WBS Description Discipline Block No Vs Duration Start Date Finish Date Measur Quantity Quantity
Progress 31,08 07,09 14,09 21,09 28,09 05,10 12,10
Actual ement
06,09 13,09 20,09 27,09 04,10 11,10 18,10
92 93 94 95 96 97 98
A Block #2
5 Step-up Transformer 2 -
2 Plan 173 days 26,Apr,19 16,Okt,19 -
a Installation Electrical
2 Actual -
2 Plan 26,Apr,19 % 100,00 100,00
Electrical 100%
2 Actual 1 days 26,Apr,19 26,Apr,19 100,00
I Transformer on base
2 Plan
Resources
2 Actual
2 Plan 4 days 01,Sep,19 05,Sep,19 % 100,00 100,00 100,00
Electrical 80%
2 Actual 80,00 10,00 10,00 10,00
II Support Installation
2 Plan 5
Resources
2 Actual 5 5 5
2 Plan 6 days 06,Sep,19 12,Sep,19 % 100,00 100,00 100,00
Electrical 100%
2 Actual 45,00 15,00 15,00 15,00
III Installation Radiator Bank
2 Plan 5
Resources
2 Actual 5 5 5
2 Plan 6 days 13,Sep,19 19,Sep,19 % 100,00 100,00 10,00 90,00
Electrical 0%
2 Actual -
IV Conservator Oil
2 Plan 5 5
Resources
2 Actual
2 Plan 5 days 21,Sep,19 26,Sep,19 % 100,00 - 100,00
Electrical 40%
2 Actual 25,00 5,00 5,00 5,00
V All Pipe Connection install
2 Plan 5
Resources
2 Actual 5 5 5
2 Plan 4 days 12,Okt,19 16,Okt,19 % 100,00 -
Electrical 0%
2 Actual -
VI HV Turret, Bushing HV & Netral HV
2 Plan
Resources
2 Actual
2 Plan 14 days 26,Sep,19 10,Okt,19 % 100,00 - 10,00 60,00 30,00
Electrical 0%
2 Actual -
b Oil Filteration 2 5 5 5
Plan
Resources
2 Actual
c Electrical and I&C work
2 Plan 16 days 06,Sep,19 05,Okt,19 % 100,00 35,00 10,00 25,00 30,00 25,00 10,00
Electrical 0%
2 Actual -
I Control Panel Installation
2 Plan 5 5 5 5 5
Resources
2 Actual
2 Plan 40 days 06,Sep,19 16,Okt,19 Mtrs 100,00 15,00 5,00 10,00 20,00 30,00 20,00 15,00
Electrical 0%
2 Actual -
II Contol cabling work
2 Plan 5 5 5 5 5 5
Resources
2 Actual
2 Plan 28 days 06,Okt,19 20,Okt,19 % 100,00 - 30,00 60,00
Electrical 0%
2 Actual -
d Function Test 2 5
Plan
Resources
2 Actual
6 Unit Auxiliary Transformer 2
2 Plan 144 days 13,Mei,19 04,Okt,19
a Installation Electrical
2 Actual
2 Plan 13,Mei,19 % 100,00 100,00
Electrical 100%
2 Actual 13,Mei,19 13,Mei,19 100,00
I Unit Auxiliary Transformer on base
2 Plan
Resources
2 Actual
2 Plan 4 days 06,Sep,19 10,Sep,19 % 100,00 100,00 100,00
Electrical 10%
2 Actual 20,00 20,00
II Support Installation
2 Plan 5
Resources
2 Actual 5
2 Plan 5 days 11,Sep,19 16,Sep,19 % 100,00 100,00 50,00 50,00
Electrical 0%
2 Actual -
III Installation Radiator Bank
2 Plan 5 5
Resources
2 Actual
2 Plan 4 days 11,Sep,19 15,Sep,19 % 100,00 100,00 50,00 50,00
Electrical 0%
2 Actual -
IV All Pipe installation
2 Plan 5 5
Resources
2 Actual
2 Plan 7 days 27,Sep,19 04,Okt,19 % 100,00 - 100,00
Electrical 0%
2 Actual -
V All Bushing & Netral installation
2 Plan 5
Resources
2 Actual
11 500KV Substation
-
a Installation