PROPOSED DRYER WAREHOUSE (Revision 1.

1)
CONTRACTOR: MARIÑAS & CO. BUILDERS, INC 27-Nov-19 13:55
Activity ID Activity Name October 2019 November 2019 December 2019 January 2020 February 2020 March 2020 April 2020 May 2020 June 2020
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 01 08 15 22 29 05 12 19 26 03 10 17 24 31 07

Son-oc Warehouse 2 (REV 1.1) Son-oc Warehouse 2 (REV 1.1), 27.96%


PRELIMINARIES PRELIMINARIES, 88.04%
A1130 As-Built Drawing Preparation
A1040 Demobalization
A1120 Management and Supervision 100%
A1110 Safety Requirements 100%
A1000 Engineering and Detailing 100%
A1010 Construction Permits 100%
A1020 Bonds and Insurances 100%
A1030 Mobilization 100%
A1100 Temporary Facilities 100%
SITE DEVELOPMENT SITE DEVELOPMENT, 27.96%
WAREHOUSE 2 WAREHOUSE 2, 27.96%
1.1 EARTHWORKS 1.1 EARTHWORKS, 100%
Footing Excavation Footing Excavation, 100%
A1630 Footing Excavation GL 14-13 100%
A1620 Footing Excavation GL 17-15 100%
A1610 Footing Excavation GL 20-18 100%
Footing Tie Beam Excavation Footing Tie Beam Excavation, 100%
A1640 FTB Excavation GL 20-18 100%
A1660 FTB Excavation GL 14-13 100%
A1650 FTB Excavation GL 17-15 100%
1.2 CONCRETE LEAN 1.2 CONCRETE LEAN, 100%
A1690 Concrete Lean GL 14-13 100%
A1680 Concrete Lean GL 17-15 100%
A1670 Concrete Lean GL 20-18 100%
1.3 REINFORCEMENT 1.3 REINFORCEMENT, 39.23%
Column Footing Column Footing, 100%
A1710 Footing Rebars GL 17-15 100%
A1720 Footing Rebars GL 14-13 100%
A1700 Footing Rebars GL 20-18 100%
Column Pedestal Column Pedestal, 100%
1st Lift Column Pedestal 1st Lift Column Pedestal, 100%
A1750 Column 1st Lift Rebars GL 14-13 100%
A1740 Column 1st Lift Rebars GL 17-15 100%
A1730 Column 1st Lift Rebars GL 20-18 100%
2nd Lift Column Pedestal 2nd Lift Column Pedestal, 100%
A1770 Column 2nd Lift Rebars GL 17-15 100%
A1780 Column 2nd Lift Rebars GL 14-13 100%
A1760 Column 2nd Lift Rebars GL 20-18 100%
Footing Tie Beam Footing Tie Beam, 100%
A1790 FTB Rebars GL 20-18 100%
A1800 FTB Rebars GL 17-15 100%
A1810 FTB Rebars GL 14-13 100%
Wall Footing Wall Footing, 66.67%
A2430 WF Rebars 17-15
A2440 WF Rebars 14-13 45.45%
A2420 WF Rebars 20-18 51.15%
Ramps Ramps, 0%
A2450 Ramps Rebars
1.4 FORMWORKS 1.4 FORMWORKS, 37.47%
Column Footing Column Footing, 100%
A1820 Footing Formworks GL 20-18 100%
A1840 Footing Formworks GL 14-13 100%
A1830 Footing Formworks GL 17-15 100%
Column Pedestal Column Pedestal, 93.49%
1st Lift Column Pedestal 1st Lift Column Pedestal, 100%
A1870 Column 1st Lift Formworks GL 14-13 100%
A1850 Column 1st Lift Formworks GL 20-18 100%
A1860 Column 1st Lift Formworks GL 17-15 100%
2nd Lift Column Pedestal 2nd Lift Column Pedestal, 15.36%
A1900 Column 2nd Lift Formworks GL 14-13 18.18%
A1890 Column 2nd Lift Formworks GL 17-15 15.36%
A1880 Column 2nd Lift Formworks GL 20-18 61.51%
Footing Tie Beam Footing Tie Beam, 100%
A1930 FTB Formworks GL 14-13 100%
A1920 FTB Formworks GL 17-15 100%

Actual Level of Effort CLIENT: ALTURAS GROUP OF COMPANIES


Actual Work
LOCATION: LUMANGOG , UBAY, BOHOL
Remaining Work Page 1
Milestone PREPARED BY: MARIÑAS & CO.BUILDERS INC.
% Complete
Summary
PROPOSED DRYER WAREHOUSE (Revision 1.1)
CONTRACTOR: MARIÑAS & CO. BUILDERS, INC 27-Nov-19 13:55
June 2020 July 2020 August 2020 September 2020 October 2020 November 2020 December 2020 January 2021 February 2021 March 2021 April 2021 May 2021
14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 07 14 21 28 07 14 21 28 04 11 18 25 02 09
V 1.1), 27.96%

Actual Level of Effort CLIENT: ALTURAS GROUP OF COMPANIES


Actual Work
LOCATION: LUMANGOG , UBAY, BOHOL
Remaining Work Page 2
Milestone PREPARED BY: MARIÑAS & CO.BUILDERS INC.
% Complete
Summary
PROPOSED DRYER WAREHOUSE (Revision 1.1)
CONTRACTOR: MARIÑAS & CO. BUILDERS, INC 27-Nov-19 13:55
Activity ID Activity Name October 2019 November 2019 December 2019 January 2020 February 2020 March 2020 April 2020 May 2020 June 2020
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 01 08 15 22 29 05 12 19 26 03 10 17 24 31 07
A1910 FTB Formworks GL 20-18 100%
Wall Footing Wall Footing, 18.07%
A2470 WF Formworks 17-15
A2480 WF Formworks 14-13 45.45%
A2460 WF Formworks 20-18 51.15%
Ramps Ramps, 0%
A2490 Ramps Formworks
1.5 CONCRETING AND CURING WORKS 1.5 CONCRETING AND CURING WORKS, 38.08%
Column Pedestal Column Pedestal, 81.63%
1st Lift Column Pedestal 1st Lift Column Pedestal, 100%
A1540 Column 1st Lift Concreting GL 17-15 100%
A1560 Stripping Forms GL 17-15 100%
A1940 Column 1st Lift Concreting GL 14-13 100%
A1950 Stripping Forms GL 14-13 100%
A1390 Column 1st Lift Concreting GL 20-18 100%
A1400 Stripping Forms GL 20-18 100%
2nd Lift Column Pedestal 2nd Lift Column Pedestal, 0%
A1410 Column 2nd Lift Concreting GL 20-18
A1420 Stripping Forms GL 20-18
A1570 Column 2nd Lift Concreting GL 17-15
A1580 Stripping Forms GL 17-15
A1960 Column 2nd Lift Concreting GL 14-13
A1970 Stripping Forms GL 14-13
Column Footing Column Footing, 100%
A1585 Footing Concreting GL 14-13 100%
A1595 Stripping Forms GL 14-13 100%
A1575 Stripping Forms GL 17-15 100%
A1565 Footing Concreting GL 17-15 100%
A1550 Footing Concreting GL 20-18 100%
A1555 Stripping Forms GL 20-18 100%
Footing Tie Beam Footing Tie Beam, 100%
A1440 Stripping Forms GL 20-18 100%
A1600 Stripping Forms GL 17-15 100%
A1990 Stripping Forms GL 14-13 100%
A1980 FTB Concreting GL 14-13 100%
A1590 FTB Concreting GL 17-15 100%
A1430 FTB Concreting GL 20-18 100%
Wall Footing Wall Footing, 9.53%
A2370 WF Concreting 17-15
A2390 Stripping Forms
A2360 Stripping Forms 45.42%
A2410 Stripping Forms 45.45%
A2350 WF Concreting 20-18 51.15%
A2400 WF Concreting 14-13 45.42%
Ramps Ramps, 0%
A2380 Ramps Concreting
A2500 Stripping Forms
1.6 SLAB-ON-GRADE 1.6 SLAB-ON-GRADE, 0%
A1450 SOG Concrete GL 20-19
A1460 SOG Concrete GL 19-18
A1470 SOG Concrete GL 18-17
A1480 SOG Concrete GL 17-16
A1490 SOG Concrete GL 16-15
A1500 SOG Concrete GL 15-14
A1510 SOG Concrete GL 14-13
1.7 STRUCTURAL WORKS 1.7 STRUCTURAL WORKS, 1.83%
Anchor Bolts Anchor Bolts, 12.98%
A2010 Installation of Anchor Bolts GL 17-15 15.38%
A2020 Installation of Anchor Bolts GL 14-13 18.19%
A2000 Installation of Anchor Bolts GL 20-18 61.52%
Erection Erection, 0%
A2030 Erection GL 20-18
A2040 Erection GL 17-15
A2050 Erection GL 14-13
Roof Framing Roof Framing, 0%
Installation of Rafters Installation of Rafters, 0%
A2060 Installation of Rafters GL 20-18
A2070 Installation of Rafters GL 17-15

Actual Level of Effort CLIENT: ALTURAS GROUP OF COMPANIES


Actual Work
LOCATION: LUMANGOG , UBAY, BOHOL
Remaining Work Page 3
Milestone PREPARED BY: MARIÑAS & CO.BUILDERS INC.
% Complete
Summary
PROPOSED DRYER WAREHOUSE (Revision 1.1)
CONTRACTOR: MARIÑAS & CO. BUILDERS, INC 27-Nov-19 13:55
June 2020 July 2020 August 2020 September 2020 October 2020 November 2020 December 2020 January 2021 February 2021 March 2021 April 2021 May 2021
14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 07 14 21 28 07 14 21 28 04 11 18 25 02 09

Actual Level of Effort CLIENT: ALTURAS GROUP OF COMPANIES


Actual Work
LOCATION: LUMANGOG , UBAY, BOHOL
Remaining Work Page 4
Milestone PREPARED BY: MARIÑAS & CO.BUILDERS INC.
% Complete
Summary
PROPOSED DRYER WAREHOUSE (Revision 1.1)
CONTRACTOR: MARIÑAS & CO. BUILDERS, INC 27-Nov-19 13:55
Activity ID Activity Name October 2019 November 2019 December 2019 January 2020 February 2020 March 2020 April 2020 May 2020 June 2020
22 29 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 02 09 16 23 01 08 15 22 29 05 12 19 26 03 10 17 24 31 07
A2080 Installation of Rafters GL 14-13
General Framing General Framing, 0%
A2090 Installation of Purlins and Sagrods GL 20-18
A2100 Installation of Cross bracing GL 17-15
A2110 Installation of Purlins and Sagrods GL 17-15
A2120 Installation of Cross bracing GL 17-15
A2130 Installation of Purlins and Sagrods GL 14-13
A2140 Installation of Cross bracing GL 17-15
Side Framing Side Framing, 0%
A2150 Installation of Purlins and Sagrods GL 20-18
A2160 Installation of Cross bracing GL 17-15
A2170 Installation of Purlins and Sagrods GL 17-15
A2180 Installation of Cross bracing GL 17-15
A2190 Installation of Purlins and Sagrods GL 14-13
A2200 Installation of Cross bracing GL 17-15
1.8 MASONRY WORKS 1.8 MASONRY WORKS, 0%
CHB Laying CHB Laying, 0%
A2220 CHB Laying GL 17-15
A2230 CHB Laying GL 14-13
A2210 CHB Laying GL 20-18 45.71%
Plastering Plastering, 0%
A2240 Plastering GL 20-18
A2250 Plastering GL 17-15
A2260 Plastering GL 14-13
1.9 ARCHITECTURAL WORKS 1.9 ARCHITECTURAL WORKS, 0%
A2270 Installation of Roof GL 20-18
A2280 Installation of Roof GL 17-15
A2290 Installation of Roof GL 14-13
A2300 Wall Cladding GL 20-18
A2310 Wall Cladding GL 17-15
A2320 Wall Cladding GL 14-13
PUNCHLISTING PUNCHLISTING, 0%
A2330 Warehouse 2 Punchlisting
A2340 Project Turnover

Actual Level of Effort CLIENT: ALTURAS GROUP OF COMPANIES


Actual Work
LOCATION: LUMANGOG , UBAY, BOHOL
Remaining Work Page 5
Milestone PREPARED BY: MARIÑAS & CO.BUILDERS INC.
% Complete
Summary
PROPOSED DRYER WAREHOUSE (Revision 1.1)
CONTRACTOR: MARIÑAS & CO. BUILDERS, INC 27-Nov-19 13:55
June 2020 July 2020 August 2020 September 2020 October 2020 November 2020 December 2020 January 2021 February 2021 March 2021 April 2021 May 2021
14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 07 14 21 28 07 14 21 28 04 11 18 25 02 09

WORKS, 0%

Actual Level of Effort CLIENT: ALTURAS GROUP OF COMPANIES


Actual Work
LOCATION: LUMANGOG , UBAY, BOHOL
Remaining Work Page 6
Milestone PREPARED BY: MARIÑAS & CO.BUILDERS INC.
% Complete
Summary