Sl No Complaint # Type Date & Time Description Location Status Job Order #

35 201901016653 Mech (Plumbing) 21-JAN-2019 09:36 Damaged Gratings at kitchen SPCKIT/Room W.I.P 201901017019
41 201902017701 Mech (Plumbing) 21-FEB-2019 09:27 STC toilet is in a poor condition at male section STC1F/Room W.I.P 201902018069
62 201904019044 Mech (Plumbing) 02-APR-2019 13:47 cars cover is damaged at tamimi Parking OUT/Room W.I.P 201904019411
70 201904019477 Mech (Plumbing) 21-APR-2019 15:30 Material work order, Need to purchase Mechanical Materials for use NH1GF/Room W.I.P 201904019845
98 201906020430 Mech (Plumbing) 15-JUN-2019 10:21 Need to repair underground utility (MAJOR ACTIVITY Plumbing with suGH2/Room W.I.P 201906020798
136 201906020806 Mech (Plumbing) 26-JUN-2019 10:18 PM OF LPG GAS CYLINDERS (1-15) PLUMBINGNH-2 NH-2 LaydownSPCKIT/Room K W.I.P 201906021174
138 201906020810 Mech (Plumbing) 26-JUN-2019 10:31 Need to Change/Replace O Ring in Sand Filter at Swimming Pool Pump NH2GF/Room
Ro W.I.P 201906021178
158 201906020844 Mech (Plumbing) 27-JUN-2019 07:48 Water leakage from skimmer plumbingSports Center Ground Floor S SPCGF/Room W.I.P 201906021212
180 201906020890 Mech (Plumbing) 30-JUN-2019 07:44 Please check and fix the leakage in the toilet bowl - at office TC&CS S NH2F2/Room W.I.P 201906021258
184 201906020896 Mech (Plumbing) 30-JUN-2019 11:02 Please check and fix the leakage in the toilet bowl - at office TC&CS S NH2F2/Room W.I.P 201906021264
227 201907020946 Mech (Plumbing) 01-JUL-2019 09:24 male toilet flash not working at HR building G floor HRCGF/Room W.I.P 201907021315
229 201907020948 Mech (Plumbing) 01-JUL-2019 10:33 Need to check and fix wc bowel clogged up.(ASAP) A144/Room W.I.P 201907021316
232 201907020952 Mech (Plumbing) 01-JUL-2019 13:54 Check and fix low water pressure in bathroom sink taps A201/Room W.I.P 201907021320
236 201907020957 Mech (Plumbing) 01-JUL-2019 14:08 Check and need apply silicon around Wc seat A316/Room W.I.P 201907021325
237 201907020958 Mech (Plumbing) 01-JUL-2019 15:05 Fix hose at admin building 4th floor. AB4F/Room W.I.P 201907021326
247 201907020969 Mech (Plumbing) 02-JUL-2019 08:47 need to chek and fix wc bowel glogged up. A348/Room W.I.P 201907021340

Summary :

Day Total No. of Compla 255

________________________________________________________________________________________________________________________________________________
______________________________________________x000D_GVBABU - ENGR020 02-JUL-2019 15:36
waiting for quotation.
Pre Approval Done, waiting for Material Delivery from Procurement
Closed by Today
pre approval done. Waiting for material Delivery to be close
RFI done to be closed by today.
closed
Pre approval received today. Closing tomorrow or soon
under observation
Closed
Closed
Closed
Closed
Closed
Closed
Closed
Closed

________________________________________________________________________________________________________________________________________________
______________________________________________x000D_GVBABU - ENGR020 02-JUL-2019 15:36
1 201708000901 Mech (HVAC) 21-AUG-2017 08:30
2 201708001198 Mech (HVAC) 27-AUG-2017 11:56
3 201711003507 Mech (HVAC) 20-NOV-2017 10:45
4 201802005043 Electrical 21-FEB-2018 07:15
5 201803005621 Mech (HVAC) 28-MAR-2018 15:07
6 201804005932 Mech (HVAC) 17-APR-2018 07:51
7 201804006536 Mech (HVAC) 30-APR-2018 14:36
8 201806008816 Mech (HVAC) 19-JUN-2018 11:09
9 201806008817 Mech (HVAC) 19-JUN-2018 11:11
10 201806008820 Mech (HVAC) 19-JUN-2018 11:15
11 201806008838 Civil 20-JUN-2018 08:17
12 201806008854 Mech (HVAC) 20-JUN-2018 10:34
13 201807009134 Civil 04-JUL-2018 12:21
14 201807009485 Mech (HVAC) 15-JUL-2018 07:27
15 201807009591 Civil 16-JUL-2018 11:20
16 201810012667 Civil 09-OCT-2018 09:12
17 201810013128 Civil 17-OCT-2018 09:41
18 201810013397 Electronics 22-OCT-2018 08:34
19 201810013398 Electronics 22-OCT-2018 08:36
20 201810013399 Electronics 22-OCT-2018 08:39
21 201810013400 Electronics 22-OCT-2018 08:41
22 201810013951 Mech (HVAC) 28-OCT-2018 11:13
23 201810014236 Civil 31-OCT-2018 10:41
24 201810014268 Electronics 31-OCT-2018 15:47
25 201811014662 Mech (HVAC) 07-NOV-2018 14:29
26 201812015520 Civil 02-DEC-2018 14:14
27 201812015848 Appliance 12-DEC-2018 17:48
28 201812015969 Appliance 22-DEC-2018 16:13
29 201812016035 Civil 23-DEC-2018 14:28
30 201812016050 Appliance 24-DEC-2018 09:00
31 201901016315 Mech (HVAC) 08-JAN-2019 15:30
32 201901016425 Mech (HVAC) 12-JAN-2019 12:35
33 201901016506 Electrical 15-JAN-2019 11:38
34 201901016592 Appliance 20-JAN-2019 07:51
35 201901016653 Mech (Plumbing) 21-JAN-2019 09:36
36 201901016816 Mech (HVAC) 28-JAN-2019 07:24
37 201901016844 Mech (HVAC) 29-JAN-2019 07:30
38 201902017033 Electronics 05-FEB-2019 08:26
39 201902017463 Electrical 17-FEB-2019 10:03
40 201902017619 Mech (HVAC) 20-FEB-2019 07:37
41 201902017701 Mech (Plumbing) 21-FEB-2019 09:27
42 201903017986 Mech (HVAC) 05-MAR-2019 08:49
43 201903017997 Electrical 05-MAR-2019 10:54
44 201903018048 Electrical 06-MAR-2019 10:19
45 201903018055 Civil 06-MAR-2019 13:18
46 201903018317 Civil 12-MAR-2019 09:14
47 201903018414 Civil 13-MAR-2019 11:08
48 201903018476 Civil 14-MAR-2019 14:07
49 201903018543 Electronics 17-MAR-2019 10:19
50 201903018544 Electronics 17-MAR-2019 10:24
51 201903018552 Electrical 17-MAR-2019 13:28
52 201903018648 Appliance 19-MAR-2019 08:11
53 201903018649 Appliance 19-MAR-2019 08:14
54 201903018708 Electrical 20-MAR-2019 11:43
55 201903018741 Civil 21-MAR-2019 09:45
56 201903018745 Electrical 21-MAR-2019 09:50
57 201903018903 Mech (HVAC) 28-MAR-2019 13:54
58 201903018916 Civil 30-MAR-2019 13:42
59 201903018958 Civil 31-MAR-2019 13:56
60 201904019022 Civil 02-APR-2019 08:31
61 201904019025 Mech (HVAC) 02-APR-2019 08:39
62 201904019044 Mech (Plumbing) 02-APR-2019 13:47
63 201904019070 Mech (HVAC) 03-APR-2019 10:50
64 201904019131 Electrical 04-APR-2019 14:38
65 201904019145 Mech (HVAC) 06-APR-2019 11:29
66 201904019251 Electronics 10-APR-2019 10:11
67 201904019344 Civil 15-APR-2019 13:20
68 201904019346 Civil 15-APR-2019 13:22
69 201904019401 Civil 16-APR-2019 15:32
70 201904019477 Mech (Plumbing) 21-APR-2019 15:30
71 201904019549 Civil 24-APR-2019 09:57
72 201904019578 Electrical 27-APR-2019 06:44
73 201904019579 Electrical 27-APR-2019 06:44
74 201905019673 Civil 01-MAY-2019 14:06
75 201905019735 Civil 02-MAY-2019 14:20
76 201905019819 Mech (HVAC) 05-MAY-2019 15:38
77 201905019842 Civil 06-MAY-2019 13:59
78 201905019945 Mech (HVAC) 12-MAY-2019 10:59
79 201905019951 Mech (HVAC) 12-MAY-2019 11:24
80 201905019988 Civil 14-MAY-2019 11:17
81 201905020002 Electrical 15-MAY-2019 13:34
82 201905020018 Civil 16-MAY-2019 10:15
83 201905020031 Electrical 18-MAY-2019 09:47
84 201905020052 Civil 19-MAY-2019 13:48
85 201905020090 Mech (HVAC) 20-MAY-2019 16:26
86 201905020092 Civil 21-MAY-2019 07:53
87 201905020093 Civil 21-MAY-2019 07:56
88 201905020095 Civil 21-MAY-2019 07:58
89 201905020103 Mech (HVAC) 21-MAY-2019 08:19
90 201905020122 Civil 22-MAY-2019 07:42
91 201905020126 Civil 22-MAY-2019 10:51
92 201905020129 Mech (HVAC) 22-MAY-2019 13:50
93 201906020395 Civil 12-JUN-2019 11:01
94 201906020425 Electronics 15-JUN-2019 07:22
95 201906020426 Electronics 15-JUN-2019 07:23
96 201906020427 Electronics 15-JUN-2019 07:24
97 201906020428 Electronics 15-JUN-2019 07:25
98 201906020430 Mech (Plumbing) 15-JUN-2019 10:21
99 201906020451 Civil 16-JUN-2019 10:07
100 201906020468 Mech (HVAC) 16-JUN-2019 15:52
101 201906020494 Mech (Fire Prot. 17-JUN-2019 10:34
102 201906020549 Mech (HVAC) 18-JUN-2019 11:16
103 201906020570 Civil 18-JUN-2019 15:27
104 201906020571 Civil 18-JUN-2019 15:29
105 201906020593 Mech (HVAC) 19-JUN-2019 08:54
106 201906020614 Civil 19-JUN-2019 15:05
107 201906020625 Civil 20-JUN-2019 09:13
108 201906020631 Electrical 20-JUN-2019 09:32
109 201906020634 Mech (HVAC) 20-JUN-2019 09:41
110 201906020635 Mech (HVAC) 20-JUN-2019 09:42
111 201906020669 Mech (HVAC) 23-JUN-2019 08:03
112 201906020670 Mech (HVAC) 23-JUN-2019 08:09
113 201906020671 Mech (HVAC) 23-JUN-2019 08:11
114 201906020672 Mech (HVAC) 23-JUN-2019 08:12
115 201906020673 Mech (HVAC) 23-JUN-2019 08:13
116 201906020674 Mech (HVAC) 23-JUN-2019 08:14
117 201906020675 Mech (HVAC) 23-JUN-2019 08:16
118 201906020676 Mech (HVAC) 23-JUN-2019 08:17
119 201906020677 Mech (HVAC) 23-JUN-2019 08:18
120 201906020678 Mech (HVAC) 23-JUN-2019 08:19
121 201906020679 Mech (HVAC) 23-JUN-2019 08:20
122 201906020680 Mech (HVAC) 23-JUN-2019 08:21
123 201906020681 Electrical 23-JUN-2019 08:22
124 201906020682 Mech (HVAC) 23-JUN-2019 08:24
125 201906020683 Mech (HVAC) 23-JUN-2019 08:25
126 201906020684 Mech (HVAC) 23-JUN-2019 08:27
127 201906020686 Electrical 23-JUN-2019 09:09
128 201906020698 Electrical 23-JUN-2019 11:15
129 201906020726 Electrical 24-JUN-2019 11:29
130 201906020727 Electrical 24-JUN-2019 11:30
131 201906020759 Civil 25-JUN-2019 09:43
132 201906020779 Civil 25-JUN-2019 13:52
133 201906020793 Electronics 26-JUN-2019 07:26
134 201906020800 Civil 26-JUN-2019 08:51
135 201906020804 Civil 26-JUN-2019 09:37
136 201906020806 Mech (Plumbing) 26-JUN-2019 10:18
137 201906020809 Appliance 26-JUN-2019 10:26
138 201906020810 Mech (Plumbing) 26-JUN-2019 10:31
139 201906020822 Mech (HVAC) 26-JUN-2019 14:55
140 201906020823 Mech (HVAC) 26-JUN-2019 14:56
141 201906020824 Mech (HVAC) 26-JUN-2019 14:58
142 201906020825 Mech (HVAC) 26-JUN-2019 14:59
143 201906020826 Mech (HVAC) 26-JUN-2019 15:01
144 201906020827 Mech (HVAC) 26-JUN-2019 15:03
145 201906020828 Mech (HVAC) 26-JUN-2019 15:04
146 201906020829 Mech (HVAC) 26-JUN-2019 15:05
147 201906020830 Mech (HVAC) 26-JUN-2019 15:07
148 201906020831 Mech (HVAC) 26-JUN-2019 15:08
149 201906020832 Mech (HVAC) 26-JUN-2019 15:09
150 201906020833 Mech (HVAC) 26-JUN-2019 15:10
151 201906020834 Mech (HVAC) 26-JUN-2019 15:11
152 201906020835 Mech (HVAC) 26-JUN-2019 15:12
153 201906020836 Mech (HVAC) 26-JUN-2019 15:13
154 201906020837 Electrical 26-JUN-2019 15:35
155 201906020838 Electrical 26-JUN-2019 15:37
156 201906020839 Electrical 26-JUN-2019 15:38
157 201906020842 Civil 27-JUN-2019 07:27
158 201906020844 Mech (Plumbing) 27-JUN-2019 07:48
159 201906020846 Mech (HVAC) 27-JUN-2019 09:06
160 201906020858 Electronics 27-JUN-2019 13:56
161 201906020859 Electronics 27-JUN-2019 13:58
162 201906020860 Electrical 27-JUN-2019 14:31
163 201906020861 Civil 27-JUN-2019 14:32
164 201906020873 Mech (HVAC) 29-JUN-2019 13:52
165 201906020874 Mech (HVAC) 29-JUN-2019 16:03
166 201906020875 Mech (HVAC) 29-JUN-2019 16:06
167 201906020876 Mech (HVAC) 29-JUN-2019 16:09
168 201906020877 Mech (HVAC) 29-JUN-2019 16:09
169 201906020878 Mech (HVAC) 29-JUN-2019 16:10
170 201906020879 Mech (HVAC) 29-JUN-2019 16:11
171 201906020880 Mech (HVAC) 29-JUN-2019 16:12
172 201906020881 Mech (HVAC) 29-JUN-2019 16:13
173 201906020882 Mech (HVAC) 29-JUN-2019 16:14
174 201906020883 Mech (HVAC) 29-JUN-2019 16:15
175 201906020884 Mech (HVAC) 29-JUN-2019 16:16
176 201906020885 Mech (HVAC) 29-JUN-2019 16:17
177 201906020886 Mech (HVAC) 29-JUN-2019 16:19
178 201906020887 Mech (HVAC) 29-JUN-2019 16:20
179 201906020888 Mech (HVAC) 29-JUN-2019 16:21
180 201906020890 Mech (Plumbing) 30-JUN-2019 07:44
181 201906020892 Mech (HVAC) 30-JUN-2019 08:42
182 201906020893 Civil 30-JUN-2019 09:13
183 201906020895 Mech (HVAC) 30-JUN-2019 09:48
184 201906020896 Mech (Plumbing) 30-JUN-2019 11:02
185 201906020900 Civil 30-JUN-2019 11:37
186 201906020901 Civil 30-JUN-2019 11:41
187 201906020902 Civil 30-JUN-2019 11:42
188 201906020903 Mech (HVAC) 30-JUN-2019 13:22
189 201906020904 Mech (HVAC) 30-JUN-2019 13:43
190 201906020905 Mech (HVAC) 30-JUN-2019 13:44
191 201906020906 Mech (HVAC) 30-JUN-2019 13:45
192 201906020907 Mech (HVAC) 30-JUN-2019 13:48
193 201906020908 Mech (HVAC) 30-JUN-2019 13:50
194 201906020909 Mech (HVAC) 30-JUN-2019 13:51
195 201906020910 Mech (HVAC) 30-JUN-2019 13:52
196 201906020911 Mech (HVAC) 30-JUN-2019 13:53
197 201906020912 Mech (HVAC) 30-JUN-2019 13:54
198 201906020913 Mech (HVAC) 30-JUN-2019 13:55
199 201906020914 Mech (HVAC) 30-JUN-2019 13:56
200 201906020915 Mech (HVAC) 30-JUN-2019 13:58
201 201906020916 Mech (HVAC) 30-JUN-2019 13:59
202 201906020917 Mech (HVAC) 30-JUN-2019 14:00
203 201906020918 Mech (HVAC) 30-JUN-2019 14:01
204 201907020919 Civil 01-JUL-2019 06:17
205 201907020920 Civil 01-JUL-2019 06:19
206 201907020921 Civil 01-JUL-2019 06:22
207 201907020922 Mech (HVAC) 01-JUL-2019 07:30
208 201907020923 Mech (HVAC) 01-JUL-2019 07:30
209 201907020924 Electronics 01-JUL-2019 07:34
210 201907020925 Electronics 01-JUL-2019 07:35
211 201907020926 Electronics 01-JUL-2019 07:36
212 201907020927 Electronics 01-JUL-2019 07:37
213 201907020928 Electronics 01-JUL-2019 07:38
214 201907020929 Electronics 01-JUL-2019 07:39
215 201907020930 Electronics 01-JUL-2019 07:40
216 201907020931 Electronics 01-JUL-2019 07:41
217 201907020932 Electronics 01-JUL-2019 07:42
218 201907020933 Electronics 01-JUL-2019 07:43
219 201907020934 Electronics 01-JUL-2019 07:44
220 201907020935 Electronics 01-JUL-2019 07:44
221 201907020936 Appliance 01-JUL-2019 07:58
222 201907020937 Mech (HVAC) 01-JUL-2019 08:42
223 201907020938 Mech (HVAC) 01-JUL-2019 08:30
224 201907020939 Civil 01-JUL-2019 09:05
225 201907020940 Civil 01-JUL-2019 09:07
226 201907020941 Electronics 01-JUL-2019 09:08
227 201907020946 Mech (Plumbing) 01-JUL-2019 09:24
228 201907020947 Civil 01-JUL-2019 09:25
229 201907020948 Mech (Plumbing) 01-JUL-2019 10:33
230 201907020950 Civil 01-JUL-2019 13:40
231 201907020951 Mech (HVAC) 01-JUL-2019 13:52
232 201907020952 Mech (Plumbing) 01-JUL-2019 13:54
233 201907020953 Civil 01-JUL-2019 13:59
234 201907020955 Civil 01-JUL-2019 14:01
235 201907020956 Civil 01-JUL-2019 14:07
236 201907020957 Mech (Plumbing) 01-JUL-2019 14:08
237 201907020958 Mech (Plumbing) 01-JUL-2019 15:05
238 201907020959 Janitorial 01-JUL-2019 15:07
239 201907020960 Mech (HVAC) 01-JUL-2019 15:45
240 201907020962 Civil 02-JUL-2019 08:39
241 201907020963 Electrical 02-JUL-2019 08:41
242 201907020964 Electronics 02-JUL-2019 08:43
243 201907020965 Electronics 02-JUL-2019 08:44
244 201907020966 Electronics 02-JUL-2019 08:45
245 201907020967 Electronics 02-JUL-2019 08:46
246 201907020968 Electronics 02-JUL-2019 08:47
247 201907020969 Mech (Plumbing) 02-JUL-2019 08:47
248 201907020970 Electronics 02-JUL-2019 08:48
249 201907020971 Electronics 02-JUL-2019 08:49
250 201907020972 Electronics 02-JUL-2019 08:51
251 201907020973 Mech (HVAC) 02-JUL-2019 08:51
252 201907020974 Mech (HVAC) 02-JUL-2019 08:52
253 201907020975 Electronics 02-JUL-2019 09:11
254 201907020976 Janitorial 02-JUL-2019 11:03
255 201907020978 Mech (HVAC) 02-JUL-2019 13:38
CH-EC-2Damaged ON/OFF handle to be replaced
AHU-2 Handel found broken , to be rplaced .
Check and fix two A/ C units in lobby area not working.
Ceck and fix there are some lights not working near the reception area.
Replacement or Repair of damage Fan Motor for precision AC (stulz) . Urgent
AC not working in the corridors near room 116Urgent
Electrical panel door lock damaged and bended by hitting on the frame due to wind, Admin Roof.
Corridor area near Room A-332 A/C not working CKT# Corridor-3-D-3
Corridor area near Room A-320 A/C not working CKT# Corridor-3-E-2
Corridor AC # 2-D-3 near room A-238 not working check and fix
Lockers in different areas specially on 3rd floor and 1st floor are no locks so customers can not use them
Corridor A/C CKT# 3-F-3 not working near Room A-303
"Material Work Order need to purchase Glass partition & Frameless glass door"
AC- 1-A-1- Corridor unit not working
Stair tile need to change in 2nd floor at NH2
We have a glass broken at 7th floor, office#704 and we need you support to fix and replace the broken
The VP complained about his office glass wall because the other day when strong wind attack with sand
Replacement of 2 damage Power Amplifier for P.A. SystemLocation: Admin & NH1
Replacement of O.S. (Operating System) for Public Address system
Repair of 1 faulty / malfunction power amplifier for P.A. systemLocation: NH1 - SubControl Room
Check, troubleshoot and repair speaker and speaker system for Outdoor facility (Zone1 & Zone 2)
A/C is not working 3rd floor EER Room AS306 (NH-1)
Tamimi need to provide proper storage for all chemical material as per standard
Material work order for calibration of fire pump equipment's such as pressure gauges ,pressure relief valve
Repair the damaged insulation for AHU-5 Admin Building.
Need to put glass on all hot and cold Counters
#1 Dryer not working in loundry 1st floor NH1.need to check and fix
Check &repair/replace damaged two dryers switch knobs for both 1st floor laundry room & as well as 2n
Floor tiles installed to be rectified - making sound during footing on it.1F- Near Elevator
Check and fix two dryers not working 1st floor laundry room dryer # 2 &dryer #3.
salad counter not working
2 door chiller not working-Counter
6 Lights are not working at STC at 2nd floor
Check and fix dryer # 1 nh1 laundry 2nd floor not working.
Damaged Gratings at kitchen
check and repair PACU - 1 fresh air units
AC is not working ( EER Room ) near masjid
PURCASHING OF SPARE PARTS FOR FIRE ALARM DEVICES (SMOKE DETECTORS,HEAT DETECTO
3 Lights are not working at Admin 1st floor next to U-Drive
3 CHILLER IN BUTCHER ROOM/TEMPERATURE NOT GOOD
STC toilet is in a poor condition at male section
Overload Relay is damaged feeding 1 compressor- need to be replaced - AHU-3
two Light without cover behind admin building
Replacement of SWG equipment such as Over Current Protection Relays and Automated Spring Charger
change drawer lock at admin building ws516.
Installing a film at NH2 window next to the printer.
Replacement of single door (Fire Rated) and frameAdmin G. Floor (Switchgear Room) .
Doors gasket repair admin Bldg (generator room ground floor)
Material requirement for Fire extinguisher to be replaced (17 pcs) at SBC
Material requirement for Spare material of Fire Hydrant
UPS-PLUGS - Type C19 to be replaced with cableNH-2All-TER Room
Check and fix washing machine #1 and dryer #2 not working in 1st floor laundry.
Check and fix Dryer #2 not working in 2nd floor laundry.
5 lights aren't working near Admin little garden near main stairs
install glass on the door of HR Employee Relations (HR building 1st floor) .
3 Lights aren't working behind Masjid near NH1
CHECK & REPARE A/C UNIT (ASG 12)
Check and need to install wall mounted clothes hangers for both men and as well as ladies toilet area in
Provide and install glass at cafeteria near of entrance of female toilet:
Near miss for window glass broken at Gate 1 .
Repair and Changing of contactor in AC unit of PACU-WC-03
cars cover is damaged at tamimi Parking
Fixing or Changing of BELTS in AC unit of KEF-WC-02
Replace the damage breaker 200AT in AHU-3 power panel - ( Tag name - 3B) - Rooftop- AHU-3 Control p
Check and fix A/C not working in laundry room NH1 1st floor
"Materail work order" Recoupling for Hydrotest failed fire hose-28 pcsElectronics SBC
crack on wall at admin building 1st floor near security manager office
change cabinet lock at admin building 5th floor in front of ws-541
Install a mirrorToilet at the Admin Bldg. - 4th floor
Material work order, Need to purchase Mechanical Materials for use in Pump Room Expansion Tank Blad
crack on mirror at HR elevator.
PM of Booster pumps control panel # 01
PM of Booster pumps control panel # 02
Re-Paint Multisuports Hall complete Civil Sports Center first Floor
Stair Hand rail is missing in Oasis Building 3rd floor to going top roof
Relocate the diffuserLocation: Ground floor - BMS room
Door handle need to fix at admin building 5th floor near EER room.
Check and fix exhaust fans are not working both male and female toilet in Oasis Gf area
Check and fix both suites SUT1 & as well as SUT2 exhaust fans are not working
Change cabinet lock at Hr building 3rd floor in front of ws-321.
Installation of Electrical Fly Killer at Sadara Dining Main Gate.
Window is covered with board at altamimi portable please remove it.
Need to check & replace one light is not working in NH-1 emergency Generator room.
Change drawer lock at training building COSL store
Noise coming from AC check and fix permission tomorrow
duplicate copies of keys Room # 402 Qty 3
duplicate copies of keys Room # 403 Qty2
duplicate copies of keys Room # 412 Qty2
Need to check & repair A/C unit given sound in NH-1 EER room ASG-18
send the maintenance crew to fix the drawer of our new Commercial DirectorOur office is at 3rd Floor,
Toilet hose hanger is damaged in masalah
Material Work Order For Critical Materials of HVAC units.
Fix door stopper at Hr building 1st floor.
PM JOB FOR ELEVATOR-L1, EQUIPMENT NO#11341267
PM JOB FOR ELEVATOR-L2 EQUIPMENT NO#11341268
PM JOB FOR ELEVATOR-L3, EQUIPMENT NO#11341269
PM JOB FOR ELEVATOR-L8, EQUIPMENT NO#42916483
Need to repair underground utility (MAJOR ACTIVITY Plumbing with supporting teams)
Need to fix the crack in admin building near to the smoking shelter.
Check and fix A/C not enough cooling.Oasis 3rd floor lobby area.
first aid check list has not checked in admin building all floors
ACs at our IT Stores in NH2 are not working.
install Curtain at admin building 3rd floor inside the room in it store.
install curtain at admin building 3rd floor it store.
PM OF A/C UNIT (ASG 12)
door handle is broken at gate 2 toilet door
door handle is broken at gate2
lighting is not working at TER room (BS-306)
AC is not cooling at TER room (BS-107)
AC is not working at TER room (BS-102)
PM OF A/C UNIT FOR ROOM A-101
PM OF A/C UNIT FOR ROOM A-102
PM OF A/C UNIT FOR ROOM A-103
PM OF A/C UNIT FOR ROOM A-104
PM OF A/C UNIT FOR ROOM A-105
PM OF A/C UNIT FOR ROOM A-106
PM OF A/C UNIT FOR ROOM A-107
PM OF A/C UNIT FOR ROOM A-108
PM OF A/C UNIT FOR ROOM A-109
PM OF A/C UNIT FOR ROOM A-110
PM OF A/C UNIT FOR ROOM A-111
PM OF A/C UNIT FOR ROOM A-112
1 Floricent light not working in staircase Gate#2 2nd floor NH1
PM OF A/C UNIT FOR ROOM A-113
PM OF A/C UNIT FOR ROOM A-114
PM OF A/C UNIT FOR ROOM A-115
1 fluorescent light not working in 2nd floor laundry.
light is not working at nh2 -1st floor storage 14
6 LIGHT ARE NOT WORKING NEAR NH1 PARKING IN FRONT OF GATE 1
2 LIGHTS ARE NOT WORKING NEXT TO GATE 1
repaint wall stair at sport center parking
block park to be removed to be normal parking-Sport Center Prking
PM JOB FOR SALTO DOOR ACCESS CONTROL SYSTEM AT NH-1 3.FLOOR
Ceiling tile not fixed properly chance of falling ,Nh-1 1st floor Near room A115
All male toilet doors not close probably at admin building 8th floor
PM OF LPG GAS CYLINDERS (1-15) PLUMBINGNH-2 NH-2 Laydown Kitchen Area
heater is damaged at kitchen
Need to Change/Replace O Ring in Sand Filter at Swimming Pool Pump Room (NH-2 GF ) .Location:
PM OF A/C UNIT FOR ROOM A-161HVACNH-11st ROOF TOP
PM OF A/C UNIT FOR ROOM A-162HVACNH-11st ROOF TOP
PM OF A/C UNIT FOR ROOM A-163HVACNH-11st ROOF TOP
PM OF A/C UNIT FOR ROOM A-164HVACNH-11st ROOF TOP
PM OF A/C UNIT FOR ROOM A-165HVACNH-11st ROOF TOP
PM OF A/C UNIT FOR ROOM A-166HVACNH-11st ROOF TOP
PM OF A/C UNIT FOR ROOM A-167HVACNH-11st ROOF TOP
PM OF A/C UNIT FOR ROOM A-168HVACNH-11st ROOF TOP
PM OF A/C UNIT FOR ROOM A-169HVACNH-11st ROOF TOP
PM OF A/C UNIT FOR ROOM A-170HVACNH-11st ROOF TOP
PM OF A/C UNIT FOR ROOM A-171HVACNH-11st ROOF TOP
PM OF A/C UNIT FOR ROOM A-172HVACNH-11st ROOF TOP
PM OF A/C UNIT FOR ROOM A-173HVACNH-11st ROOF TOP
PM OF A/C UNIT FOR ROOM A-174HVACNH-11st ROOF TOP
PM OF A/C UNIT FOR ROOM A-175HVACNH-11st ROOF TOP
Installation of a New Outlet for Vending Machines (additional Scope) as per MOC Number: E008P0782
Installation of a New Outlet for Vending Machines (additional Scope) as per MOC Number: E008P07820
Installation of a New Outlet for Vending Machines (additional Scope) as per MOC Number: E008P07820
Water leakage from skimmer-Sports Center Ground Floor Swimming pool
Water leakage from skimmer plumbingSports Center Ground Floor Swimming pool
A/c thermostat has no power check and fix.
Need to fix sound mixer in multisports hall ( BMS)
Need to move fire Extingusher in multisports hall from one place to another
One room light not working near Staff room-Sport center 3rd floor
Two tiles were broken in Shower & locker room Sport center 2nd floor
CHECK AND REPAIR OF CHILLER 2 ADMIN BUILDING
PM OF A/C UNIT FOR ROOM A-216NH-12nd ROOF TOP
PM OF A/C UNIT FOR ROOM A-217HVACNH-12nd ROOF TOP
PM OF A/C UNIT FOR ROOM A-218HVACNH-12nd ROOF TOP
PM OF A/C UNIT FOR ROOM A-219HVACNH-12nd ROOF TOP
PM OF A/C UNIT FOR ROOM A-220HVACNH-12nd ROOF TOP
PM OF A/C UNIT FOR ROOM A-221HVACNH-12nd ROOF TOP
PM OF A/C UNIT FOR ROOM A-222HVACNH-12nd ROOF TOP
PM OF A/C UNIT FOR ROOM A-223HVACNH-12nd ROOF TOP
PM OF A/C UNIT FOR ROOM A-224HVACNH-12nd ROOF TOP
PM OF A/C UNIT FOR ROOM A-225HVACNH-12nd ROOF TOP
PM OF A/C UNIT FOR ROOM A-226HVACNH-12nd ROOF TOP
PM OF A/C UNIT FOR ROOM A-227HVACNH-12nd ROOF TOP
PM OF A/C UNIT FOR ROOM A-228HVACNH-12nd ROOF TOP
PM OF A/C UNIT FOR ROOM A-229HVACNH-12nd ROOF TOP
PM OF A/C UNIT FOR ROOM A-230HVACNH-12nd ROOF TOP
Please check and fix the leakage in the toilet bowl - at office TC&CS Sr.Manager Room B220 ( Noted : Nee
the air conditioner is not working in (SBC NH2 - 3F , Room.B325)
Repair the drawer lock at Admin GF Security control center
Check and repair AC in NH1 Outdoor - GF ( EER / ASG18 )
Please check and fix the leakage in the toilet bowl - at office TC&CS Sr.Manager Room B219 ( Noted : Nee
Table at Admin First Floor to be removed
Ceramic is damaged at BMS room at Admin Ground Floor
Door Handle at Admin first floor needs to be changed
Need to check and fix A/C not cooling.(ASAP)
PM OF A/C UNIT FOR ROOM A-231HVACNH-12nd ROOF TOP
PM OF A/C UNIT FOR ROOM A-232HVACNH-12nd ROOF TOP
PM OF A/C UNIT FOR ROOM A-233HVACNH-12nd ROOF TOP
PM OF A/C UNIT FOR ROOM A-234HVACNH-12nd ROOF TOP
PM OF A/C UNIT FOR ROOM A-235HVACNH-12nd ROOF TOP
PM OF A/C UNIT FOR ROOM A-236HVACNH-12nd ROOF TOP
PM OF A/C UNIT FOR ROOM A-237HVACNH-12nd ROOF TOP
PM OF A/C UNIT FOR ROOM A-238HVACNH-12nd ROOF TOP
PM OF A/C UNIT FOR ROOM A-239HVACNH-12nd ROOF TOP
PM OF A/C UNIT FOR ROOM A-240HVACNH-12nd ROOF TOP
PM OF A/C UNIT FOR ROOM A-241HVACNH-12nd ROOF TOP
PM OF A/C UNIT FOR ROOM A-242HVACNH-12nd ROOF TOP
PM OF A/C UNIT FOR ROOM A-243HVACNH-12nd ROOF TOP
PM OF A/C UNIT FOR ROOM A-244HVACNH-12nd ROOF TOP
PM OF A/C UNIT FOR ROOM A-245HVACNH-12nd ROOF TOP
Check and fix bathroom door lock issue.we have permission for today morning.
Check and fix window curtain nchain broken.
Check and fix bathroom door handle broken.we have permission for today morning.
Check and repair Restaurant Exhaust fans Admin buildng 1F Location: ADMIN GF/1F OutdoorDiscipli
send the A/C crew at NH2, Room # 305 to check window insulation and A/C filter
PM JOB FOR FIRE EXTINGUISHERS (FE-AGF-01 TO FE-AGF-028)
PM JOB FOR FIRE EXTINGUISHERS (FE-A1F-01 TO FE-A1F-07)
PM JOB FOR FIRE EXTINGUISHERS (FE-A2F-01 TO FE-A2F-06)
PM JOB FOR FIRE EXTINGUISHERS (FE-A3F-01 TO FE-A3F-09)
PM JOB FOR FIRE EXTINGUISHERS (FE-A4F-01 TO FE-A4F-07)
PM JOB FOR FIRE EXTINGUISHERS (FE-A5F-01 TO FE-A5F-07)
PM JOB FOR FIRE EXTINGUISHERS (FE-A6F-01 TO FE-A6F-07)
PM JOB FOR FIRE EXTINGUISHERS (FE-A7F-01 TO FE-A7F-07)
PM JOB FOR FIRE EXTINGUISHERS (FE-A8F-01 TO FE-A8F-06)
PM JOB FOR FIRE EXTINGUISHERS (FE-ARF-01 TO FE-ARF-06)
PM JOB FOR PA SYSTEM OUT DOOR SPEAKER CLEANING (SW-01)
PM JOB FOR SATV SYSTEM IN OASIS G.FLOOR
PM check and repair bowling appliance in sport center.
provide AC Technician to check and fix the AC which is not working at Naffoura Building 2, Room B228.
AC at ER Manager, HR building 1st floor
fix tissue handle ( masalah bathroom )
remove NO PARKING sign beside sport center
arrange wire at NH-2 building 1st floor room #140
male toilet flash not working at HR building G floor
Repair tolite door at NH-2 building in room #108
Need to check and fix wc bowel clogged up.(ASAP)
the drawer cabinets locks that located at Admin building 3rd floor IT-Help desk ( W.S 325 )
Check and fix a/c not enough cooling
Check and fix low water pressure in bathroom sink taps
Check and fix entrance door not closing properly and cupboards shelve has fallen need to refix
Check and need grouting throughout the bathroom floor tiles
Check and need grouting throughout the bathroom floor tiles
Check and need apply silicon around Wc seat
Fix hose at admin building 4th floor.
Clean wall at admin building 4th floor in front of men bathroom.
check and fix Delux 6 living room A/C not working.DLX6/Room
Repair tolite door at NH-2 building in pantry
Light does not work in room 303 at NH-2 building .
PM JOB FOR FIRE EXTINGUISHERS (FE-HRGF-01 TO FE-HRGF-15)
PM JOB FOR FIRE EXTINGUISHERS (FE-HR1F-01 TO FE-HR1F-11)
PM JOB FOR FIRE EXTINGUISHERS (FE-HR2F-01 TO FE-HR2F-12)
PM JOB FOR FIRE EXTINGUISHERS (FE-HR3F-01 TO FE-HR3F-12)
PM JOB FOR FIRE EXTINGUISHERS (FE-HRRF-01 TO FE-HRRF-03)
need to chek and fix wc bowel glogged up.
PM JOB FOR PA SYSTEM OUT DOOR SPEAKER CLEANING (SW-02)
PM JOB FOR SALTO DOOR ACCES SYSTEM (ROOM G101 TO ROOM G111)
PM JOB FOR SATV SYSTEM IN OASIS 1.FLOOR
AC not working at NH-2 building 1st floor Room#103
need to check and fix A/C its automatically shutting off now and then.
Check and need to install 43"inches LED smart tv .
MATERIAL WORK ORDER LPG GAS CYLINDER 10PCS
Check and fix A/c not enough cooling
ABRT/Room W.I.P 201708001024
ABGF/Room W.I.P 201710002297
OAS3F/Room W.I.P 201711003656
OASGF/Room W.I.P 201802005244
ABRT/Room W.I.P 201803005893
NH2F1/Room W.I.P 201804006235
ABRT/Room W.I.P 201804006834
NH1F3/Room W.I.P 201806009145
NH1F3/Room W.I.P 201806009144
NH1F2/Room W.I.P 201806009141
SPC3F/Room W.I.P 201806009168
NH1F3/Room W.I.P 201806009180
HRCGF/Room W.I.P 201807009461
NH2F1/Room W.I.P 201807009822
NH2F2/Room W.I.P 201807009922
AB7F/Room W.I.P 201810013001
AB5F/Room W.I.P 201810013481
AB1F/Room W.I.P 201810013747
ABGF/Room W.I.P 201810013748
NH1F1/Room W.I.P 201810013751
OUT/Room W.I.P 201810013753
NH1F3/Room W.I.P 201810014304
PC/Room W.I.P 201810014620
NH1GF/Room W.I.P 201810014638
ABRT/Room W.I.P 201811015025
SPCKIT/Room W.I.P 201812015875
NH1F1/Room W.I.P 201812016214
NH1F1/Room W.I.P 201812016335
NH2F1/Room W.I.P 201812016401
NH1F1/Room W.I.P 201812016416
RSTRNT/Room W.I.P 201901016681
SPCKIT/Room W.I.P 201901016790
STC1F/Room W.I.P 201901016873
NH1F2/Room W.I.P 201901016958
SPCKIT/Room W.I.P 201901017019
NH1RT/Room W.I.P 201901017184
NH1GF/Room W.I.P 201901017210
ABGF/Room W.I.P 201902017401
AB1F/Room W.I.P 201902017817
RSTRNT/Room W.I.P 201902017986
STC1F/Room W.I.P 201902018069
STCRT/Room W.I.P 201903018353
OUT/Room W.I.P 201903018359
ABGF/Room W.I.P 201903018415
AB5F/Room W.I.P 201903018422
NH2F1/Room W.I.P 201903018684
ABGF/Room W.I.P 201903018781
ABGF/Room W.I.P 201903018843
AB1F/Room W.I.P 201903018910
OUT/Room W.I.P 201903018911
NH2F1/Room W.I.P 201903018915
NH1F1/Room W.I.P 201903019014
NH1F2/Room W.I.P 201903019016
OUT/Room W.I.P 201903019074
HRC1F/Room W.I.P 201903019116
OUT/Room W.I.P 201903019108
NH1RT/Room W.I.P 201903019270
OASGF/Room W.I.P 201903019283
RSTRNT/Room W.I.P 201903019325
OUT/Room W.I.P 201904019389
SPCRT/Room W.I.P 201904019391
OUT/Room W.I.P 201904019411
SPCRT/Room W.I.P 201904019437
STCRT/Room W.I.P 201904019500
NH1F1/Room W.I.P 201904019508
ABGF/Room W.I.P 201904019618
AB1F/Room W.I.P 201904019713
AB5F/Room W.I.P 201904019714
AB4F/Room W.I.P 201904019769
NH1GF/Room W.I.P 201904019845
HRC1F/Room W.I.P 201904019916
NH1GF/Room W.I.P 201904019939
NH1GF/Room W.I.P 201904019940
SPC1F/Room W.I.P 201905020041
OAS3F/Room W.I.P 201905020102
ABGF/Room W.I.P 201905020187
AB5F/Room W.I.P 201905020210
OASGF/Room W.I.P 201905020313
SUT1/Room W.I.P 201905020319
HRC3F/Room W.I.P 201905020357
RSTRNT/Room W.I.P 201905020370
OUT/Room W.I.P 201905020386
NH1GF/Room W.I.P 201905020399
STCGF/Room W.I.P 201905020420
G106/Room W.I.P 201905020461
AB4F/Room W.I.P 201905020465
AB4F/Room W.I.P 201905020466
AB4F/Room W.I.P 201905020467
NH1GF/Room W.I.P 201905020464
NH2F3/Room W.I.P 201905020490
OUT/Room W.I.P 201905020494
OUT/Room W.I.P 201905020497
HRC1F/Room W.I.P 201906020763
ABGF/Room W.I.P 201906020793
ABGF/Room W.I.P 201906020794
ABGF/Room W.I.P 201906020795
HRCGF/Room W.I.P 201906020796
GH2/Room W.I.P 201906020798
OUT/Room W.I.P 201906020819
OAS3F/Room W.I.P 201906020836
AB1F/Room W.I.P 201906020868
NH2F2/Room W.I.P 201906020917
AB3F/Room W.I.P 201906020938
AB3F/Room W.I.P 201906020939
NH1RT/Room W.I.P 201906020961
OUT/Room W.I.P 201906020986
OUT/Room W.I.P 201906020995
NH2F3/Room W.I.P 201906021003
NH2F1/Room W.I.P 201906020999
NH2F1/Room W.I.P 201906021000
NH1RT/Room W.I.P 201906021037
NH1RT/Room W.I.P 201906021038
NH1RT/Room W.I.P 201906021039
NH1RT/Room W.I.P 201906021040
NH1RT/Room W.I.P 201906021041
NH1RT/Room W.I.P 201906021042
NH1RT/Room W.I.P 201906021043
NH1RT/Room W.I.P 201906021044
NH1RT/Room W.I.P 201906021045
NH1RT/Room W.I.P 201906021046
NH1RT/Room W.I.P 201906021047
NH1RT/Room W.I.P 201906021048
NH1F2/Room W.I.P 201906021052
NH1RT/Room W.I.P 201906021049
NH1RT/Room W.I.P 201906021050
NH1RT/Room W.I.P 201906021051
NH1F2/Room W.I.P 201906021053
NH2F1/Room W.I.P 201906021064
OUT/Room W.I.P 201906021094
OUT/Room W.I.P 201906021095
OUT/Room W.I.P 201906021127
OUT/Room W.I.P 201906021140
NH1F3/Room W.I.P 201906021161
NH1F1/Room W.I.P 201906021169
AB8F/Room W.I.P 201906021172
SPCKIT/Room W.I.P 201906021174
SPCKIT/Room W.I.P 201906021177
NH2GF/Room W.I.P 201906021178
NH1RT/Room W.I.P 201906021190
NH1RT/Room W.I.P 201906021191
NH1RT/Room W.I.P 201906021192
NH1RT/Room W.I.P 201906021193
NH1RT/Room W.I.P 201906021194
NH1RT/Room W.I.P 201906021195
NH1RT/Room W.I.P 201906021196
NH1RT/Room W.I.P 201906021197
NH1RT/Room W.I.P 201906021198
NH1RT/Room W.I.P 201906021199
NH1RT/Room W.I.P 201906021200
NH1RT/Room W.I.P 201906021201
NH1RT/Room W.I.P 201906021202
NH1RT/Room W.I.P 201906021203
NH1RT/Room W.I.P 201906021204
HRCGF/Room W.I.P 201906021205
NH1F1/Room W.I.P 201906021206
SPC1F/Room W.I.P 201906021207
SPCGF/Room W.I.P 201906021210
SPCGF/Room W.I.P 201906021212
A140/Room W.I.P 201906021214
SPC1F/Room W.I.P 201906021225
SPC1F/Room W.I.P 201906021226
SPC3F/Room W.I.P 201906021227
SPC2F/Room W.I.P 201906021228
ABRT/Room W.I.P 201906021241
NH1RT/Room W.I.P 201906021242
NH1RT/Room W.I.P 201906021243
NH1RT/Room W.I.P 201906021244
NH1RT/Room W.I.P 201906021245
NH1RT/Room W.I.P 201906021246
NH1RT/Room W.I.P 201906021247
NH1RT/Room W.I.P 201906021248
NH1RT/Room W.I.P 201906021249
NH1RT/Room W.I.P 201906021250
NH1RT/Room W.I.P 201906021251
NH1RT/Room W.I.P 201906021252
NH1RT/Room W.I.P 201906021253
NH1RT/Room W.I.P 201906021254
NH1RT/Room W.I.P 201906021255
NH1RT/Room W.I.P 201906021256
NH2F2/Room W.I.P 201906021258
NH2F3/Room W.I.P 201906021260
ABGF/Room W.I.P 201906021261
NH1GF/Room W.I.P 201906021263
NH2F2/Room W.I.P 201906021264
AB1F/Room W.I.P 201906021267
ABGF/Room W.I.P 201906021268
AB1F/Room W.I.P 201906021269
A261/Room W.I.P 201906021271
NH1RT/Room W.I.P 201906021272
NH1RT/Room W.I.P 201906021273
NH1RT/Room W.I.P 201906021274
NH1RT/Room W.I.P 201906021275
NH1RT/Room W.I.P 201906021276
NH1RT/Room W.I.P 201906021277
NH1RT/Room W.I.P 201906021278
NH1RT/Room W.I.P 201906021279
NH1RT/Room W.I.P 201906021280
NH1RT/Room W.I.P 201906021281
NH1RT/Room W.I.P 201906021282
NH1RT/Room W.I.P 201906021283
NH1RT/Room W.I.P 201906021284
NH1RT/Room W.I.P 201906021285
NH1RT/Room W.I.P 201906021286
A207/Room W.I.P 201907021287
A207/Room W.I.P 201907021288
A105/Room W.I.P 201907021289
AB1F/Room W.I.P 201907021291
NH2F3/Room W.I.P 201907021290
ABGF/Room W.I.P 201907021292
AB1F/Room W.I.P 201907021293
AB2F/Room W.I.P 201907021294
AB3F/Room W.I.P 201907021295
AB4F/Room W.I.P 201907021296
AB5F/Room W.I.P 201907021297
AB6F/Room W.I.P 201907021298
AB7F/Room W.I.P 201907021299
AB8F/Room W.I.P 201907021300
ABRT/Room W.I.P 201907021301
OUT/Room W.I.P 201907021303
OASGF/Room W.I.P 201907021302
SPC1F/Room W.I.P 201907021304
NH2F2/Room W.I.P 201907021306
HRC1F/Room W.I.P 201907021305
OUT/Room W.I.P 201907021307
OUT/Room W.I.P 201907021308
NH2F1/Room W.I.P 201907021311
HRCGF/Room W.I.P 201907021315
NH2F1/Room W.I.P 201907021309
A144/Room W.I.P 201907021316
AB3F/Room W.I.P 201907021318
A201/Room W.I.P 201907021319
A201/Room W.I.P 201907021320
A240/Room W.I.P 201907021321
A240/Room W.I.P 201907021322
A316/Room W.I.P 201907021323
A316/Room W.I.P 201907021325
AB4F/Room W.I.P 201907021326
AB4F/Room W.I.P 201907021327
OAS2F/Room W.I.P 201907021328
NH2F3/Room W.I.P 201907021330
NH2F3/Room W.I.P 201907021331
HRCGF/Room W.I.P 201907021332
HRC1F/Room W.I.P 201907021333
HRC2F/Room W.I.P 201907021334
HRC3F/Room W.I.P 201907021335
HRCRT/Room W.I.P 201907021336
A348/Room W.I.P 201907021340
OUT/Room W.I.P 201907021337
OAS1F/Room W.I.P 201907021338
OAS1F/Room W.I.P 201907021339
NH2F1/Room W.I.P 201907021341
A224/Room W.I.P 201907021342
A156/Room W.I.P 201907021343
SPCKIT/Room W.I.P 201907021344
A162/Room W.I.P 201907021346