1 Change History
Version Date Modified Approved Reason for Change Change
by by
1 09.12.14 mew wolj First version for release Initial release
2 22-01-15 mew wolj Final Version after Review by Not marked in document, as first
factories and QE version was not published to public
3 150914 wolj mahb Specify “initial sample” Add: “under serial conditions” in
2.1.1.
4 151218 mahb mew Formal errors Correction of formal errors in the
header and footer.
5 160120 mahb mew Numbering of chapter 4 changed Changed the numbering in
Some sentences were not clear chapter 4 to be in line with the
enough EMPB TPL.
Minor changes, but not the
content itself
Remark: The Change History only contains the summary of the changes and no details. The detailed
changes are marked with yellow in the document, for minor changes mark the title and the changed text. For
complete new chapters or sections, mark only the title in yellow.
Disclosure to third parties only with the approval of the Baumer Management Services AG- Global Process Owner - All rights are reserved -
Document1 Baumer
02.12.2019 11:15/ mew 2/6 Frauenfeld Switzerland
2 Purpose and Scope
2.1 Purpose
This document describes the requirements for the handling of Initial Samples by the
supplier. It is used to achieve the most rapid and effective integration of new products into
Baumer and it is clearly directing the responsibility for the quality of the products directly
at the beginning to the supplier.
Furthermore, this is the first step to implement the common quality targets and a
cooperative relationship. If there is a deviation between a purchase order for samples and
this BWI, the purchase order has higher priority.
2.2 Scope
This Guideline is valid for all suppliers delivering to the Baumer Group.
3 ISIR Guideline
3.1 Terms
Disclosure to third parties only with the approval of the Baumer Management Services AG- Global Process Owner - All rights are reserved -
Document1 Baumer
02.12.2019 11:15/ mew 3/6 Frauenfeld Switzerland
All samples must be clearly marked (for example: with a red label), also outside of the packaging. If Initial
Sample parts will be delivered with other materials in one shipment, the sample parts have to be separated
clearly from the other materials.
A complete filled out Initial Sample report (e.g. Baumer Template *81131619*) or a similar report according
to VDA and all other necessary documents for review (drawings, specifications, etc.) must be enclosed to the
delivery. The assignment of samples to the Initial Sample report must be clearly visible (Sample Number on
the part have to match with the sample number within the report).
Independent on the chosen ISIR- Template, the Coversheet of the Baumer ISIR TPL *81131619* (which be
delivered enclosed to the purchase order) has to be filled out, to be attached to the delivery and has to be
sent advanced to the email- address mentioned in the Baumer ISIR Template.
A properly completed Initial Sample Inspection Report, combined with the performance of the tests, offers
Baumer the assurance, that all necessary steps to prove the quality capability of the product were
conducted.
Disclosure to third parties only with the approval of the Baumer Management Services AG- Global Process Owner - All rights are reserved -
3.7 Results
After complete Initial Sample testing, the supplier and the internal functions within Baumer will be
informed immediately of the decision. Following decisions can be made:
Released:
The complete release of the initial samples means that the sample parts and/or documentations meets all
our requirements and the required/ related documentation is complete. The supplier is now authorized to
deliver series parts based on a coming Baumer purchase order.
Document1 Baumer
02.12.2019 11:15/ mew 4/6 Frauenfeld Switzerland
4 Content of Submission Levels
Document1 Baumer
02.12.2019 11:15/ mew 5/6 Frauenfeld Switzerland
5 Training, Verification, Monitoring
n.a.
6 Annex
Document1 Baumer
02.12.2019 11:15/ mew 6/6 Frauenfeld Switzerland