates same as that of the specified valud in this
ambiguities and misunderstandings arising out standard.
of inadequate understanding of the various
systems followed. *Method of measurement of building and civil
engineering works (jrst revision 1.
0.3 Since different trades are not related to iRules for rounding off numerical values ( rcvisad ).
1
place as given below: 3.2 The cement concrete in piles shall be
measured in cubic metres, arrived at by multi-
a) Linear dimensions shall be measured to plying the cross-sectional area of the pile by the
the nearest 0’01 m, length of the pile as cast from the head of the
pile to the tip of shoes.
b) Areas shall be worked out to the nearest
0’01 ms, and
3.3 NO deduction shall be made for chamfers,
C) Cubic contents shall be worked to the tapered points or the volume of reinforcement
nearest 0’01 ms. or holes for lifting piles.
2.5 Work to be Measured Separately - The 3.4 The formwork, links and sleeves shall be
situations, such as, in/under water, liquid mud, included in the description of the item.
marshy land, tidal condition, etc, in which work
is to be executed shall be stated. 3.5 The reinforcement shall be measured sepa-
rately [see IS : 1200 (Part 8)-1975* 1.
2.5.1 The level of high and low water tides
where occurring, shall be stated. 3.6 The sho:ts for each size shall be enumerated
separately, stating the approximate weight.
2.6 Bills of Quantities - The bills of quan-
tities shall fully describe the materials and 3.7 Driving piles to a given level and redriving
workmanship, and accurately represent the of lengthened piles shall be measured in running
work to be executed. metres, separate measurements being made for
piles of 5 m length and less and subsequently
2.7 A general description of the nature of site for every 1 m length range. The driving of
shall be stated. piles shall be measured from the tip of the
shoes up to the level as shown in the drawings.
2.8, The available information as to the strata The raker piles shall be measured along the
through which the piles are to be driven shall axis of the pile.
be stated or reference showing records of bores
be given. 3.8 The measurement of handling, transporta-
tion and pitching of piles shall be enumerated
2.9 If piles are to be provided from any level for each occasion.
other than the ground level, it shall be stated.
If the piling frame is to be lowered or raised, 3.9 For stripping the heads of the piles, the
the exact height and nature of working shall length to be stripped shall be stated and
be described, separate items shall be provided measured per linear metre.
for driving raker/in groups/isolated/lengthened/
trial piles. 3.10 Stripping off the head of the piles for bond
length shall be enumerated.
2.10 Items shall include any extra excavation
filling and/or ramming required at the time of 3.11 When concrete piles are lengthened in
construction for the movement of piling frame position, after they have been lowered, the
for executing piling work. cement concrete when used for lengthening
shall be measured as a separate item. This
2.11 Bringing plant to the site and erecting it item shall include the extra labour involved in
and dismantling and taking it back, shall be stripping the exposed end to form connection
measured separately as lump sum items. of new with old work and any excavation,
NOTE-Shifting of plant at site of work shall be if required.
included in the item of piles.
4. METHOD OF MEASUREMENT OF
2.12 If load testing is to be done, the provision TIMBER PILES
for such, test shall be specified and measured
separately. 4.1 Timber piles shall be described and
measured in running metre stating the species
3. METHOD OF MEASUREMENT OF of timber [see IS : 2911 (Part 2 )-198071 and
PRECAST REINFORCED CONCRETE size of the pile. If over 5’0 m in length, the
PILES length extra over 5 m shall be measured in
stages of one metre.
3.1 The precast reinforced concrete piles shall
be described accordmg to the grade of concrete,
*Method of measurement of building and civil
section and length, the extra strength of the engineering works: Part 8 Steel-work and ironwork
heads being stated. Any requisite mould shall ( third revision ) .
be included in the description as also the iCode of practice for design and construction of pile
necessary strapping, bolts and lifting holes. foundations: Part 2 Timber piles ( Jrst revision ).
2
IS : 1’200 ( Part 23 ) - 1988
4.1.1 The diameter of the pile shall be arrived 5.4 Lifting, handling, pitching, engaging
at by measuring girth at two metres below the through interlocks or clutches of an adjacent
large end of the pile. Any tolerance on the sheet piles and driving shall be measured
cross-sectional dimensions of timber in permit- separately for each type in square metres
ting above or below those shown in drawings obtained by multiplying the length of the
shall be specified. embedded portion of the pile in soil and half
of the perimeter as defined in IS : 2314-1986*.
4.1.2 Shaping and shoeing of pile shall be The length of the embedded portion shall be
enumerated, stating the approximate weight of obtained by measuring from the level of the
the shoe and size of the pile. ground where the tip of the sheet pile first
touches before driving, to the ultimate level of
4.2 Handling, transportation and pitching of the tip of the piles after driving.
piles shall be enumerated for each occasion.
5.5 Wherever sheet piles are to be driven under/
4.3 Driving timber piles shall be measured from in water necessitating the use of special hammers
the tip of the shoe to the ground level as shown and/or loader frames, such piles shall be des-
in the drawings or as found at site at the time cribed and measured separately.
of driving. The method of measurement of
5.6 Driving corner piles and junction piles shall
driving pile shall be the same as given in 3.7.
be measured in running metres representing
This item shall also include cutting the top of
the length of embedment.
the pile and dressing it for fixing mild steel ring
against splitting during driving. 5.7 Cutting or burning through steel piles shall
be measured in running metres as extra over
4.4 The supply and fixing of iron rings to the the pile. The disposal of cut length shall be
pile head before driving and also the labour described.
involved in cutting off the ringed portion or
any portion damaged in driving shall be in- 5.8 Extraction of piles other than those describ-
cluded in the description of the item. ed in 5.6 shall be measured separately in
square metres obtained by multiplying the
4.5 Joints in piles shall be described and enu- embedded length in soil by the nominal width
merated. of piles from the centre of the clutches.
Operations such as lifting, handling and remov-
5. METHOD OF MEASUREMENT OF ing from the site shall be described and included
STEEL SHEET PILES ( PERMANENT) in the item.
3
ISr126o(Part23)-1988
6.6 Empty boring shall be measured separately touches before driving to the ultimate level of
in running metres and the length shall be from the tip of the piles after driving.
working ground level to the cut off level of the
pile. The type of filling shall be stated. 8.4 Wherever sheet piles are to be driven
under/in water necessitating the use of special
7. METHOb OF MEASUREMENT OF hammers and,‘or loader frames, such piles shall
CAST IN SITU BORED REINFORCED be described by measuring separately.
CONCRETE PILES
8.5 Driving corner piles and junction piles shall
7.1 Empty boring shall be measured separately be measured separately.
in running metres and the length shall be from
working level to the cut off level of the pile. 8.6 Cutting piles shall be measured in running
The type of filling shall be stated. metres as extra over. The disposal of cut length
shall be described.
7.2 The boring through boulders and rock
strata shall be measured extra over. 8.7 The extraction of piles other than due to
defective driving shall be measured separately
7.3 Reinforcement .in pile including bars to be in square metres as mentioned in 8.3.
left in the pile cap for embedment shall be
measured separately. 9. METHOD QF MEASUREMENT OF
TIMBER SHEET PILES
7.4 The description of the pile shall state the
nominal diameter, grade of concrete, size of 9.1 The timber sheet piles shall be described
aggregate, the reinforcing bars, the length of and measured in running metres stating the
cage, and the provision of liners, if any. species of timber and cross-section.
7.5 Permanent mild steel liners, if provided, 9.2 Handling, transportation and pitching of
shall be measured separately in weight in piles shall be enumerated for each occasion.
accordance with IS : 1200 ( Part 8)-1975* from
working level to foundation level. 9.3 Driving timber sheet piles shall be measured
in square metres obtained by multiplying the
7.6 In case of under-reamed or bulb based length of the embedded portion of the pile in
piles, the bulbs shall be measured and enume- soil and half the perimeter of the construction.
rated. The description of piles shall state the
diameter of the bulb. 9.4 Whenever sheet piles are to be driven
under/in water necessitating the use of special
8. METHOD OF MEASUREMENT OF hammers and/or loader frames, such piles shall
REINFORCED CEMENT CONCRETE be described and measured separately.
SHEET PILES
9.5 The corner and junction piles shall be
8.1 The reinforced cement concrete sheet piles measured separately.
shall be measured in cubic metres arrived at by
multiplying the cross-sectional area of the pile 9.6 Cutting pile shall be measured in running
by the length of the pile as cast from the head metres as extra over. The disposal of cut length
of the pile to the tip of the shoes. shall be described.
8.2 The description of the item shall include 9.7 The extraction of piles other than due to
the cross-sectional shape, grade of concrete, defective driving shall be measured separately
size of aggregate and extra strength of the head. as in 9.3.
Any requisite mould shall be included in the
description as also necessary strapping, bolts 10. METHOD OF MEASUREMENT OF
and lifting holes. BORED PRECAST CONCRETE PILES
8.3 Lifting, handling, pitching engaging through 10.1 The precast reinforced concrete bored
adjacent piles and driving shall be measured piles shall be described according to grade of
separately for each type in square metres obtain- concrete, and size of aggregate section and
ed by mu!tiplying the length of the embedded length, the extra strength of the heads being
portion of the pile and half the parameter of stated. Any requisite mould shall be included
the section. The length of the embeded portion in the description as also the necessary
shall be obtained by measuring from the level strapping, bolts and lifting holes.
of the ground where the tip of the pile first
10.2 The cement concrete shall be measured
separately in cubic metres arrived at by multi-
*Method of measurement of building and civil
engineering works: Part 8 Steelwork and ironwork (U&-d plying the cross-sectional area of the pile by the
rcoision ) . length of pije as cast from the head of the pile
4
lsrl2oo(Part23)-I986
to the tip. No deduction shall be made for working ground level to the cut off level of the
chamfers, tapered points or the volume of rein- pile. The boring through boulders and rock
forcement or holes for lifting piles. strata except in respect of isolated boulders not
exceeding the diameter of the pile shaft shall be
10.3 The formwork, links and sleeves shall be made measured as extra over.
included in the description of the item.
10.7 The measurement of handling, transF
10.4 The reinforcement shall be measured portation and pitching of piles shall be enume-
separately [see IS : 1200 (Part 8)-1975*]. rated for each occasion.
10.3 Placing pile shaft shall be measured in 10.8 For strapping the heads of the pile, the
running metres from founding level to working length to be stripped shall be stated and
level of the pile. measured in running metres.
10.6 Empty boring shall be measured separately 10.9 Stripping off the heads of the pile for bond
in running metres and the length shall be from length shall be enumerated.
*Method of measurement of building and civil engineer- 10.10 Grouting shall be measured in cubic
ing works: Part 8 Steelwork and ironwork ( third revision ). metres describing fully the type of method.
5
IS : 1200 ( Part 24) -1983
( Reaffirmed 2007 )
Indian Standard
METHOD FOR
MEASUREMENT OF BUILDING AND
CIVIL ENGINEERING WORKS
PART 24 WELL FOUNDATIONS
( Third Revision)
Fourth Reprint NOVEMBER 2003
© Copyright 1983
Gr 2 December 1983
IS : 1200 ( Part 24 ) • 1983
0.4.1 Since different trades are not related to one another, the
Sectional Committee during its second revision decided that for each
trade as given in IS : 1200-1964· separate standards shall be issued
as different parts as it would be helpful to users in using the specific
standard. This Part 24 covering method of measurement of well
foundation applicable to buildings as well as to civil engineering works
was published in 1971. In view of the large number of comments
received on this standard ( Part 24) the Sectional Committee decided
to revise this Part incorporating the changes to keep the latest method as
being followed by most of the organizations.
0.5 In case of such works, it is desired that the following information
be also made available:
i) A general description of the nature of the work at site and the
cross..section of the river bed showing therein the low water
level and high flood level;
ii) Water logging whether due to nature of the soil or any other
reason; and
iii) The strata through which wells are likely to be sunk or reference
showing records of bores.
0.6 For the purpose of deciding whether a particular requirement of this
standard is complied with, the final value, observed or calculated,
expressing the result of a measurement, shall be rounded off in accordance
with IS : 2-19601. The number of significant places retained in the
rounded off value should be the same as that of the specified value in
this standard.
I. SCOPE
1.1 This standard ( Part 24 ) covers the method of measurement of well
foundations.
2. GENERAL
2.1 CJ.bbIDI or Items - Items may be clubbed together provided these
are basis of the detailed description of the items stated in this standard.
2.2 BookiDI 01 Dime••loas - In booking dimensions, the order shall
be consistent and generally in the sequence of length, width and height
or depth or thickness.
4
IS I 1200 ( Part 24 ) • Its3
3. WELL SINKING
3.1 The item of well sinking shall include use of kentiledge to the extent
required for sinking and correcting the well in position.
3.2 The provision of island, if required, shall be measured separately.
3.3 The sinking shall be measured in running metres stating the shape
and vize, For this purpose, measurement shall be taken from the level
at which the cutting edge is pitched to the level at which it rests finally.
NOT'; - 1 he level of curtine edge shall be plane joining the lower most portion of
the WE'll r urb, \\ )11< h cuts into the' 5011 during sinking or acts as a penetration face.
5
IS I 1200 ( Part 24 ) • 198:1
4. STEINING AND CURB
4.1 Concrete/brick work/stone masonry in the steining and concrete in
top plug and curb shall be described and measured in cubic metres. The
formwork shall be included in the item.
4.2 Concrete in the bottom plug including sump, if any, shall be
measured on the basis of cement bags consumed.
4.3 The filling in the well shall be measured in cubic metre stating the
type of filling.
4.4 Measurement for the reinforcement including mild steel bars, steel
links, binders and steel flats shall be made separately as specified in
IS : 1200 ( Part 8 )-1974·
4.5 Measurement for the steel cutting edge and steel armouring ( if done)
shall be made separately, as specified in IS : 1200 ( Part 8 )-1974*.
4.6 Cutting off the extra height of steining where required shall be
measured in cubic metres,
5. PNEUMATIC SINKING
5.1 Works executed under different working pressure range ( see IS :
4138-1977t ) shall be rneasured separately.
5.2 Pneumatic sinking shall be measured in running metres stating the
size and shape. The depth of sinking shall be measured from the level
at which air is introduced to the level at which air is stopped.
5.3 The following shall be measured separately:
a) Bringing of and removing the pneumatic sinking plant from the
site;
b) Usc of this plant when fitted on well/when not fitted on well ( to
be measured separately);
c) Fixing and removing of adopter and airlock:
d) Corbel slab; and
e) Keeping the well under pressure during plugging, guniting,
repairing, inspection, testing but excluding sinking.
( Second Revision )
Sixth Reprint DECEMBER 1998
( locorporatlo. Amendments No. I and 2)
© Copyright 1975
BUREAU OF INDIAN STANDARDS
MANAK BHAVAN, 9 BAHADUR SHAH ZAFAR MARG
NEW DELHI 110002
Gr 2 February 1972
IS: 1200 ( Part XXV ) • 1'71
0.6 For the purpose of deciding whether a particular requirement of this
standard is complied with, the final value, observed or calculated, express-
ing the result of a measurement, shall be rounded off in accordance with
IS: 2·1960*. The number of significant places retained in the rounded off
value should be the same as that of the specified value in this standard.
1. SCOPE
1.1 This standard .' Part XXV) covers the method of measurement of
tunneling
2. GENERAL RULES
2.1 Clubbing ofltelDs - Items may be clubbed together and that the
break-up of the clubbed items is agreed to be on the basis of the detailed
description of the items stated in this standard.
2.2 BookiDg of Dimensions - In booking dimensions, the order shall be
consistent and generally in the sequence of length, width and height or
depth -or thickness.
2.3 Me••urements - All work shall be measured net in decimal svstem
as fixed in its place as given below
4
IS : 1200 ( Part XXV ) • 1971
2.6 Bills of ~uaDtities - The bills of quantities shall fully describe the
materials and workmanship, and accurately represent the work to be
executed.
2.7 A general nature of site shall be stated. All available information as
to the strata through which the tunnel is to be driven along with the ridges
and valleys, the tunnel crosses shall be stated. The inclination at which the
tunnel is to be driven may also be mentioned,
6
IS I 1200( Part XXV) • It71
5. CONCRETE LINING
5.1 Measurement for the concrete lining shall be made of the quantity of
concrete placed between the formwork or the outside surface of the steel
shell when used and the pay line, which shall be ' B ' line or pay line adopted
for excavation at the place. The item of concrete lining shall be inclusive
of formwork. No deduction shall be made for the volume of the reinforce-
ment, but the volume of permanent steel supports (see 4.2) where
provided shall be deducted from the total volume of concrete lining
[see also IS: 1200 (Part 11)-1968*].
5.1.1 The concrete required to fill in the overbreaks beyond 'B' line
shall be measured along with the main concrete lining or it will be
included in the primary concrete lining, if primary concrete is done.
7
IS: 1200( Part26) - 1987
(Reaffirmed 2002)
(Reaffirmed 1992)
Indian Standard
METHOD OF MEASUREMENT OF
BUILDING AND CIVIL ENGINEERING WORK
PART 26 ACID RESISTANT LINING
( Third Reprint AUGUST 1998 )
0 Copyright 1987
1. SCOPE
2. GENERAL
4
IS : 1200 ( Part 26 ) - 1987
2.8 Expansion and dumy joints, and the filler shall be included in the
description of item.
2.12 Curved work, conical work and spherical work shall be described
separately stating the radius.
3. METHOD OF MEASUREMENT
5
IS : 1200 ( Part 26 ) - 1987
6
IS 1200 ( Pa:3 27 ) : 1992
( Reaffirmed 2002 )
UDC 69'003.12
:624.13
@ BIS 1992
Indian Standard
METHOD OF MEASUREMENT OF BUILDING
ANDCIVIL ENGINEERING WORKS
PART 27 EARTH WORK DONE BY MECHANICAL APPLIANCES
a) work in or under water, A mixture of soil and water in fluid or weak solid
b) Work in or under foul position, state.
1
IS 1200 ( Part 27 ) : 1992
Indian Standard
METHOD OF BUILDING AND CIVIL
ENGINEERING WORKS
PART 28 SOUND INSULATION WORK
@ BIS 1992
Indian Standard
METHOD OF BUILDING AND CIVIL
ENGINEERING WORKS
PART 28 SOUND INSULATION WORK
b) Number of coats and thickness of each 6.1 Description shall include rises and other
coat; roundings and shapes.
6.2 Work in repairs shall be so described stating
c) Nature of surface treatment; thickness of dubbing, if any.
d) Nature of base; and 6.3 Sound insulation work on ceilings, walls and
floor shall be measured separately.
e) Curved work, conical work, special work
and elliptical work stating the radius. 7 METHOD OF MEASUREMENT
5 METHOD OF MEASUREMENT 7.1 Work in isolating area not exceeding 1 m2
each shall be so described stating the nature
5.1 All works shall be measured, net, in decimal thereof.
system, as fixed in its place as given below:
7.2 Curved work, conical work and spherical work
a) Each dimensions shall be measured to the shall be described separately stating the radius.
nearest 0’01 m, where any dimensions is
more than 25 metre it shall be measured 7.3 Opening dia 0’3 m2 or less shall not be ded-
nearest to 0’1 m, and ucted for the purpose of measurement.
7.4 Sound insulation work at a height greater than
b) Areas shall be calculated to the nearest IO m above ground/datum level shall be measured
0’01 m2. separately in stages of 5 m height in case there is
5.2 Ceiling Work/False Ceiling Work no floor in between. If there is a fioor at a height
not exceeding 5 m, then it shall be measured
It shall be measured on the basis of finished work. separately for each storey.
I
IS 3861:2002
m’lfh?wm-
Wlai$-fwQT, *a*Ma
Indian Standard
METHOD OF MEASUREMENT OF PLINTH,
CARPET AND RENTABLE AREAS OF BUILDINGS
(Second Revision )
..
>,
@ BIS 2002
IS 3861:2002
Indian Standard
METHOD OF MEASUREMENT OF PLINTH,
CARPET AND RENTABLE AREAS OF BUILDINGS
(Second Revision )
1 SCOPE 2.8 Porch
This standard covers method of measurement of It is a covered structure supported on pillars or otherwise
plinth, carpet and rentable areas of old and new for the purpose of pedestrian or vehicular approach
buildings. to a building.
2 TERMINOLOGY 3 GENERAL
2.0 For the purpose of this standard, the following 3.1 Linear measurement shall be measured to nearest
definitions shall apply. 0.01 m, and areas shall be worked out to the nearest
0.01 m2.
2.1 Plinth Area
3.2 The areas of each of the following categories shall
Plinth area shall mean the built-up covered be measured separately and shall not be clubbed
measured at the floor level of the basement or of any together:
storey ( see 4 ).
a) Basement;
2.2 Carpet Area
b) Floor without cladding ( stilted floor);
Carpet area shall mean the floor area of the usable
rooms at any floor level ( see 5 ). c) Floors including top floor which may be partly
covered;
2.3 Rentable Area
d) Mezzanine floor including additional floor for
Rentable area shall mean the carpet area at any floor seating in assembly building/theatre,
level including areas as detained in 6. auditorium, etc;
2.4 Balcony e) Garage;
A horizontal projection with a hand-rail, balustrade Accommodation for service staffi
9
or a parapet, to serve as passage or sitting out place.
g) Stair cover ( mumty );
2.5 Mezzanine Floor
h) Machine room;
An intermediate floor in between two main floors having
minimum height of 2.2 m from the floor and having a -0 Porch; and
proper and permanent access to it.
k) Towers, turrets, domes projecting above the
NOTE — Where rules of the local bodies permit terrace level at terrace.
intermediate floor of minimum 1.8 m clear height, these
be also considered as mezzanine floor for the purpose 4 MEASUREMENT OF PLINTH AREA
of measurement.
4.1 Plinth area shall be the built up covered areas
2.6 Stair Cover ( Mumty ) measured for the categories mentioned in 3.2 and shall
Itis a structure with a roof over a staircase and its
include such areas as given in 4.1.1 and exclude the
landing, built to enclose only the stairs for the purpose areas given in 4.1.2.
of providing protection from weather and not used 4.1.1 For the purpose of plinth area, following shall
for human habitation. be included:
2.7 Loft a) Area of the wall at the floor level excluding
A structure providing intermediate storage space in plinth offsets, if any; when the building
between two main floors without having a permanent consists of columns projecting beyond
access and at a height not less than 2.0 m from the cladding, the plinth area shall be taken up
to the external face of cladding ( in case of
floor below.
1
IS 3861 :2002
corrugated sheet cladding outer edge of a) Door and other openings in the wall;
corrugation shall be considered );
b) Pillars, intermediate pillars, supports or any
NOTE — In case. a common wall is owned jointly other such obstruction within the plinth area
by two owners, only half the area of such walls irrespective of their location;
shall be included in the plinth area of one owner.
c) Pilaster along wall exceeding 300 cm2 in
b) Shafts for sanitary, water supply installations,
area;
garbage chute, telecommunication, electrical,
fire fighting, air-conditioning and lifts; d) Flues which are within the wall;
c) Stair case; e) Built-in cupboard, almirah and shelf appearing
within a height of 2.2 m from floor; and
d) In case of open verandah with parapets:
o Fire place projecting beyond the face of the
1) 100 percent areas for the portion protected
wall in living or bed room.
by the projections above, and
5.1.2 The following shall be excluded from the wall
2) 50 percent area for the portion
area:
unprotected from above.
a) Pilaster along wall not exceeding 300 cm2 in
e) 100 percent area of the balcony protected by
area, and
projection above and 50 percent area of the
unprotected balcony; and b) Chullah platform projecting beyond the face
of the wall.
9 In case of alcove made by cantilevering a slab
beyond external wall: 5.2 The carpet area shall be the area worked out as
in 5.1 excluding the area of the following portion:
1) 25 percent of the area for the alcove of
height up to 1 m, a) Verandah;
NOTE — The various dimensions could be measured 6.1.1 The rentable area shall be carpet area as worked
internally or externally. out in 5 but shall further include the following:
5.].1 The following shall be included in the wall a) The carpet area of kitchen, pantry, store,
area: lavatory, bath room; and
2
IS 3861:2002
6.1.2 While accounting the rentable area for 6.2.2 While accounting the rentable area for the
category mentioned in 3.2 b), one-fourth carpet area category mentioned in 3.2 b), one-fourth carpet area
shall be accounted for. shall be accounted for.